CN207377563U - The shaft wall structure and constructing device of the high spray curtain pile of shaft collar section - Google Patents

The shaft wall structure and constructing device of the high spray curtain pile of shaft collar section Download PDF

Info

Publication number
CN207377563U
CN207377563U CN201720905872.1U CN201720905872U CN207377563U CN 207377563 U CN207377563 U CN 207377563U CN 201720905872 U CN201720905872 U CN 201720905872U CN 207377563 U CN207377563 U CN 207377563U
Authority
CN
China
Prior art keywords
high spray
shaft
wall
spray curtain
circle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720905872.1U
Other languages
Chinese (zh)
Inventor
董亚宁
陈轲
李雷
郝鸿声
臧庆
张建宏
武晓鸣
胡小坡
唐铁军
方伟
苏小明
芦海洋
王晓玲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Maanshan Iron and Steel Mining Resources Group Co Ltd
Original Assignee
Magang Group Holding Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Magang Group Holding Co Ltd filed Critical Magang Group Holding Co Ltd
Priority to CN201720905872.1U priority Critical patent/CN207377563U/en
Application granted granted Critical
Publication of CN207377563U publication Critical patent/CN207377563U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The shaft wall structure of the high spray curtain pile of shaft collar section is related to the Mine Shaft Lining of poor strata, it is included in the vertical that thick aqueous backfill topsoil is set, feature is, using wellbore centre line as the center of circle, the high spray curtain wall of circular ring shape of three circles head and the tail closing is at least set along pit shaft famine radial line periphery, 800~1000mm of thickness of height spray curtain wall, depth are more than the thickness of thick aqueous backfill topsoil.Constructing device, the successively high spray drilling of first, the three, the second circle of construction, high spray curtain wall, then pour the reinforced concrete borehole wall are set.Advantage be it is novel, it is simple in structure, it is reliable and stable, the borehole wall is escorted using height spray curtain wall, enhances bearing capacity and non-deformability, water plugging effect is good;Construction is quick, convenient, can realize pit shaft speed excavation and masonry, save money, it is ensured that mining production is smoothed out.

Description

The shaft wall structure and constructing device of the high spray curtain pile of shaft collar section
Technical field:
The utility model belongs to the Mine Shaft Lining and constructing device of mine vertical shaft construction more particularly to poor strata.
Background technology
Underground mining, vertical are important promotion, ventilation, transport, draining and the personnel safety passage for contacting underground and earth's surface, Preliminary shaft is the part that upper wellbore is connected directly with earth's surface, directly bears the whole load that pit shaft promotes facility.Therefore, vertical well Neck structure must have enough bearing capacity and non-deformability.With the rapid development of global mining industry, shared by underground mining Ratio it is increasing, vertical is increasingly deeper, the stratum that passes through becomes increasingly complex.It especially backfills topsoil and forms complicated, table Soil is clay layer or is that clay mixes layer with rubble, ore, and the soil body is in fluffy, and irregular, uneven, compactness is low, and distribution is big Metering-orifice gap, intensity are low, low bearing capacity, water penetration are strong, aqueous with there is stronger mobility under pressure water or the effect of power water, The disasters such as pit shaft water burst and the differential settlement on earth's surface well head basis is easily caused to occur, damage pit shaft facility or casualties, Production is seriously affected to be smoothed out.
The conventional method of disposal of thick aqueous backfill topsoil is soil replacement method or freezing where shaft collar.Soil replacement method is reinforced Structure all excavates thick aqueous backfill topsoil, pours shaft wall structure first, then back-filling in layers homogeneous soil again, existing defects It is:Earth's surface excavation area is big, is restricted by existing building around, it is difficult to carry out large area excavation;Back-filling in layers homogeneous geotechnique Phase is long, and cost is high.Freezing ruggedized construction is then to bore a circle or two circle freezing holes to stablizing rock stratum or wellbore bottom from earth's surface 10m~20m, complete opening, which is set, in freezing hole freezes steel pipe, arranges refrigeration station in earth's surface, is cycled refrigerating fluid by freezing steel pipe Freezing hole bottom is delivered to, so as to reach freezing shaft whole body country rock, achievees the purpose that water-impervious reinforces country rock, existing defects are: Refrigeration system equipment is long in time limit, cost is high, power consumption is big.Practice have shown that above two method all there are it is long in time limit, cost is high, sternly Ghost image rings the defects of production.It is extremely urgent to seek more rational well shaft wall structure.
The content of the invention
The defects of in order to overcome the prior art, the object of the present invention is to provide a kind of wells of the high spray curtain pile of shaft collar section Wall construction, constructing device and method, simple in structure, stable, reliable, construction quickly, can guarantee the stability of shaft collar.
The shaft wall structure of the high spray curtain pile of shaft collar section is included in the vertical that thick aqueous backfill topsoil is set, in well Rock stratum is excavated in the waste radial line of cylinder, the borehole wall is poured between the net radial line of pit shaft and pit shaft famine radial line, its main feature is that, with wellbore centre line For the center of circle, at least set the circular ring shape of three circles head and the tail closing is high to spray curtain wall along pit shaft famine radial line periphery, outside pit shaft famine radial line 0.6m sets the high spray curtain wall of first lap, and 1.2~2m sets the high spray curtain wall of the second circle outside the high spray curtain wall of first lap, the The high spray curtain wall of the 3rd circle of 1.2~2m settings outside the high spray curtain wall of two circles, and so on, the borehole wall is escorted, enhancing bearing capacity resists Deformability and waterproof ability;800~1000mm of thickness of the high spray curtain wall, depth are more than thick aqueous backfill topsoil Thickness;Injection pressure water hole is set in the pit shaft, carries out injection pressure water test, Gao Pen curtain walls area sets coring drilling, and coring is sentenced Disconnected wall quality;The borehole wall is made of inner and outer wall, and outer wall is the armored concrete not less than 300mm thickness, and inner wall is Not less than the armored concrete of 600mm thickness.
It is further improved, the high spray curtain wall is connected and composed by the high spray curtain pile on same circle, the high spray Curtain pile is to be frozen into cylindric pile body by cement mortar spray to default high spray drilling using three pipe High-pressure Spiral Spray Technologies, The pile body and pile body of same circle are overlapped to connect into the high spray curtain wall of a circular ring shape.
It is further improved, the high spray drilling, is vertically to be drilled to down from ground using drilling machine, depth is more than thick aqueous Thickness of surface soil is backfilled, bore diameter is not less than 130mm, and spacing is not more than 0.9m between two drillings;The cement mortar spray Enter high spray drilling and expand to periphery, expanded diameter is 800mm~1000mm, is had between stake and stake overlapping not less than 100mm Bonding pad.
It is further improved, coring drilling is symmetrical arranged in Gao Pen curtain walls area for two, using drilling machine from ground Face is vertically drilled to down, and depth is more than high spray curtain pile depth 5m, bore diameter 91mm, judges high spray matter according to the core of taking-up Amount.
It is further improved, the injection pressure water hole is at least one, is set in the net radial line of pit shaft, is hung down using drilling machine from ground It is directly drilled to down, depth is more than high spray curtain pile depth 5m, bore diameter 168mm, and pressure injection water test is carried out to drilling, checks high Spray curtain wall water plugging effect.
It is further improved, the outer wall concrete grade is not less than C30, and double steel bar, principal rod are arranged in concrete Diameter is not less than 20mm, is arranged along pit shaft periphery, spacing 300mm;Branch's muscle diameter is not less than 20mm, along wellbore centre line direction Arrangement, spacing 300mm.
It is further improved, the internal-wall concrete label is not less than C30, and individual layer reinforcing bar, principal rod are arranged in concrete Diameter is not less than 20mm, is arranged along pit shaft periphery, spacing 300mm;Branch's muscle diameter is not less than 20mm, along wellbore centre line direction Arrangement, spacing 300mm.
Also provide it is a kind of it is high spray curtain pile shaft lining structural construction device, its main feature is that the device include cementing tank, water tank, Level-one agitator, two level agitator, operation console, high-pressure injection pump, high-pressure hydraulic pump, air compressor machine, drilling machine and high spray booth vehicle are formed, just It is near to be located above near wellbore or pit shaft;The cementing tank, water tank are connected respectively by cement elephant trunk, water pipe and level-one agitator It connects, level-one agitator is connected with two level agitator by mud tube, and two level agitator is connected with high-pressure injection pump by cement mortar pipe, high Pressure injection stock pump, high-pressure hydraulic pump, air compressor machine are connected respectively by slip casting high-voltage tube, high-pressure water pipe, high-pressure air hose with high spray booth vehicle;It is described Cementing tank, water tank, level-one agitator, two level agitator, high-pressure injection pump, high-pressure hydraulic pump, air compressor machine, drilling machine, high spray booth vehicle It is electrically connected by control cable and operation console.
A kind of shaft lining structural construction method of the high spray curtain pile of shaft collar section is also provided, is carried out as follows:
1st, shaft collar section construction line calibration
(1), wellbore centre point is calibrated in earth's surface according to design coordinate, it is only straight according to the pit shaft of wellbore centre point and design Footpath and lining thickness calibrate the net radial line of pit shaft and waste radial line;
(2), 0.6m arranges the high spray curtain pile drilling of first lap arrangement outside pit shaft famine radial line, and spacing is little between two drillings In 0.9m;
(3), the high spray curtain pile drilling of the second circle is arranged again outside the high spray curtain pile of first lap, spacing is little between two drillings In 0.9m, the circle remote of the second circle and first lap is not more than 1.2m;
(4), the high spray curtain pile drilling of the 3rd circle is arranged again outside the high spray curtain pile of the second circle, spacing is little between two drillings In 0.9m, the circle remote of the 3rd circle and the second circle is not more than 1.2m;
The 2nd, constructing device is set by cementing tank, water tank, level-one agitator, two level agitator, high-pressure injection pump, high pressure water Pump, air compressor machine, slip casting high-voltage tube, high-pressure water pipe, high-pressure air hose, drilling machine, high spray booth vehicle and operation console are located near wellbore nearby Or above pit shaft, and relevant device is attached successively;
3rd, the high spray curtain pile boring drill interval drilling of first lap of constructing, every one hole of a hole drill, depth is more than thick aqueous Thickness of surface soil is backfilled, bore diameter is not less than 130mm, and hole position deviation is not more than 1% no more than 2cm, hole deviation rate;
4th, the high spray curtain wall of high-pressure rotary-spray first lap is every hole spray
(1), design proportion is pressed in slurrying, releases quantitative cement in cementing tank by cement elephant trunk, by water pipe from water Quantitative water is released in case and is sent to the level-one agitator with homogenizer, after mixing time is not less than 30s, by what is prepared Cement grout is put by cement mortar pipe with mixing slowly in the two level mixing drum of machine, is slowly stirred;
(2), the cement grout in high-pressure delivery two level mixing drum is connected to high-pressure injection pump, high pressure injection by cement mortar pipe Cement grout in two level mixing drum is transported to the drilling rod of high spray booth vehicle by stock pump by high-pressure slip-casting pipe, will using high-pressure hydraulic pump Water is transported to the drilling rod of high spray booth vehicle by high-pressure water pipe, and air is transported to high spray booth vehicle by high-pressure air hose using air compressor machine Drilling rod;
(3) high pressure jetting sprays drilling hole bottom by supreme under the drilling rod of high spray booth vehicle, and operation console is by controlling cable connection extremely High-pressure grouting pump, high-pressure hydraulic pump and air compressor machine;Start-up operation platform is sent into satisfactory slurry, gas and water, the ratio of cement mortar Again not less than 1.5, pressure is 0.2~1.0Mpa, and water flow is 55~70L/min;The pressure of high pressure water is 34~38Mpa, stream It measures as 60~80L/min;The pressure of compressed air is 0.6~0.8Mpa, flow is 0.8~1.2m3/ min, treats cement grout Emerge aperture when, by design hoisting way and promote speed and promote drilling rod from bottom to top, until the whole spray promoted to design is high Journey stop-spraying, cement grout are frozen into cylindrical concrete stake;Then spray is carried out to the drilling between two again to build, form stake stake part It is overlapped the high spray curtain wall being connected;
5th, by the high spray curtain pile drilling of the 3rd circle of step 3 construction;
6th, high spray curtain wall is enclosed by step 4 high-pressure rotary-spray the 3rd;
7th, by the high spray curtain pile drilling of the second circle of step 3 construction;
8th, high spray curtain wall is enclosed by step 4 high-pressure rotary-spray second;
9th, high spray quality inspection
The wellbore centre symmetric position in high spray curtain wall reinforcing scope between first lap and the 3rd circle randomly chooses Two positions, construction coring drilling, are drilled to down using drilling machine from ground, and depth is more than high spray curtain pile depth 5m, and drilling is straight Footpath 91mm judges high spray quality according to the core of taking-up;Construction finishes, the boring cement mortar complete opening closure of two corings;
10th, pressure injection water test
A position is randomly choosed in the net radial line of pit shaft as pressure injection water hole, is drilled to down from ground using drilling machine, deeply Degree is more than high spray curtain pile depth 5m, bore diameter 168mm, and pressure injection water test is carried out to drilling, checks high spray curtain wall water blockoff Effect;After pressure injection water test, the pressure injection water hole cement mortar complete opening that construction finishes is blocked;
11st, pit shaft preliminary shaft section outer wall is poured
Pit shaft, casting concrete, each cutting depth are gradually excavated from top to bottom in the range of the waste radial line of pit shaft design No more than 2m, preliminary shaft outer wall armored concrete is then poured, until preliminary shaft bottom;Concrete thickness is not less than 300mm, and label is not Less than C30, double steel bar is arranged in concrete, principal rod diameter is not less than 20mm, is arranged along pit shaft periphery, spacing 300mm; Branch's muscle diameter is not less than 20mm, is arranged along wellbore centre line direction spacing 300mm;
12 pour pit shaft preliminary shaft section inner wall
From preliminary shaft bottom continuous placing preliminary shaft inner wall armored concrete from bottom to top, until well head earth's surface, concrete thickness Not less than 600mm, label is not less than C30;Arrangement double steel bar in concrete, principal rod diameter are not less than 20mm, along pit shaft week Side arranges that spacing thickness is not less than 300mm 300mm;Branch's muscle diameter is not less than 20mm, along wellbore centre line direction spacing 300mm is arranged;
13rd, Demolition Construction device, construction terminate.
Compared with prior art, advantage is novel, simple in structure, reliable and stable, and well is escorted using height spray curtain wall Wall, enhances bearing capacity and non-deformability, water plugging effect are good;Construction is quick, convenient, can realize pit shaft speed excavation and masonry, saves Expense, it is ensured that the safe and smooth progress of mining production.
Description of the drawings
Below against attached drawing, the utility model is described in further detail.
The shaft wall structure schematic diagram of the high spray curtain wall of Fig. 1 shaft collars section.
Fig. 2 is high spray curtain wall shaft collar structure A-A sectional schematic diagrams.
Fig. 3 high spray drilling arrangement schematic diagrames.
The high spray curtain wall borehole wall of Fig. 4 shaft collars section applies constructing device configuration schematic diagram.
In figure:1st, the net radial line 3 of shaft of vertical well 1.1, wellbore centre line 2, pit shaft, pit shaft famine radial line 4, outer wall 5, interior The high spray curtain of high high the 9, second circle of spray curtain pile drilling of the 8, the 3rd circle of spray curtain pile drilling of wall 6, backfill topsoil 7, first lap Curtain stake drilling 10, the high spray curtain wall 13 of high spray curtain wall 12, second circle of high spray curtain wall the 11, the 3rd circle of first lap, coring Drilling 14, injection pressure water hole 15, cementing tank 16, cement elephant trunk 17, water tank 18, water pipe 19, level-one agitator 20, mud tube 21st, two level agitator 22, cement mortar pipe 23, operation console 24, control cable 25, high-pressure injection pump 26, high-pressure hydraulic pump 27, Air compressor machine 28, slip casting high-voltage tube 29, high-pressure water pipe 30, high-pressure air hose 31, drilling machine 32, high spray booth vehicle
Specific embodiment
The shaft wall structure of the high spray curtain pile of a kind of shaft collar section it can be seen from Fig. 1, Fig. 2, Fig. 3, is included in thick aqueous Backfill the shaft of vertical well 1 that topsoil is set, rock stratum excavated in the pit shaft famine radial line 3, the net radial line 2 of pit shaft and pit shaft famine radial line it Between pour the borehole wall, be the center of circle with wellbore centre line 1.1, along pit shaft famine radial line periphery at least set three circles head and the tail closing circular ring shape Height spray curtain wall, 0.6m sets the high spray curtain wall 10 of first lap outside pit shaft famine radial line, the 1.5m outside the high spray curtain wall of first lap The high spray curtain wall 12 of second circle is set, the outside the high spray curtain walls of two circles 1.5m the high spray curtain wall 11 of the 3rd circle is set, successively Analogize, escort the borehole wall, enhancing bearing capacity, non-deformability and waterproof ability;The thickness 850mm of the high spray curtain wall is deep Degree is more than the thickness of thick aqueous backfill topsoil;Injection pressure water hole 14 is set in the pit shaft, carries out injection pressure water test, height spray curtain Wall area sets coring drilling 13, and coring judges wall quality;The borehole wall is made of inner wall 4 and outer wall 5, and outer wall 350mm is thick Armored concrete, the armored concrete of inner wall 700mm thickness.
The high spray curtain wall 10 of the first lap, the high spray curtain wall 11 of first lap, the it can be seen from Fig. 1, Fig. 2, Fig. 3 The high spray curtain wall 12 of one circle is connected and composed by the high spray curtain pile on same circle, and the high spray curtain pile is using three pipe high pressures Rotary spray technique is frozen into cylindric pile body, the pile body and pile body with circle are mutual by cement mortar spray to default high spray drilling Overlapping connects into the high spray curtain wall of a circular ring shape.
High the 8, second circle of spray drilling of high the 7, the 3rd circle of spray drilling of the first lap is high it can be seen from Fig. 1, Fig. 2, Fig. 3 Spray drilling 9 is vertically drilled to down using drilling machine 31 from ground, and depth is more than thick aqueous backfill thickness of surface soil, bore diameter 150mm;The cement mortar spray enters high spray drilling and expands to periphery, and expanded diameter 850mm has between stake and stake The overlapping bonding pad of 120mm.
Coring drilling 13 is two it can be seen from Fig. 1, Fig. 2, Fig. 3, is symmetrically set in Gao Pen curtain walls area It puts, is vertically drilled to down from ground using drilling machine, depth is more than high spray curtain pile depth 5m, bore diameter 91mm, according to taking-up Core judge high spray quality.
By Fig. 1, Fig. 2, it can be seen from the injection pressure water hole 14, set in the net radial line of pit shaft, using drilling machine from ground It is vertically drilled to down, depth is more than high spray curtain pile depth 5m, bore diameter 168mm, carries out pressure injection water test to drilling, checks Height spray curtain wall water plugging effect.
The 4 Concrete Thick 350mm of outer wall it can be seen from Fig. 1, Fig. 2, Fig. 3, label C30, the interior arrangement clad steel of concrete Muscle (is not marked in figure), principal rod diameter 25mm, is arranged along pit shaft periphery, spacing 300mm;Branch muscle diameter 22mm, along pit shaft Centerline direction arrangement, spacing 300mm.
The 5 Concrete Thick 700mm of inner wall it can be seen from Fig. 1, Fig. 2, Fig. 3, label C30, the interior arrangement individual layer steel of concrete Muscle, principal rod diameter 25mm are arranged, spacing 300mm along pit shaft periphery;Branch muscle diameter 22mm, along wellbore centre line direction cloth It puts, spacing 300mm.
The shaft lining structural construction device of the high spray curtain pile of shaft collar section it can be seen from Fig. 1, Fig. 4, including cementing tank 15th, water tank 17, level-one agitator 19, two level agitator 21, operation console 23, high-pressure injection pump 25, high-pressure hydraulic pump 26, air compressor machine 27th, drilling machine 31 and high spray booth vehicle 32 are formed, and are located at nearby above near wellbore or pit shaft;The cementing tank, water tank respectively by Cement elephant trunk 16, water pipe 18 are connected with level-one agitator, and level-one agitator is connected with two level agitator by mud tube 20, and two level is stirred It mixes bucket to be connected by cement mortar pipe 22 with high-pressure injection pump, high-pressure injection pump, high-pressure hydraulic pump, air compressor machine are respectively by slip casting high-voltage tube 28th, high-pressure water pipe 29, high-pressure air hose 30 are connected with high spray booth vehicle;The cementing tank, water tank, level-one agitator, two level stirring Bucket, high-pressure injection pump, high-pressure hydraulic pump, air compressor machine, drilling machine, high spray booth vehicle are electrically connected by control cable 24 and operation console.
The shaft lining structural construction method of the high spray curtain pile of shaft collar section, carries out as follows:
1st, shaft collar section construction line calibration
(1), wellbore centre point is calibrated in earth's surface according to design coordinate, it is only straight according to the pit shaft of wellbore centre point and design Footpath and lining thickness calibrate the net radial line of pit shaft and waste radial line line;
(2), 0.6m arranges the high spray curtain pile drilling of first lap arrangement, spacing between two drillings outside pit shaft famine radial line 0.8m;
(3), the high spray curtain pile drilling of the second circle, spacing between two drillings are arranged again outside the high spray curtain pile of first lap 0.8m, the circle remote 1.2m of the second circle and first lap;
(4), the high spray curtain pile drilling of the 3rd circle, spacing between two drillings are arranged again outside the high spray curtain pile of the second circle 0.8m, the circle remote 1.2m of the 3rd circle and the second circle;
The 2nd, constructing device is set by cementing tank, water tank, level-one agitator, two level agitator, high-pressure injection pump, high pressure water Pump, air compressor machine, slip casting high-voltage tube, high-pressure water pipe, high-pressure air hose, drilling machine, high spray booth vehicle and operation console are located near wellbore nearby Or above pit shaft, and relevant device is attached successively.
3rd, the high spray curtain pile boring drill interval drilling of first lap of constructing, every one hole of a hole drill, depth is more than thick aqueous Thickness of surface soil, bore diameter 130mm are backfilled, hole position deviation is not more than 1% no more than 2cm, hole deviation rate;
4th, the high spray curtain wall of high-pressure rotary-spray first lap is every hole spray
(1), design proportion is pressed in slurrying, is released a certain amount of cement from cementing tank 15 is inner by cement elephant trunk 16, is passed through water Pipe 18 releases a certain amount of water to the level-one agitator 19 with homogenizer in water tank, after mixing time is not less than 30s, The cement grout prepared is put by mud tube 20 with mixing slowly in the two level agitator 21 of machine, is slowly stirred;
(2), the cement grout in high-pressure delivery two level mixing drum is connected to high-pressure injection pump 25 by cement mortar pipe 22, high The drilling rod that cement grout in two level mixing drum is transported to high spray booth vehicle 32 by pressure injection stock pump by high-pressure slip-casting pipe (is not marked in figure Note), water using high-pressure hydraulic pump by high-pressure water pipe is transported to the drilling rod of high spray booth vehicle, air is passed through into high pressure using air compressor machine Air hose is transported to the drilling rod of high spray booth vehicle;
(3) high pressure jetting sprays drilling hole bottom by supreme under the drilling rod of high spray booth vehicle, and operation console 23 is by controlling cable connection To high pressure high-pressure injection pump 25, high-pressure hydraulic pump 26 and air compressor machine 27;Start-up operation platform is sent into satisfactory slurry, gas and water, cement The proportion 1.6 of slurry, pressure 0.6Mpa, flow 60L/min;The pressure of high pressure water is 36Mpa, flow 70L/min;Pressure The pressure of contracting air is 0.7Mpa, flow 1.0m3/ min, when cement grout emerges aperture, by design hoisting way and It promotes speed and promotes drilling rod from bottom to top, until promoting the whole spray elevation stop-spraying to design, cement grout is frozen into cylindrical water Mud stake;Then spray is carried out to the drilling between two again to build, form stake stake and partly overlap the high spray curtain wall being connected;
5th, by the high spray curtain pile drilling of the 3rd circle of step 3 construction;
6th, high spray curtain wall is enclosed by step 4 high-pressure rotary-spray the 3rd;
7th, by the high spray curtain pile drilling of the second circle of step 3 construction;
8th, high spray curtain wall is enclosed by step 4 high-pressure rotary-spray second;
9th, high spray quality inspection
The wellbore centre symmetric position random selection two in the range of high spray curtain reinforcement between first lap and the 3rd circle A position, construction coring drilling, is drilled to down using drilling machine from ground, and depth is more than high spray curtain pile depth 5m, bore diameter 91mm judges high spray quality according to the core of taking-up;Construction finishes, the boring cement mortar complete opening closure of two corings;
10th, pressure injection water test
A position is randomly choosed in the net radial line of pit shaft as pressure injection water hole, is drilled to down from ground using drilling machine, deeply Degree is more than high spray curtain pile depth 5m, bore diameter 168mm, and pressure injection water test is carried out to drilling, checks high spray curtain water blockoff effect Fruit;After pressure injection water test, the pressure injection water hole cement mortar complete opening that construction finishes is blocked;
11st, pit shaft preliminary shaft section outer wall is poured
Pit shaft, casting concrete, each cutting depth are gradually excavated from top to bottom in the range of the waste radial line of pit shaft design Then 1.8m pours 5 armored concrete of preliminary shaft outer wall, thickness 350 mm, concrete grade C30, until preliminary shaft bottom;Concrete Interior arrangement double steel bar (being not marked in figure), principal rod diameter are not less than 25mm, are arranged along pit shaft periphery, spacing 300mm;Branch Muscle diameter is not less than 22mm, is arranged along wellbore centre line direction spacing 300mm;
12nd, pit shaft preliminary shaft section outer wall is poured
From preliminary shaft bottom 4 armored concrete of continuous placing preliminary shaft inner wall from bottom to top, until well head earth's surface, thickness 700mm, Concrete grade C30, concrete is interior to arrange double steel bar (being not marked in figure), and principal rod diameter 25mm is arranged along pit shaft periphery, Spacing 300mm;Branch's muscle diameter is not less than 22mm, is arranged along wellbore centre line direction spacing 300mm;
13rd, Demolition Construction device, construction terminate.

Claims (8)

1. the shaft wall structure of the high spray curtain pile of shaft collar section is included in the shaft of vertical well (1) that thick aqueous backfill topsoil is set, Pit shaft is excavated in the net radial line of pit shaft (2), the borehole wall is poured between the net radial line of pit shaft and pit shaft famine radial line (3), which is characterized in that With wellbore centre line (1.1) for the center of circle, the high spray curtain of circular ring shape of three circles head and the tail closing is at least set along pit shaft famine radial line periphery Wall, 0.6m sets the high spray curtain wall (10) of first lap outside pit shaft famine radial line, and 1.2~2m is set outside the high spray curtain wall of first lap The high spray curtain wall (12) of second circle, the outside the high spray curtain walls of two circles 1.2~2m the high spray curtain wall (11) of the 3rd circle is set;Institute 800~the 1000mm of thickness for the high spray curtain wall stated, depth are more than the thickness of thick aqueous backfill topsoil;It is set in the pit shaft Injection pressure water hole (14) carries out injection pressure water test, and Gao Pen curtain walls area sets coring drilling (13), and coring judges wall quality;Institute The borehole wall stated is made of inner wall (5) and outer wall (4), outer wall be not less than 300mm thickness armored concrete, inner wall for not less than The armored concrete of 600mm thickness.
2. the shaft wall structure of the high spray curtain pile of shaft collar section according to claim 1, which is characterized in that described first The high spray curtain wall (10) of circle, the high spray curtain wall (11) of the 3rd circle, the high spray curtain wall (12) of the second circle are by the high spray curtain on same circle Curtain stake connects and composes, and the high spray curtain pile is to be bored cement mortar spray to default high spray using three pipe High-pressure Spiral Spray Technologies In hole, cylindric pile body is frozen into, pile body and the pile body with circle overlapped connect into the high spray curtain wall of an annular.
3. the shaft wall structure of the high spray curtain pile of shaft collar section according to claim 1, which is characterized in that described first The high spray drilling (7) of circle, the high spray drilling (8) of the 3rd circle, the high spray drilling (9) of the second circle are using drilling machine (31) from the vertical drill down in ground Into depth is more than thick aqueous backfill thickness of surface soil, and bore diameter is not less than 130mm;Cement mortar spray enter high spray drilling and to Periphery is expanded, and expanded diameter is 800mm~1000mm, there is the overlapping bonding pad not less than 100mm between stake and stake.
4. the shaft wall structure of the high spray curtain pile of shaft collar section according to claim 1, which is characterized in that the coring (13) are drilled as two, is symmetrical arranged in Gao Pen curtain walls area, is vertically drilled to down from ground using drilling machine, depth is more than height Curtain pile depth 5m, bore diameter 91mm are sprayed, high spray quality is judged according to the core of taking-up.
5. the shaft wall structure of the high spray curtain pile of shaft collar section according to claim 1, which is characterized in that the injection pressure Water hole (14) is at least one, is set in the net radial line of pit shaft, is vertically drilled to down from ground using drilling machine, and depth is more than high spray curtain Curtain stake depth 5m, bore diameter 168mm carry out pressure injection water test to drilling, check high spray curtain wall water plugging effect.
6. the shaft wall structure of the high spray curtain pile of shaft collar section according to claim 1, which is characterized in that the outer wall (4) concrete is not less than C30 for label, double steel bar is arranged in concrete, principal rod diameter is not less than 20mm, along pit shaft periphery Arrangement, spacing 300mm;Branch's muscle diameter is not less than 20mm, is arranged along wellbore centre line direction, spacing 300mm.
7. the shaft wall structure of the high spray curtain pile of shaft collar section according to claim 1, which is characterized in that the inner wall (5) concrete is not less than C30 for label, individual layer reinforcing bar is arranged in concrete, principal rod diameter is not less than 20mm, along pit shaft periphery Arrangement, spacing 300mm;Branch's muscle diameter is not less than 20mm, is arranged along wellbore centre line direction, spacing 300mm.
8. the constructing device of the shaft wall structure of the high spray curtain pile of shaft collar section according to claim 1, which is characterized in that The device includes cementing tank (15), water tank (17), level-one agitator (19), two level agitator (21), operation console (23), high pressure injection Stock pump (25), high-pressure hydraulic pump (26), air compressor machine (27), drilling machine (31) and high spray booth vehicle (32) are formed, and are located near wellbore nearby Or above pit shaft;The cementing tank, water tank are connected respectively by cement elephant trunk (16), water pipe (18) with level-one agitator, level-one Agitator is connected with two level agitator by mud tube (20), and two level agitator is connected with high-pressure grouting pump by cement mortar pipe (22) It connects, high-pressure grouting pump, high-pressure hydraulic pump, air compressor machine are respectively by slip casting high-voltage tube, high-pressure water pipe, high-pressure air hose and high spray booth vehicle Connection;The cementing tank, water tank, level-one agitator, two level agitator, high-pressure injection pump, high-pressure hydraulic pump, air compressor machine, drilling machine, High spray booth vehicle is electrically connected by control cable by control cable (24) and operation console.
CN201720905872.1U 2017-07-25 2017-07-25 The shaft wall structure and constructing device of the high spray curtain pile of shaft collar section Active CN207377563U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720905872.1U CN207377563U (en) 2017-07-25 2017-07-25 The shaft wall structure and constructing device of the high spray curtain pile of shaft collar section

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720905872.1U CN207377563U (en) 2017-07-25 2017-07-25 The shaft wall structure and constructing device of the high spray curtain pile of shaft collar section

Publications (1)

Publication Number Publication Date
CN207377563U true CN207377563U (en) 2018-05-18

Family

ID=62299031

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720905872.1U Active CN207377563U (en) 2017-07-25 2017-07-25 The shaft wall structure and constructing device of the high spray curtain pile of shaft collar section

Country Status (1)

Country Link
CN (1) CN207377563U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107227958A (en) * 2017-07-25 2017-10-03 马钢(集团)控股有限公司 Shaft wall structure, constructing device and the method for the high spray curtain pile of shaft collar section

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107227958A (en) * 2017-07-25 2017-10-03 马钢(集团)控股有限公司 Shaft wall structure, constructing device and the method for the high spray curtain pile of shaft collar section
CN107227958B (en) * 2017-07-25 2023-07-04 马钢(集团)控股有限公司 Well wall structure of vertical well neck section high-spraying curtain pile, construction device and construction method

Similar Documents

Publication Publication Date Title
CN107246267B (en) Vertical shaft wall structure in bad stratum, construction device and construction method
CN106545005B (en) A kind of reinforcing body and reinforcement means of subway tunnel shield end
CN103334770B (en) One is grown up reverse-slope tunnel ultra high water pressure rich water zone of fracture construction method
CN103628912B (en) The construction method of filling grouting is processed in a kind of goaf
CN103899351B (en) A kind of filling reinforcement means of processing complicated cavity
CN103306687A (en) Construction method for deformation control via horizontal whirling jet grouting of long cantilever in soft-rock tunnel
CN102561950B (en) Process for realizing grouting consolidation for aggregates filled in cavities of strata and jetting drill bit
CN106759297A (en) A kind of construction method of support pile and three pipe high-pressure rotary jet grouting pile deep basal pits
CN207377562U (en) Mine Shaft Lining and constructing device in a kind of poor strata
CN110130936B (en) Construction method for sudden encountering untreated karst cave or crack in shield tunneling process
CN108252719B (en) Plastic flow modeling shape red clay layer construction method is worn under a kind of urban shallow tunnel
CN108590706A (en) One kind being used for speciality single-track railway tunnel drifter with booms Construction Techniques of Grouting in Heavy Curtain
CN108265706A (en) A kind of engineering pile and pile-formation process in solution cavity geology
CN111411970B (en) Shield starting construction method under geological condition of water-rich sand layer
CN106284295A (en) Multichannel high-pressure vibro-grouting jet groutinl construction method
WO2021082843A1 (en) Weak stratum-based reinforcement method for shield tunnel covered by shallow soil
CN106638643A (en) Water-stopping-curtain construction device and method
CN114808990A (en) High-pressure pre-filling karst cave pile foundation construction method
CN107227958A (en) Shaft wall structure, constructing device and the method for the high spray curtain pile of shaft collar section
CN107060779A (en) A kind of anti-cut construction method of narrow regions ultra-deep passage inclined shaft
CN107191188B (en) Bedrock section bad aquifer positioning and targeting grouting vertical shaft wall structure, construction device and construction method
CN207377561U (en) The bad water-bearing layer positioning targeting slip casting Mine Shaft Lining of rock section and constructing device
CN207377563U (en) The shaft wall structure and constructing device of the high spray curtain pile of shaft collar section
CN207406345U (en) Rich water sand-pebble layer shield tunnel end horizontal grouting ruggedized construction
CN112593943A (en) Vertical shaft neck section well wall structure in thick water-containing backfill soil layer and construction method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20180809

Address after: 243071 No. 1899 Taibai Road, Ma'anshan economic and Technological Development Zone, Anhui

Patentee after: Magang Group mining industry Co., Ltd

Address before: 243000 8 Jiuhua Road, Yushan, Ma'anshan, Anhui

Patentee before: Magang (Group) Holding Company Ltd.

CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 243071 No. 1899 Taibai Road, Ma'anshan economic and Technological Development Zone, Anhui

Patentee after: Anhui Maanshan Iron and Steel Mining Resources Group Co., Ltd.

Address before: 243071 No. 1899 Taibai Road, Ma'anshan economic and Technological Development Zone, Anhui

Patentee before: Magang Group mining industry Co., Ltd