CN207377125U CN201721456727.6U CN201721456727U CN207377125U CN 207377125 U CN207377125 U CN 207377125U CN 201721456727 U CN201721456727 U CN 201721456727U CN 207377125 U CN207377125 U CN 207377125U
Authority
CN
China
Prior art keywords
stull
channel steel
living
perpendicular support
square steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721456727.6U
Other languages
Chinese (zh)
Inventor
李英章
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201721456727.6U priority Critical patent/CN207377125U/en
Application granted granted Critical
Publication of CN207377125U publication Critical patent/CN207377125U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Media Introduction/Drainage Providing Device (AREA)

Abstract

It is a kind of that flexible balcony falsework system is adjusted, it is made of channel steel base, adjusting screw, perpendicular support, diagonal brace, stull, square steel casing living.Perpendicular support, stull, diagonal brace form a stable triangular construction, and channel steel base top and perpendicular support bottom construct for interior mantle fiber, adjust screw and the two links together.Square steel casing top cover living can move, its upper part has perpendicular baffle in stull along rung level direction.The utility model advantage is:It is simple in construction, easy to disassemble and assemble, it can be dismounted in construction.

Description

It is a kind of that flexible balcony falsework system is adjusted
Technical field
Flexible balcony falsework system is adjusted the utility model is related to a kind of, in constructing for balcony, to balcony It is supported.
Background technology
Balcony formwork bracing system is currently to take from a kind of upward form of construction work in ground, and all after-pouring components are adopted It is constructed with this construction method, such construction method is unfavorable for the requirement of construction period, in addition in the setting of falsework Upright bar needs on the same line up and down for upper requirement, in order to which the vertical force that construction loads generates is transferred downwards.
The content of the invention
The utility model is in view of the deficiencies of the prior art, it is proposed that and it is a kind of that flexible balcony falsework system is adjusted, The formwork bracing system is different from the existing template-setup mode upward from ground, has using the support system convenient fast The characteristics of prompt, time saving and energy saving, can accomplish synchronously to construct.
It is described in the utility model to be made of channel steel base, adjusting screw, perpendicular support, diagonal brace, stull, square steel casing living(Fig. 1).
Channel steel base 0 has through hole 1, and through hole runs through channel steel bottom, for channel steel base to be fixed.
There is interior mantle fiber end 12 in the upper end of channel steel base 0.
Perpendicular support 4 is made of channel steel, there is through hole 5 in perpendicular support, and through hole runs through channel steel bottom, for by channel steel base It is fixed.
Interior mantle fiber end 3 is arranged at perpendicular support bottom.
It adjusts screw 2 channel steel base and perpendicular support link together.The silk mouth at the interior mantle fiber end 12 of channel steel base upper end erects The silk mouth at the interior mantle fiber end 3 of bottom is supportted, is all matched with adjusting the silk mouth of screw.
Stull 10 is made of channel steel, is welded together with perpendicular support 3.Stull 10 and perpendicular support are vertical configuration.
Multiple round holes 11 on the lateral margin of stull 10, distance is identical between round hole.
The effect of stull is to prevent balcony component, moves downward in vertical direction.
Diagonal brace 6 is made of channel steel, and its one end is connected with perpendicular support 3, one end is connected with stull 10, and three is by being welded and fixed Together.Triangular construction between three, according to the indeformable characteristic of triangle so that the support stability higher.
Square steel casing 7 living is sleeved in stull, has multiple round holes 8 on square steel casing side living.The circle of square steel casing 7 living The diameter in hole 8 is identical with 11 diameter of round hole in stull 10.
Above-mentioned design so that when square steel casing 7 living is slided on a certain position, the round hole of side can and it is horizontal Round hole 11 in support 10 coincides.Use screw rod, you can square steel casing 7 living and stull 10 are fixed together.
Perpendicular block 9 is arranged at 7 top of square steel casing living, and perpendicular block 9 is welded on square steel casing 7 living.
The effect of perpendicular baffle is to prevent that balcony component is mobile in level side.
Adjust screw by rotating, the distance between adjustable slot steel base and perpendicular support, be also equal to have adjusted pedestal with The distance between stull.Have adjusted the height of entire stent.
Description of the drawings
Fig. 1 is the structural map of the utility model.
Wherein:0 --- channel steel base;1 --- through hole;2 --- adjust screw;3 --- interior mantle fiber end;4 --- perpendicular support; 5 --- through hole;6 --- diagonal brace;7 --- square steel casing living;8 --- round hole;9 --- perpendicular baffle;10 --- stull; 11 --- round hole;12 --- interior mantle fiber end.
Fig. 2 is the effect schematic diagram of the utility model.
Wherein:0 --- channel steel base;1 --- through hole;2 --- adjust screw;3 --- interior mantle fiber end;4 --- perpendicular support; 5 --- through hole;6 --- diagonal brace;7 --- square steel casing living;8 --- round hole;9 --- perpendicular baffle;10 --- stull; 11 --- round hole;12 --- interior mantle fiber end;13 --- wall;14 --- balcony;15 --- perforation screw;16 --- perforation silk Bar;17 --- nut;18 --- nut.
Specific embodiment
With reference to Fig. 1, Fig. 2, specific embodiment of the present utility model is described below.
Stull 10, perpendicular support 4, diagonal brace 6 are all made of channel steel, are welded together to form a stable triangular construction.
0 top of channel steel base is interior mantle fiber end 12, and it is interior mantle fiber end 3 to erect support bottom.The interior mantle fiber end on channel steel base top The silk mouth at the interior mantle fiber end 3 of 12 silk mouth and perpendicular support bottom, the silk mouth with adjusting screw 2 match, adjust screw 2 and consolidate the two It is scheduled on together.
Through screw 15 through round hole 5 and wall 13 in perpendicular support, it is fixed using nut 17.It is worn through screw 16 The round hole 1 and wall 13 in perpendicular support are crossed, is fixed using nut 18.
Entire stent has just been fixed on wall.
The effect of stull 10 is to prevent balcony component 14 from moving in the horizontal direction, and the effect of perpendicular baffle is to prevent balcony structure Part 14 moves in the horizontal direction.
Rotation adjusts screw, you can adjusts the distance between channel steel base and perpendicular support.Perpendicular support drives diagonal brace and stull movement, Equal to the height for changing the stent.
Square steel casing 7 living can move in the horizontal direction, and perpendicular baffle is driven to move, change perpendicular baffle and wall 13 it Between distance, equal to changing stent width in the horizontal direction.

Claims (2)

1. a kind of be adjusted flexible balcony falsework system, it is characterised in that:By channel steel base, adjusting screw, erect support, oblique Support, stull, square steel casing living are formed, and erect support, stull, diagonal brace form a stable triangular construction, channel steel base top with Perpendicular support bottom constructs for interior mantle fiber, adjusts screw and the two links together.
2. a kind of adjustable flexible balcony falsework system according to claim 1, it is characterised in that:Square steel set living Tube top is sleeved in stull, can be moved along rung level direction, its upper part has perpendicular baffle.
CN201721456727.6U 2017-11-05 2017-11-05 It is a kind of that flexible balcony falsework system is adjusted Expired - Fee Related CN207377125U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721456727.6U CN207377125U (en) 2017-11-05 2017-11-05 It is a kind of that flexible balcony falsework system is adjusted

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721456727.6U CN207377125U (en) 2017-11-05 2017-11-05 It is a kind of that flexible balcony falsework system is adjusted

Publications (1)

Publication Number Publication Date
CN207377125U true CN207377125U (en) 2018-05-18

Family

ID=62334088

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721456727.6U Expired - Fee Related CN207377125U (en) 2017-11-05 2017-11-05 It is a kind of that flexible balcony falsework system is adjusted

Country Status (1)

Country Link
CN (1) CN207377125U (en)

Similar Documents

Publication Publication Date Title
CN106088587B (en) A kind of Combined formwork support system
CN106121222B (en) A kind of adjusting beam bed die plate supporting device and beam bottom mold method
CN109056744A (en) A kind of the fixation device and its application method of building foundation pit supporting mechanism
CN205314504U (en) Building platform for outdoor building and indoor decoration
CN201730342U (en) Control support for controlling plainness of large area concrete construction
CN207377125U (en) It is a kind of that flexible balcony falsework system is adjusted
CN206289964U (en) For the climbing form system of sloping core construction
CN203271140U (en) Civil engineering pipe fitting shelf
CN208380489U (en) A kind of interior decoration staircase convenient for storage
CN207700711U (en) Laminated floor slab support construction
CN211114714U (en) Building scaffold convenient to remove
CN203654695U (en) Foldable support frame
CN205164048U (en) Multistage over -and -under type sports dancing barre of doing exercises
CN204418652U (en) The independent support frame of construction formwork
CN208137382U (en) A kind of high-building construction folding support stand
CN207296339U (en) Construction folding support stand
CN206513001U (en) One kind rotation ladder scaffolding
CN205024685U (en) Cloth machine suitable for enrockment concrete placement
CN107940200A (en) Foot-operated measurement foot stool easy to operation
CN204385885U (en) There is the bridge construction tower crane pile foundation sustaining wall of two governor motion
CN209195003U (en) Telescopic hanging landing beam
CN211881643U (en) Fence for poultry with height adjusting function
CN109025239B (en) Climbing supporting device for constructional engineering
CN204225459U (en) A kind of building site bracing frame
CN207011318U (en) A kind of portable vertical greening device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180518

Termination date: 20191105

CF01 Termination of patent right due to non-payment of annual fee