CN207331035U - Steel construction tower galvanizing equipment - Google Patents
Steel construction tower galvanizing equipment Download PDFInfo
- Publication number
- CN207331035U CN207331035U CN201721457063.5U CN201721457063U CN207331035U CN 207331035 U CN207331035 U CN 207331035U CN 201721457063 U CN201721457063 U CN 201721457063U CN 207331035 U CN207331035 U CN 207331035U
- Authority
- CN
- China
- Prior art keywords
- zinc
- material conveying
- zinc pot
- conveying platform
- sub
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Coating With Molten Metal (AREA)
Abstract
The utility model announces a kind of steel construction tower galvanizing equipment, belongs to steel construction tower manufacturing technology field.Feed mechanism is equipped with front of zinc pot, zinc-plated transmission mechanism is equipped with above zinc pot, zinc pot rear is equipped with receiving mechanism, and feed mechanism includes lifting platform, workbench;Material conveying platform is installed on workbench slide;Feeding oil cylinder is connected between material conveying platform rear end and workbench;Zinc-plated transmission mechanism includes the shaft above zinc pot;Two groups of opposite sub-struts are fixed with shaft;Every group of sub-strut has four, is evenly arranged;Gusseted is hinged with sub-strut end;Uniformly distributed suspension hook is fixed with gusseted;Suspension hook is corresponded with the arc groove on the material conveying platform;Receiving mechanism is symmetrical with feeding machine structure.The utility model has multiple stations, and when can ensure that steel pipe is zinc-plated, is separated from each other in zinc pot not overlapping, improves production efficiency, has prevented Caton phenomenon, rate of effectively reducing the number of rejects and seconds, improves quality and benefits.
Description
Technical field
It the utility model is related to the manufacturing technology field of steel construction tower, and in particular to a kind of steel construction tower assembling
The galvanizing equipment of steelwork component before.
Background technology
Tower is generally divided into following several classes from the type of section steel material:1st, angle steel tower:Main material and web member mainly use angle
The steel tower that steel makes.Triangle tower, four turrets, five turrets, hexagonal tower, Octagonal pagoda are had according to section parameter difference.Communicate the most frequently used
For four turrets and triangle tower.2nd, steel tube tower:Main material uses steel pipe, oblique material etc. using angle steel or the steel tower of steel pipe manufacturing, root
According to the same angle steel tower of cross sectional shape classification, most commonly used communication is three towers and four towers.3rd, single-pipe tower (only tower) whole tower
Body uses the cantilevered structures that single large diameter steel pipe makes.4th, mast or Guywire tower:(or drawn by gin pole and towline
Rope) form highrise steel structure.
During tower Assembling, mostly using mode connecting components such as welding, flange, bolts.In order to ensure tower
Service life, it is necessary to before assembly to each component carry out it is zinc-plated, to ensure the corrosion resistance of tower.Steel pipe is zinc-plated now
In technique, each station production 1 of steel pipe is less efficient, and carries out sub-material from the steel pipe that zinc pot is chosen with material separating disc, due to
Choosing the incline direction of pipe can not ensure, so Caton phenomenon is more, can be stuck in when on flat on material separating disc, cause excessive curved
The production time is also influenced while pipe and useless pipe.
The content of the invention
In order to solve the above technical problems, the utility model provides, a kind of station is more, and efficient steel construction tower is zinc-plated to be set
It is standby.
The utility model is achieved through the following technical solutions:A kind of steel construction tower galvanizing equipment, including zinc pot, the zinc
Pot front is equipped with feed mechanism, is equipped with zinc-plated transmission mechanism above zinc pot, zinc pot rear is equipped with receiving mechanism, the feed mechanism
Including lifting platform;The lifting platform is equipped with workbench;The workbench is equipped with horizontally disposed slide, workbench
Material conveying platform is installed on slide;Feeding oil cylinder is connected between the material conveying platform rear end and workbench, before material conveying platform
Close to zinc pot, material conveying platform front end upper surface is provided with uniformly distributed arc groove at end;The zinc-plated transmission mechanism is included in zinc pot
The shaft of side;Two groups of opposite sub-struts are fixed with the shaft;Sub-strut described in every group has four, is evenly arranged;In the pair
Support end is hinged with gusseted;Uniformly distributed suspension hook is fixed with the gusseted;On the suspension hook and the material conveying platform
Arc groove correspond;The receiving mechanism and feeding machine structure are symmetrical.
It is further:Bracing piece is connected between the opposite sub-strut.
Slide bar is connected between the opposite gusseted base;Two sliding blocks are slidably fitted with the slide bar,
The sliding block is equipped with the positioning pin for being used for being positioned at sliding block on slide bar;The suspension hook is fixed on sliding block.
The material conveying platform front end is provided with uniformly distributed bar shaped groove.
Compared with prior art, the beneficial effects of the utility model are:Zinc-plated transmission mechanism has four gusseteds, each
Gusseted has multiple stations, and when can ensure that steel pipe is zinc-plated, is separated from each other in zinc pot not overlapping, improves production effect
Rate;Feed mechanism and receiving mechanism replace the material separating disc of original technology, have prevented Caton phenomenon, rate of effectively reducing the number of rejects and seconds, lifting
Quality and benefits.
Brief description of the drawings
Fig. 1 is the utility model structure diagram;
Fig. 2 is A-A direction views in Fig. 1.
In figure:1st, zinc pot;2nd, lifting platform;3rd, workbench;4th, material conveying platform;4-1, bar shaped groove;5th, feeding oil cylinder;6、
Shaft;7th, sub-strut;8th, gusseted;9th, suspension hook;10th, rewinding platform;11st, rewinding oil cylinder;12nd, bracing piece;13rd, slide bar;14th, it is sliding
Block;15th, positioning pin.
Embodiment
The following is a combination of the drawings in the embodiments of the present utility model, and the technical scheme in the embodiment of the utility model is carried out
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are without making creative work
All other embodiments obtained, shall fall within the protection scope of the present invention.
As depicted in figs. 1 and 2, a kind of steel construction tower galvanizing equipment, including zinc pot 1, the front of zinc pot 1 are equipped with feeder
Structure, the top of zinc pot 1 are equipped with zinc-plated transmission mechanism, and 1 rear of zinc pot is equipped with receiving mechanism.
Feed mechanism includes lifting platform 2, and lifting platform 2 selects hydraulic elevator platform, can lift certain height.In lifting platform
2 are equipped with workbench 3, and workbench 3 is equipped with horizontally disposed slide, material conveying platform is provided with 3 slide of workbench
4;Feeding oil cylinder 5 is connected between 4 rear end of material conveying platform and workbench 3.Under the drive of feeding oil cylinder 5, material conveying platform 4 can
With towards zinc pot 1 close to and away from a certain distance.Opened close to zinc pot 1,4 front end upper surface of material conveying platform 4 front end of material conveying platform
There is uniformly distributed arc groove;During work, steel pipe is placed on 4 arc groove of material conveying platform.4 front end of material conveying platform is provided with uniformly distributed bar shaped
Straight slot 4-1, bar shaped groove 4-1 coordinate with suspension hook 9, are hooked in easy to suspension hook 9 under steel pipe.
Stating zinc-plated transmission mechanism includes the shaft 6 positioned at the top of zinc pot 1;Two groups of opposite sub-struts 7 are fixed with shaft 6;
Every group of sub-strut 7 has four, is evenly arranged;Bracing piece 12 is connected between opposite sub-strut 7, to improve the rigidity of sub-strut 7, is prevented
Stress deformation.7 end of sub-strut is hinged with gusseted 8, and slide bar 13 is connected between opposite 8 base of gusseted;Slide bar 13
On be slidably fitted with two sliding blocks 14, be equipped with sliding block 14 and be used to for sliding block 14 to be positioned at positioning pin 15 on slide bar 13;Hang
Hook 9 is fixed on sliding block 14.The distance between two suspension hooks 9 can be adjusted by sliding block 14, conveniently adapt to the steel of different length
Pipe.
Receiving mechanism includes lifting platform 2, workbench, rewinding platform 10, rewinding oil cylinder 11.Receiving mechanism and feed mechanism
Symmetrical configuration, here, not repeating.
The course of work:
Material conveying platform 4 is in retracted mode, steel pipe is placed in the arc groove of 4 front end of material conveying platform;
Shaft 6 rotates, and the sub-strut 7 of nearside is into level;
Material conveying platform 4 stretches out, under gusseted 8;
Lifting platform 2 rises, and drives material conveying platform 4 that suspension hook 9 is hooked under steel pipe under gusseted 8;
Lifting platform 2 declines, and driving material conveying platform 4, suspension hook 9 hooks steel pipe away under gusseted 8;
Material conveying platform 4 is retracted, and shaft 6 rotates, and drives gusseted 8, and suspension hook 9 hooks steel pipe and sinks to zinc pot;
After zinc-plated, gusseted 8 is moved at receiving mechanism, into level;
The rewinding platform 10 of receiving mechanism stretches out, and then, lifting platform 2 drives rewinding platform 10 to rise, and catches steel pipe;
Suspension hook 9 is released, lifting platform 2 drives rewinding platform 10 to decline, and rewinding platform 10 is retracted;Complete zinc-plated process;
Zinc-plated good steel pipe is withdrawn, into subsequent processing.
While there has been shown and described that the embodiment of the utility model, for the ordinary skill in the art,
It is appreciated that these embodiments can be carried out with a variety of changes in the case where not departing from the principle of the utility model and spirit, repaiied
Change, replace and modification, the scope of the utility model are defined by the appended claims and the equivalents thereof.
Claims (4)
1. a kind of steel construction tower galvanizing equipment, including zinc pot(1), the zinc pot(1)Front is equipped with feed mechanism, zinc pot(1)
Top is equipped with zinc-plated transmission mechanism, zinc pot(1)Rear is equipped with receiving mechanism, it is characterised in that:The feed mechanism includes lifting
Platform(2);The lifting platform(2)It is equipped with workbench(3);The workbench(3)Horizontally disposed slide is equipped with, is worked
Platform(3)Material conveying platform is installed on slide(4);The material conveying platform(4)Rear end and workbench(3)Between be connected with feeding
Oil cylinder(5), material conveying platform(4)Front end is close to zinc pot(1), material conveying platform(4)Front end upper surface is provided with uniformly distributed arc groove;It is described
Zinc-plated transmission mechanism includes being located at zinc pot(1)The shaft of top(6);The shaft(6)On be fixed with two groups of opposite sub-struts
(7);Sub-strut described in every group(7)There are four, be evenly arranged;In the sub-strut(7)End is hinged with gusseted(8);Described three
Angle supports(8)Under be fixed with uniformly distributed suspension hook(9);The suspension hook(9)With the material conveying platform(4)On arc groove one it is a pair of
Should;The receiving mechanism and feeding machine structure are symmetrical.
2. steel construction tower galvanizing equipment according to claim 1, it is characterised in that:The opposite sub-strut(7)Between
It is connected with bracing piece(12).
3. steel construction tower galvanizing equipment according to claim 1, it is characterised in that:The opposite gusseted(8)
Slide bar is connected between base(13);The slide bar(13)On be slidably fitted with two sliding blocks(14), in the sliding block(14)On
Equipped with for by sliding block(14)It is positioned at slide bar(13)On positioning pin(15);The suspension hook(9)It is fixed on sliding block(14)On.
4. steel construction tower galvanizing equipment according to claim 1, it is characterised in that:The material conveying platform(4)Open front end
There is uniformly distributed bar shaped groove(4-1).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721457063.5U CN207331035U (en) | 2017-11-05 | 2017-11-05 | Steel construction tower galvanizing equipment |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721457063.5U CN207331035U (en) | 2017-11-05 | 2017-11-05 | Steel construction tower galvanizing equipment |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207331035U true CN207331035U (en) | 2018-05-08 |
Family
ID=62364213
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721457063.5U Active CN207331035U (en) | 2017-11-05 | 2017-11-05 | Steel construction tower galvanizing equipment |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207331035U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109355607A (en) * | 2018-12-21 | 2019-02-19 | 重庆佰鸿机械设备有限公司 | A kind of steel tube hot galvanizing device |
-
2017
- 2017-11-05 CN CN201721457063.5U patent/CN207331035U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109355607A (en) * | 2018-12-21 | 2019-02-19 | 重庆佰鸿机械设备有限公司 | A kind of steel tube hot galvanizing device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201713215U (en) | Flange pipe hanger | |
CN106756702A (en) | A kind of continuous production flexibility coating steel pipe production line | |
CN207331035U (en) | Steel construction tower galvanizing equipment | |
CN202186835U (en) | Device for hoisting motor stator | |
CN203144540U (en) | Electrolytic manganese production line and negative plate crane | |
CN205932922U (en) | Reinforcement cage hoisting pulley gear | |
CN207258679U (en) | Workpiece reversing device | |
CN206384707U (en) | A kind of cylinder type object stone tongs | |
CN206955528U (en) | A kind of novel labour saving hoisting mechanism | |
CN211521362U (en) | Aluminum profile lifting device | |
CN203402809U (en) | Three-group vertical connection pulley block series connection type hanging row | |
CN206569904U (en) | A kind of suspender for lifting steel plate | |
CN207047357U (en) | A kind of full-automatic planer hangs hang plating production line | |
CN213085198U (en) | Balance hanging beam group lifting appliance | |
CN205045696U (en) | Iron tower lower margin cable suspension device for hot -galvanize | |
CN210479565U (en) | Self-lifting pipe placing and discharging frame | |
CN201220236Y (en) | Large-sized roller loader | |
CN210585536U (en) | Automobile mould surface spraying equipment | |
CN106743603A (en) | The c-type clasp cutting agency of c-type clasp charging equipment | |
CN202139005U (en) | Hanging basket rope-aligning mechanism | |
CN202447841U (en) | Tool for fixing winch connecting plates for marine crane | |
CN205802755U (en) | A kind of efficient lifting device for changing dust-removal cloth-bag | |
CN216737200U (en) | Workpiece hoisting device | |
CN217377007U (en) | Special lifting appliance for reverse balance flange wind power tower cylinder | |
CN214031376U (en) | Roller coater lower roll replacing lifting appliance |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |