CN207315411U - The first branch structure of straight median septum under song on two side-wall pilot tunnel bored tunnel - Google Patents

The first branch structure of straight median septum under song on two side-wall pilot tunnel bored tunnel Download PDF

Info

Publication number
CN207315411U
CN207315411U CN201721342938.7U CN201721342938U CN207315411U CN 207315411 U CN207315411 U CN 207315411U CN 201721342938 U CN201721342938 U CN 201721342938U CN 207315411 U CN207315411 U CN 207315411U
Authority
CN
China
Prior art keywords
steel
median septum
tunnel
pilot tunnel
arch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721342938.7U
Other languages
Chinese (zh)
Inventor
陈庆章
姜学军
陈典华
王宏斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 18th Bureau Group Co Ltd
Municipal Engineering Co Ltd of China Railway 18th Bureau Group Co Ltd
Original Assignee
China Railway 18th Bureau Group Co Ltd
Rail Transit Engineering Co Ltd of China Railway 18th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 18th Bureau Group Co Ltd, Rail Transit Engineering Co Ltd of China Railway 18th Bureau Group Co Ltd filed Critical China Railway 18th Bureau Group Co Ltd
Priority to CN201721342938.7U priority Critical patent/CN207315411U/en
Application granted granted Critical
Publication of CN207315411U publication Critical patent/CN207315411U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The utility model discloses branch structure at the beginning of straight median septum under song on a kind of two side-wall pilot tunnel bored tunnel, including steel grating, I-steel, steel arch-shelf, connecting plate and concrete;The first branch even structure is arranged on tunnel Longitudinal extending direction;Steel arch-shelfAdd gunite concrete median septum, steel arch-shelfAdd the interim inverted arch of gunite concrete;Median septum uses the support form of upper curve lower part straight line, selects steel grating to carry out top median septumSupporting erection and barrel supporting, using I-steel as lower part median septumSkeleton is set up, and junction, as connecting plate, preliminary bracing system is collectively forming with gunite concrete using steel plate.The utility model can reduce reinforcing bar it is curved cut with welding job amount, improve construction efficiency, reduce support replacement process, effectively shorten the construction period, reduce trolley volume, easy to construct, at the same reduce the soil disturbance caused by construction period is long, it is ensured that construction safety.

Description

The first branch structure of straight median septum under song on two side-wall pilot tunnel bored tunnel
Technical field
Bored tunnel field is the utility model is related to, at the beginning of particularly a kind of bored tunnel based on two side-wall pilot tunnel construction Branch structure.
Background technology
For the bored tunnel of two side-wall pilot tunnel construction, the excavation carried out especially in Urban underground Tunnel, over the ground The sedimentation of table with construction built up, the excavation of lower pilot tunnel is carried out after top heading excavation to certain distance, under lead Construction of the excavation in hole to upper pilot tunnel has a certain impact, when existing lower pilot drive support pattern causes lower pilot drive supporting Between it is long, influence overall construction speed.
Do not increasing to carry out the engineering method that can accelerate construction progress again of soil disturbance increase settling amount gram it would therefore be desirable to have a kind of Clothes mitigate drawbacks described above.
The content of the invention
The utility model is in view of the deficiencies of the prior art, there is provided straight interval under song on a kind of two side-wall pilot tunnel bored tunnel The first branch structure of wall.
To achieve these goals, the utility model employs following technical scheme:
Straight median septum just branch structure, including steel grating, I-steel, steel arch under song on a kind of two side-wall pilot tunnel bored tunnel Frame, connecting plate and concrete;The first branch even structure is arranged on tunnel Longitudinal extending direction;The steel grating is arranged on Upper mid-board internal face and upper pilot tunnel internal face, the steel grating set on upper mid-board internal face add gunite concrete to form two Side median septum, the steel grating that is set on upper pilot tunnel internal face adds pneumatically placed concrete to form barrel supporting;The steel arch-shelfIf The pilot tunnel bottom on being arranged on is put, the steel arch-shelf set on upper pilot tunnel bottomGunite concrete is added to form median septum;It is described Steel arch-shelfLower pilot tunnel internal face is arranged on, the steel arch-shelf set on lower pilot tunnel internal faceAdd gunite concrete to be formed to face When inverted arch;The I-steel is arranged on lower mid-board internal face, and the I-steel set on lower mid-board internal face adds spray mixed Solidifying soil forms both sides median septum;The I-steel, steel grating, the junction of steel arch-shelf are connected by connecting plate;Described Median septumCurve support form is presented;The median septumStraight line support form is presented.
As the further explanation of the utility model, the I-steel uses work 25a I-steel.
As the further explanation of the utility model, the material that the connecting plate uses is steel plate.
As the further explanation of the utility model, the both sides median septumBetween form shape space wide at the top and narrow at the bottom.
As the further explanation of the utility model, the both sides median septumBetween form wide space up and down.
The utility model has the following advantages:
1. reduce reinforcing bar it is curved cut with welding job amount, using the I-steel of canonical form, improve construction efficiency, effectively contracting Casual labourer's phase.
2. be not required to remove steel skeleton when inverted arch pours, avoid the occurrence of because tearing excessive, the reduction support replacement process that overhangs existing sedimentation open, Reduce the destruction to preliminary bracing system, it is ensured that construction safety.
3. the interim inverted arch of joint, provides operation side for the lining construction of arch two, reduces trolley volume, easy to construct, carry High workload efficiency.
4. reducing the bored tunnel construction period using two side-wall pilot tunnel, production efficiency is improved, while reduce because of construction Soil disturbance caused by excessive cycle.
Brief description of the drawings
Fig. 1 is the sectional view of the utility model.
Reference numeral:1- median septums, 2- median septums, 3- median septums, 4- connecting plates, 5- barrel supportings, 6- inverted arch.
Embodiment
The present invention is further described below in conjunction with the accompanying drawings.
Embodiment 1:
Straight median septum just branch structure, including steel grating, I-steel, steel arch under song on a kind of two side-wall pilot tunnel bored tunnel Frame, connecting plate 4 and concrete;The first branch even structure is arranged on tunnel Longitudinal extending direction;The steel grating is set In upper mid-board internal face and upper pilot tunnel internal face, the steel grating set on upper mid-board internal face adds gunite concrete to be formed Both sides median septum1, the steel grating set on upper pilot tunnel internal face adds pneumatically placed concrete to form barrel supporting 5;The steel arch-shelfPilot tunnel bottom is arranged on, the steel arch-shelf set on upper pilot tunnel bottomGunite concrete is added to form median septum2; The steel arch-shelfLower pilot tunnel internal face is arranged on, the steel arch-shelf set on lower pilot tunnel internal faceAdd gunite concrete shape Into interim inverted arch 6;The I-steel is arranged on lower mid-board internal face, and the I-steel set on lower mid-board internal face adds Pneumatically placed concrete forms both sides median septum3;The I-steel, steel grating, the junction of steel arch-shelf are connected by connecting plate 4; The median septum1 is presented curve support form;The median septum3 are presented straight line support form.
The I-steel uses work 25a I-steel.
The material that the connecting plate 4 uses is steel plate.
The both sides median septumShape space wide at the top and narrow at the bottom is formed between 1.
The both sides median septumSpace wide up and down is formed between 3.
The construction technology of the utility model, Specific construction flow step sequence are:
Preliminary bracing, median septum are carried out after the completion of top heading excavation1 adds gunite concrete to construct using steel grating, Steel arch-shelfReserve and lower pilot tunnel median septum lower part3 connecting portions.
Lower pilot drive is excavated using benching tunnelling method, is excavated Internal periphery and is used stalk form, in being carried out using work 25a I-steel Next door3 skeletal supports, with upper pilot tunnel median septum1 is attached using steel connecting plate 4, median septumI-steel connects in 3 It is attached using connecting plate 4, gunite concrete forms just branch median septum system.
When inverted arch 6 is laid with, concrete between I-steel is abolished, reinforcing bar binding is carried out, runs into reinforcing bar and conflict with I-steel position When, it can be passed through in I-steel belly jewel hole.Pay attention to the uncured waterproof material of rubber asphalt and applying at EVA splash guard lap joints Work quality control, pre-buried good Grouting Pipe.Top median septum1 is removed before carrying out the lining of arch two and pouring, lower part median septum3 are removed after the completion of two linings perform, and the cutting of steel skeleton is carried out from 6 surface of inverted arch.

Claims (5)

1. just branch structure, the first branch even structure are arranged on straight median septum under song on a kind of two side-wall pilot tunnel bored tunnel Tunnel Longitudinal extending direction;It is characterized in that:Including steel grating, I-steel, steel arch-shelf, steel arch-shelf, connecting plate(4)With it is mixed Solidifying soil;The steel grating is arranged on mid-board internal face and upper pilot tunnel internal face, is set on upper mid-board internal face Steel grating adds gunite concrete to form median septum(1), the steel grating that is set on upper pilot tunnel internal face adds pneumatically placed concrete to form hole Body supporting(5);The steel arch-shelfPilot tunnel bottom is arranged on, the steel arch-shelf set on upper pilot tunnel bottomAdd injection coagulation Soil forms median septum(2);The steel arch-shelfLower pilot tunnel internal face is arranged on, the steel arch set on lower pilot tunnel internal face FrameGunite concrete is added to form interim inverted arch(6);The I-steel is arranged on lower mid-board internal face, in lower mid-board The I-steel set on wall adds pneumatically placed concrete to form median septum(3);The I-steel, steel grating, steel arch-shelf, steel arch FrameBetween junction pass through connecting plate(4)Connection;The median septum(1)Curve support form is presented;The interval Wall(3)Straight line support form is presented.
2. the first branch structure of straight median septum under song on a kind of two side-wall pilot tunnel bored tunnel according to claim 1, it is special Sign is:The I-steel uses work 25a I-steel.
3. the first branch structure of straight median septum under song on a kind of two side-wall pilot tunnel bored tunnel according to claim 1, it is special Sign is:The connecting plate(4)Using steel plate.
4. the first branch structure of straight median septum under song on a kind of two side-wall pilot tunnel bored tunnel according to claim 1, it is special Sign is:The median septum of the upper mid-board both sides(1)Between form shape space wide at the top and narrow at the bottom.
5. the first branch structure of straight median septum under song on a kind of two side-wall pilot tunnel bored tunnel according to claim 1, it is special Sign is:The median septum of the lower mid-board both sides(3)Between form wide space up and down.
CN201721342938.7U 2017-10-18 2017-10-18 The first branch structure of straight median septum under song on two side-wall pilot tunnel bored tunnel Expired - Fee Related CN207315411U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721342938.7U CN207315411U (en) 2017-10-18 2017-10-18 The first branch structure of straight median septum under song on two side-wall pilot tunnel bored tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721342938.7U CN207315411U (en) 2017-10-18 2017-10-18 The first branch structure of straight median septum under song on two side-wall pilot tunnel bored tunnel

Publications (1)

Publication Number Publication Date
CN207315411U true CN207315411U (en) 2018-05-04

Family

ID=62381763

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721342938.7U Expired - Fee Related CN207315411U (en) 2017-10-18 2017-10-18 The first branch structure of straight median septum under song on two side-wall pilot tunnel bored tunnel

Country Status (1)

Country Link
CN (1) CN207315411U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109751063A (en) * 2019-02-26 2019-05-14 中铁第四勘察设计院集团有限公司 A kind of large section tunnel supporting construction and its construction method
CN109973100A (en) * 2019-05-21 2019-07-05 中铁第六勘察设计院集团有限公司 A kind of support form that realizing Tunneling by mining method minor-circle turn and construction method
CN110566228A (en) * 2019-09-24 2019-12-13 中铁第六勘察设计院集团有限公司 tunnel middle partition wall with repeated jacking and locking functions and construction method thereof
CN110863841A (en) * 2019-11-29 2020-03-06 中交第二航务工程局有限公司 Two-lining three-step construction method for large-span shallow-buried underground excavation tunnel
CN111828051A (en) * 2020-07-28 2020-10-27 中建七局安装工程有限公司 Construction method of two-lining middle partition wall injection tunnel with support
CN112253139A (en) * 2020-11-03 2021-01-22 中铁隆工程集团有限公司 Construction method for channel range main hole excavation flow

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109751063A (en) * 2019-02-26 2019-05-14 中铁第四勘察设计院集团有限公司 A kind of large section tunnel supporting construction and its construction method
CN109973100A (en) * 2019-05-21 2019-07-05 中铁第六勘察设计院集团有限公司 A kind of support form that realizing Tunneling by mining method minor-circle turn and construction method
CN109973100B (en) * 2019-05-21 2024-02-09 中铁第六勘察设计院集团有限公司 Supporting form for realizing small-radius turning of tunnel by mining method and construction method
CN110566228A (en) * 2019-09-24 2019-12-13 中铁第六勘察设计院集团有限公司 tunnel middle partition wall with repeated jacking and locking functions and construction method thereof
CN110566228B (en) * 2019-09-24 2024-02-09 中铁第六勘察设计院集团有限公司 Tunnel middle partition wall with repeated supporting and locking functions and construction method thereof
CN110863841A (en) * 2019-11-29 2020-03-06 中交第二航务工程局有限公司 Two-lining three-step construction method for large-span shallow-buried underground excavation tunnel
CN111828051A (en) * 2020-07-28 2020-10-27 中建七局安装工程有限公司 Construction method of two-lining middle partition wall injection tunnel with support
CN111828051B (en) * 2020-07-28 2022-04-15 中建七局安装工程有限公司 Construction method of two-lining middle partition wall injection tunnel with support
CN112253139A (en) * 2020-11-03 2021-01-22 中铁隆工程集团有限公司 Construction method for channel range main hole excavation flow

Similar Documents

Publication Publication Date Title
CN207315411U (en) The first branch structure of straight median septum under song on two side-wall pilot tunnel bored tunnel
CN105386778B (en) Tunnel excavation lining construction chassis and tunnel excavation lining construction method
CN205422813U (en) Detachable filling and retaining wall
CN106869172A (en) In-situ deposited prefabricated split-mounting type subway underground station construction method
CN203905966U (en) Lining mold used for at-one-time concrete pouring of tunnel inverted arch structure
CN203034467U (en) Combined steel pile cofferdam with water-proof fore shafts
CN102733827A (en) Tunnel arch exchanging construction method and construction structure in tunnel arch exchanging construction
CN101852083A (en) Quick supporting method for large-deformation roadway easy to fall, break and loosen and apparatus thereof
CN101864960A (en) Carst region double-arch road tunnel construction method
CN106761778A (en) A kind of underground digging in subway station construction technology suitable for upper-soft lower-hard ground
CN101864959A (en) Method for tunneling construction of main structure of underground station
CN106381926A (en) Detachable assembly type splicing node for reinforced concrete columns
CN106014446B (en) A kind of reinforcement means of enhancing high ground stress soft rock stress tunnel inverted arch structural stability
CN107725064A (en) Tunnel partition wall structure and the method that tunnel step excavation is realized using middle-wall method
CN106930777A (en) The construction method of the lining of Bored Section of Metro main track assembled two
CN208280965U (en) Coal mine deep well tunnel smooth surface concrete spraying support structure
CN103470272A (en) Trolley for concrete construction on multiple sections by employing mining method and construction method thereof
CN106223967A (en) A kind of great burying rectangle or class Rectangular Tunnel shield-tunneling construction device and method
CN104389612A (en) Treatment method for tunnel local collapse
CN109184704B (en) Small clear distance tunnel excavation and middle rock clamping reinforcement technology
CN103939113A (en) Suspension rail type construction trolley
CN108590680A (en) A kind of construction method that launching shaft foundation pit vertical section pours
CN107313787A (en) A kind of tunnel lining trolley end mould and construction method
CN107191006B (en) Dismantling and repairing method for refractory concrete layer of diversion trench
CN203499697U (en) Trolley used for concrete construction of various cross sections through mining method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 300350 Tianjin city Jinnan District double Township

Co-patentee after: CHINA RAILWAY 18 BUREAU GROUP MUNICIPAL ENGINEERING Co.,Ltd.

Patentee after: CHINA RAILWAY 18 BUREAU GROUP Co.,Ltd.

Address before: 300350 Tianjin city Jinnan District double Township

Co-patentee before: CHINA RAILWAY 18 BUREAU GROUP TRACK TRAFFIC PROJECT Co.,Ltd.

Patentee before: CHINA RAILWAY 18 BUREAU GROUP Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180504