CN207314299U - A kind of arrangement of the narrow steep full tunnel-spillway in river valley bank - Google Patents
A kind of arrangement of the narrow steep full tunnel-spillway in river valley bank Download PDFInfo
- Publication number
- CN207314299U CN207314299U CN201721155732.3U CN201721155732U CN207314299U CN 207314299 U CN207314299 U CN 207314299U CN 201721155732 U CN201721155732 U CN 201721155732U CN 207314299 U CN207314299 U CN 207314299U
- Authority
- CN
- China
- Prior art keywords
- control
- spillway
- arrangement
- approach channel
- channel hole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000011144 upstream manufacturing Methods 0.000 claims abstract description 4
- 238000010276 construction Methods 0.000 abstract description 11
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances data:image/svg+xml;base64,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 data:image/svg+xml;base64,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 O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 abstract description 4
- 238000009412 basement excavation Methods 0.000 abstract description 2
- 230000000903 blocking Effects 0.000 abstract description 2
- 238000007599 discharging Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000006011 modification reaction Methods 0.000 description 1
- 239000011148 porous material Substances 0.000 description 1
Abstract
The utility model discloses a kind of arrangement of the narrow steep full tunnel-spillway in river valley bank, including approach channel hole section, control section and the barrel section being arranged in massif, approach channel hole section is located at control section upstream side, control section downstream connects with barrel section, and approach channel hole section and control section also are disposed in massif.The approach channel hole section is free-flow spillway tunnel, and horizontal layout is combined using straight line with bend, and section is gateway opening type, and the wide Parallel to the flow direction in hole is descending, and hole height is constant.The overcurrent weir-type of the control section is practical weir, to improve water blocking elevation, increases conveyance capacity.The arrangement of the utility model, avoids a wide range of excavation of the steep side slope of spillway import, reduces high slope, avoids construction interference of the narrow steep River Valley Slope construction to dam foundation pit, ensure that the duration of a project.
Description
Technical field
A kind of arrangement of hydraulic and hydroelectric engineering spillway on bank is the utility model is related to, more particularly, to a kind of narrow
The arrangement of the steep full tunnel-spillway in river valley bank.
Background technology
Spillway on bank in hydraulic and hydroelectric engineering, since water inlet elevation is higher, so the current in spillway are
Without pressure free flow, its arrangement also has a kind of common arrangement " to draw in addition to " approach channel section+control section+lets out groove section "
Canal section+control section+barrel section ".Second of arrangement is bank tunnel-spillway, it is generally the case that bank tunnel-spillway
Import approach channel section arranges that control section is arranged in massif using the tower arrangement of bank built by the mountain, barrel section using open channel.Work as work
Position river valley where journey is narrow, bank slope is steep, during tower using bank using open channel, the control section arrangement of import approach channel section, import department
Position easily forms and excavates high slope, simultaneously because spillway import is close apart from dam, spillway import position is constructed to dam
Foundation pit construction interference is very big, and dam construction is often the key for controlling the duration, so the arrangement of research spillway, especially
It is that research avoids construction interference, the import arrangement of reduction high slope from being highly desirable.
Free-flow spillway tunnel in hydraulic and hydroelectric engineering, to meet flow-shape requirement in hole, generally using straight line, when
When arrangement is limited to be needed to turn, the arrangement of bend free-flow spillway tunnel just becomes the key technical problem for needing to study.
On the overcurrent weir-type of control section, there is pressure flood discharge on the tower control section of bank of either spillway on bank, or bank
Hole is arranged in the control section in massif, its overcurrent weir-type is using flat weir or hump weir, when needing to improve conveyance capacity,
It is necessary the practical weir of research conveyance capacity higher.
Utility model content
Technical problem to be solved in the utility model is to provide a kind of narrow steep full tunnel-spillway in river valley bank
Arrangement, solves the interference problem of narrow steep river valley construction, reduces slope height.
Technical solution is used by the utility model:A kind of arrangement knot of the narrow steep full tunnel-spillway in river valley bank
Structure, including approach channel hole section, control section and the barrel section being arranged in massif, approach channel hole section are located at control section upstream side, control section
Downstream connects with barrel section, and approach channel hole section and control section also are disposed in massif.
Approach channel hole section is free-flow spillway tunnel, and horizontal layout is combined using straight line with bend, and section is gateway opening type, hole
Wide Parallel to the flow direction is descending, and hole height is constant.
The overcurrent weir-type of the control section is practical weir, to improve water blocking elevation, increases conveyance capacity.
The beneficial effects of the utility model are:
(1) arrangement of the narrow steep full tunnel-spillway in river valley bank, because approach channel hole section and control section use ground
Lower the cavern layout, reduces import slope height and difficulty of construction;
(2) since spillway import is close to dam arrangement, the underground chamber arrangement that approach channel hole section is used with control section,
Avoid spillway import construction to dam foundation pit construction interference, it is ensured that the duration of a project, have good social benefit and
Economic benefit, provides mentality of designing and reference for similar engineering bank flood discharging tunnel arrangement, has reference.
Brief description of the drawings
Fig. 1 is the arrangement floor map of the narrow steep full tunnel-spillway in river valley bank of the utility model.
Fig. 2 is the profile of Fig. 1.
In figure:1-approach channel hole section;2-control section;3-barrel section.
Embodiment
The utility model is described in further detail with reference to the accompanying drawings and detailed description:
As depicted in figs. 1 and 2, the arrangement of the narrow steep full tunnel-spillway in river valley bank of the utility model, bag
Approach channel hole section 1, control section 2 and the barrel section 3 being arranged in massif are included, approach channel hole section 1 is located at 2 upstream side of control section, control section 2
Downstream connects with barrel section 3, and approach channel hole section 1 and control section 2 also are disposed in massif.
The approach channel hole section 1 is free-flow spillway tunnel, and horizontal layout is combined using straight line with bend, and section is gateway opening type,
The wide Parallel to the flow direction in hole is descending, and hole height is constant.
The overcurrent weir-type of the control section 2 is practical weir.
It is described in detail with reference to embodiment:
Certain big (2) type Hydropower Project, the narrow bank slope in river valley is steep, and it is attached that the full tunnel-spillway import in bank is located at dam
Closely.The arrangement of spillway import is tower according to conventional bank, then import side slope maximum excavation height about 135m, side slope branch
It is big to protect quantities, disturbs dam foundation pit construction, influences the crucial duration of engineering.To solve the above problems, spillway import approach channel
Section and control section are arranged in massif.
As depicted in figs. 1 and 2, approach channel hole section 1, control section 2 and barrel section 3, are arranged in massif.
Approach channel hole section 1 be free flow tunnel, the horizontal layout being combined using straight line with bend, to meet that import hydraulics is wanted
To ask, the stability of increase import position underground chamber, straightway import both sides use tubaeform arrangement, and in tunnel intermediate arrangement
Dividing pier.Approach channel hole 1 centerline length of section is 94m, and base slope 0, section is gateway opening type, and cross dimensions is (wide for 12-26 × 25m
× high), control flow rate of water flow is not more than 5m/s.
Control section 2 is arranged in the straightway downstream of approach channel hole section 1, long 28.43m, and overcurrent weir-type is practical weir, and weir is high
8.0m, if a gate hole, lock pore size is 12.0m × 10.0m.
Barrel section 3 is arranged in 2 downstream of control section, is connected by transition with control section 2, sectional form is gateway opening
Type, cross dimensions are 12-8 × 10.5-9m (wide × high).
The import arrangement of spillway, fully combines the steep topographic and geologic condition of the narrow bank slope in import position river valley,
Approach channel hole section and control section are arranged in massif, solve the problems, such as the high slope that open intake arrangement is brought, and
Spillway import is constructed construction interference problem to dam foundation pit, ensure that the duration of a project, obtain good social benefit and
Economic benefit.
Embodiment described above is merely to illustrate the technological thought and feature of the utility model, and its object is to make ability
Technical staff in domain is it will be appreciated that the content of the utility model and implement according to this, it is impossible to only limits this practicality with the present embodiment
New the scope of the claims, i.e., the equal change or modification that all revealed spirit of the utility model is made, still can be new in this practicality
In the scope of the claims of type.
Claims (3)
1. a kind of arrangement of the narrow steep full tunnel-spillway in river valley bank, including approach channel hole section (1), control section (2) and
The barrel section (3) being arranged in massif, approach channel hole section (1) are located at control section (2) upstream side, control section (2) downstream and barrel
Section (3) connects, it is characterised in that approach channel hole section (1) and control section (2) also are disposed in massif.
2. the arrangement of the narrow steep full tunnel-spillway in river valley bank according to claim 1, it is characterised in that described
Approach channel hole section (1) is free-flow spillway tunnel, and horizontal layout is combined using straight line with bend, and section is gateway opening type, and hole is wide to flow downstream
Direction is descending, and hole height is constant.
3. the arrangement of the narrow steep full tunnel-spillway in river valley bank according to claim 1, it is characterised in that described
The overcurrent weir-type of control section (2) is practical weir.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721155732.3U CN207314299U (en) | 2017-09-11 | 2017-09-11 | A kind of arrangement of the narrow steep full tunnel-spillway in river valley bank |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721155732.3U CN207314299U (en) | 2017-09-11 | 2017-09-11 | A kind of arrangement of the narrow steep full tunnel-spillway in river valley bank |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207314299U true CN207314299U (en) | 2018-05-04 |
Family
ID=62385841
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721155732.3U Active CN207314299U (en) | 2017-09-11 | 2017-09-11 | A kind of arrangement of the narrow steep full tunnel-spillway in river valley bank |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207314299U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110821521A (en) * | 2019-11-15 | 2020-02-21 | 中铁建大桥工程局集团第五工程有限公司 | Construction method for excavation and support of hydropower station spillway cavern |
-
2017
- 2017-09-11 CN CN201721155732.3U patent/CN207314299U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110821521A (en) * | 2019-11-15 | 2020-02-21 | 中铁建大桥工程局集团第五工程有限公司 | Construction method for excavation and support of hydropower station spillway cavern |
CN110821521B (en) * | 2019-11-15 | 2021-08-20 | 中铁建大桥工程局集团第五工程有限公司 | Construction method for excavation and support of hydropower station spillway cavern |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103410130B (en) | Multi-purpose tunnel arrangement structure | |
CN207314299U (en) | A kind of arrangement of the narrow steep full tunnel-spillway in river valley bank | |
CN104963322B (en) | A kind of key water control project facility | |
CN204163057U (en) | A kind of for the blocking dam in mud-rock flow | |
CN203821344U (en) | Forward water inlet and sand sluicing flush gallery structure of hydropower station | |
CN205475065U (en) | Tower import crowd combined layout structure of steep narrow many holes of river valley of side slope bank | |
CN103195029A (en) | Lateral-inflow and rolling-energy-dissipation bank spillway | |
CN210395267U (en) | Asymmetric open type spillway | |
CN109356097A (en) | The water discharge tunnel makeup of the imports for ditch water process | |
CN103290804A (en) | Method and structure for providing downstream ecological flow after gate locking of stream guidance water release structure | |
CN203144971U (en) | Debris flow drainage structure combining open channel and box culvert | |
CN204849678U (en) | Novel butyl dam structure | |
CN209429047U (en) | The water discharge tunnel makeup of the imports for ditch water process | |
CN204715315U (en) | A kind of separating inlet mouth arrangement | |
CN204875721U (en) | Diversion tunnel export energy absorber | |
CN103614986B (en) | It a kind of is applicable to the pressure free current inlet method that Tailings Dam drains off floodwaters | |
CN108755619B (en) | Side-channel type spillway for reservoir flood discharge | |
CN207314298U (en) | A kind of arrangement of hydraulic and hydroelectric engineering bank flood discharging tunnel | |
CN203393688U (en) | Multipurpose tunnel arrangement structure | |
CN210288301U (en) | Dam body flood discharge structure suitable for severe cold high earthquake area | |
CN103243692B (en) | The Construction Arrangement method that water conservancy diversion combines with flood discharge | |
Rajaei et al. | Laboratory Analysis of Energy Losses in Gabion Steeped Spillways With and Without Sedimentation at Upstream | |
CN203307783U (en) | Ring-type thin-wall weir head structure of spillway of vertical shaft | |
CN207958878U (en) | A kind of traffic aisle for local material dam | |
CN203383184U (en) | Step type ecological landscape water retaining dam suitable for city watercourse |