CN207312923U - A kind of heavy-duty steel component hanging apparatus - Google Patents

A kind of heavy-duty steel component hanging apparatus Download PDF

Info

Publication number
CN207312923U
CN207312923U CN201721304195.4U CN201721304195U CN207312923U CN 207312923 U CN207312923 U CN 207312923U CN 201721304195 U CN201721304195 U CN 201721304195U CN 207312923 U CN207312923 U CN 207312923U
Authority
CN
China
Prior art keywords
column
right sides
heavy
sliding part
hanging apparatus
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721304195.4U
Other languages
Chinese (zh)
Inventor
李林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shaanxi Chen Kun Steel Structure Co Ltd
Original Assignee
Shaanxi Chen Kun Steel Structure Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shaanxi Chen Kun Steel Structure Co Ltd filed Critical Shaanxi Chen Kun Steel Structure Co Ltd
Priority to CN201721304195.4U priority Critical patent/CN207312923U/en
Application granted granted Critical
Publication of CN207312923U publication Critical patent/CN207312923U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model provides a kind of heavy-duty steel component hanging apparatus,It is related to lifting technical field,Including base,The left and right sides is arranged with column above base,Column bottom is equipped with left and right sides of mounting base mounting base and is equipped with mounting hole,The slide of above-below direction is arranged with left and right sides of column,Sliding part is arranged with column,The left and right sides is arranged with several rollers inside sliding part,Roller is arranged in slide,Several steel wire ropes are equipped with the inside of sliding part,The fixing end of steel wire rope is fixedly connected with sliding part,The movable end of steel wire rope is divided into two strands,Hook is equipped with per strand steel wire rope,Fixed pulley is equipped with the top of column,The outside of sliding part is equipped with lifting rope,Chassis interior is equipped with hydraulic lifting post,Hydraulic lifting post upper end is fixedly connected with top plate,The utility model has simple in structure,It is easy to use,The advantages of safe,The stabilization of heavy-duty steel component can be maintained in hoisting process,Make it accurate in place.

Description

A kind of heavy-duty steel component hanging apparatus
Technical field
It the utility model is related to lifting technical field, and in particular to a kind of heavy-duty steel component hanging apparatus.
Background technology
With the rapid economic development in our country, the rigid demand of the development of each enterprise, its workshop is also with expanding economy Scale constantly increases.Steel-structure factory building is because construction-time is short, intensity is high, lightweight, energy saving, durable, economy, plasticity and good toughness etc. Feature, enables steel-structure factory building industry to be applied on a large scale in industry and life.
Heavy-duty steel lifting component used in conventional steel-structure factory building is lifted by crane by large scale hoisting machinery, by heavy type Steel steel member is promoted to certain altitude and position from ground, is then installed or is moved on vehicle and is transported, due to Steel member weight is big, and size is big, is easily influenced in hoisting process by ambient wind, accurate in place very difficult, and when wind is big Easily rock, cause to tilt, there is some potential safety problems.
Utility model content
(One)The technical problem of solution
In view of the deficiencies of the prior art, the utility model provides a kind of heavy-duty steel component hanging apparatus, has structure letter It is single, it is easy to use, it is safe the advantages of, the stabilization of heavy-duty steel component can be maintained in hoisting process, makes it accurately in place.
(Two)Technical solution
In order to achieve the above object, the utility model is achieved by the following technical programs:
A kind of heavy-duty steel component hanging apparatus, including base, the base top left and right sides is arranged with column, described Column bottom, which is equipped with left and right sides of mounting base described in mounting base, is equipped with mounting hole, and fixing bolt is through the mounting hole by described in Mounting base is fixedly connected with the base, is equipped with reinforcing prop on the outside of the column, the reinforcing prop upper end is fixed with the column Connection, the reinforcing prop lower end also are provided with mounting hole, and fixing bolt passes through the mounting hole by the reinforcing prop and the base It is fixedly connected, the slide of above-below direction is arranged with left and right sides of the column, sliding part, the cunning are arranged with the column The left and right sides is arranged with several rollers inside moving part, and the roller is arranged in the slide, on the inside of the sliding part Equipped with several steel wire ropes, the fixing end of the steel wire rope is fixedly connected with the sliding part, the movable end point of the steel wire rope Into two strands, hook is equipped with every strand steel wire rope, fixed pulley is equipped with the top of the column, the outside of the sliding part, which is equipped with, hangs Rope, respectively around being fixedly connected after the fixed pulley of the left and right sides, the chassis interior is equipped with the lifting rope of the left and right sides Hydraulic lifting post, the hydraulic lifting post upper end are fixedly connected with top plate, several supporting blocks are equipped with above the top plate.
Further, several shafts, the shaft are uniformly provided with from top to bottom on inner wall at left and right sides of the sliding part It is equipped with the roller.
Further, the junction of the left and right sides lifting rope is connected with the suspension hook of hoisting machinery.
Further, the top plate is located between the column of the left and right sides.
Further, the supporting block is arcuate structure.
Further, the column and the sliding part are four-prism type.
Further, the quantity of the hydraulic lifting post for 2 and is symmetrical set.
(Three)Beneficial effect
The utility model provides a kind of heavy-duty steel component hanging apparatus, has the advantages that:
The steel wire rope of the left and right sides can mutually be mounted by hook, and wherein one is arranged on heavy-duty steel component in steel wire rope Side, another stock are arranged on below heavy-duty steel component, and two strand steel wire ropes can effectively fix heavy-duty steel component, pass through column and steel Cord can effectively maintain the stabilization of heavy-duty steel component in hoisting process, make it will not be because of ambient wind or unbalance stress Even run-off the straight displacement, causes security risk or inaccurate influence transport in place and installation, and the present apparatus is simple in structure, holds It is quick detachable and mobile, it is easy to use, influenced by construction site small.
Brief description of the drawings
In order to illustrate the embodiment of the utility model or the technical proposal in the existing technology more clearly, below will be to embodiment Or attached drawing needed to be used in the description of the prior art is briefly described, it should be apparent that, drawings in the following description are only It is some embodiments of the utility model, for those of ordinary skill in the art, in the premise not made the creative labor Under, other attached drawings can also be obtained according to these attached drawings.
Fig. 1 is the structure diagram of the utility model;
Fig. 2 is by the structure diagram after heavy-duty steel lifting component with steel wire rope;
Figure label represents respectively:
1st, base;2nd, hydraulic lifting post;3rd, top plate;4th, column;5th, supporting block;6th, mounting base;7th, ribs;8th, slide; 9th, sliding part;10th, roller;11st, fixed pulley;12nd, suspension hook.
Embodiment
It is new below in conjunction with this practicality to make the purpose, technical scheme and advantage of the utility model embodiment clearer Attached drawing in type embodiment, the technical scheme in the utility model embodiment is clearly and completely described, it is clear that is retouched The embodiment stated is the utility model part of the embodiment, instead of all the embodiments.Based on the implementation in the utility model Example, those of ordinary skill in the art's all other embodiments obtained without creative efforts, belongs to The scope of the utility model protection.
A kind of heavy-duty steel component hanging apparatus, including base 1, the top of base 1 left and right sides are arranged with column 4, column 4 Bottom is equipped with mounting base 6, and the left and right sides of mounting base 6 is equipped with mounting hole, and fixing bolt passes through mounting hole by mounting base 6 and base 1 is fixedly connected, and the outside of column 4 is equipped with reinforcing prop 7, and 7 upper end of reinforcing prop is fixedly connected with column 4, and 7 lower end of reinforcing prop also is provided with solid Determine hole, reinforcing prop 7 is fixedly connected by fixing bolt through mounting hole with base 1, and the left and right sides of column 4 is arranged with above-below direction Slide 8, sliding part 9 is arranged with column 4, the inside of sliding part 9 left and right sides is arranged with several rollers 10, and roller 10 is equal It is arranged in slide 8, the inner side of sliding part 9 is equipped with several steel wire ropes, and the fixing end of steel wire rope is fixedly connected with sliding part 9, steel The movable end of cord is divided into two strands, and per being equipped with hook on strand steel wire rope, the top of column 4 is equipped with fixed pulley 11, sliding part 9 outside Side is equipped with lifting rope, and for the lifting rope of the left and right sides respectively around being fixedly connected after the fixed pulley 11 of the left and right sides, base 1 is internally provided with liquid Lifting column 2 is pressed, 2 upper end of hydraulic lifting post is fixedly connected with top plate 3, and the top of top plate 3 is equipped with several supporting blocks 5.
Wherein, several shafts are uniformly provided with 9 left and right sides inner wall of sliding part from top to bottom, shaft is equipped with roller 10。
Wherein, the junction of left and right sides lifting rope is connected with the suspension hook 12 of hoisting machinery.
Wherein, top plate 3 is between left and right sides column 4.
Wherein, supporting block 5 is arcuate structure.
Wherein, column 4 and sliding part 9 are four-prism type.
Wherein, the quantity of hydraulic lifting post 2 for 2 and is symmetrical set.
One embodiment of the utility model is:
Steel member is placed on top plate 3, and after hydraulic lifting post 2 rises to certain altitude, the steel wire rope of the left and right sides is passed through Hook mutually mounts, steel wire rope wherein one be arranged on above heavy-duty steel component, another stock is arranged on heavy type after passing through supporting block 5 Below steel member, the suspension hook 12 of hoisting machinery, which is above carried, to be lifted steel member and continues up, and hydraulic lifting post 2 is contracted to bottom In seat 1, transport vehicle opens upper bed-plate 1, and between transport vehicle left and right wheels, the suspension hook 12 of hoisting machinery declines top plate 3, by steel structure Part is placed on transport vehicle, and the steel wire rope of the left and right sides is separated, and completes lifting.
It should be noted that herein, relational terms such as first and second and the like are used merely to a reality Body or operation are distinguished with another entity or operation, are deposited without necessarily requiring or implying between these entities or operation In any this actual relation or order.Moreover, term " comprising ", "comprising" or its any other variant are intended to Non-exclusive inclusion, so that process, method, article or equipment including a series of elements not only will including those Element, but also including other elements that are not explicitly listed, or further include as this process, method, article or equipment Intrinsic key element.In the absence of more restrictions, the key element limited by sentence "including a ...", it is not excluded that Also there are other identical element in process, method, article or equipment including the key element.
Above example is only to illustrate the technical solution of the utility model, rather than its limitations;Although with reference to foregoing reality Example is applied the utility model is described in detail, it will be understood by those of ordinary skill in the art that:It still can be to preceding State the technical solution described in each embodiment to modify, or equivalent substitution is carried out to which part technical characteristic;And these Modification is replaced, and the essence of appropriate technical solution is departed from the spirit and model of various embodiments of the utility model technical solution Enclose.

Claims (7)

1. a kind of heavy-duty steel component hanging apparatus, including base(1), it is characterised in that the base(1)It is right at left and right sides of top Title is equipped with column(4), the column(4)Bottom is equipped with mounting base(6), the mounting base(6)The left and right sides is equipped with mounting hole, Fixing bolt passes through the mounting hole by the mounting base(6)With the base(1)It is fixedly connected, the column(4)Outside is set There is reinforcing prop(7), the reinforcing prop(7)Upper end and the column(4)It is fixedly connected, the reinforcing prop(7)Lower end also is provided with solid Determine hole, fixing bolt passes through the mounting hole by the reinforcing prop(7)With the base(1)It is fixedly connected, the column(4)It is left Right both sides are arranged with the slide of above-below direction(8), the column(4)On be arranged with sliding part(9), the sliding part(9)It is interior Several rollers are arranged with left and right sides of portion(10), the roller(10)It is arranged at the slide(8)It is interior, the sliding part (9)Inner side is equipped with several steel wire ropes, the fixing end of the steel wire rope and the sliding part(9)It is fixedly connected, the steel wire rope Movable end be divided into two strands, be equipped with hook, the column per on strand steel wire rope(4)Top is equipped with fixed pulley(11), the cunning Moving part(9)Outside be equipped with lifting rope, the lifting rope of the left and right sides bypasses the fixed pulley of the left and right sides respectively(11)It is solid afterwards Fixed connection, the base(1)It is internally provided with hydraulic lifting post(2), the hydraulic lifting post(2)Upper end and top plate(3)It is fixed to connect Connect, the top plate(3)Top is equipped with several supporting blocks(5).
2. heavy-duty steel component hanging apparatus as claimed in claim 1, it is characterised in that the sliding part(9)In the left and right sides Several shafts are uniformly provided with wall from top to bottom, the shaft is equipped with the roller(10).
3. heavy-duty steel component hanging apparatus as claimed in claim 1, it is characterised in that the junction of the left and right sides lifting rope With the suspension hook of hoisting machinery(12)It is connected.
4. heavy-duty steel component hanging apparatus as claimed in claim 1, it is characterised in that the top plate(3)Positioned at the left and right sides The column(4)Between.
5. heavy-duty steel component hanging apparatus as claimed in claim 1, it is characterised in that the supporting block(5)For arcuate structure.
6. heavy-duty steel component hanging apparatus as claimed in claim 1, it is characterised in that the column(4)With the sliding part (9)It is four-prism type.
7. heavy-duty steel component hanging apparatus as claimed in claim 1, it is characterised in that the hydraulic lifting post(2)Quantity For 2 and it is symmetrical set.
CN201721304195.4U 2017-10-11 2017-10-11 A kind of heavy-duty steel component hanging apparatus Expired - Fee Related CN207312923U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721304195.4U CN207312923U (en) 2017-10-11 2017-10-11 A kind of heavy-duty steel component hanging apparatus

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721304195.4U CN207312923U (en) 2017-10-11 2017-10-11 A kind of heavy-duty steel component hanging apparatus

Publications (1)

Publication Number Publication Date
CN207312923U true CN207312923U (en) 2018-05-04

Family

ID=62429302

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721304195.4U Expired - Fee Related CN207312923U (en) 2017-10-11 2017-10-11 A kind of heavy-duty steel component hanging apparatus

Country Status (1)

Country Link
CN (1) CN207312923U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111501561A (en) * 2020-04-20 2020-08-07 台州蓝锐机电科技有限公司 Installation and construction method of steel structure truss

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111501561A (en) * 2020-04-20 2020-08-07 台州蓝锐机电科技有限公司 Installation and construction method of steel structure truss

Similar Documents

Publication Publication Date Title
CN106760197A (en) A kind of method that allowable error is installed in steel column structure and its control
CN111042540A (en) Construction method for aerial butt joint of ground suspension cables of super-large-span prestressed pipe truss
CN207312923U (en) A kind of heavy-duty steel component hanging apparatus
CN206233122U (en) For bridge cantilever construction with Hanging Basket movable tower crane
CN105781205A (en) In-place guiding device for segmented hoisting and air pairing of heavy tower equipment
CN206308626U (en) Operating platform for installing hanging basket at top of pier body of pier
CN105645275A (en) Cable hoisting crane and construction method thereof
CN1048065C (en) Method and equipment for construction of concrete cylinder
CN203613464U (en) Slip form construction cargo transportation device
CN206174481U (en) Jack -up instrument is used in fan hoist and mount of tuber pipe and suspension type installation
CN205976394U (en) Convenient low layer construction scaffolding
CN211871214U (en) Three-telescopic-rod double-beam bridge crane and anti-deviation device
CN210658056U (en) Bridge steel stand hoist and mount device of turning
CN203602284U (en) Pulley bracket and rotary drilling rig
CN207538207U (en) A kind of steel structural upright column
CN209957241U (en) Steel hanger
CN205935720U (en) Steel truss frame that slides
CN206917297U (en) A kind of large-span steel girder upper air installing system in place
CN206665957U (en) A kind of detachable auxiliary hanger
CN205170164U (en) Balanced title of lever
CN205688822U (en) Heavy component transportation system after reverse construction method disassembly
CN205634685U (en) Cable crane hoist
CN209142773U (en) A kind of prefabricated components storing unit
CN209322324U (en) A kind of large form handling apparatus
CN219489414U (en) Double-cableway temporary bearing horse for main cable crossing river of cable machine

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180504

Termination date: 20201011

CF01 Termination of patent right due to non-payment of annual fee