CN207260155U - The balanced moving trolley of concrete cast - Google Patents

The balanced moving trolley of concrete cast Download PDF

Info

Publication number
CN207260155U
CN207260155U CN201721036256.3U CN201721036256U CN207260155U CN 207260155 U CN207260155 U CN 207260155U CN 201721036256 U CN201721036256 U CN 201721036256U CN 207260155 U CN207260155 U CN 207260155U
Authority
CN
China
Prior art keywords
main body
compartment main
hopper
moving trolley
base
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721036256.3U
Other languages
Chinese (zh)
Inventor
徐振家
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Haimen Luqiao Construction Co Ltd
Original Assignee
Haimen Luqiao Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Haimen Luqiao Construction Co Ltd filed Critical Haimen Luqiao Construction Co Ltd
Priority to CN201721036256.3U priority Critical patent/CN207260155U/en
Application granted granted Critical
Publication of CN207260155U publication Critical patent/CN207260155U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model discloses a kind of concrete to pour into a mould balanced moving trolley,Including compartment main body,Hopper,Base,Compartment main body is rectangular box body,The lower end of compartment main body is fixedly connected with the upper end of base,Hopper is funnel-form,Upper end is big mouth,Lower end is osculum,Hopper is installed on the top of compartment main body,Uniform intervals are fixedly connected with the upper end of four supporting rods around the big mouth in upper end of hopper,Four supporting rod lower ends are fixedly connected with base,Compartment main body is wrapped in interior by the space that four supporting rods are formed,The upper end of compartment main body is provided with and the corresponding feed inlet of hopper osculum,The bottom of two opposite flanks of compartment main body corresponds and is provided with two discharge ports,The lower end of base is evenly arranged with four directive wheels,Lower end in compartment main body corresponding to feed inlet is provided with triangle deflector,The vertex correspondence of deflector is set in the lower end of feed inlet,The base of deflector extends to the both sides of compartment main body and is connected with discharge port.

Description

The balanced moving trolley of concrete cast
Technical field
The utility model belongs to building machinery field, and in particular to a kind of piping lane construction pours into a mould balanced walking with concrete Car.
Background technology
The concrete cast of piping lane side wall fails both sides balanced charging at the same time on request, causes mold bending, integral shift Quality accident.Meanwhile because wall steel bar is higher by plane 20-30cm in template, the cavity of wall is narrow in addition, mechanization pump truck It cannot be introduced into inside cavity, when construction causes a large amount of concrete to fall on the outside of template, causes to waste and pollutes, and controls both sides wall Charging at the same time is limited to manual control, and displacement bias happens occasionally, and speed is low.
Utility model content
To solve the problem above-mentioned, the utility model provides a kind of balanced moving trolley of concrete cast, including compartment main body 1st, hopper 2, base 3, the compartment main body 1 are rectangular box body, and the lower end and the upper end of base 3 of the compartment main body 1 are fixed Connection, the hopper 2 is funnel-form, and upper end is big mouth, and lower end is osculum, and the hopper 2 is installed on the upper of the compartment main body 1 Square, uniform intervals are fixedly connected with the upper end of four supporting rods 4 around the big mouth in upper end of the hopper 2, four supporting rods 4 Lower end is fixedly connected with the base 3, and the compartment main body 1 is wrapped in interior, institute by the space that four supporting rods 4 are formed The upper end for stating compartment main body 1 is provided with and the corresponding feed inlet 15 of 2 osculum of hopper, two phases of the compartment main body 1 Two discharge ports 7 are provided with to the bottom one-to-one corresponding of side, the lower end of the base 3 is evenly arranged with four directive wheels 5, institute State the lower end in compartment main body 1 corresponding to the feed inlet 15 and be provided with triangle deflector 6, the vertex pair of the deflector 6 The lower end of feed inlet 15 described in Ying Yu is set, the base of the deflector 6 extend to the both sides of the compartment main body 1 and with it is described Discharge port 7 connects.
Preferably, shunt regulator device 8 is provided with the compartment main body 1, the shunt regulator device 8 includes support Plate 81, swing handle 82, turbine reduction box 83, rotation axis 84, flow distribution plate 85, the rotation axis 84 are installed on the compartment main body Between 1 two other opposite flank, and one end extends to the outside of the compartment main body 1, and the flow distribution plate 85 is installed on In the rotation axis 84 and the lower section at 15 center of feed inlet is arranged on, it is right that the support plate 81 is arranged on compartment main body 1 The side that rotation axis 84 described in Ying Yu extends, the turbine reduction box 83 is fixed at the upper end of the support plate 81, described Swing handle 82 is arranged on 83 outer wall of turbine reduction box, the swing handle 82 and the whirlpool in the turbine reduction box 83 Wheel connects, and the worm screw in the turbine reduction box 83 is connected with the rotation axis 84.
Preferably, it is provided with dispensing valve 9 on the osculum of the lower end of the hopper 2.
Preferably, there are horizontally arranged sunshading board 10 in the upper end both sides of the hopper 2.
Preferably, the compartment main body 1 is provided with stent 11 close to the side of the discharge port 7, and the stent 11 extends To the outside of the discharge port 7 to pre-determined distance, there is the first splash-back 12 being vertically arranged in the outer end of the stent 11.
Preferably, the second splash-back 13 being vertically arranged is arranged at the bottom that the compartment main body 1 corresponds to the discharge port 7.
Preferably, it is separated by pre-determined distance between first splash-back 12 and second splash-back 13.
Preferably, there is the reinforcing rib 14 that uniform intervals are set on first splash-back 12.
The concrete of the utility model pours into a mould balanced moving trolley, and shunt regulator device is provided with compartment main body, and shunting is adjusted Regulating device includes support plate, swing handle, turbine reduction box, rotation axis, flow distribution plate, and support plate is arranged on the one of compartment main body Side, turbine reduction box are fixed at the upper end of support plate, and swing handle is arranged on turbine deceleration box outer wall, swing handle with Turbine in turbine reduction box connects, and the worm screw in turbine reduction box passes through turbine reduction box one with rotating axis connection, rotation axis Side extends to the opposite side of turbine reduction box, and flow distribution plate is vertically arranged in the lower section at feed inlet center, and flow distribution plate is consolidated with rotation axis Fixed connection, the concrete flow quantity on both sides, to ensure the equilibrium of both sides concreting, operation are adjusted by rotary motion handle Simply, several workers construct with regard to concrete can be used to pour into a mould balanced moving trolley, improve construction efficiency.
Brief description of the drawings
Fig. 1 is the front view of the utility model.
Fig. 2 is the side view of the utility model.
Fig. 3 is the usage state diagram of the utility model.
Embodiment
The utility model is described further below in conjunction with attached drawing.
As shown in Figs. 1-2, a kind of balanced moving trolley of concrete cast of the utility model, including compartment main body 1, hopper 2, bottom Seat 3, the compartment main body 1 is rectangular box body, and the lower end of the compartment main body 1 is fixedly connected with the upper end of base 3, the material Bucket 2 is funnel-form, and upper end is big mouth, and lower end is osculum, and the hopper 2 is installed on the top of the compartment main body 1, the hopper Uniform intervals are fixedly connected with the upper end of four supporting rods 4 around the 2 big mouth in upper end, four supporting rods, 4 lower end with it is described Base 3 is fixedly connected, and the compartment main body 1 is wrapped in interior, the compartment main body 1 by the space that four supporting rods 4 are formed Upper end be provided with and the corresponding feed inlet 15 of 2 osculum of hopper, the bottom of two opposite flanks of the compartment main body 1 One-to-one corresponding is provided with two discharge ports 7, and the lower end of the base 3 is evenly arranged with four directive wheels 5, the compartment main body 1 The interior lower end corresponding to the feed inlet 15 is provided with triangle deflector 6, and the vertex correspondence of the deflector 6 is in the charging The lower end of mouth 15 is set, and the base of the deflector 6 extends to the both sides of the compartment main body 1 and is connected with the discharge port 7. Be provided with shunt regulator device 8 in the compartment main body 1, the shunt regulator device 8 include support plate 81, swing handle 82, Turbine reduction box 83, rotation axis 84, flow distribution plate 85, the rotation axis 84 be installed on the compartment main body 1 two other is opposite Between side, and one end extends to the outside of the compartment main body 1, and the flow distribution plate 85 is installed in the rotation axis 84 simultaneously And the lower section at 15 center of feed inlet is arranged on, the support plate 81 is arranged on compartment main body 1 and corresponds to the rotation axis 84 The side of extension, the turbine reduction box 83 are fixed at the upper end of the support plate 81, and the swing handle 82 is arranged on On 83 outer wall of turbine reduction box, the swing handle 82 is connected with the turbine in the turbine reduction box 83, the turbine Worm screw in reduction box 83 is connected with the rotation axis 84, rotates the swing handle 82, adjusts the angle of the flow distribution plate 85, It is left to the flow of both sides concrete respectively with regard to that can adjust.Dispensing valve 9 is provided with the osculum of the lower end of the hopper 2, is used for Control the whereabouts of 2 inner concrete of hopper.There are horizontally arranged sunshading board 10 in the upper end both sides of the hopper 2, with Worker stands when constructing on the base 3, stands on base, prevents being exposed to the sun for the sun.The compartment main body 1 is close to the discharging Mouthfuls 7 side is provided with stent 11, and the stent 11 extends to the outside of the discharge port 7 to pre-determined distance, the stent There is the first splash-back 12 being vertically arranged in 11 outer end.The compartment main body 1 has corresponding to the bottom of the discharge port 7 to be set vertically The second splash-back 13 put, first splash-back 12 and second splash-back 13 sputter when can place concreting Go.It is separated by pre-determined distance between first splash-back 12 and second splash-back 13, limitation concreting is in cavity It is interior.There is the reinforcing rib 14 that uniform intervals are set on first splash-back 12.
As shown in figure 3, the construction technology of concreting equilibrium car, requires according to design drawing, opened naturally on soil 20 Foundation trench is dug, the concrete floor 17 of casting concrete bed course 16 and piping lane on the bottom of foundation trench, then places outer wall backform 19 On the surface of the concrete floor 17, poured in the cavity between the concrete cushion 16 and the outer wall backform 19 Guide rail, is installed on the upper end of the outer wall backform 19 by concrete, and balanced moving trolley is poured into a mould on guide rail using the concrete Walking is poured, and construction personnel can pour situation according in the cavity of both sides, be adjusted by rotating the swing handle 82 The concrete flow quantity on both sides is saved, to ensure the equilibrium of both sides concreting.
The concreting equilibrium car to the utility model in a manner of brief description of the drawings is described above, the skill of this area Art personnel should be appreciated that the present disclosure is not limited to embodiments described above, in the case of without departing from the scope of the utility model, It can make a variety of changes, change and replace.

Claims (8)

1. a kind of balanced moving trolley of concrete cast, including compartment main body (1), hopper (2), base (3), the compartment main body (1) it is rectangular box body, the lower end of the compartment main body (1) is fixedly connected with the upper end of base (3), and the hopper (2) is leakage Bucket-shaped, upper end is big mouth, and lower end is osculum, and the hopper (2) is installed on the top of the compartment main body (1), the hopper (2) The big mouth in upper end around uniform intervals be fixedly connected with the upper end of four supporting rods (4), four supporting rods (4) lower end and institute State base (3) to be fixedly connected, the compartment main body (1) is wrapped in interior, the car by the space that four supporting rods (4) are formed The upper end of railway carriage or compartment main body (1) be provided with the corresponding feed inlet of the hopper (2) osculum (15), the two of the compartment main body (1) The bottom of a opposite flank corresponds and is provided with two discharge ports (7), and the lower end of the base (3) is evenly arranged with four and leads To wheel (5), the lower end in the compartment main body (1) corresponding to the feed inlet (15) is provided with triangle deflector (6), described The vertex correspondence of deflector (6) is set in the lower end of the feed inlet (15), and the base of the deflector (6) extends to the car The both sides of railway carriage or compartment main body (1) are simultaneously connected with the discharge port (7).
2. the balanced moving trolley of concrete cast according to claim 1, it is characterised in that set on the compartment main body (1) Shunt regulator device (8) is equipped with, the shunt regulator device (8) includes support plate (81), swing handle (82), turbine reduction box (83), rotation axis (84), flow distribution plate (85), the rotation axis (84) be installed on the compartment main body (1) two other is opposite Between side, and one end extends to the outside of the compartment main body (1), and the flow distribution plate (85) is installed on the rotation axis (84) on and the lower section at the feed inlet (15) center is arranged on, it is corresponding that the support plate (81) is arranged on compartment main body (1) In the side of the rotation axis (84) extension, the turbine reduction box (83) is fixed at the upper end of the support plate (81), The swing handle (82) is arranged on turbine reduction box (83) outer wall, and the swing handle (82) is slowed down with the turbine Turbine in case (83) connects, and the worm screw in the turbine reduction box (83) is connected with the rotation axis (84).
3. the balanced moving trolley of concrete cast according to claim 1, it is characterised in that the lower end of the hopper (2) Dispensing valve (9) is provided with osculum.
4. the balanced moving trolley of concrete cast according to claim 3, it is characterised in that the upper end two of the hopper (2) There is horizontally arranged sunshading board (10) in side.
5. the balanced moving trolley of concrete cast according to claim 1, it is characterised in that the compartment main body (1) is close The side of the discharge port (7) is provided with stent (11), and the stent (11) extends to the outside of the discharge port (7) to pre- If distance, there is the first splash-back (12) being vertically arranged in the outer end of the stent (11).
6. the balanced moving trolley of concrete cast according to claim 5, it is characterised in that the compartment main body (1) is corresponding There is the second splash-back (13) being vertically arranged in the bottom of the discharge port (7).
7. the balanced moving trolley of concrete according to claim 6 cast, it is characterised in that first splash-back (12) with It is separated by pre-determined distance between second splash-back (13).
8. the balanced moving trolley of concrete cast according to claim 7, it is characterised in that on first splash-back (12) There is the reinforcing rib (14) that uniform intervals are set.
CN201721036256.3U 2017-08-18 2017-08-18 The balanced moving trolley of concrete cast Expired - Fee Related CN207260155U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721036256.3U CN207260155U (en) 2017-08-18 2017-08-18 The balanced moving trolley of concrete cast

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721036256.3U CN207260155U (en) 2017-08-18 2017-08-18 The balanced moving trolley of concrete cast

Publications (1)

Publication Number Publication Date
CN207260155U true CN207260155U (en) 2018-04-20

Family

ID=61925316

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721036256.3U Expired - Fee Related CN207260155U (en) 2017-08-18 2017-08-18 The balanced moving trolley of concrete cast

Country Status (1)

Country Link
CN (1) CN207260155U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110777812A (en) * 2019-11-12 2020-02-11 中国十七冶集团有限公司 Symmetrical backfill construction method for two sides of power channel foundation pit
CN111218951A (en) * 2020-02-10 2020-06-02 中国十七冶集团有限公司 Grouting method of fan foundation concrete grouting device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110777812A (en) * 2019-11-12 2020-02-11 中国十七冶集团有限公司 Symmetrical backfill construction method for two sides of power channel foundation pit
CN111218951A (en) * 2020-02-10 2020-06-02 中国十七冶集团有限公司 Grouting method of fan foundation concrete grouting device

Similar Documents

Publication Publication Date Title
CN207260155U (en) The balanced moving trolley of concrete cast
CN103911922B (en) A kind of railway self-compacting concrete moves bottler placer
CN206815851U (en) A kind of mixed mud with agitating function pours device
CN107336343B (en) Automatic material cloth integrated device that changes of concrete
CN104815952A (en) Layered sand flowing device for phenolic sand molding
CN206874291U (en) One kind two serves as a contrast chute and enters modular system by window
CN205713133U (en) A kind of concrete-agitating pours device
CN202861390U (en) Three-dimensional mobile molten iron pouring trolley
CN206475289U (en) A kind of concrete turns to expect cloth integrated apparatus automatically
CN105345922A (en) Concrete dropping device in prefabricated slab production line
CN103357832B (en) A kind of pneumatic feeding type automatic slag adding machine
CN208533556U (en) A kind of combination unit poured convenient for mixed tower blower foundation
CN204199708U (en) Concrete divides hopper
CN104821534A (en) Side channel cable trough combined body, preparation method and side channel cable trough combined structure
CN105971285B (en) A kind of concrete stirring pours device
CN210828359U (en) Concrete pouring equipment for construction equipment
CN207209468U (en) A kind of quick system of putting in storage of big discrepancy in elevation grinding coagulation soil for preventing aggregate separated
CN209261225U (en) A kind of tool for pouring concrete into steel column
CN211447813U (en) Concrete pumping-free non-intermittent full-range chute pouring device
CN210434375U (en) Movable foaming agent production equipment
CN207194466U (en) Removable sandwich wall cement casting device
CN207260153U (en) Concrete construction pouring structure waterborne
CN201056033Y (en) Consolidation type sand and stone mixture making trolley
CN206662253U (en) Automatic pouring machine
CN203212954U (en) Movable pouring hopper

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180420

Termination date: 20210818