CN209261225U - A kind of tool for pouring concrete into steel column - Google Patents
A kind of tool for pouring concrete into steel column Download PDFInfo
- Publication number
- CN209261225U CN209261225U CN201822026361.XU CN201822026361U CN209261225U CN 209261225 U CN209261225 U CN 209261225U CN 201822026361 U CN201822026361 U CN 201822026361U CN 209261225 U CN209261225 U CN 209261225U
- Authority
- CN
- China
- Prior art keywords
- steel column
- tool
- pouring concrete
- material filling
- pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
The utility model discloses a kind of tools for pouring concrete into steel column, belong to engineering equipment field.The tool includes interior material filling bucket and auxiliary funnel, and interior material filling bucket lower part is equipped with a material feeding control pipe, can control blanking velocity.It is equipped with pull ring at the top of interior material filling bucket, the wirerope of tower crane or truck crane can be hung.Feed pipe below auxiliary funnel can be inserted into inside steel column to be poured, and the support plate of auxiliary funnel is greater than steel column section, may be supported at the top of steel column, receive the concrete flowed into from interior material filling bucket, and be injected into steel column.The interior material filling bucket size of the utility model can be selected according to the interior concrete amount filled every time, and concrete can be previously placed in interior material filling bucket, solve the problems, such as to fill in the steel column of high-altitude, practicability height.
Description
Technical field
The utility model belongs to engineering equipment field, and in particular to a kind of tool for pouring concrete into steel column.
Background technique
By two kinds of material groups of different nature it is integral it is cooperative be configured to combined member, can be with by combined member
Group is shaped to composite structure.It is higher and higher to the bearing requirements vertically constructed in the building of large-space large-span now,
Middle steel core concrete column is one of the most common type combined member.Interior filling concrete is combined in the component steel column, reaches collaboration
Complementary effect.The component has the advantages that bearing capacity is high, moulding and good toughness, fire resistance is excellent.But it is poured in pipe mixed
The technique for coagulating soil is not well solved always, and site operation is relatively complicated.
It is filled in steel column generally there are two types of scheme, pressure jacks inner irrigating method and falls two kinds naturally from steel column is suitable for reading.Pressure top
Rising inner irrigating method be easy to cause steel column to burst, and influences structural behaviour.Therefore the scheme to fall naturally has preferably real from principle
With property, but the common concrete hopper size of this method is larger, and bottom opening is big, and high-altitude application hush panel is difficult, and steel column is cut
Face is small, easily cause few filling or fill, the concrete of spilling from falling from high altitude be a larger security risk.
Therefore, a kind of equipment for nature whereabouts concrete perfusion is urgently provided in the prior art.It is submitted in applicant
The utility model patent application No. is CN201821045018.3 in, disclose a kind of in steel-concrete combined structure
Fill the auxiliary funnel of concrete.The device integrally can carry out flexible operating to hush panel by control-rod, and then adjust hush panel
Sealed condition in Grouting Pipe can realize the control of slip casting rate by adjusting hush panel.However in actual use,
The device itself can not lay in a large amount of concrete, can only be used as loading hopper, and concrete still needs to pass through bottom pump
The modes such as promotion are injected in hopper, and convenience is restricted.Therefore, it is necessary to it is further improved.
Summary of the invention
Utility model aims to solve problems of the prior art, and provide a kind of for filling mixed in steel column
Coagulate the tool of soil.
Specific technical solution used by the utility model is as follows:
A kind of tool for pouring concrete into steel column comprising interior material filling bucket and auxiliary funnel;The interior material filling bucket
Including storage hopper, lifting pull ring, bracket, material feeding control pipe;Several lifting pull rings, storing are fixed at the top of the storage hopper
Bucket is installed on bracket, can be supported in plane by bracket;The storage hopper lower part is in back taper, and bottom offers
Through-hole;Material feeding control pipe includes circular pipe, shaft, sealed piece and supporting element, the top connection of the circular pipe through-hole;
The side wall of circular pipe offers arc-shaped slit along cross section, and a shaft is fixed on the circular pipe side wall of arc-shaped slit side;
The sealed piece is made of hush panel and the rotating handle that is fixed in hush panel, aperture and runs through shape by shaft in hush panel
At revolute pair, the supporting element is set to below arc-shaped slit, is used to support and is limited sealed piece and rotates in the plane;Hush panel
During rotation, it is inserted into the arc-shaped slit and blocks the inner cavity of circular pipe;The auxiliary funnel include into
Hopper, support plate and Grouting Pipe wherein feeding funnel bottom part aperture and connect Grouting Pipe, and the support plate is sheathed on outside Grouting Pipe
Portion and the two is fixed;The circular pipe size, which is less than feed hopper, to be protruded into feed hopper.
Preferably, the side wall of the feed hopper is formed by four pieces of trapezoidal steel plate splicings, the cross section of feed hopper is from upper
It is gradually reduced under.
Preferably, being fixed with several hanging rings at the top of the feed hopper.
Preferably, the support board size is greater than steel column top opening size to be poured, keep support plate whole
It is supported in above steel column.
Preferably, connecting steel wire ropes on the lifting pull ring.
Preferably, the bracket is made of square tube or angle steel.
It tapping and is revolved respectively preferably, the shaft is made of two nuts and a reinforcing bar, outside reinforcing bar both ends
There is a nut, two nuts are respectively welded on the circular pipe side wall for being fixed on arc-shaped slit two sides.
Preferably, the lifting pull ring totally 4, be uniformly distributed on the circumference at the top of storage hopper.
Preferably, the hush panel is gap-matched with shaft.
Preferably, the supporting element is an arc-shaped strip piece, fitting circular pipe side wall is fixed.
The utility model in terms of existing technologies, has the advantages that
1) material filling bucket size can be selected according to the interior concrete amount filled every time in, and concrete can be previously placed in interior material filling bucket
In, it solves the problems, such as to fill in the steel column of high-altitude, practicability is high;
2) two tools of material filling bucket and auxiliary funnel only need the i.e. controllable blanking velocity of a controller in;
3) pull ring is equipped at the top of material filling bucket, the wirerope of tower crane or truck crane can be hung;
4) pull ring is equipped at the top of auxiliary funnel, overall weight is little, and transhipment only needs one;
5) support plate of auxiliary funnel is greater than steel column section, may be supported at the top of steel column, is not necessarily to other fixations;
6) feed pipe below auxiliary funnel can be inserted into inside steel column to be poured, and not will cause concrete and overflows steel column.
Detailed description of the invention
Fig. 1 is the whole use state diagram of the tool for pouring concrete into steel column;
Fig. 2 is the structural schematic diagram of interior material filling bucket;
Fig. 3 is the structural schematic diagram that material feeding controls pipe;
Fig. 4 is the structural schematic diagram under another visual angle of material feeding control pipe;
Fig. 5 is the structural schematic diagram of auxiliary funnel;
Fig. 6 is material feeding control pipe, the combining structure schematic diagram of auxiliary funnel and steel column under the state that pours;
In figure: wirerope 1, interior material filling bucket 2, auxiliary funnel 3, steel column 4, storage hopper 201, lifting pull ring 202, bracket 203,
Material feeding control pipe 204, circular pipe 2041, shaft 2042, sealed piece 2043, supporting element 2044, hanging ring 301, feed hopper 302,
Support plate 303 and Grouting Pipe 304.
Specific embodiment
The utility model is further elaborated and is illustrated with reference to the accompanying drawings and detailed description.In the utility model
The technical characteristic of each embodiment can carry out the corresponding combination under the premise of not conflicting with each other.
As shown in Figure 1, a kind of tool for pouring concrete into steel column, main structure includes wirerope 1, interior material filling bucket
2 and auxiliary funnel 3, it is promoted entirely through tower crane or truck crane, and 4 top of steel column to be poured is set up in by auxiliary funnel 3.
As shown in Fig. 2, interior material filling bucket 2 includes storage hopper 201, lifting pull ring 202, bracket 203, material feeding control pipe 204.Storage
201 top of hopper is cylindrical, and lower part is in cone shape.In the present embodiment, 201 upper opening diameter about 2m of storage hopper, gradually
It closes up downwards, lower port diameter about 300mm.201 top of storage hopper is circumferentially uniformly fixed with 4 lifting pull rings 202, lifts by crane pull ring
It can connect wirerope 1 on 202, in order to loop wheel machine lifting.Storage hopper 201 is installed on bracket 203, bracket 203 by square tube or
Angle steel is made, and to save cost, has four legs, storage hopper 201 can be supported in plane by bracket 203.Storage hopper
201 bottoms offer through-hole, and the concrete materials of storage inside are flowed downward by the through-hole.Such as the institute of Fig. 3 and 4
Show, it includes circular pipe 2041, shaft 2042, sealed piece 2043 and supporting element 2044, circular pipe 2041 that material feeding, which controls pipe 204,
201 bottom of top airtight connection storage hopper through-hole, material is able to enter in the pipeline.The side wall of circular pipe 2041 is along horizontal
Section offers arc-shaped slit, which probably covers 1/2 or so pipe circumference, 2041 side of circular pipe of arc-shaped slit side
A shaft 2042 is fixed on wall.Shaft 2042 is made of two nuts and a reinforcing bar, outside reinforcing bar both ends tapping and point
It is not screwed with a nut, two nuts are respectively welded on 2041 side wall of circular pipe for being fixed on arc-shaped slit two sides.Sealed piece
2043 effect is the slip casting channel as needed for blocking circular pipe 2041, it is by hush panel and to be fixed in hush panel
Rotating handle composition, aperture and revolute pair is formed there through by shaft 2042 in hush panel, enables hush panel in rotation hand
Along 2042 Plane Rotation of shaft under the drive of handle.In order to guarantee the smooth of rotation, hush panel is gap-matched with shaft 2042,
Opening diameter in hush panel is greater than 2042 outer diameter 2mm~5mm of shaft.Supporting element 2044 is set to below arc-shaped slit, is one
Arc-shaped strip piece can be used reinforcing bar and bend.Supporting element 2044 is bonded 2041 side wall of circular pipe and fixes.Hush panel exists
Lower surface is limited sealed piece 2043 and is rotated in the plane by 2044 upper support of supporting element in rotation process.Hush panel 401 is turning
It during dynamic, is inserted into arc-shaped slit, and the head of hush panel 401 is rounded, lower part is in rectangle, can after entering pipeline
The inner cavity of circular pipe 2041 is blocked, so that concrete can not continue to flow downward along circular pipe 2041 by hush panel.When
When hush panel 401 is swapped out again, the flow channel of concrete is reopened, and it is adjustable to open amplitude.
The effect of interior material filling bucket 2 is to need to store concrete according to the predetermined amount of pouring, and is then lifted to aerial, root together
It is irrigated according to needs.It is directly more difficult with the alignment steel column 4 of circular pipe 2041 however since interior 2 volume of material filling bucket is larger,
Therefore the utility model is additionally provided with an auxiliary funnel 3 and is assisted.As shown in figure 5, auxiliary funnel 3 include hanging ring 301,
Feed hopper 302, support plate 303 and Grouting Pipe 304, the side wall of feed hopper 302 by four pieces of trapezoidal steel plates (thick 3mm or so) splicings and
At the cross section of feed hopper 302 is gradually reduced from top to bottom, is in inversed taper platform shape, width suitable for reading about 500mm × 500mm.Wherein into
302 bottom of hopper opens the hole diameter 100mm~200mm and connects Grouting Pipe 304, length about 300mm, thick 3mm or so, and diameter is also
100mm~200mm, it is consistent with aperture.Support plate 303 is the steel plate of one piece of rectangle, and middle part aperture enables plate body to be arranged
Outside Grouting Pipe 304, and the two is welded and fixed.303 size of support plate is greater than 4 top opening size of steel column to be poured, and makes
Support plate 303 can overally support above steel column 4, as shown in Figure 6.2041 size of circular pipe should be guaranteed that less than feed hopper
302, it can protrude into feed hopper 302.Two hanging rings 301 are fixed on the top of feed hopper 302, in order to lift.
The application method of the tool is as follows:
1. auxiliary funnel 3 is inserted into 4 top opening of steel column by operator;
2. first closing the material feeding control pipe 204 that interior material filling bucket 2 exports, it is mixed that commodity are filled in the inward-facing material filling bucket 2 in ground
Solidifying soil, then metal binding wire rope 1,4 position of steel column filled in needing is promoted to by tower crane or truck crane;
3. opening material feeding in the position of slightly higher than auxiliary funnel 3 and controlling pipe 204, concrete is made to enter auxiliary funnel 3
In, and inject in steel column 4 in turn, by the speed of the insertion extent control blanking of hush panel, complete to fill in concrete;
4. each equipment of disassembly, cleaning pours in case carrying out next round.
Embodiment described above is a kind of preferable scheme of the utility model, and so it is not practical to limit
It is novel.Those of ordinary skill in related technical field can be in the case where not departing from the spirit and scope of the utility model
It makes a variety of changes and modification.Therefore all mode technical solutions obtained for taking equivalent substitution or equivalent transformation, all fall within
In the protection scope of the utility model.
Claims (10)
1. a kind of tool for pouring concrete into steel column, which is characterized in that including interior material filling bucket (2) and auxiliary funnel (3);
The interior material filling bucket (2) includes storage hopper (201), lifting pull ring (202), bracket (203), material feeding control pipe (204);
Several liftings pull ring (202) are fixed at the top of the storage hopper (201), storage hopper (201) is installed on bracket (203),
It can be supported in plane by bracket (203);Storage hopper (201) lower part is in back taper, and bottom offers through-hole;
Material feeding control pipe (204) includes circular pipe (2041), shaft (2042), sealed piece (2043) and supporting element (2044), circle
The top connection of pipeline (2041) through-hole;The side wall of circular pipe (2041) offers arc-shaped slit, arc along cross section
It stitches and is fixed with a shaft (2042) on circular pipe (2041) side wall of side;The sealed piece (2043) by hush panel and
The rotating handle composition being fixed in hush panel aperture and is formed there through revolute pair by shaft (2042) in hush panel, described
Supporting element (2044) is set to below arc-shaped slit, is used to support and is limited sealed piece (2043) and rotates in the plane;Hush panel
(401) during rotation, it is inserted into the arc-shaped slit and blocks the inner cavity of circular pipe (2041);
The auxiliary funnel (3) includes feed hopper (302), support plate (303) and Grouting Pipe (304), wherein feed hopper (302)
Bottom opening simultaneously connects Grouting Pipe (304), and the support plate (303) is sheathed on Grouting Pipe (304) outside and the two is fixed;Institute
Circular pipe (2041) size stated, which is less than feed hopper (302), can protrude into feed hopper (302).
2. being used for the tool of pouring concrete into steel column as described in claim 1, which is characterized in that the feed hopper (302)
Side wall formed by four pieces of trapezoidal steel plate splicings, the cross section of feed hopper (302) is gradually reduced from top to bottom.
3. being used for the tool of pouring concrete into steel column as described in claim 1, which is characterized in that the feed hopper (302)
Top is fixed with several hanging rings (301).
4. being used for the tool of pouring concrete into steel column as described in claim 1, which is characterized in that the support plate (303)
Size is greater than steel column (4) top opening size to be poured, and overally support support plate (303) can above steel column (4).
5. being used for the tool of pouring concrete into steel column as described in claim 1, which is characterized in that the lifting pull ring
(202) connecting steel wire ropes (1) on.
6. as described in claim 1 be used for pouring concrete into steel column tool, which is characterized in that the bracket (203) by
Square tube or angle steel are made.
7. as described in claim 1 be used for pouring concrete into steel column tool, which is characterized in that the shaft (2042) by
Two nuts and reinforcing bar composition, the outer tapping in reinforcing bar both ends are simultaneously screwed with a nut respectively, and two nuts, which are respectively welded, to be consolidated
Due on circular pipe (2041) side wall of arc-shaped slit two sides.
8. being used for the tool of pouring concrete into steel column as described in claim 1, which is characterized in that the lifting pull ring
(202) totally 4, be uniformly distributed on the circumference at the top of storage hopper (201).
9. being used for the tool of pouring concrete into steel column as described in claim 1, which is characterized in that the hush panel and shaft
(2042) it is gap-matched.
10. being used for the tool of pouring concrete into steel column as described in claim 1, which is characterized in that the supporting element
It (2044) is an arc-shaped strip piece, fitting circular pipe (2041) side wall is fixed.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201822026361.XU CN209261225U (en) | 2018-12-04 | 2018-12-04 | A kind of tool for pouring concrete into steel column |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201822026361.XU CN209261225U (en) | 2018-12-04 | 2018-12-04 | A kind of tool for pouring concrete into steel column |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209261225U true CN209261225U (en) | 2019-08-16 |
Family
ID=67561967
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201822026361.XU Active CN209261225U (en) | 2018-12-04 | 2018-12-04 | A kind of tool for pouring concrete into steel column |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209261225U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111608184A (en) * | 2020-05-08 | 2020-09-01 | 五冶集团上海有限公司 | Core filling device for tubular pile |
-
2018
- 2018-12-04 CN CN201822026361.XU patent/CN209261225U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111608184A (en) * | 2020-05-08 | 2020-09-01 | 五冶集团上海有限公司 | Core filling device for tubular pile |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208885016U (en) | Concrete casting device and casting system | |
CN208965549U (en) | A kind of poured pile construction package of mortar leakage prevention | |
CN203145473U (en) | Concrete pouring distributing device | |
CN106368210A (en) | Large-diameter hollow steel thread pile and construction method thereof | |
CN108756890A (en) | A kind of sliding mode system being in the milk for vertical shaft concreting and rock mass | |
CN107152028B (en) | Rotatable truss type concrete pouring chute system and construction method thereof | |
CN104815952A (en) | Layered sand flowing device for phenolic sand molding | |
CN209261225U (en) | A kind of tool for pouring concrete into steel column | |
CN206646509U (en) | A kind of storage compartment rack device of suitable large aperture foundation first set back cover perfusion | |
CN106522630A (en) | Rotating type concrete distribution device applied to sliding formwork | |
CN109098178A (en) | A kind of concrete-spouting plant | |
CN210238494U (en) | Supplementary booster-type building biax stirring stake machine | |
CN207105284U (en) | A kind of barrel type concrete blanking device | |
CN208717938U (en) | Using the communication iron tower foundation of Screw Anchor | |
CN204199708U (en) | Concrete divides hopper | |
CN201507118U (en) | Large-volume concrete hopper for construction of high-rise building or multi-storey basement | |
CN109433054A (en) | A kind of refractory material uniform mixing device | |
CN204780928U (en) | Major diameter bored concrete pile concrete first set groundwater increment controlling means | |
CN105696468B (en) | Underwater concreting method in the construction of water Bridge | |
CN207072028U (en) | Small-sized mixing station with enhanced feature | |
CN209384226U (en) | A kind of Manual hole pile digging device in shifting sand layers | |
CN207244625U (en) | One kind can revolve type truss-like concreting chuting system | |
CN206299129U (en) | A kind of large-sized concrete cloth system | |
CN206205456U (en) | A kind of efficient concrete wall placing installation | |
CN210369938U (en) | A can have enough to meet need sleeve for pouring stake core |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |