CN207259973U - A kind of wet seam construction Hanging Basket of bridge floor - Google Patents

A kind of wet seam construction Hanging Basket of bridge floor Download PDF

Info

Publication number
CN207259973U
CN207259973U CN201721217448.4U CN201721217448U CN207259973U CN 207259973 U CN207259973 U CN 207259973U CN 201721217448 U CN201721217448 U CN 201721217448U CN 207259973 U CN207259973 U CN 207259973U
Authority
CN
China
Prior art keywords
supporting rod
rod
bridge floor
wet seam
hanging basket
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721217448.4U
Other languages
Chinese (zh)
Inventor
梁军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201721217448.4U priority Critical patent/CN207259973U/en
Application granted granted Critical
Publication of CN207259973U publication Critical patent/CN207259973U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of wet seam construction Hanging Basket of bridge floor, including the first support column, connecting rod, pull rod, hanging rod, web plate, second support bar, the 3rd supporting rod, the 4th supporting rod;Advantage; wet seam is carried out to bridge floor with Hanging Basket auxiliary using the wet seam construction of bridge floor provided by the utility model; hanging rod is suspended on bridge floor; wet seam worker stands in Hanging Basket; connecting rod and pull rod on first support column, second support bar, the 3rd supporting rod and the 4th supporting rod, safeguard protection is carried out to the staff in Hanging Basket, avoids the wet seam staff of bridge floor when carrying out wet seam to bridge floor; fall from Hanging Basket, cause security incident.The wet seam construction cradle structure of bridge floor provided by the utility model is simple, removes and installs conveniently, uses manpower and material resources sparingly.

Description

A kind of wet seam construction Hanging Basket of bridge floor
Technical field
The utility model belongs to field of bridge construction, and in particular to a kind of wet seam construction Hanging Basket of bridge floor.
Background technology
In bridge construction, it usually needs using Hanging Basket as auxiliary tool, aid in the wet seam of bridge floor to construct, it is existing Cradle structure it is complicated, installation and removal are required to using instrument auxiliary installation, installation inconvenience.It is steady after existing Hanging Basket installation Qualitative not high, staff easily occurs security incident, influences the construction of bridge when using Hanging Basket.Existing Hanging Basket Need dismounting to preserve after the completion of use, do not dismantle preservation and take up a large area, move inconvenience, wasting space resource, it has not been convenient to Promoted in bridge construction process.
Utility model content
In view of the above-mentioned problems of the prior art, the utility model provides a kind of simple in structure, bridge floor easy to use Wet seam construction Hanging Basket.
Its technical solution is:
A kind of wet seam construction Hanging Basket of bridge floor, including the first support column, connecting rod, pull rod, hanging rod, web plate, the second support Bar, the 3rd supporting rod, the 4th supporting rod;
First support column, second support bar, the 3rd supporting rod and the 4th supporting rod are parallel to each other and surround one jointly Cuboid, the connecting rod are two groups, and two groups of connecting rods are arranged in parallel, and one group of connecting rod is perpendicular to the first support column and second support bar two End is fixedly connected with the first support column and second support bar respectively, and another group of connecting rod is perpendicular to the 3rd supporting rod and the 4th supporting rod Both ends are fixedly connected with the 3rd supporting rod and the 4th supporting rod respectively, and connecting rod on the supporting rod of supporting rod junction with being provided with card Mouthful, the connecting rod two end is arranged in bayonet, and the pull rod is two groups, and two groups of pull rods are arranged in parallel, one group of pull rod both ends difference It is connected with the first support column and the 4th supporting rod, another group of pull rod both ends are connected with second support bar and the 3rd supporting rod respectively, First support column, second support bar, the 3rd supporting rod and the 4th supporting rod one end are fixedly connected with web plate, the first support Column, second support bar, the 3rd supporting rod and the 4th supporting rod other end are connected with hanging rod.
Wet seam is carried out to bridge floor with Hanging Basket auxiliary using the wet seam construction of bridge floor provided by the utility model, hanging rod is hanged Hang on bridge floor, wet seam worker stands in Hanging Basket, the first support column, second support bar, the 3rd supporting rod and the 4th support Connecting rod and pull rod on bar, carry out safeguard protection to the staff in Hanging Basket, avoid the wet seam staff of bridge floor to bridge When face carries out wet seam, fall from Hanging Basket, cause security incident.The wet seam construction Hanging Basket knot of bridge floor provided by the utility model Structure is simple, removes and installs conveniently, uses manpower and material resources sparingly.
Further, first support column, second support bar, the 3rd supporting rod and the 4th supporting rod are divided into two-stage up and down, Higher level supports shank diameter to be more than subordinate's support shank diameter, and subordinate's supporting rod can freely stretch in higher level's supporting rod, the higher level Through hole is provided with first support column of supporting rod and subordinate's supporting rod, second support bar, the 3rd supporting rod and the 4th supporting rod.
Coordinated using the higher level's support and subordinate's supporting rod of minor diameter of major diameter, connecting rod two end is extend on supporting rod Through hole in, the supporting rod of upper and lower two-stage can be relatively fixed, realize the flexible of construction hanging basket, construction hanging basket can be effectively improved Service efficiency.
Further, the pull rod passes through fulcrum and the first support column, second support bar, the 3rd supporting rod and the 4th supporting rod Connection mode be it is hinged, the fixed pivot be arranged on the first support column, second support bar, the 3rd supporting rod and the 4th support On bar.
Pull rod is hinged with the first support column, second support bar, the 3rd supporting rod and the 4th supporting rod, the wet seam construction of bridge floor Used with Hanging Basket after completing, the distance between the first support column of pulling, the 3rd supporting rod and second support bar, the 4th supporting rod, The wet seam construction of bridge floor quickly can be subjected to contraction storage with Hanging Basket, it is easy to operate, save and hang the wet seam construction of bridge floor Floor space when basket is stored, it is easy to operate, the cost of the wet seam of bridge floor is saved, improves the work efficiency of the wet seam of bridge floor.
Further, it is provided with bracing piece on the web plate.
Bracing piece is avoided that operator station when on web plate, and web plate is extended the service life of web plate, saved by gravity deformation The about cost of the wet seam construction Hanging Basket of bridge floor, improves the work efficiency of the wet seam of bridge floor.
Further, the hanging rod is hinged with connecting plate one end, and the connecting plate other end is hinged on support by hanging rod hinged block On bar, the supporting bar top is provided with leg.
The setting of leg enables the wet seam construction of bridge floor to be used by the use of Hanging Basket as Hanging Basket the wet seam of bridge floor progress, at the same time The wet seam construction of bridge floor can also be used by the use of Hanging Basket as ladder while can not find suitable mount point, improve that bridge floor is wet connects The service efficiency of construction Hanging Basket is stitched, saves the cost of the wet seam of bridge floor, improves the work efficiency of the wet seam of bridge floor.
Further, the hanging rod is two.
Using two hanging rods so that the wet seam construction of bridge floor is more stable after being installed with Hanging Basket, avoids producing security incident, carries The work efficiency of the high wet seam of bridge floor.
Beneficial effect:
1st, wet seam is carried out to bridge floor with Hanging Basket auxiliary using the wet seam construction of bridge floor provided by the utility model, by hanging rod It is suspended on bridge floor, wet seam worker stands in Hanging Basket, the first support column, second support bar, the 3rd supporting rod and the 4th Connecting rod and pull rod on strut, carry out safeguard protection to the staff in Hanging Basket, avoid the wet seam staff of bridge floor right When bridge floor carries out wet seam, fall from Hanging Basket, cause security incident.The wet seam construction Hanging Basket of bridge floor provided by the utility model It is simple in structure, remove and install conveniently, use manpower and material resources sparingly.
2nd, coordinated using the higher level's support and subordinate's supporting rod of minor diameter of major diameter, connecting rod two end is extend into supporting rod On through hole in, the supporting rod of upper and lower two-stage can be relatively fixed, realize the flexible of construction hanging basket, construction hanging basket can be effectively improved Service efficiency.
3rd, pull rod is hinged with the first support column, second support bar, the 3rd supporting rod and the 4th supporting rod, and the wet seam of bridge floor is applied Work with Hanging Basket using completing after, pull between the first support column, the 3rd supporting rod and second support bar, the 4th supporting rod away from From, the wet seam construction of bridge floor quickly can be subjected to contraction storage with Hanging Basket, it is easy to operate, save and use the wet seam construction of bridge floor Floor space when Hanging Basket is stored, it is easy to operate, the cost of the wet seam of bridge floor is saved, improves the work efficiency of the wet seam of bridge floor.
4th, bracing piece is avoided that operator station when on web plate, and web plate is extended the service life of web plate by gravity deformation, The cost of the wet seam construction Hanging Basket of bridge floor is saved, improves the work efficiency of the wet seam of bridge floor.
5th, the setting of leg enables the wet seam construction of bridge floor to carry out wet seam to bridge floor as Hanging Basket by the use of Hanging Basket and uses, together When the wet seam construction of bridge floor can also be used by the use of Hanging Basket as ladder while can not find suitable mount point, improve bridge floor it is wet The service efficiency of seam construction Hanging Basket, saves the cost of the wet seam of bridge floor, improves the work efficiency of the wet seam of bridge floor.
6th, using two hanging rods so that the wet seam construction of bridge floor is more stable after being installed with Hanging Basket, avoids producing security incident, Improve the work efficiency of the wet seam of bridge floor.
Brief description of the drawings
Fig. 1 is the utility model structure diagram;
Figure 1A direction views when Fig. 2 collapses for Hanging Basket;
Fig. 3 is Fig. 2A-A to sectional view;
Fig. 4 is mesh-plate structure schematic diagram;
Fig. 5 is supporting bar structure schematic diagram;Wherein, the first support columns of 1-, 2- connecting rods, 3- fulcrums, 4- pull rods, 5- hanging rods Hinged block, 6- hanging rods, 7- web plates, 8- bracing pieces, 9- connecting plates, 10- legs, 11- bayonets, 12- second support bars, 13- the 3rd Supporting rod, the 4th supporting rods of 14-.
Embodiment
As shown in Figs 1-4, the wet seam construction Hanging Basket of a kind of bridge floor, including the first support column 1, connecting rod 2, pull rod 4, hanging rod 6th, web plate 7, second support bar 12, the 3rd supporting rod 13, the 4th supporting rod 14;
First support column 1, second support bar 12, the 3rd supporting rod 13 and the 4th supporting rod 14 are parallel to each other and enclose jointly Into a cuboid, the connecting rod 2 is two groups, and two groups of connecting rods 2 are arranged in parallel, and one group of connecting rod 2 is perpendicular to the first support column 1 and the Two supporting rods, 12 both ends are fixedly connected with the first support column 1 and second support bar 12 respectively, and another group of connecting rod 2 is perpendicular to the 3rd Strut 13 and 14 both ends of the 4th supporting rod are fixedly connected with the 3rd supporting rod 13 and the 4th supporting rod 14 respectively, connecting rod 2 and support Bayonet 11 is provided with the supporting rod of bar junction, 2 both ends of connecting rod are arranged in bayonet 11, the pull rod 4 be two groups, two Group pull rod 4 is arranged in parallel, and one group of 4 both ends of pull rod is connected with the first support column 1 and the 4th supporting rod 14 respectively, another group of pull rod 4 Both ends are connected with 12 and the 3rd supporting rod 13 of second support bar respectively, first support column 1, second support bar 12, the 3rd Strut 13 and 14 one end of the 4th supporting rod are fixedly connected with web plate 7, the first support column 1, second support bar 12, the 3rd supporting rod 13 It is connected with 14 other end of the 4th supporting rod with hanging rod 6.
Further, first support column 1, second support bar 12, the 3rd supporting rod 13 and the 4th supporting rod 14 divide to be upper Lower two-stage, higher level support shank diameter to be more than subordinate's support shank diameter, and subordinate's supporting rod can freely stretch in higher level's supporting rod, institute State the first support column 1, second support bar 12, the 3rd supporting rod 13 and the 4th supporting rod of higher level's supporting rod and subordinate's supporting rod Through hole is provided with 14.
Further, the pull rod 4 passes through 3 and first support column 1 of fulcrum, second support bar 12, the 3rd supporting rod 13 and The connection mode of four supporting rods 14 be it is hinged, the fulcrum 3 be fixed at the first support column 1, second support bar 12, the 3rd On 13 and the 4th supporting rod 14 of strut.
Further, it is provided with bracing piece 8 on the web plate 7.
Further, the hanging rod 6 is hinged with 9 one end of connecting plate, and 9 other end of connecting plate is hinged on by hanging rod hinged block 5 On supporting rod, the supporting bar top is provided with leg 10.
Further, the hanging rod 6 is two.
Wet seam is carried out to bridge floor with Hanging Basket auxiliary using the wet seam construction of bridge floor provided by the utility model, hanging rod is hanged Hang on bridge floor, wet seam worker stands in Hanging Basket, the first support column 1, second support bar 12, the 3rd supporting rod 13 and the 4th Connecting rod 2 and pull rod 3 on supporting rod 14, safeguard protection is carried out to the staff in Hanging Basket, avoids the wet seam work people of bridge floor Member falls from Hanging Basket when carrying out wet seam to bridge floor, causes security incident.The wet seam construction of bridge floor provided by the utility model It is simple with cradle structure, remove and install conveniently, use manpower and material resources sparingly.

Claims (6)

  1. A kind of 1. wet seam construction Hanging Basket of bridge floor, it is characterised in that including the first support column (1), connecting rod (2), pull rod (4), Hanging rod (6), web plate (7), second support bar (12), the 3rd supporting rod (13), the 4th supporting rod (14);
    First support column (1), second support bar (12), the 3rd supporting rod (13) and the 4th supporting rod (14) are parallel to each other altogether With a cuboid is surrounded, the connecting rod (2) is two groups, and two groups of connecting rods (2) are arranged in parallel, and one group of connecting rod (2) is perpendicular to first Support column (1) and second support bar (12) both ends are fixedly connected with the first support column (1) and second support bar (12) respectively, another Group connecting rod (2) perpendicular to the 3rd supporting rod (13) and the 4th supporting rod (14) both ends respectively with the 3rd supporting rod (13) and the 4th Strut (14) is fixedly connected, and connecting rod (2) on the supporting rod of supporting rod junction with being provided with bayonet (11), the connecting rod (2) two End is arranged in bayonet (11), and the pull rod (4) is two groups, and two groups of pull rods (4) are arranged in parallel, one group of pull rod (4) both ends difference Be connected with the first support column (1) and the 4th supporting rod (14), another group of pull rod (4) both ends respectively with second support bar (12) and Three supporting rods (13) connect, first support column (1), second support bar (12), the 3rd supporting rod (13) and the 4th supporting rod (14) one end is fixedly connected with web plate (7), the first support column (1), second support bar (12), the 3rd supporting rod (13) and the 4th Strut (14) other end is connected with hanging rod (6).
  2. A kind of 2. wet seam construction Hanging Basket of bridge floor according to claim 1, it is characterised in that first support column (1), second support bar (12), the 3rd supporting rod (13) and the 4th supporting rod (14) are divided into two-stage up and down, and higher level supports shank diameter Shank diameter is supported more than subordinate, subordinate's supporting rod can freely stretch in higher level's supporting rod, higher level's supporting rod and subordinate's branch It is provided with the first support column (1) of strut, second support bar (12), the 3rd supporting rod (13) and the 4th supporting rod (14) logical Hole.
  3. 3. the wet seam construction Hanging Basket of a kind of bridge floor according to claim 1, it is characterised in that the pull rod (4) passes through The connection side of fulcrum (3) and the first support column (1), second support bar (12), the 3rd supporting rod (13) and the 4th supporting rod (14) Formula is hinged, and the fulcrum (3) is fixed at the first support column (1), second support bar (12), the 3rd supporting rod (13) and On four supporting rods (14).
  4. 4. the wet seam construction Hanging Basket of a kind of bridge floor according to claim 1, it is characterised in that set on the web plate (7) It is equipped with bracing piece (8).
  5. 5. the wet seam construction Hanging Basket of a kind of bridge floor according to claim 1, it is characterised in that the hanging rod (6) is with connecting Fishplate bar (9) one end is hinged, and connecting plate (9) other end is hinged on supporting rod by hanging rod hinged block (5), the supporting bar top It is provided with leg (10).
  6. 6. the wet seam construction Hanging Basket of a kind of bridge floor according to claim 1, it is characterised in that the hanging rod (6) is two Root.
CN201721217448.4U 2017-09-21 2017-09-21 A kind of wet seam construction Hanging Basket of bridge floor Active CN207259973U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721217448.4U CN207259973U (en) 2017-09-21 2017-09-21 A kind of wet seam construction Hanging Basket of bridge floor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721217448.4U CN207259973U (en) 2017-09-21 2017-09-21 A kind of wet seam construction Hanging Basket of bridge floor

Publications (1)

Publication Number Publication Date
CN207259973U true CN207259973U (en) 2018-04-20

Family

ID=61918646

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721217448.4U Active CN207259973U (en) 2017-09-21 2017-09-21 A kind of wet seam construction Hanging Basket of bridge floor

Country Status (1)

Country Link
CN (1) CN207259973U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108589552A (en) * 2018-06-11 2018-09-28 交通运输部科学研究院 A kind of collapsible suspension apparatus

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108589552A (en) * 2018-06-11 2018-09-28 交通运输部科学研究院 A kind of collapsible suspension apparatus
CN108589552B (en) * 2018-06-11 2023-07-21 交通运输部科学研究院 Folding suspension device

Similar Documents

Publication Publication Date Title
CN207259973U (en) A kind of wet seam construction Hanging Basket of bridge floor
CN209799310U (en) Building scaffold convenient to dismantle transportation
CN205132955U (en) Hoist and mount operation of electric power industry low latitude is with hoist and mount frame
CN208039790U (en) A kind of movable type scaffold bracket for overhead construction of building engineering
CN203257123U (en) Building supporting frame convenient to fold
CN215167811U (en) Multifunctional scaffold for constructional engineering
CN202550348U (en) Folding multifunctional overhauling frame for overhauling isolating switch
CN205446933U (en) Novel tuber pipe gallows
CN201198659Y (en) Formwork support system of prilling tower hanging structure
CN210508296U (en) Fixing support for house building engineering
CN207749810U (en) A kind of Novel moveable scaffold
CN207069964U (en) Photovoltaic panel installing support
CN215523805U (en) Solar cell panel mounting rack convenient to dismantle
CN205400059U (en) Novel aluminum alloy template is to pulling -on piece system
CN216913799U (en) Simple and easy wire rope stores pylon of assemblization
CN213297110U (en) Scaffold connecting device convenient to detach for construction
CN211714549U (en) Hanging flower basket structure for urban construction
CN219158338U (en) Anti-falling device for road and bridge construction
CN210690509U (en) Air quality detector
CN215167951U (en) Anti-falling scaffold
CN216305327U (en) Scaffold for building engineering
CN214235494U (en) Auxiliary tool for cleaning pulverized coal
CN219826027U (en) Bottom reinforcing anti-toppling structure
CN213625241U (en) Support with extending structure for building construction management
CN214303660U (en) Foldable ladder

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant