CN207211181U - A kind of horizontal substation framework basis and overhead transmission line column foot foundation bolt mounting platform - Google Patents

A kind of horizontal substation framework basis and overhead transmission line column foot foundation bolt mounting platform Download PDF

Info

Publication number
CN207211181U
CN207211181U CN201721095896.1U CN201721095896U CN207211181U CN 207211181 U CN207211181 U CN 207211181U CN 201721095896 U CN201721095896 U CN 201721095896U CN 207211181 U CN207211181 U CN 207211181U
Authority
CN
China
Prior art keywords
channel
section steel
foundation bolt
angle bar
bolt
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721095896.1U
Other languages
Chinese (zh)
Inventor
邵广伟
郑鹏
任兆龙
张运山
纪忠军
张雷
侯文明
刘国福
刘冰
张天宇
杨光
佟凤楠
魏巍
杨耀龙
朱沈宁
佟胜恩
王帅
王志良
马群
贾宏宇
铁金越
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Liaoning Electric Power Construction Supervision Co Ltd
State Grid Corp of China SGCC
Original Assignee
Liaoning Electric Power Construction Supervision Co Ltd
State Grid Corp of China SGCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Liaoning Electric Power Construction Supervision Co Ltd, State Grid Corp of China SGCC filed Critical Liaoning Electric Power Construction Supervision Co Ltd
Priority to CN201721095896.1U priority Critical patent/CN207211181U/en
Application granted granted Critical
Publication of CN207211181U publication Critical patent/CN207211181U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Foundations (AREA)

Abstract

A kind of horizontal substation framework basis and overhead transmission line column foot foundation bolt mounting platform, foundation bolt head end is in a vertical plane, and foundation bolt is axially horizontal vertical with head end, and foundation bolt is welded and fixed by stirrup, reinforcing bar;By in bolt sleeve plate weld to upper angle bar and lower angle bar, upper angle bar and lower angle bar are welded on the 3rd channel-section steel and the 6th channel-section steel, angle bar is respectively welded on first channel-section steel and the 5th channel-section steel and is connected with transverse axis, the first channel-section steel, the first square steel, the second channel-section steel, the second square steel, the 3rd channel-section steel, the 4th channel-section steel, the 5th channel-section steel, the 6th channel-section steel are welded together respectively, adjusting nut is welded on transverse axis and the 3rd channel-section steel, angle bar, crossbeam, regulating bolt is connected with adjusting nut.The utility model preparation method is simple, easy for installation, safe and reliable, ensures installation accuracy requirement, and foundation bolt mounting stability is good, is adapted to site operation, foundation bolt top mark height is easily controllable, applied in power Transmission equipment construction technical field of construction.

Description

A kind of horizontal substation framework basis and overhead transmission line column foot foundation bolt mounting platform
Technical field
The utility model is related to a kind of horizontal substation framework basis in power Transmission equipment construction technical field of construction with Overhead transmission line column foot heavy type foundation bolt mounting platform.
Background technology
At present, substation framework basis is installed with overhead transmission line column foot bolt in power Transmission equipment construction technical field of construction What is solved always is undesirable.According to state's net company standard technological standards storehouse(2012 editions), transformer substation framework basic standard technique (0101020105)To foundation bolt installation requirement misalignment of axe 0-2mm, perpendicularity deviation 0-1mm, overhead transmission line column foot standard Technique(0201010101-T1)It is required that with group foundation bolt column off-centring 8mm, absolute altitude deviation 10mm--5mm.
Generally there is transformer substation framework basis foundation bolt installation method generally to take using engineering method in prior art construction Two ways:The first, adds steel pipe to fix welding with two pieces of cage plates, sets up scaffold reinforcing, and rank is used because framework basis Ladder type basis, the fixed support of foundation bolt must be removed during model sheetinstallat.Foundation bolt installation loses stability, constructs Difficulty is larger, and site operation seldom uses this engineering method.Second, majority is dragged using two lumps of wood are added in lower single order template Live in a ladder template.On most under single order template, if two channel-section steels, hold single order template.Fixed foundation bolt cage plate.By Add channel-section steel weight to cause two channel-section steel bending subsidences in the jacketed plate weight of foundation bolt, cause foundation bolt top mark height also under It is heavy.Such as 2012 editions technological standards storehouses 0201010101-T3 ladders basis finished product(Anchor support)Scheme, the print that second order basal plane occurs in figure Trace, display channel-section steel have been sunk down into next layer concrete top layer, it was demonstrated that foundation bolt top mark height also sinks therewith.Circuit column foot More about 400 kilograms of foot bolt weight, column foot is mostly 7 stratum, bigger plus template weight deflection, and standard technology requires bolt The high deviation 0-1mm of top mark, therefore the high extremely difficult control of foundation bolt top mark.Need to design substation framework basis and overhead transmission line column foot Foundation bolt is stable, is reliable, easy to operate, ensures construction precision requirement.Therefore, a kind of horizontal substation framework basis is developed It is always new problem anxious to be resolved with overhead transmission line column foot heavy type foundation bolt mounting platform.
The content of the invention
The purpose of this utility model is to provide a kind of horizontal substation framework basis and overhead transmission line column foot heavy type lower margin spiral shell Bolt mounting platform, to overcome existing substation framework basis and the making of overhead transmission line column foot heavy type foundation bolt and mounting process skill Defect present on art, the utility model, which effectively solves template and its support, should have enough bearing capacitys, rigidity and stably Property, the weight, lateral pressure and construction loads of casting concrete can be reliably born, is realized in foundation bolt installation process to peace Fill precision requirement, and stably, it is easily operated, safe and reliable, foundation bolt mounting stability is good, difficulty of construction compared with It is small, it is particularly suitable for and site operation, foundation bolt top mark height is easily controllable.
What the purpose of this utility model was realized in:A kind of horizontal substation framework basis and overhead transmission line column foot lower margin spiral shell Bolt mounting platform, including foundation bolt, stirrup, inner template, gusset, base anchor, reinforcing bar, angle bar, adjustment regulating bolt, crossbeam, First channel-section steel, the first square steel, the second channel-section steel, the second square steel, lower angle bar, bolt cage plate, the 3rd channel-section steel, upper angle bar, transverse axis, the 4th Channel-section steel, the 5th channel-section steel, the 6th channel-section steel, adjusting nut, described foundation bolt, stirrup, inner template, gusset, base anchor, reinforcing bar group Into foundation bolt component part, foundation bolt head end is in a vertical plane, foundation bolt axial direction level and head end Face is vertical, and foundation bolt is welded and fixed by stirrup, reinforcing bar;By in bolt sleeve plate weld to upper angle bar and lower angle bar, upper angle bar It is welded to lower angle bar on the 3rd channel-section steel and the 6th channel-section steel, angle bar is respectively welded on the first channel-section steel and the 5th channel-section steel and is connected with transverse axis Connect, respectively by the first channel-section steel, the first square steel, the second channel-section steel, the second square steel, the 3rd channel-section steel, the 4th channel-section steel, the 5th channel-section steel, the 6th Channel-section steel welds together, and adjusting nut is welded on transverse axis and the 3rd channel-section steel, angle bar, crossbeam, and regulating bolt connects with adjusting nut Connect, in the first channel-section steel and the 5th channel-section steel upper end grooved bore, crossbeam is put into slotted eye;
Aperture size on described bolt cage plate is consistent with the arc diameter that inner template outer is distributed, and is welded to angle Aperture center position and center of arc's position consistency of inner template outer distribution on the bolt cage plate of iron and lower angle bar.
The structure of the present utility model for being characterized by it.Its mounting process principle is to carry out basic mould according to design requirement Plate is installed, and after theodolite, spirit level detection are qualified, on most below two joists of single order template, corner symmetrically sets up four branch Reinforcing bar is supportted, the weight after bar diameter combines according to foundation bolt determines with height, piece plastic tube of every reinforcing bar overcoat, reinforcing bar Bottom is padded with cement block, and bottom is blocked with cement mortar, it is ensured that does not enter concrete when being poured in plastic tube;Beneficial to later stage reinforcing bar Taking-up, the spacer bar can set up according to the weight of foundation bolt under lower step template, reinforce and complete when spacer bar Afterwards, you can the foundation bolt entirety after cage plate is installed in the installation suitable for reading of single order template additional on most, errorless through theodolite, spirit level detection After can casting concrete, spirit level, theodolite random monitoring ensure the precision of foundation bolt installation in concreting process It is required that after form removal, spacer bar can be extracted out, mortar is filled in plastic tube;1 pre-buried installation of foundation bolt, will by design Ask and carry out foundation forms installation, on most below two joists of single order template, corner symmetrically sets up four spacer bars, supporting steel Muscle diameter is according to the weight after the combination of foundation bolt 1 and height determination, piece plastic tube of every spacer bar overcoat, spacer bar Bottom is padded with cement block, and bottom is blocked with cement mortar, it is ensured that is not entered concrete when being poured in plastic tube, is easy to the later stage to support The taking-up of reinforcing bar, the spacer bar can be set up according to the weight of foundation bolt 1 under lower step template;When spacer bar is reinforced After the completion of, you can the foundation bolt entirety after bolt cage plate 5 is installed in the installation suitable for reading of single order template additional on most, with theodolite, level After instrument detection foundation bolt integrally meets installation accuracy requirement, you can casting concrete, spirit level, warp in concreting process Latitude instrument random monitoring ensures the required precision of foundation bolt installation, after form removal, can extract spacer bar out, back-up sand in plastic tube Slurry.
A kind of horizontal substation framework basis compared with prior art, has with overhead transmission line column foot foundation bolt mounting platform Preparation method is simple, easy for installation, safe and reliable, ensures installation accuracy requirement, and foundation bolt mounting stability is good, construction The advantages that difficulty is smaller, is particularly suitable for and site operation, and foundation bolt top mark is high easily controllable, it is defeated by electric power is widely used in Send in equipment construction technical field of construction.
Brief description of the drawings
Below in conjunction with the accompanying drawings and the utility model is described in detail embodiment.
Fig. 1 is structural representation of the present utility model.
Fig. 2 is Fig. 1 A-A sectional views.
Fig. 3 is Fig. 1 top view.
Fig. 4 is Fig. 3 B direction views.
Fig. 5 is the structural representation of the utility model foundation bolt component part.
Fig. 6 is Fig. 5 top view.
Fig. 7 is the structural representation of the utility model internal model plate part.
Fig. 8 is Fig. 7 top view.
Embodiment
Referring to the drawings, a kind of horizontal substation framework basis and overhead transmission line column foot foundation bolt mounting platform, including lower margin Bolt 1, stirrup 2, inner template 3, gusset 4, base anchor 5, reinforcing bar 6, angle bar 7, adjustment regulating bolt 8, crossbeam 9, the first channel-section steel 10, First square steel 11, the second channel-section steel 12, the second square steel 13, lower angle bar 14, bolt cage plate 15, the 3rd channel-section steel 16, upper angle bar 17, transverse axis 18th, the 4th channel-section steel 19, the 5th channel-section steel 20, the 6th channel-section steel 21, adjusting nut 22, described foundation bolt 1, stirrup 2, inner template 3, Gusset 4, base anchor 5, reinforcing bar 6 form foundation bolt component part, and the head end of foundation bolt 1 is in a vertical plane, ground Foot bolt 1 is axially horizontal vertical with head end, and foundation bolt 1 is welded and fixed by stirrup 2, reinforcing bar 6;Bolt cage plate 15 is welded Onto upper angle bar 17 and lower angle bar 14, upper angle bar 17 and lower angle bar 14 are welded on the 3rd channel-section steel 16 and the 6th channel-section steel 21, the Angle bar 7 is respectively welded on one channel-section steel 10 and the 5th channel-section steel 20 and is connected with transverse axis 18, respectively by the first channel-section steel 10, the first square steel 11st, the second channel-section steel 12, the second square steel 13, the 3rd channel-section steel 16, the 4th channel-section steel 19, the 5th channel-section steel 20, the 6th channel-section steel 21 are welded on one Rise, adjusting nut 22 is welded on the channel-section steel 16 of transverse axis 18 and the 3rd, angle bar 7, crossbeam 9, regulating bolt 8 connects with adjusting nut 22 Connect, in the first channel-section steel 10 and the upper end grooved bore of the 5th channel-section steel 20, crossbeam 9 is put into slotted eye.
Aperture size on described bolt cage plate 15 is consistent with the arc diameter that the outer of inner template 3 is distributed, and is welded to Aperture center position and the center of arc position of the outer of inner template 3 distribution on the bolt cage plate 15 of upper angle bar 17 and lower angle bar 14 Unanimously.
Described a kind of horizontal substation framework basis and the preparation method of overhead transmission line column foot foundation bolt mounting platform is: Cage plate is fixed by design drawing bolt distribution processing bolt, the cage plate is symmetrically fixed with two angle steel;Set up in processing district horizontal Workbench, foundation bolt weight weight can be assembled in horizontal workbench, beneficial to carrying, safety and stability;By foundation bolt cage plate It is fixed on workbench.Foundation bolt is inserted into cage plate, horizontal workbench detects cage plate perpendicularity, lower margin spiral shell with level meter Bolt levelness;Ensure that bolt is higher by that cage plate is highly consistent, and foundation bolt bottom liner cage plate is fixed, top cage plate adds fine setting fixed Position, it is qualified after testing to weld stirrup afterwards;This group of foundation bolt is firmly bundled and removed, carries out next group of assembling; Heavy foundation bolt component processing district makes horizontal workbench, will according to the diameter of design drawing foundation bolt 1 and position distribution Ask, processing inner template 3, bolt cage plate 15, angle bar 7, crossbeam 9, the first channel-section steel 10, square steel 11, the 3rd channel-section steel 12, square steel 13, under Angle bar 14, the 3rd channel-section steel 16, upper angle bar 17, transverse axis 18, the 4th channel-section steel 19, the 5th channel-section steel 20, the 6th channel-section steel 21, bolt cage plate 15 On aperture size will with the outer of inner template 3 be distributed arc diameter it is consistent, by bolt cage plate 15 be welded to upper angle bar 17 and under On angle bar 14, then upper angle bar 17 and lower angle bar 14 are welded on the 3rd channel-section steel 16 and the 6th channel-section steel 21, the He of the first channel-section steel 10 Angle bar 7 is respectively welded on 5th channel-section steel 20, and is connected with transverse axis 18, respectively by the first channel-section steel 10, square steel 11, the second channel-section steel 12, Square steel 13, the 3rd channel-section steel 16, the 4th channel-section steel 19, the 5th channel-section steel 20, the 6th channel-section steel 21 weld together, in the groove of transverse axis 18 and the 3rd Steel 16, angle bar 7, adjusting nut 22 is welded on crossbeam 9, regulating bolt 8 is screwed into adjusting nut 22 respectively, in the first channel-section steel 10 With the upper end grooved bore of the 5th channel-section steel 20, crossbeam 9 is put into slotted eye, pitch-row and Diagonal Dimension will meet between bolt cage plate 15 The requirement of foundation bolt design drawing, and in approximately the same plane, complete the system of the horizontal tooling platform of heavy foundation bolt component After work, foundation bolt 1 is respectively put into bolt cage plate 15, rear portion is carried on a shoulder pole by transverse axis 18 and crossbeam 9, and inner template 3 is put into Foundation bolt 1 works as postmedian so that size is fixed by inner template outer arc position size between the rear portion of foundation bolt 1, measurement The length of bolt cage plate 15 is stretched out on whole heads of foundation bolt 1, makes its length consistent, rotation adjustment regulating bolt 8, uses level meter With axial horizontal accuracy between the detection radial direction of foundation bolt 1, technical requirements, rotation adjustment regulating bolt 8, with level are complied with Between the instrument detection head end of foundation bolt 1, it is set to ensure in a vertical plane, it is between detection foundation bolt head and diagonal Size between line meets Design Requirement Drawing, and stirrup 2 and reinforcing bar 6 are welded on foundation bolt 1, completes one group of heavy type lower margin The making of bolt.
Described a kind of horizontal substation framework basis and the mounting process of overhead transmission line column foot foundation bolt mounting platform is former Reason is to carry out foundation forms installation according to design requirement, after theodolite, spirit level detection are qualified, single order template two on most Below joist, corner symmetrically sets up four spacer bars, and the weight after bar diameter combines according to foundation bolt determines with height, Piece plastic tube of every reinforcing bar overcoat, reinforcing bar bottom are padded with cement block, and bottom is blocked with cement mortar, it is ensured that is poured in plastic tube Do not enter concrete when building;Beneficial to the taking-up of later stage reinforcing bar, the spacer bar can be according to the weight of foundation bolt in lower step mould Set up under plate, after the completion of spacer bar reinforcing, you can the foundation bolt after cage plate is installed in the installation suitable for reading of single order template additional on most It is overall, after theodolite, spirit level detection are errorless can casting concrete, spirit level in concreting process, theodolite with Machine monitoring ensures the required precision of foundation bolt installation, after form removal, can extract spacer bar out, filling mortar is in plastic tube Can;1 pre-buried installation of foundation bolt, foundation forms installation, on most below two joists of single order template, four are carried out by design requirement Angle symmetrically sets up four spacer bars, and the weight after spacer bar diameter combines according to foundation bolt 1 determines with height, every branch Reinforcing bar piece plastic tube of overcoat is supportted, spacer bar bottom is padded with cement block, and bottom is blocked with cement mortar, it is ensured that in plastic tube Do not enter concrete when pouring, be easy to the taking-up of later stage spacer bar, the spacer bar can be according to the weight of foundation bolt 1 in bottom Set up under ladder template;After the completion of spacer bar reinforcing, you can after bolt cage plate 5 is installed in the installation suitable for reading of single order template additional on most Foundation bolt it is overall, after integrally meeting installation accuracy requirement with theodolite, spirit level detection foundation bolt, you can pour coagulation Soil, spirit level, theodolite random monitoring ensure the required precision of foundation bolt installation in concreting process, after form removal, Spacer bar can be extracted out, mortar is filled in plastic tube.

Claims (2)

1. a kind of horizontal substation framework basis and overhead transmission line column foot foundation bolt mounting platform, including it is foundation bolt, stirrup, interior Template, gusset, base anchor, reinforcing bar, angle bar, adjustment regulating bolt, crossbeam, the first channel-section steel, the first square steel, the second channel-section steel, second Square steel, lower angle bar, bolt cage plate, the 3rd channel-section steel, upper angle bar, transverse axis, the 4th channel-section steel, the 5th channel-section steel, the 6th channel-section steel, regulation spiral shell It is female, it is characterised in that:Described foundation bolt, stirrup, inner template, gusset, base anchor, reinforcing bar composition foundation bolt component portion Point, foundation bolt head end is in a vertical plane, foundation bolt axial direction horizontal, stirrup, reinforcing bar vertical with head end Foundation bolt is welded and fixed;By in bolt sleeve plate weld to upper angle bar and lower angle bar, upper angle bar and lower angle bar are welded to On three channel-section steels and the 6th channel-section steel, angle bar is respectively welded on the first channel-section steel and the 5th channel-section steel and is connected with transverse axis, respectively by the first groove Steel, the first square steel, the second channel-section steel, the second square steel, the 3rd channel-section steel, the 4th channel-section steel, the 5th channel-section steel, the 6th channel-section steel weld together, Weld adjusting nut on transverse axis and the 3rd channel-section steel, angle bar, crossbeam, regulating bolt is connected with adjusting nut, in the first channel-section steel and 5th channel-section steel upper end grooved bore, crossbeam is put into slotted eye.
2. a kind of horizontal substation framework basis according to claim 1 and overhead transmission line column foot foundation bolt mounting platform, It is characterized in that:Aperture size on described bolt cage plate is consistent with the arc diameter that inner template outer is distributed, and is welded to Aperture center position and center of arc's position consistency of inner template outer distribution on the bolt cage plate of upper angle bar and lower angle bar.
CN201721095896.1U 2017-08-30 2017-08-30 A kind of horizontal substation framework basis and overhead transmission line column foot foundation bolt mounting platform Expired - Fee Related CN207211181U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721095896.1U CN207211181U (en) 2017-08-30 2017-08-30 A kind of horizontal substation framework basis and overhead transmission line column foot foundation bolt mounting platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721095896.1U CN207211181U (en) 2017-08-30 2017-08-30 A kind of horizontal substation framework basis and overhead transmission line column foot foundation bolt mounting platform

Publications (1)

Publication Number Publication Date
CN207211181U true CN207211181U (en) 2018-04-10

Family

ID=61825957

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721095896.1U Expired - Fee Related CN207211181U (en) 2017-08-30 2017-08-30 A kind of horizontal substation framework basis and overhead transmission line column foot foundation bolt mounting platform

Country Status (1)

Country Link
CN (1) CN207211181U (en)

Similar Documents

Publication Publication Date Title
CN102677890B (en) Chimney building formwork lifting device and construction method
CN203247603U (en) High-position foundation bolt positioning device
CN204703182U (en) Crab-bolt stock
CN106906955A (en) A kind of integral prefabricated reinforcing bar web frame of shear wall and its construction method
CN206722404U (en) A kind of narrow end wall single side formwork horizontal reinforcing device
CN112049146A (en) Steel structure foundation embedded part and technological process thereof
CN108756226A (en) Circular columns template construction technique
CN209652970U (en) A kind of large diameter steel pipe installation buttress
CN113550431B (en) Annular steel plate type stirrup for beam column joint area of stiff structure and construction method of annular steel plate type stirrup
CN105586833A (en) Construction method for integrally forming large cast-in-place thin-wall high pier through stiff skeleton reinforcement cage
CN109267493A (en) A kind of construction method installed across river steel lid beam
CN206599919U (en) A kind of integral prefabricated reinforcing bar web frame of shear wall
CN104481167A (en) High-formwork construction method for miscellaneous fill ground
CN203867158U (en) Cantilever type scaffold structure with positioning plug for fixation
CN111424674A (en) Foundation pit reverse construction method steel pipe structure column butt joint platform and butt joint method
CN104358405B (en) The full hall pattern board supporting system of a kind of heavy duty
CN207048305U (en) A kind of shear wall, which dissipates, spells formwork support structure
CN206941823U (en) A kind of shock isolating pedestal
CN103343639A (en) Efficiently-adjusting module sliding system
CN207211182U (en) A kind of vertical substation framework basis and overhead transmission line column foot foundation bolt mounting platform
CN207211181U (en) A kind of horizontal substation framework basis and overhead transmission line column foot foundation bolt mounting platform
CN105839851B (en) Using the construction method for the prefabricated frame trestle that segmentation connection is formed
CN107587770A (en) Disjunctor storehouse synchronization slding form operation method
CN206637189U (en) A kind of large-scale tower crane foundation pre-embedded bolt fixing device
CN206189607U (en) Rag bolt location structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180410

Termination date: 20180830