CN207205635U - A kind of elevator installation tooling for welding platform - Google Patents

A kind of elevator installation tooling for welding platform Download PDF

Info

Publication number
CN207205635U
CN207205635U CN201720986735.5U CN201720986735U CN207205635U CN 207205635 U CN207205635 U CN 207205635U CN 201720986735 U CN201720986735 U CN 201720986735U CN 207205635 U CN207205635 U CN 207205635U
Authority
CN
China
Prior art keywords
mounting groove
welded
telescope motor
plummer
mounting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720986735.5U
Other languages
Chinese (zh)
Inventor
阮俊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Province A Construction And Installation Co Ltd
Original Assignee
Anhui Province A Construction And Installation Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Province A Construction And Installation Co Ltd filed Critical Anhui Province A Construction And Installation Co Ltd
Priority to CN201720986735.5U priority Critical patent/CN207205635U/en
Application granted granted Critical
Publication of CN207205635U publication Critical patent/CN207205635U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Butt Welding And Welding Of Specific Article (AREA)

Abstract

The utility model discloses a kind of elevator installation tooling for welding platform, including workbench, the top both sides of the workbench are installed with fixed station, two fixed stations side close to each other offers the first mounting groove, the first telescope motor is installed with the side inwall that two the first mounting grooves are located remotely from each other, electric rotating machine is installed with the output shaft of two the first telescope motors, grip block is welded with the output shaft of two electric rotating machines, two grip blocks are respectively positioned between two fixed stations, support column is installed with the top of the fixed station, the second telescope motor is installed with the top of support column, the support column is welded with plummer close to the side of workbench middle position, movable block is slidably fitted with plummer, the bottom of movable block extends to the lower section of plummer.The utility model is easy to carry out comprehensive welding to workpiece body, time saving and energy saving, simple in construction, easy to use.

Description

A kind of elevator installation tooling for welding platform
Technical field
It the utility model is related to technical field of welding equipment, more particularly to a kind of elevator installation tooling for welding platform.
Background technology
Welding equipment includes welding machine, welding procedure equipment and welding auxiliary implement, with the development of science and technology people are to welding The requirement more and more higher of equipment.
The existing most structure of welding equipment is relatively more fixed, is not easy to carry out multi-point welding, welds sometimes for to be welded The object connect constantly carries out position adjustment, expends time and efforts, therefore we have proposed a kind of elevator installation platform Welding tooling, for solving the above problems.
The content of the invention
The purpose of this utility model is to solve shortcoming present in prior art, and a kind of elevator installation proposed is applied Work tooling for welding platform.
To achieve these goals, the utility model employs following technical scheme:
A kind of elevator installation tooling for welding platform, including workbench, the fixed peace in top both sides of the workbench Equipped with fixed station, two fixed stations side close to each other offers the first mounting groove, and two the first mounting grooves are located remotely from each other Side inwall on be installed with the first telescope motor, be installed with rotation on the output shaft of two the first telescope motors Rotating motor, grip block is welded with the output shaft of two electric rotating machines, two grip blocks are respectively positioned between two fixed stations, institute State and support column is installed with the top of fixed station, the second telescope motor, the support column are installed with the top of support column Plummer is welded with close to the side of workbench middle position, movable block is slidably fitted with plummer, the bottom of movable block is prolonged The lower section of plummer is extended, and movable block is located at the top of fixed station.
Preferably, carrier block, two carrier blocks side close to each other are welded with the output of first telescope motor The second mounting groove is offered, electric rotating machine is fixedly installed in side of corresponding second mounting groove away from the second installation channel opening On inwall.
Preferably, the 3rd mounting groove is offered at the top of the workbench, two fixed stations are located at the 3rd mounting groove respectively Both sides, be installed with the 3rd telescope motor, the output shaft of the 3rd telescope motor in the bottom interior wall of the 3rd mounting groove On be welded with mounting table, mounting table is located at the top of workbench, and mounting table is placed between two fixed stations on mounting table There is the workpiece body being adapted with grip block.
Preferably, the bottom of the plummer offers the 4th mounting groove, is welded with the both sides inwall of the 4th mounting groove Same slide bar, movable block are slidably mounted on slide bar, and through hole is offered in the top inner wall of the 4th mounting groove.
Preferably, it is welded with pushing block on the output shaft of second telescope motor, the bottom of pushing block and plummer Top is in contact.
Preferably, mobile column is installed with the top of the movable block, mobile column is through through hole and extends to plummer Top, mobile column mutually welds close to the side of the second telescope motor with pushing block.
Preferably, the bottom of the movable block offers the 5th mounting groove, and peace is fixed in the top inner wall of the 5th mounting groove Equipped with the 4th telescope motor, mounting blocks are welded with the output shaft of the 4th telescope motor, mounting blocks are located at the lower section of movable block, and The bottom of mounting blocks is installed with welding gun, and welding gun is located at the top of fixed station.
The beneficial effects of the utility model:By workbench, fixed station, the first telescope motor, carrier block, electric rotating machine, Grip block, the 3rd telescope motor and mounting table are engaged, and are easy to clamp workpiece body, are rotated with this, by holding Microscope carrier, slide bar, movable block, mobile column, the second telescope motor, pushing block, the 4th telescope motor, mounting blocks and support column match Close, be easy to Butt welding gun to move, the utility model is easy to carry out comprehensive welding to workpiece body, time saving and energy saving, structure letter It is single, it is easy to use.
Brief description of the drawings
Fig. 1 be the utility model proposes a kind of elevator installation tooling for welding platform main structure diagram;
Fig. 2 be the utility model proposes a kind of elevator installation tooling for welding platform part A structural representation.
In figure:1 workbench, 2 fixed stations, 3 first mounting grooves, 4 first telescope motors, 5 carrier blocks, 6 electric rotating machines, 7 folders Hold plate, 8 plummers, 9 the 4th mounting grooves, 10 slide bars, 11 movable blocks, 12 mobile columns, 13 second telescope motors, 14 pushing blocks, 15 4th telescope motor, 16 mounting blocks, 17 support columns.
Embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, the technical scheme in the embodiment of the utility model is carried out Clearly and completely describing, it is clear that described embodiment is only the utility model part of the embodiment, rather than whole Embodiment.
Reference picture 1-2, a kind of elevator installation tooling for welding platform, including workbench 1, the top both sides of workbench 1 Fixed station 2 is installed with, two fixed stations 2 side close to each other offers the first mounting groove 3, two first installations The first telescope motor 4 is installed with the side inwall that groove 3 is located remotely from each other, on the output shaft of two the first telescope motors 4 Electric rotating machine 6 is installed with, grip block 7, two 7 equal positions of grip block are welded with the output shaft of two electric rotating machines 6 Between two fixed stations 2, the top of fixed station 2 is installed with support column 17, and the top of support column 17 is installed with Two telescope motors 13, support column 17 are welded with plummer 8 close to the side of the middle position of workbench 1, are slidably installed on plummer 8 There is movable block 11, the bottom of movable block 11 extends to the lower section of plummer 8, and movable block 11 is located at the top of fixed station 2, passes through Workbench 1, fixed station 2, the first telescope motor 4, carrier block 5, electric rotating machine 6, grip block 7, the 3rd telescope motor and mounting table It is engaged, is easy to clamp workpiece body, is rotated with this, passes through plummer 8, slide bar 10, movable block 11, mobile column 12nd, the second telescope motor 13, pushing block 14, the 4th telescope motor 15, mounting blocks 16 and support column 17 are engaged, and are easy to Butt welding gun Move, the utility model is easy to carry out comprehensive welding to workpiece body, time saving and energy saving, simple in construction, easy to use.
In the utility model, carrier block 5 is welded with the output of the first telescope motor 4, two carrier blocks 5 are close to each other Side offers the second mounting groove, and electric rotating machine 6 is fixedly installed in corresponding second mounting groove away from the second installation channel opening Side inwall on, the top of workbench 1 offers the 3rd mounting groove, and two fixed stations 2 are located at the two of the 3rd mounting groove respectively Side, the 3rd telescope motor is installed with the bottom interior wall of the 3rd mounting groove, is welded with the output shaft of the 3rd telescope motor Mounting table, mounting table is located at the top of workbench 1, and mounting table is placed with and pressed from both sides on mounting table between two fixed stations 2 Hold the workpiece body that plate 7 is adapted, the bottom of plummer 8 offers the 4th mounting groove 9, on the both sides inwall of the 4th mounting groove 9 Same slide bar 10 is welded with, movable block 11 is slidably mounted on slide bar 10, is offered in the top inner wall of the 4th mounting groove 9 logical Hole, pushing block 14 is welded with the output shaft of the second telescope motor 13, the bottom of pushing block 14 connects with the top of plummer 8 Touch, the top of movable block 11 is installed with mobile column 12, and mobile column 12 is through through hole and extends to the top of plummer 8, moves Dynamic post 12 welds close to the side of the second telescope motor 13 and the phase of pushing block 14, and the bottom of movable block 11 offers the 5th installation Groove, the 4th telescope motor 15 is installed with the top inner wall of the 5th mounting groove, is welded on the output shaft of the 4th telescope motor 15 Mounting blocks 16 are connected to, mounting blocks 16 are located at the lower section of movable block 11, and the bottom of mounting blocks 16 is installed with welding gun, welding gun position In the top of fixed station 2, by workbench 1, fixed station 2, the first telescope motor 4, carrier block 5, electric rotating machine 6, grip block 7, 3rd telescope motor and mounting table are engaged, and are easy to clamp workpiece body, are rotated with this, by plummer 8, are slided Bar 10, movable block 11, mobile column 12, the second telescope motor 13, pushing block 14, the 4th telescope motor 15, mounting blocks 16 and support Post 17 is engaged, and is easy to Butt welding gun to move, and the utility model is easy to carry out comprehensive welding, time saving province to workpiece body Power, it is simple in construction, it is easy to use.
Operation principle:During work, workpiece body is placed on mounting table first, now opens the first telescope motor 4, is led to Crossing carrier block 5 promotes grip block 7 to clamp workpiece body, now drives mounting table to return to the 3rd by the 3rd telescope motor In mounting groove, the 4th telescope motor 15 is then opened, welding gun is carried out the movement in vertical direction by mounting blocks 16, to workpiece The one side of body welded, it is necessary to when, the second telescope motor 13 can be opened, by pushing block 14 promote mobile column 12 in slide bar Slide on 10, be adjusted with the position of this Butt welding gun, when needing the another side of welding workpiece body, open electric rotating machine 6, Workpiece body is overturn, another side welded with this.
It is described above, the only preferable embodiment of the utility model, but the scope of protection of the utility model is not This is confined to, any one skilled in the art is in the technical scope that the utility model discloses, according to this practicality New technical scheme and its utility model design are subject to equivalent substitution or change, should all cover in protection model of the present utility model Within enclosing.

Claims (7)

1. a kind of elevator installation tooling for welding platform, including workbench(1), it is characterised in that the workbench(1)Top Portion both sides are installed with fixed station(2), two fixed stations(2)Side close to each other offers the first mounting groove(3), Two the first mounting grooves(3)The first telescope motor is installed with the side inwall being located remotely from each other(4), two first flexible Motor(4)Output shaft on be installed with electric rotating machine(6), two electric rotating machines(6)Output shaft on be welded with folder Hold plate(7), two grip blocks(7)It is respectively positioned on two fixed stations(2)Between, the fixed station(2)Top be installed with branch Dagger(17), support column(17)Top be installed with the second telescope motor(13), the support column(17)Close to workbench (1)The side of middle position is welded with plummer(8), plummer(8)On be slidably fitted with movable block(11), movable block(11)'s Bottom extends to plummer(8)Lower section, and movable block(11)Positioned at fixed station(2)Top.
2. a kind of elevator installation tooling for welding platform according to claim 1, it is characterised in that described first is flexible Motor(4)Output on be welded with carrier block(5), two carrier blocks(5)Side close to each other offers the second mounting groove, Electric rotating machine(6)On side inwall of second mounting groove corresponding to being fixedly installed in away from the second installation channel opening.
A kind of 3. elevator installation tooling for welding platform according to claim 1, it is characterised in that the workbench (1)Top offer the 3rd mounting groove, two fixed stations(2)It is located at the both sides of the 3rd mounting groove, the 3rd installation respectively The 3rd telescope motor is installed with the bottom interior wall of groove, mounting table is welded with the output shaft of the 3rd telescope motor, is placed Platform is located at workbench(1)Top, and mounting table is located at two fixed stations(2)Between, it is placed with mounting table and grip block(7) The workpiece body being adapted.
A kind of 4. elevator installation tooling for welding platform according to claim 1, it is characterised in that the plummer (8)Bottom offer the 4th mounting groove(9), the 4th mounting groove(9)Both sides inwall on be welded with same slide bar(10), move Motion block(11)It is slidably mounted on slide bar(10)On, the 4th mounting groove(9)Top inner wall on offer through hole.
5. a kind of elevator installation tooling for welding platform according to claim 1, it is characterised in that described second is flexible Motor(13)Output shaft on be welded with pushing block(14), pushing block(14)Bottom and plummer(8)Top be in contact.
A kind of 6. elevator installation tooling for welding platform according to claim 1, it is characterised in that the movable block (11)Top be installed with mobile column(12), mobile column(12)Through through hole and extend to plummer(8)Top, it is mobile Post(12)Close to the second telescope motor(13)Side and pushing block(14)Mutually weld.
A kind of 7. elevator installation tooling for welding platform according to claim 1, it is characterised in that the movable block (11)Bottom offer the 5th mounting groove, be installed with the 4th telescope motor in the top inner wall of the 5th mounting groove(15), 4th telescope motor(15)Output shaft on be welded with mounting blocks(16), mounting blocks(16)Positioned at movable block(11)Lower section, and Mounting blocks(16)Bottom be installed with welding gun, welding gun is located at fixed station(2)Top.
CN201720986735.5U 2017-08-09 2017-08-09 A kind of elevator installation tooling for welding platform Expired - Fee Related CN207205635U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720986735.5U CN207205635U (en) 2017-08-09 2017-08-09 A kind of elevator installation tooling for welding platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720986735.5U CN207205635U (en) 2017-08-09 2017-08-09 A kind of elevator installation tooling for welding platform

Publications (1)

Publication Number Publication Date
CN207205635U true CN207205635U (en) 2018-04-10

Family

ID=61817873

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720986735.5U Expired - Fee Related CN207205635U (en) 2017-08-09 2017-08-09 A kind of elevator installation tooling for welding platform

Country Status (1)

Country Link
CN (1) CN207205635U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108581295A (en) * 2018-06-22 2018-09-28 滁州市可欣机械科技有限公司 A kind of mechanical processing welding tooling
CN108747149A (en) * 2018-06-22 2018-11-06 滁州市可欣机械科技有限公司 A kind of mechanical processing welding method
CN110948150A (en) * 2018-09-26 2020-04-03 天津龙净环保科技有限公司 Robot welding tool station
CN111390572A (en) * 2019-01-02 2020-07-10 淄博职业学院 Omnidirectional machining device convenient for teaching
CN111438828A (en) * 2020-03-30 2020-07-24 大同新成新材料股份有限公司 Turnover type automatic drilling machine for intelligent pantograph carbon slide plate and drilling method thereof

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108581295A (en) * 2018-06-22 2018-09-28 滁州市可欣机械科技有限公司 A kind of mechanical processing welding tooling
CN108747149A (en) * 2018-06-22 2018-11-06 滁州市可欣机械科技有限公司 A kind of mechanical processing welding method
CN110948150A (en) * 2018-09-26 2020-04-03 天津龙净环保科技有限公司 Robot welding tool station
CN111390572A (en) * 2019-01-02 2020-07-10 淄博职业学院 Omnidirectional machining device convenient for teaching
CN111438828A (en) * 2020-03-30 2020-07-24 大同新成新材料股份有限公司 Turnover type automatic drilling machine for intelligent pantograph carbon slide plate and drilling method thereof
CN111438828B (en) * 2020-03-30 2021-11-30 大同新成新材料股份有限公司 Turnover type automatic drilling machine for intelligent pantograph carbon slide plate and drilling method thereof

Similar Documents

Publication Publication Date Title
CN207205635U (en) A kind of elevator installation tooling for welding platform
CN203254224U (en) Overturn transporting mechanism and loading equipment
CN206200296U (en) A kind of bonding machine
CN203726040U (en) Automobile body numerical control combined welding clamp
CN201744818U (en) Rotary free-angle welding device
CN207606435U (en) A kind of wind-driven generator square chest outside weld annular seam welding device
CN204545770U (en) A kind of robot ambulation welding processing center
CN202539774U (en) Multifunctional automatic welding center of pipe fitting
CN101590578B (en) Welding device for gantry-shaped steel of forklift
CN205552556U (en) High efficiency electric manipulator
CN210359927U (en) Flexible sliding table for vehicle body welding production line
CN205237492U (en) Convertible photovoltaic inverter installs tool
CN213945485U (en) Small-frame robot welding workstation
CN211219630U (en) Drilling machine workstation rotary moving mechanism
CN203448934U (en) Switch cabinet welding device
CN207326427U (en) Coupling member of miniature combined machine tool
CN206358844U (en) A kind of box body overturning machine tool structure
CN204183131U (en) Girth welding machine
CN207564053U (en) A kind of wind-driven generator cylinder welding device
CN208377886U (en) A kind of transport fixture for suit doors production
CN202934257U (en) Microbit welding mechanical hand and microbit automatically-welding machine
CN107297724A (en) A kind of portable power service kit case
CN211136082U (en) Aluminum alloy tool table convenient to weld
CN213165259U (en) Power equipment is with maintenance device convenient to adjust
CN204018975U (en) The multistation material platform of automatic welding machine for circular seam

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180410

Termination date: 20180809