CN207194484U - A kind of assembled level chooses net support system - Google Patents

A kind of assembled level chooses net support system Download PDF

Info

Publication number
CN207194484U
CN207194484U CN201720772107.7U CN201720772107U CN207194484U CN 207194484 U CN207194484 U CN 207194484U CN 201720772107 U CN201720772107 U CN 201720772107U CN 207194484 U CN207194484 U CN 207194484U
Authority
CN
China
Prior art keywords
wall body
supporting frame
stress
support system
stress supporting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720772107.7U
Other languages
Chinese (zh)
Inventor
尹友俊
闫亮
李奇
尹文才
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Jingneng Construction Group Co ltd
Original Assignee
BEIJING KUANGJIAN CONSTRUCTION Co Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING KUANGJIAN CONSTRUCTION Co Co Ltd filed Critical BEIJING KUANGJIAN CONSTRUCTION Co Co Ltd
Priority to CN201720772107.7U priority Critical patent/CN207194484U/en
Application granted granted Critical
Publication of CN207194484U publication Critical patent/CN207194484U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

It the utility model is related to a kind of assembled level and choose net support system, including the wall body built-in fitting being embedded in advance in wall body structure and the end stress pedestal being fixedly connected with the wall body built-in fitting, also include stress supporting frame and Double-layer water plain net, the stress supporting frame is hinged with the end stress pedestal, the Double-layer water plain net is arranged above the stress supporting frame, and it sets up simplicity, and cost is cheap, and it is safe and reliable, while install, remove conveniently.

Description

A kind of assembled level chooses net support system
Technical field
Building external horizontal protective field is the utility model is related to, more particularly to a kind of assembled level chooses net support system System.
Background technology
Existing horizontal net protectiving scheme is set up using 48 steel pipes mostly, sets up that difficulty is big, required for setting up Labour cost and circulation material take height.Also partial protection scheme also uses shaping type building external safety net, but in security On go back Shortcomings, mainly stress pedestal in end is fixedly connected with mode with what stress supporting frame used, while installs, removes It is nor very convenient.
Utility model content
The technical problems to be solved in the utility model is to provide a kind of assembled level and chooses net support system, to original construction Technique is improved, it is intended to which, by entirely being designed and produced to the Force Calculation of support system, each component, actual field installation makes Studied in detail with the several aspects of maintenance, form a set of effective support system scheme.
To achieve the above object, the utility model provides a kind of assembled level and chooses net support system, including is embedded in advance Wall body built-in fitting in wall body structure and the end stress pedestal being fixedly connected with the wall body built-in fitting, in addition to stress branch Support body and Double-layer water plain net, the stress supporting frame are hinged with the end stress pedestal, and the Double-layer water plain net is set Above the stress supporting frame.
Preferably, one end of the Double-layer water plain net is connected to the wall body structure, and the other end is connected to the stress branch Support is held in vitro.
Preferably, in addition to stressed wire rope, the stressed wire rope are located above the stress supporting frame, and one end connects The wall body structure is connected to, the other end is connected to the outer end of the stress supporting frame.
Preferably, one end of the stressed wire rope is connected by bolt with the wall body structure, and the other end passes through back-off It is connected in the U-shaped button on the stress supporting frame with the stress supporting frame.
Preferably, in addition to stressed wire rope, respectively positioned at the stress supporting frame over and under, one end is connected to The wall body structure, the other end are connected to the stress supporting frame.
Preferably, one end of the stressed wire rope is connected by bolt with the wall body structure, and the other end passes through back-off It is connected in the U-shaped button on the stress supporting frame with the stress supporting frame.
Preferably, the wall body built-in fitting is arranged at the external angle position of the wall body structure, and the end stress pedestal is fitted With external corner.
Preferably, the wall body built-in fitting is arranged at the straight angle position of the wall body structure, and the end stress pedestal is fitted Angle of trim.
The beneficial effect of above-mentioned technical proposal of the present utility model is:
Assembled level in such scheme chooses net support system, sets up simplicity, and cost is cheap, and securely and reliably, together When installation, remove it is convenient.
Brief description of the drawings
Fig. 1 is that assembled level of the present utility model chooses net support system schematic diagram;
Fig. 2 is external corner hinged joint schematic diagram of the present utility model;
Fig. 3 is straight angle hinged joint schematic diagram of the present utility model.
Description of reference numerals:
1st, wall body built-in fitting;
2nd, end stress pedestal;
3rd, stress supporting frame;
4th, bolt;
5th, Double-layer water plain net;
6th, stressed wire rope;
7th, steel wire rope is protected.
Embodiment
To make the technical problems to be solved in the utility model, technical scheme and advantage clearer, below in conjunction with accompanying drawing And specific embodiment is described in detail.
As shown in figure 1, the utility model, which provides a kind of assembled level, chooses net support system, including it is embedded in wall body structure in advance In wall body built-in fitting 1 and the end stress pedestal 2 that is fixedly connected with the wall body built-in fitting 1, in addition to stress support frame Body 3 and Double-layer water plain net 5, the stress supporting frame 3 and the end stress pedestal be hinged 2, the Double-layer water plain net 5 is set Above the stress supporting frame 3, during use, first during main structure construction by wall body built-in fitting 1 according to Design attitude carry out it is precisely pre-buried, treat outer protection support body before removing by the installation of end stress pedestal 2, after outer protective frame is removed Stress supporting frame 3 is lifted in place by tower crane, adjusts installation after angle, treats that whole support system installation and debugging are complete Into rear tight double layer security horizontal net, level is chosen when net support system no longer plays safety protection function and utilizes tower crane or crane It is removed according to the opposite sequence of installation and carries out daily maintenance, wall body built-in fitting sets during main structure construction Put, by the accurate pre-buried destruction avoided to agent structure of built-in fitting, stress supporting frame 3 is adopted with end stress pedestal 2 With the type of attachment of hinged joint, stress can be supported when Double-layer water plain net 5 is by heavy impact by the design of hinged joint Slight rotation is produced between support body 3 and end stress pedestal 2, offsets the part moment of flexure received at node.
Specifically, as shown in figure 1, one end of the Double-layer water plain net 5 is connected to the wall body structure, the other end is connected to The outer end of stress supporting frame 3, it is tensioned after the completion of debugging is installed to prevent falling from high altitude thing.
Specifically, as shown in figure 1, also including stressed wire rope 6, the stressed wire rope 6 is located at the stress support frame The top of body 3, one end are connected to the wall body structure, and the other end is connected to the outer end of the stress supporting frame 3.
Specifically, as shown in figure 1, one end of the stressed wire rope 6 is connected by bolt 4 with the wall body structure, separately One end is connected by back-off in the U-shaped button on support frame as described above body with the stress supporting frame 3.
Specifically, as shown in figure 1, also include protection steel wire rope 7, respectively above the stress supporting frame 3 and under Side, one end are connected to the wall body structure, and the other end is connected to the stress supporting frame 3.
Specifically, as shown in figure 1, one end of the stressed wire rope 6 is connected by bolt 4 with the wall body structure, separately One end is connected by back-off in the U-shaped button on the stress supporting frame 3 with the stress supporting frame 3.
With regard to this, the setting of safety steel cable is divided to stress and protection two kinds of setting forms again, and stressed wire rope 6 can ensure Support system stability used in everyday, the design of protection steel wire rope 7 are intended to support system by ensuring stress after enormous impact Supporting frame 3 is movable in the range of safe and reasonable, and power is discharged by safety steel cable to be made so as to play very big buffering With also ensureing the security of support system while being played a protective role to pendant people, junk.
Specifically, as shown in Fig. 2 the wall body built-in fitting is arranged at the external angle position of the wall body structure, the end Stress pedestal 2 is adapted to external corner.
Specifically, as shown in figure 3, the wall body built-in fitting is arranged at the straight angle position of the wall body structure, the end Stress pedestal 2 is adapted to the straight angle.
In such scheme, the setting of wall body built-in fitting during main structure construction, accurate by built-in fitting pre-buried avoids Destruction to agent structure;Type of attachment of the stress supporting frame 3 with end stress pedestal 2 using hinged joint, to pendant people, falls Also the security of support system is ensured while thing plays a protective role;The setting of safety steel cable is divided to two kinds of stress and protection again Setting form, support system stability used in everyday was both ensured, and can is enough to ensure frame after support system is by enormous impact Body is movable in the range of safe and reasonable, and it sets up simplicity, and cost is cheap, and securely and reliably, while install, remove conveniently.
Described above is preferred embodiment of the present utility model, it is noted that for the ordinary skill of the art For personnel, on the premise of principle described in the utility model is not departed from, some improvements and modifications can also be made, these improvement The scope of protection of the utility model is also should be regarded as with retouching.

Claims (8)

1. a kind of assembled level chooses net support system, it is characterised in that including the wall body built-in fitting being embedded in advance in wall body structure And the end stress pedestal being fixedly connected with the wall body built-in fitting, in addition to stress supporting frame and Double-layer water plain net, institute State stress supporting frame to be hinged with the end stress pedestal, the Double-layer water plain net is arranged on the stress supporting frame Side.
2. assembled level according to claim 1 chooses net support system, it is characterised in that the one of the Double-layer water plain net End is connected to the wall body structure, and the other end is connected to the stress supporting frame outer end.
3. assembled level according to claim 1 chooses net support system, it is characterised in that also including stressed wire rope, The stressed wire rope is located above the stress supporting frame, and one end is connected to the wall body structure, and the other end is connected to institute State the outer end of stress supporting frame.
4. assembled level according to claim 3 chooses net support system, it is characterised in that the one of the stressed wire rope End be connected by bolt with the wall body structure, the other end by back-off in the U-shaped button on the stress supporting frame with it is described Stress supporting frame connects.
5. assembled level according to claim 1 chooses net support system, it is characterised in that also include protection steel wire rope, Respectively positioned at the stress supporting frame over and under, one end is connected to the wall body structure, and the other end is connected to institute State stress supporting frame.
6. assembled level according to claim 5 chooses net support system, it is characterised in that the one of the stressed wire rope End be connected by bolt with the wall body structure, the other end by back-off in the U-shaped button on the stress supporting frame with it is described Stress supporting frame connects.
7. assembled level according to claim 1 chooses net support system, it is characterised in that the wall body built-in fitting is set In the external angle position of the wall body structure, the end stress pedestal is adapted to external corner.
8. assembled level according to claim 1 chooses net support system, it is characterised in that the wall body built-in fitting is set In the straight angle position of the wall body structure, the end stress pedestal is adapted to the straight angle.
CN201720772107.7U 2017-06-29 2017-06-29 A kind of assembled level chooses net support system Expired - Fee Related CN207194484U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720772107.7U CN207194484U (en) 2017-06-29 2017-06-29 A kind of assembled level chooses net support system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720772107.7U CN207194484U (en) 2017-06-29 2017-06-29 A kind of assembled level chooses net support system

Publications (1)

Publication Number Publication Date
CN207194484U true CN207194484U (en) 2018-04-06

Family

ID=61785227

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720772107.7U Expired - Fee Related CN207194484U (en) 2017-06-29 2017-06-29 A kind of assembled level chooses net support system

Country Status (1)

Country Link
CN (1) CN207194484U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111561171A (en) * 2020-04-30 2020-08-21 中国五冶集团有限公司 External-insertion portable type limb protection structure and protection method for high-altitude plank road

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111561171A (en) * 2020-04-30 2020-08-21 中国五冶集团有限公司 External-insertion portable type limb protection structure and protection method for high-altitude plank road

Similar Documents

Publication Publication Date Title
CN205012627U (en) Assembly type structure outer wall protects stores pylon outward
CN109505408B (en) Outer wall hole plugging umbrella and construction method
CN202000684U (en) Outwards extending horizontal safety net system used in construction of main body structure of high-rise building
CN207144428U (en) A kind of easy-to-dismount building scaffold
CN207194484U (en) A kind of assembled level chooses net support system
CN204532049U (en) Novel iron tower cat ladder structure
CN206903256U (en) Assembled integral concrete shear wall structure regularization safety net
CN204342306U (en) A kind of novel roofing crane foundation
CN204023319U (en) For the triangular tower of cableway of constructing
CN206487178U (en) Distribution box protection canopy is used in one kind construction
CN207513202U (en) Construction discharging platform
CN206174633U (en) Building engineering protective bracket
CN108551917A (en) A kind of Landscape River movable green belt
CN204993198U (en) Simple and easy solar cell panel support
CN205557314U (en) Wind -resistant rubber shock insulation support
CN204282796U (en) Collapsible hanging basket
CN207110500U (en) The discharging of modularization ready-package and outer protection integrated system for assembled architecture
CN209482832U (en) A kind of construction enclosing
CN208309937U (en) The support construction of artistic stone curtain wall is installed
CN206385822U (en) A kind of civil engineering guard rail
CN206888141U (en) A kind of well lid with anti-drop net
CN203701559U (en) Guiding device for external scaffold
CN206309262U (en) A kind of tower bar maintenance ladder
CN204920416U (en) Simple and easy transmission tower structure
CN206385772U (en) One kind exempts from welding steel structure attachment structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 102399 No. 32, Heishan Avenue, Mentougou District, Beijing

Patentee after: Beijing Jingneng Construction Group Co.,Ltd.

Address before: 102399 No. 32, Heishan Avenue, Mentougou District, Beijing

Patentee before: BEIJING KUANGJIAN CONSTRUCTION GROUP CO.,LTD.

CP01 Change in the name or title of a patent holder
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180406

CF01 Termination of patent right due to non-payment of annual fee