CN207131358U CN201721015902.8U CN201721015902U CN207131358U CN 207131358 U CN207131358 U CN 207131358U CN 201721015902 U CN201721015902 U CN 201721015902U CN 207131358 U CN207131358 U CN 207131358U
Authority
CN
China
Prior art keywords
bottom plate
side wall
mud
storage box
taken out
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721015902.8U
Other languages
Chinese (zh)
Inventor
高登峰
朱肖慧
孙杰
张娅萍
闫计强
付银岿
白铭宇
黄士军
高敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Civil Engineering Co Ltd
Original Assignee
China Construction Civil Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Civil Engineering Co Ltd filed Critical China Construction Civil Engineering Co Ltd
Priority to CN201721015902.8U priority Critical patent/CN207131358U/en
Application granted granted Critical
Publication of CN207131358U publication Critical patent/CN207131358U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses the mud storage box that a kind of drilled pile is taken out of, belong to field of engineering building, for solve in the prior art mud be directly stacked at job site cause construction inconvenience, environmental pollution the problems such as design.The mud storage box that the utility model drilled pile is taken out of includes rectangular-shaped bottom plate and the side wall being arranged on bottom plate, bottom plate and side wall form mud accommodating cavity, bottom plate and side wall are made by metal material, side wall positioned at floor length direction and the side wall positioned at baseplate width direction are made up of at least one piece of metallic plate respectively, it is welded to connect between adjacent metal sheets by the first longitudinally disposed channel-section steel, the bottom of the first longitudinally disposed channel-section steel is welded on bottom plate, and hanger is provided with side wall.The utility model is simple in construction, easy to assembly, intensity is high, and the mud that can take drilled pile out of is left concentratedly, concentrates transhipment, saves construction site, avoids making troubles to job site, avoids polluting ground and neighbouring water source.

Description

The mud storage box that a kind of drilled pile is taken out of
Technical field
It the utility model is related to field of engineering building, more particularly to the mud storage box that a kind of drilled pile is taken out of.
Background technology
In engineering construction, through frequently with drilled pile pore-forming.Drilled pile drill bit would generally take mud (including boring mud) out of, at present These mud are typically directly stacked on the bottom surface of job site, serious to pollute ground and neighbouring water source;And substantial amounts of mud accounts for It is larger with place, cause construction inconvenience;The mud of bulk storage is also not easy to arrange, operated.
Utility model content
The purpose of this utility model is to propose that a kind of mud simple in construction, being easy to drilled pile to take out of leaves fortune concentratedly Turn, place, the mud storage box that the drilled pile for polluting bottom surface and neighbouring water source can be avoided to take out of can be saved.
To use following technical scheme up to this purpose, the utility model:
The mud storage box that a kind of drilled pile is taken out of, including rectangular-shaped bottom plate and the side that is arranged on the bottom plate Wall, the bottom plate and the side wall form mud accommodating cavity, and the bottom plate and the side wall are made by metal material, be located at The side wall in the floor length direction and positioned at the baseplate width direction the side wall respectively by least one block of metal Plate forms, and is welded to connect by the first longitudinally disposed channel-section steel between the adjacent metallic plate, and longitudinally disposed described the The bottom of one channel-section steel is welded on the bottom plate, and hanger is provided with the side wall.
Further, its width is provided with more bracing pieces on the bottom plate.
Further, also bag rectangular reinforcement frame, the rectangular reinforcement frame by several pieces horizontally disposed and head and the tail successively The the second channel-section steel composition being welded to connect, the upper end of each metallic plate is welded on the rectangular reinforcement frame.
Further, the mud accommodating cavity is divided into multiple mud accommodating cavity units.
Further, mudhole is provided with the bottom plate, being provided with below the bottom plate can horizontally rotate to open Or the baffle plate of the closure mudhole.
Further, the hanger is welded on the groove of longitudinally disposed first channel-section steel.
Further, the quantity of the hanger is multiple that multiple hangers divide relative to the axisymmetrical of the bottom plate Cloth.
Further, the fixing end of the hanger is fixed in the side wall, and the height of the free end of the hanger is higher than The height of the fixing end.
The beneficial effects of the utility model are as follows:
The mud that drilled pile provided by the utility model is taken out of is welded to connect between the bottom plate and side wall of storage box, and respectively Individual side wall is made up of at least one piece of metallic plate, is welded between adjacent metal sheets by the first channel-section steel, and the structure of storage box is simple, group Dress is convenient, intensity is high, and the mud that can take drilled pile out of is left concentratedly, in time transports mud, saves construction site, avoids Made troubles to job site, avoid polluting ground and neighbouring water source;Simultaneously because being provided with hanger in side wall, further it is easy to The concentration of mud is transported.
Brief description of the drawings
Fig. 1 is the front view for the mud storage box that the drilled pile that the utility model preferred embodiment provides is taken out of;
Fig. 2 is the side view for the mud storage box that the drilled pile that the utility model preferred embodiment provides is taken out of;
Fig. 3 is the top view for the mud storage box that the drilled pile that the utility model preferred embodiment provides is taken out of.
In figure:1st, bottom plate;2nd, metallic plate;3rd, the first channel-section steel;4th, hanger;5th, bracing piece;6th, the second channel-section steel.
Embodiment
Further illustrate the technical solution of the utility model below in conjunction with the accompanying drawings and by embodiment.
Preferred embodiment:
This preferred embodiment provides the mud storage box that a kind of drilled pile is taken out of, and as shown in Figure 1 to Figure 3, it includes Rectangular-shaped bottom plate 1 and four side walls being arranged on bottom plate 1, bottom plate 1 and four side walls form mud accommodating cavity, bottom plate 1 Be made with side wall by metal material, the side wall positioned at the length direction of bottom plate 1 and the side wall positioned at the width of bottom plate 1 respectively by At least one piece of metallic plate 2 forms, and is welded to connect between adjacent metal sheets 2 by the first longitudinally disposed channel-section steel 3, is set along longitudinal direction The bottom for the first channel-section steel 3 put is welded on bottom plate 1, and hanger 4 is provided with side wall.Hanger 4 is preferably but not limited to welded in On the groove of the first longitudinally disposed channel-section steel 3.In the present embodiment, the metal in side wall can be set according to specific storage demand The parameters such as the quantity of plate 2, height.As a specific embodiment of the present embodiment, the side set along the length direction of bottom plate 1 Wall is made up of three pieces of metallic plates 2, and the side wall set along the width of bottom plate 1 is made up of two pieces of metallic plates 2.
The mud that the drilled pile that the present embodiment provides is taken out of is welded to connect between the bottom plate 1 and side wall of storage box, and respectively Individual side wall is made up of at least one piece of metallic plate 2, welded between adjacent metal sheets 2 by the first channel-section steel 3, the structure letter of storage box It is single, easy to assembly, intensity is high, the mud that can take drilled pile out of is left concentratedly, in time transports mud, save construction field Ground, avoid making troubles to job site, avoid polluting ground and neighbouring water source;Simultaneously because being provided with hanger 4 in side wall, enter One step is easy to the concentration transhipment of mud.
On the basis of said structure, in order to further improve the stability for the mud storage box that drilled pile is taken out of and strong Degree, the mud that drilled pile is taken out of storage box also bag rectangular reinforcement frame, the profile of rectangular reinforcement frame and the profile phase of bottom plate 1 Match somebody with somebody, rectangular reinforcement frame is made up of several blocks of the second channel-section steels 6 that are horizontally disposed and being welded to connect successively from beginning to end, each metallic plate 2 upper end is welded on rectangular reinforcement frame.
On the basis of said structure, in order to further improve the intensity for the mud storage box that drilled pile is taken out of, the bottom of at Its width is provided with more (herein mostly are that exponential quantity is at least two) root bracing pieces 5 on plate 1.Bracing piece 5 is preferably Metallic rod.The quantity of bracing piece 5 and distribution can be configured according to real needs.
In the present embodiment, preferably, mud accommodating cavity is divided into multiple mud accommodating cavity units.Becoming silted up When mud amount is smaller, in one or several mud accommodating cavity units that mud can be placed therein, so as to avoid mud will Mud accommodating cavity all pollutes.
On the basis of said structure, be provided with mudhole on bottom plate 1, the lower section of bottom plate 1 be provided with can horizontally rotate with Open or block the baffle plate of mudhole., can be by direct when needing to discharge in the mud in storage box in the technical program Flap shutter is realized, mud, more convenient operation are exported again without storage box is sling into upset.
On the basis of said structure, the quantity of hanger 4 is multiple, and multiple hangers 4 divide relative to the axisymmetrical of bottom plate 1 Cloth, to improve the stability that storage box transhipment makes.
On the basis of said structure, the fixing end of hanger 4 is fixed in side wall, and the height of the free end of hanger 4 is higher than The height of fixing end.That is, hanger 4 is inclined upwardly setting relative to side wall, in order to be lifted.
Technical principle of the present utility model is described above in association with specific embodiment.These descriptions are intended merely to explain this reality With new principle, and the limitation to scope of protection of the utility model can not be construed in any way.Based on explanation herein, Those skilled in the art, which would not require any inventive effort, can associate other embodiments of the present utility model, These modes are fallen within the scope of protection of the utility model.

Claims (8)

1. the mud storage box that a kind of drilled pile is taken out of, it is characterised in that including rectangular-shaped bottom plate (1) and be arranged at described Side wall on bottom plate (1), the bottom plate (1) and the side wall form mud accommodating cavity, and the bottom plate (1) and the side wall are equal It is made up of metal material, the side wall positioned at the bottom plate (1) length direction and the institute positioned at the bottom plate (1) width State side wall to be made up of at least one piece of metallic plate (2) respectively, pass through the first longitudinally disposed groove between the adjacent metallic plate (2) Steel (3) is welded to connect, and the bottom of longitudinally disposed first channel-section steel (3) is welded on the bottom plate (1), in the side wall It is provided with hanger (4).
2. the mud storage box that drilled pile according to claim 1 is taken out of, it is characterised in that on the bottom plate (1) Its width is provided with more bracing pieces (5).
3. the mud storage box that drilled pile according to claim 2 is taken out of, it is characterised in that also bag rectangular reinforcement frame, The rectangular reinforcement frame is made up of several blocks of the second channel-section steels (6) that are horizontally disposed and being welded to connect successively from beginning to end, Ge Gesuo The upper end for stating metallic plate (2) is welded on the rectangular reinforcement frame.
4. the mud storage box that the drilled pile according to any one of claims 1 to 3 is taken out of, it is characterised in that the silt Mud accommodating cavity is divided into multiple mud accommodating cavity units.
5. the mud storage box that the drilled pile according to any one of claims 1 to 3 is taken out of, it is characterised in that described Mudhole is provided with bottom plate (1), being provided with below the bottom plate (1) can horizontally rotate to open or block the mudhole Baffle plate.
6. the mud storage box that the drilled pile according to any one of claims 1 to 3 is taken out of, it is characterised in that described to hang Ear (4) is welded on the groove of longitudinally disposed first channel-section steel (3).
7. the mud storage box that the drilled pile according to any one of claims 1 to 3 is taken out of, it is characterised in that described to hang The quantity of ear (4) is multiple, and multiple hangers (4) are distributed relative to the axisymmetrical of the bottom plate (1).
8. the mud storage box that the drilled pile according to any one of claims 1 to 3 is taken out of, it is characterised in that described to hang The fixing end of ear (4) is fixed in the side wall, and the height of the free end of the hanger (4) is higher than the height of the fixing end.
CN201721015902.8U 2017-08-14 2017-08-14 The mud storage box that a kind of drilled pile is taken out of Expired - Fee Related CN207131358U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721015902.8U CN207131358U (en) 2017-08-14 2017-08-14 The mud storage box that a kind of drilled pile is taken out of

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721015902.8U CN207131358U (en) 2017-08-14 2017-08-14 The mud storage box that a kind of drilled pile is taken out of

Publications (1)

Publication Number Publication Date
CN207131358U true CN207131358U (en) 2018-03-23

Family

ID=61634840

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721015902.8U Expired - Fee Related CN207131358U (en) 2017-08-14 2017-08-14 The mud storage box that a kind of drilled pile is taken out of

Country Status (1)

Country Link
CN (1) CN207131358U (en)

Similar Documents

Publication Publication Date Title
EP3255000B1 (en) Arrangement structure of stacker device
CN208200203U (en) A kind of adjustable derrick crane of counterweight
CN110306774A (en) A kind of installation method and device of spigot-and-socket builder's jack
CN103243922A (en) Floor concrete thickness control device
CN207131358U (en) The mud storage box that a kind of drilled pile is taken out of
CN202012071U (en) Work platform for boring in water
CN206873870U (en) plastering machine
CN110700872A (en) Construction method of rail top air duct
CN210459878U (en) Vertical transportation device for construction waste
CN204126237U (en) A kind of elevator hoistway construction platform
CN207671531U (en) A kind of building block lifting cage
CN207063047U (en) A kind of gear mud weir for being used to prevent columns base sludge impurity from entering absorbing well, absorption well
CN208648531U (en) A kind of aerated blocks cage with protective cover
CN102020197A (en) Vertical transportation hanger
CN206052692U (en) A kind of bored concrete pile suspension rod
CN207144166U (en) A kind of packing formula case room and its angle supporting device
CN110274448A (en) Refractory brick dries frame
CN204662967U (en) A kind of aluminium alloys profiled template for building material transfer mouth
CN206655484U (en) A kind of Automatic Flow Concrete device for discharging
CN208470673U (en) A kind of fork truck special garbage can
CN206052691U (en) A kind of removable bored concrete pile suspension rod
CN206012590U (en) A kind of underground mine truck bucket for being easy to draining
CN205116697U (en) Easy dismouting aluminum alloy wall form
CN203753721U (en) Sealed type rebar waste box
CN210709275U (en) Improve lifting machine equipment of operating efficiency

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant