CN207109072U - One kind is used for the post-job workpiece cooling device of galvanizing - Google Patents

One kind is used for the post-job workpiece cooling device of galvanizing Download PDF

Info

Publication number
CN207109072U
CN207109072U CN201720798634.5U CN201720798634U CN207109072U CN 207109072 U CN207109072 U CN 207109072U CN 201720798634 U CN201720798634 U CN 201720798634U CN 207109072 U CN207109072 U CN 207109072U
Authority
CN
China
Prior art keywords
cooling
water
pond
galvanizing
blower fan
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720798634.5U
Other languages
Chinese (zh)
Inventor
张辉华
裴虎
陈立学
袁铭
张欢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shiyan City Association of industry and trade Limited by Share Ltd
Original Assignee
Shiyan Association Of Industry And Trade Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shiyan Association Of Industry And Trade Co Ltd filed Critical Shiyan Association Of Industry And Trade Co Ltd
Priority to CN201720798634.5U priority Critical patent/CN207109072U/en
Application granted granted Critical
Publication of CN207109072U publication Critical patent/CN207109072U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Coating With Molten Metal (AREA)

Abstract

One kind is used for the post-job workpiece cooling device of galvanizing, including pond is collected in cooling pond, spraying, cooling removes Water fan and draining water pump;Cooling pond is provided with the cooling device body;The cooling pond side is provided with blower fan water removal collecting pit;The blower fan water removal collecting pit is provided with cooling with cooling pond sidewall upper and removes Water fan;The opposite side of the cooling pond is provided with spraying and collects pond;The spraying is collected and is provided with mist cooling shower nozzle on the support of basin side wall upper end;Groundwater mining water pump is provided with the cooling pond water system and extracts water pump with surface water;Draining water pump is provided with the cooling pond drainage system.This is used for the generally T-shaped structure design of cooling device body that the post-job workpiece cooling device of galvanizing is provided with, and the ear of T words two is respectively to spray to collect pond and blower fan water removal collecting pit, is designed at upper end and is easy to cooling water to flow back to cooling pond.

Description

One kind is used for the post-job workpiece cooling device of galvanizing
Technical field
Hot-galvanizing equipment technical field is the utility model is related to, more particularly to it is a kind of cold for the post-job workpiece of galvanizing But equipment.
Background technology
Galvanizing and galvanizing by dipping are also named in galvanizing, are immersed the steel part after derusting in the zinc liquid of 500 DEG C or so thawings, Make steel member surface attachment zinc layers, so as to play corrosion-resistant purpose.It is a kind of effective anti-corrosion of metal mode, is mainly used in each row On the metal structure facility of industry.Galvanizing is developed by more ancient hot-dipping method, since France in 1836 is hot dip Since zinc is applied to industry, there is the history of more than 180 years.Traditional hot dip galvanizing process flow:Finished product acid-washing-washing- Add quickening liquid-drying-rack plating-cooling-medicine-cleaning-polishing-galvanizing completion.
The inventors discovered that existing workpiece cooling device refrigerating function is more single, cooling effect is not so good as a variety of coolings Function synthesized good cooling results, and it is relatively simple in terms of cooling water selection, it is impossible to according to Season select temperature than relatively low Water source uses as cooling water, so being directed to the problem of existing, it is necessary to be further improved and optimize to existing equipment.
Then, inventor in view of this, adhere to the relevant industries for many years it is abundant design and develop and the experience of actual fabrication, Improvement is studied for existing structure and missing, there is provided one kind is used for the post-job workpiece cooling device of galvanizing, to Reach the purpose with more more practical value.
Utility model content
The purpose of this utility model is that providing one kind is used for the post-job workpiece cooling device of galvanizing, above-mentioned to solve The refrigerating function proposed in background technology is more single, and cooling effect is poor, and relatively simple in terms of cooling water selection, Can not according to the relatively low water source of Season select temperature as cooling water the problem of.
The utility model is used for the purpose and effect of the post-job workpiece cooling device of galvanizing, by technology hand in detail below Section is reached:
One kind is used for the post-job workpiece cooling device of galvanizing, wherein, this is used for the post-job workpiece cooling of galvanizing Equipment includes:
Cooling device body, groundwater mining water pump, surface water extract water pump, cooling pond, spraying collection pond, spraying Shower nozzle, cooling cool except Water fan, blower fan water removal collecting pit and draining water pump;
Cooling pond is provided with the cooling device body;The cooling pond side is provided with blower fan water removal and collected Pond;The blower fan water removal collecting pit is provided with cooling with cooling pond sidewall upper and removes Water fan;The cooling pond it is another Side is provided with spraying and collects pond;The spraying is collected and is provided with mist cooling shower nozzle on the support of basin side wall upper end;Cooling Groundwater mining water pump is provided with the water system in pond and extracts water pump with surface water;Set on the drainage system of cooling pond There is draining water pump.
Further, the generally T-shaped structure design of the cooling device body.
Further, the spraying is collected pond and is connected with blower fan water removal collecting pit with cooling pond, and sprays and receive Collecting-tank may be contained within water level upper end in cooling pond with blower fan water removal collecting pit.
Further, described to cool except Water fan is provided with two groups, cooling pond upper end is one group, and another group is removed in blower fan Water collecting pit upper end is set.
Further, the cooling device body is designed using the seasonal double water type of cooling, using two kinds of cooling waters Source cooling cooling operation.
With existing structure in comparison, the utility model has the following advantages that:
1. the setting of the generally T-shaped structure of the utility model cooling device body, the ear of T words two is respectively to spray to collect Pond and blower fan water removal collecting pit, are designed at upper end and are advantageous to cooling water flowing back to cooling pond.
It is connected 2. pond is collected in the utility model spraying with blower fan water removal collecting pit with cooling pond, and sprays and collect Pond may be contained within the setting of water level upper end in cooling pond with blower fan water removal collecting pit, and this kind, which is designed with, to be beneficial to mist cooling The water that the upper end cooling of water caused by shower nozzle and blower fan water removal collecting pit is blown down except Water fan can by pipeline flow-direction cooling pond, And spray and collect pond with blower fan water removal collecting pit design attitude higher than water level in cooling pond, effectively prevent cooling water from returning Stream.
3. the utility model cooling is provided with two groups except Water fan, cooling pond upper end is one group, and another group is removed in blower fan Water collecting pit upper end is set, and the cooling that the cooling of cooling pond upper end removes cooling water in the cooling pond of Water fan main function position is made With the cooling that blower fan water removal collecting pit upper end is set is advantageous to carry except Water fan mainly clears up on workpiece the cooling water remained High cooling effect, and dry workpiece for the later stage and prepare.
Brief description of the drawings
Fig. 1 is the utility model structure diagram;
Fig. 2 is the utility model rear structure schematic diagram;
Fig. 3 is the utility model overlooking the structure diagram.
In figure:1- cooling device bodies, 2- groundwater mining water pumps, 3- surface water extract water pump, 4- cooling ponds, 5- sprays Mist collects pond, 6- mist cooling shower nozzles, and 7- coolings remove Water fan, 8- blower fans water removal collecting pit, 9- draining water pumps.
Embodiment
Below, embodiment of the present utility model is will be explained in, the example is shown in the accompanying drawings and the description below.Although will The utility model is described with reference to exemplary embodiment, it is to be understood that the description does not really want the utility model to be limited to this to show The embodiment of example property.On the contrary, the utility model will not only cover the exemplary embodiment, but also cover various replacements, Change, equivalent and other embodiment, it can be included in spirit of the present utility model and the model that appended claims are limited In enclosing.
Referring to Fig. 1 to accompanying drawing 3, one kind is used for the post-job workpiece cooling device of galvanizing, included:
Cooling device body 1, groundwater mining water pump 2, surface water extract water pump 3, cooling pond 4, spraying collection pond 5th, mist cooling shower nozzle 6, cooling are except Water fan 7, blower fan water removal collecting pit 8 and draining water pump 9;
Cooling pond 4 is provided with cooling device body 1;The side of cooling pond 4 is provided with blower fan water removal collecting pit 8;Wind Machine removes water collecting pit 8 and the sidewall upper of cooling pond 4 is provided with cooling and removes Water fan 7;The opposite side of cooling pond 4 is provided with Pond 5 is collected in spraying;Spraying is collected and is provided with mist cooling shower nozzle 6 on the sidewall upper support of pond 5;The water supply of cooling pond 4 Groundwater mining water pump 2 is provided with system and extracts water pump 3 with surface water;Draining is provided with the drainage system of cooling pond 4 Water pump 9.
Preferred embodiment for the post-job workpiece cooling device of galvanizing as described above, wherein, cooling device The generally T-shaped structure design of body 1, the ear of T words two are respectively to spray to collect pond 5 and blower fan water removal collecting pit 8, are designed at It is easy to cooling water to flow back to cooling pond 4 in upper end.
Preferred embodiment for the post-job workpiece cooling device of galvanizing as described above, wherein, spraying is collected Pond 5 is connected with blower fan water removal collecting pit 8 with cooling pond 4, and pond 5 is collected in spraying and blower fan water removal collecting pit 8 is equal Water level upper end in cooling pond 4 is arranged at, this kind design is easy to water caused by mist cooling shower nozzle 6 and blower fan water removal collecting pit The cooling of 8 upper ends can be by pipeline flow-direction cooling pond 4 except the water that Water fan 7 is blown down, and collection pond 5 of spraying is removed with blower fan The design attitude of water collecting pit 8 effectively prevents cooling water from flowing back higher than water level in cooling pond 4.
Preferred embodiment for the post-job workpiece cooling device of galvanizing as described above, wherein, cooling water removal Blower fan 7 is provided with two groups, and the upper end of cooling pond 4 is one group, and another group is set in blower fan water removal collecting pit 8 upper end, cooling pond The cooling of 4 upper ends removes the cooling effect of cooling water in the main function position cooling pond 4 of Water fan 7, and blower fan water removal collecting pit 8 upper end is set The cooling put mainly clears up on workpiece the cooling water remained except Water fan 7, is easy to improve cooling effect, and dry for the later stage Prepare.
Preferred embodiment for the post-job workpiece cooling device of galvanizing as described above, wherein, cooling device Body 1 is designed using the seasonal double water type of cooling, is cooled operation using two kinds of cooling water sources, uses earth's surface during winter Water is cooled as cooling water, is cooled using underground water as cooling water during summer, is easy to use in each season The minimum water of temperature uses as cooling water, effectively improves cooling effect.
The operation principle of the present embodiment:
When being used for the post-job workpiece cooling device of galvanizing using this, cooling will be injected among cooling pond first Water, water pump 3 is extracted by groundwater mining water pump 2 and surface water respectively and carries out cooling water implant operation, is opened if tangible winter Dynamic surface water extracts water pump 3 and carries out water flood operations, because winter earth's surface coolant-temperature gage is lower, cooling effect can be more preferable, if The season water fillings such as tangible summer then open groundwater mining water pump 2 and carry out water filling, because these season underground water water temperatures can be more Low, cooling effect can be more preferable, then transports part to the upper end of cooling device body 1 by hanging car, when workpiece is received by spraying During 5 upper end of collecting-tank, the mist cooling shower nozzle 6 of setting starts, and the cooling water among cooling pond 4 is sprayed by the water pump of setting To workpiece, as first cooling, prevent from being disposably put into cooling pond 4 and produce quality problems, pond 5 is collected in then spraying The water fallen can then be flowed back among cooling pond 4 by pipeline, and then hanging car continues to operate forward, reaches on cooling pond 4 Space-time, workpiece slowly decline, and entirely submerge among the cooling water of cooling pond 4, and the cooling then set is except Water fan 7 is to cooling water Cooled, cooling it is similar after, hanging car slowly lifts, and transports workpiece to blower fan water removal collecting pit 8 upper end, Ran Houtong The cooling set is crossed except Water fan 7 blows off the cooling water remained on workpiece, then removing water collecting pit 8 by blower fan flows back to cooling Among pond 4, drying passivation procedure together then can be carried out down, the draining water pump 9 of setting can be passed through when cooling water must be changed Drained replacing.
It should be noted that the standardized element that uses of the utility model can commercially, shaped piece according to Specification and accompanying drawing record can carry out customized, and the specific connected mode of each part is using ripe in the prior art Bolt, rivet, the conventional meanses such as welding, machinery, part and equipment are using in the prior art, conventional model, inventor It will not be described in detail herein.
In summary, although the utility model is described in detail with reference to the foregoing embodiments, for this area For technical staff, it can still modify to the technical scheme described in foregoing embodiments, or to which part Technical characteristic carries out equivalent substitution, all within the spirit and principles of the utility model, any modification for being made, equivalent substitution, Improve etc., it should be included within the scope of protection of the utility model.

Claims (5)

1. one kind is used for the post-job workpiece cooling device of galvanizing, it is characterised in that:Described is post-job for galvanizing Workpiece cooling device includes:
Cooling device body, groundwater mining water pump, surface water extract water pump, cooling pond, spraying collection pond, mist cooling Shower nozzle, cooling are except Water fan, blower fan water removal collecting pit and draining water pump;
Cooling pond is provided with the cooling device body;The cooling pond side is provided with blower fan water removal collecting pit;Institute State blower fan water removal collecting pit and cooling pond sidewall upper is provided with cooling and removes Water fan;The opposite side of the cooling pond is set It is equipped with spraying and collects pond;The spraying is collected and is provided with mist cooling shower nozzle on the support of basin side wall upper end;Cooling pond Groundwater mining water pump is provided with water system and extracts water pump with surface water;Draining is provided with the drainage system of cooling pond Water pump.
2. according to claim 1 be used for the post-job workpiece cooling device of galvanizing, it is characterised in that:The cooling dress Put the generally T-shaped structure design of body.
3. according to claim 1 be used for the post-job workpiece cooling device of galvanizing, it is characterised in that:The spraying is received Collecting-tank is connected with blower fan water removal collecting pit with cooling pond, and collection pond of spraying is respectively provided with blower fan water removal collecting pit In water level upper end in cooling pond.
4. according to claim 1 be used for the post-job workpiece cooling device of galvanizing, it is characterised in that:The cooling removes Water fan is provided with two groups, and cooling pond upper end is one group, and another group is set in blower fan water removal collecting pit upper end.
5. according to claim 1 or 2 be used for the post-job workpiece cooling device of galvanizing, it is characterised in that:It is described cold But device body is designed using the seasonal double water type of cooling, is cooled operation using two kinds of cooling water sources.
CN201720798634.5U 2017-07-04 2017-07-04 One kind is used for the post-job workpiece cooling device of galvanizing Expired - Fee Related CN207109072U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720798634.5U CN207109072U (en) 2017-07-04 2017-07-04 One kind is used for the post-job workpiece cooling device of galvanizing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720798634.5U CN207109072U (en) 2017-07-04 2017-07-04 One kind is used for the post-job workpiece cooling device of galvanizing

Publications (1)

Publication Number Publication Date
CN207109072U true CN207109072U (en) 2018-03-16

Family

ID=61587170

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720798634.5U Expired - Fee Related CN207109072U (en) 2017-07-04 2017-07-04 One kind is used for the post-job workpiece cooling device of galvanizing

Country Status (1)

Country Link
CN (1) CN207109072U (en)

Similar Documents

Publication Publication Date Title
CN107192111A (en) A kind of condensate water recovery device of air conditioner
CN205489168U (en) Cubical switchboard water storage heat sink
CN107151768A (en) One kind is used for the post-job workpiece cooling device of galvanizing
CN103215608B (en) Integrated-type acid-washing unit
CN207109072U (en) One kind is used for the post-job workpiece cooling device of galvanizing
CN206113692U (en) Cycling use of water and automatic water supply's closed type cooling tower
CN203785483U (en) Double-spraying reverse flow closed cooling tower containing pre-cooling filler
CN204453420U (en) Petrol storage tank abhiseca rainwater concentrates discharge, clean-up device
CN207159272U (en) It is a kind of to process the cleaning equipment after groove for quenching workpiece
CN207720811U (en) A kind of fritillaria plantation greenhouse
CN206244405U (en) A kind of hydrogen fluoride cooling system equipped with shell and tube water cooler
CN206430090U (en) A kind of device that high-temperature vapour is converted into gas at normal temperature
CN202420065U (en) Water-saving device for ice maker
CN205658286U (en) Cold water -chilling plant of fountain fruit vegetables
CN209968050U (en) High-efficient zinc cigarette dust removal absorption tower
CN208620868U (en) A kind of hot gas cooling device
CN207422930U (en) A kind of energy-saving cooling tower
CN105838832A (en) Water supply and drainage and exhaust system of blast furnace
CN208275671U (en) A kind of heating plant water attack rifle
CN112595139A (en) Closed cooling tower with coil pipe acid pickling descaling device
CN206643137U (en) A kind of hot rolling wire production line spray equipment
CN205412301U (en) Gaseous condensing equipment of dual chemical industry
CN220597667U (en) Electroplating noble metal steam internal recovery device
CN205919554U (en) Absorption type refrigerating unit
CN212390870U (en) Reverse water distribution industrial cooling tower

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 442000 Xicheng Road, Zhang Wan District, Shiyan, Hubei Province, No. 88

Patentee after: Shiyan City Association of industry and trade Limited by Share Ltd

Address before: 442000 Xicheng Road, Zhang Wan District, Shiyan, Hubei Province, No. 88

Patentee before: Shiyan Association of industry and Trade Co., Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180316