- Publication number
- CN206113692U CN206113692U CN201620985475.5U CN201620985475U CN206113692U CN 206113692 U CN206113692 U CN 206113692U CN 201620985475 U CN201620985475 U CN 201620985475U CN 206113692 U CN206113692 U CN 206113692U
- Authority
- CN
- China
- Prior art keywords
- water
- cooling tower
- closed cooling
- collecting
- heat exchange
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Heat-Exchange Devices With Radiators And Conduit Assemblies (AREA)
Abstract
The utility model relates to a cycling use of water and automatic water supply's closed type cooling tower, including the tower body, locate the dryer on tower body top, locate the air intake of tower body lower part tower wall, locate organizing from last receipts hydrophone, spray set, stainless steel heat exchange coil to setting gradually down of inner cavity of tower to and locate the catch basin of bottom in the tower body, spray set sprays the pump through one and links to each other with the catch basin, forms a loop structure, show and spray one side that the catch basin was located to the pump, the sunction inlet department that sprays the pump is equipped with filter equipment, and this filter equipment adopts stainless steel's filter screen, and the other drain that still is equipped with of filter equipment, the closed type cooling tower still includes the moisturizing device of being connected and being used for replenishing to the catch basin circulating water with external water source.
Description
Technical field
This utility model is related to cooling tower technical field, more particularly to the closed of a kind of cycling use of water and automatic water supplement is cold
But tower.
Background technology
Closed cooling tower is a kind of efficient cooling device, the cooling principle of closed cooling tower:Closed cooling tower
Conduct heat outside the evaporation enhanced tube for being mainly characterized by utilize outside tube water film of (evaporating air cooler), its course of work will be set with pump
Recirculated cooling water in standby bottom pond is transported to the spray water dispenser above the light pipe tube bank of horizontal positioned, by distributing
Cooling water is sprayed downwards device tube surface, makes tube outer surface form continuous thin water film;Simultaneously with blower fan by air from
The suction window suction of equipment lower air, makes air flow from bottom to top.Now the heat transfer outside a tube of heat-transfer pipe except by moisture film with
Outside sensible heat transfer between air stream, the rapid evaporation of tube outer surface moisture film absorbs substantial amounts of heat, enhances the outer heat transfer of pipe.Mesh
It is front to be widely used in the industries such as refrigeration, chemical industry, food, injection, metallurgy, weaving.
General, the spray equipment of closed cooling tower is connected by a spray pump with collecting-tank, forms a cycling use of water
May there is impurity in structure, the water life-time service in collecting-tank, the water direct circulation containing impurity enters back into spray equipment meeting
Cause the obstruction of spray system, the failure for causing follow-up cooling tower to use.
Because cooling tower is in running, it is necessary to evaporate a certain amount of water to take away a certain amount of heat, so necessary
Timely add the lost water yield.
Utility model content
The purpose of this utility model is to provide the closed cooling tower of a kind of cycling use of water and automatic water supplement, realize energy-conservation,
Environmental protection, spray equipment are difficult obstruction, and the technique effect of cycling use of water and automatic water supplement using smooth.
In order to solve above-mentioned technical problem, this utility model provides a kind of cycling use of water and the closed of automatic water supplement is cold
But tower, including tower body, located at the air duct on tower body top, located at the air inlet of tower body bottom tower wall, located at tower body inner chamber from upper
Water collection device, spray equipment, the rustless steel heat exchange coil group set gradually under, and in tower body bottom collecting-tank;Its
If described in rustless steel heat exchange coil group include dry tablet heat exchange coil, and the two ends of the rustless steel heat exchange coil group connect respectively
One hot water inlet port and cold water outlet;The cold water outlet is provided with a temperature sensor;The air duct is included in air duct
Demister and axial flow blower;The water collection device includes some water collecting pieces, and is arranged on rising between adjacent two water collecting piece
The socket joint connector of interval fixation;The spray equipment is connected by a spray pump with collecting-tank, forms a circulation knot
Structure;Shown spray pump is located at the side of collecting-tank;Defecator is provided with the suction inlet of the spray pump, the defecator is adopted
The drainage screen of stainless steel;And it is additionally provided with a sewage draining exit by the defecator;The closed cooling tower also include with
External source connects and for the water replanishing device of collecting-tank replenishment cycles water.
Further, the air inlet is vertically provided with air-inlet grille;The air-inlet grille by least one mesh grille according to
Secondary superposition is constituted;And the mesh grille is in cellular and is made up of some grizzly bars being connected with each other and framework.
Further, the water collecting piece includes the connecting portion located at center, and the left and right drainage for being distributed in connecting portion both sides
Portion;The connecting portion is in strip, and surface is arc;The left and right water-filtering part is provided with and is suitable to be connected with socket joint connector
Connecting hole;At least two ribs that block water are arranged with the left and right water-filtering part upper surface, i.e., on described left and right water-filtering part
End face is wavy in M types.
Further, horizontally disposed the first square tube and the second square tube for having some vertical distributions of the cylinder top of the air duct;
The cylinder top is additionally provided with some grooves being engaged with the first square tube two ends, i.e. the first square tube is inlaid in the groove,
And second the bottom surface of square tube contact with the top surface of the first square tube;The demister is arranged on the top of axial flow blower.
Further, the heat exchange coil of the monolithic is serpentine coil and adopts the serpentine configuration without longitudinal ream.
Further, the water replanishing device includes that the first moisturizing joint being located on the pool wall of collecting-tank and the second moisturizing connect
Head;And the first moisturizing joint and the second moisturizing joint are connected with the water side of a tee T;The tee T
Water inlet end is connected with the water inlet pipe of external source;The first moisturizing joint is also connected with a floating ball valve;The floating ball valve
Ball float is in collecting-tank;The position of the first moisturizing joint is higher than the second moisturizing joint.
Further, the closed cooling tower also includes that one is connected by cable, wire with spray pump and temperature sensor
Electric control constant-temperature switch board.
Further, matcoveredn is coated on the heat exchange coil outer surface of the monolithic;The protective layer is corrosion-resistant and resistance to
The protective layer of perforation.
Further, the closed cooling tower is also included located at tower top for powering too to the closed cooling tower
Positive energy photovoltaic panel.
Further, the solar energy photovoltaic panel is connected by solar recharging management module with accumulator;The accumulator
Outfan is connected Jing after functional transformer regulation with closed cooling tower.
The beneficial effects of the utility model are that closed cooling tower of the present utility model, simple structure, spray equipment passes through
One spray pump is connected with collecting-tank, forms a cycling use of water structure, energy-conserving and environment-protective, further through what is arranged at spray Pump Suction Nozzle
Drainage screen, can effectively filter the impurity in collecting-tank, prevent impurity from causing the obstruction of spray equipment.Again due to general closed cold
But tower is in running, it is necessary to evaporate a certain amount of water to take away a certain amount of heat, the automatic water supplement by arranging
Device is conducive to adding the lost water yield in time.Again by the demister for arranging, the fog removal performance of this cooling tower is enhanced.
Description of the drawings
This utility model is further illustrated with reference to the accompanying drawings and examples.
Fig. 1 is the structural representation of the water collection device of the closed cooling tower of cycling use of water of the present utility model and automatic water supplement
Figure;
Fig. 2 is the knot of the water collecting piece of the water collection device of the closed cooling tower of cycling use of water of the present utility model and automatic water supplement
Structure schematic diagram;
Fig. 3 is the structural representation of the closed cooling tower of cycling use of water of the present utility model and automatic water supplement;
Fig. 4 is that the inlet grid structure of the closed cooling tower of cycling use of water of the present utility model and automatic water supplement is illustrated
Figure;
Fig. 5 is that the structure of the air duct top end face of the closed cooling tower of cycling use of water of the present utility model and automatic water supplement is shown
It is intended to.
In figure:Water collecting piece 1, socket joint connector 2, connecting portion 3, water-filtering part 4, connecting hole 5, the rib 6 that blocks water, water collection device 7, tower
Body 8, air duct 9, air inlet 10, collecting-tank 11, spray equipment 12, rustless steel heat exchange coil group 13, spray pump 14, drainage screen 15,
Sewage draining exit 16, axial flow blower 17, demister 18, air-inlet grille 19, grizzly bar 20, framework 21, the first moisturizing joint 22, second are mended
Water swivel 23, tee T 24, ball float 25, the first square tube 26, the second square tube 27, groove 28.
Specific embodiment
This utility model is described in further detail presently in connection with accompanying drawing.These accompanying drawings are simplified schematic diagram,
Basic structure of the present utility model is only illustrated in a schematic way, therefore it only shows the composition relevant with this utility model.
Embodiment 1
As shown in Figures 1 to 5, the closed cooling tower of cycling use of water of the present utility model and automatic water supplement, including tower body
8, located at the air duct 9 on the top of tower body 8, located at the air inlet 10 of the bottom tower wall of tower body 8, located at the inner chamber of tower body 8 from top to bottom according to
The water collection device 7 of secondary setting, spray equipment 12, rustless steel heat exchange coil group 13, and in tower body 8 bottom collecting-tank 11;
If wherein described rustless steel heat exchange coil group 13 includes dry tablet heat exchange coil, and the two ends of the rustless steel heat exchange coil group 13 point
Do not connect a hot water inlet port and cold water outlet;The cold water outlet is provided with a temperature sensor;The air duct 9 includes setting
Demister 18 and axial flow blower 17 in air duct 9;The water collection device 7 includes some water collecting pieces 1, and is arranged on adjacent two
The socket joint connector 2 for playing interval fixation between water collecting piece 1;The spray equipment 12 is by a spray pump 14 and collecting-tank
11 are connected, and form a loop structure;Shown spray pump 14 is located at the side of collecting-tank 11;At the suction inlet of the spray pump 14
Defecator is provided with, the defecator adopts the drainage screen 15 of stainless steel;And it is additionally provided with a row by the defecator
Dirty mouth 16;The closed cooling tower also includes being connected with external source and for giving the moisturizing of the replenishment cycles water of collecting-tank 11 dress
Put.
Specifically, the blade of the axial flow blower 17 adopts hollow aluminum alloy material, and central hub is high-strength steel sheet, with
With enough intensity when ensureing that axial flow blower 17 rotates at a high speed.The fairshaped axial flow blower 17 of wing, is ensureing enough wind
While amount and blast, the noise of axial flow blower 17 is reduced.The drainage screen 15 is used to prevent the impurity of collecting-tank 11 direct
Spray equipment 12 is entered into, the obstruction failure of spray equipment 12 is in turn resulted in, the sewage draining exit 16 is located at the bottom of collecting-tank 11
Lowest point, maintains easily personnel's directly cleaning silt from collecting-tank 11.
Preferably, the air inlet 10 is vertically provided with air-inlet grille 19;The air-inlet grille 19 by least one it is netted
Grid is sequentially overlapped composition;And the mesh grille is in cellular and by some grizzly bars 20 being connected with each other and the structure of framework 21
Into.
Specifically, each mesh grille can be dismantled conveniently, facilitate staff to be cooled down into collecting-tank 1111
The maintaining of tower.Further through the cellular design of the air-inlet grille 19 so that ventilation-sectional area is big, and flowing resistance is little, can
Effectively to prevent from dabbling, and block sunlight enters cooling tower, and then prevents the growth of fungi-proofing and antimicrobial, it is ensured that inner loop water
Cleaning.
The water collecting piece 1 includes the connecting portion 3 located at center, and the left and right water-filtering part 4 for being distributed in the both sides of connecting portion 3;
The connecting portion 3 is in strip, and surface is arc;The left and right water-filtering part 4 is provided with and is suitable to be connected with socket joint connector 2
Connecting hole 5;At least two ribs 6 that block water, i.e., described left and right water-filtering part are arranged with the upper surface of left and right water-filtering part 4
4 upper surfaces are wavy in M types.
Specifically, the water collecting piece 1 is by the hot-forming thin slice of modified PVC material.Compared with traditional handicraft material manufacture
The windage that produces of water collection device 7 it is little, and the shape size pattern of every water collecting piece 1 is, therefore only needs to a secondary mould suction
A kind of water collecting piece 1 of modeling processing, is simple to manufacture, low cost.Simultaneously as being provided with several ribs 6 that block water, the described rib that blocks water
6 contacts area for increasing water collecting piece 1 and water, can effectively prevent saliva stream of the water droplet on water cambered surface is received, it is to avoid water collection device 7
The secondary water phenomenon of floaing for being formed.
The cylinder top of the air duct 9 is horizontally disposed first square tube 26 and the second square tube 27 of some vertical distributions;Institute
State cylinder top and be additionally provided with some grooves 28 being engaged with the two ends of the first square tube 26, i.e. the first square tube 26 and be inlaid in the groove
In 28, and the bottom surface of the second square tube 27 contacts with the top surface of the first square tube 26;The demister 18 is arranged on axial flow blower
17 top.By the demister 18 for being arranged on the top of axial flow blower 17, can be by the vapor in the humid air after heat exchange
Cold-trap is got off, and affects little to the ventilation of cooling tower, and eliminating water fog effect is good.
The heat exchange coil of the monolithic is serpentine coil and adopts the serpentine configuration without longitudinal ream.
Preferably, the rustless steel heat exchange coil group 13 is beneficial to rustless steel heat exchange coil along water (flow) direction support with favored policy
Group 13 is emptied.Specifically, in manufacturing process, each monolithic heat exchange coil is through pressure for the rustless steel heat exchange coil group 13
For the strict test of 2.5Mpa, the overall rustless steel heat exchange coil group 13 after assembling will also be through a 2.5Mpa air-tightness examination
Test, it is ensured that the pressure performance of rustless steel heat exchange coil group 13.
Preferably, the hot water inlet port top of the rustless steel heat exchange coil group 13 is additionally provided with an air inlet, is suitable to access
Pressure-air, to aid in the fast evacuation of rustless steel heat exchange coil group 13.
The water replanishing device includes the first moisturizing joint 22 and the second moisturizing joint 23 on the pool wall of collecting-tank 11;
And the first moisturizing joint 22 and the second moisturizing joint 23 are connected with the water side of a tee T 24;The tee T
24 water inlet end is connected with the water inlet pipe of external source;The first moisturizing joint 22 is also connected with a floating ball valve;The floating
The ball float 25 of ball valve is in collecting-tank 11;The position of the first moisturizing joint 22 is higher than the second moisturizing joint 23.
Specifically, when the water level in collecting-tank 11 is low, ball float 25 is reduced with water level, by the connecting rod band of fixed ball float 25
Piston in the valve body of dynamic ball-cock assembly pulls outward, and makes to produce space between valve body and piston, makes water enter collecting-tank 11.And this
Water replanishing device remains original manual water inlet while ball-cock assembly is added, so when ball-cock assembly breaks down, can be with
Moisturizing, convenient maintenance are carried out with manual.
The closed cooling tower also includes that one is automatically controlled with what spray pump 14 and temperature sensor were connected by cable, wire
Constant-temperature control cabinet.Specifically, the electric control constant-temperature switch board be suitable to receive temperature sensor send data, and according to data from
The closing of dynamic adjustment spray pump 14 and/opening, i.e., when the temperature of cooling water outlet is higher than setting high temperature values, automatic spray
Drench pump 14;When temperature drop is to the low temperature for setting, it is automatically switched off spray pump 14 to stop supplying water.By above-mentioned process, will
The cold water outlet temperature control of closed cooling tower of the present utility model ensures the temperature for cooling down in set scope
Reach requirement.Preferably, above-mentioned electric control constant-temperature switch board is additionally provided with alarm device, and the alarm device includes buzzer and red instruction
Lamp, when the temperature anomaly of cold water outlet, starts alarm device.
Preferably, matcoveredn is coated on the heat exchange coil outer surface of the monolithic;The protective layer is corrosion-resistant and resistance to
The protective layer of perforation.Specifically, the material of the heat exchange coil of the monolithic is using copper or rustless steel.Described corrosion-resistant and resistance to perforation
Protective layer material be politef.Corrosion-resistant and resistance to perforation protective layer can prevent the heat exchange coil from connecing with water
Touch, or react in the case of high temperature, and then can prevent heat exchange coil from being corroded, scale, making for heat exchange coil can be extended
With the life-span, and due to the thinner thickness of the protective layer coating, therefore the heat-exchange capacity of heat exchange coil is not interfered with.
The closed cooling tower is also included located at tower top for the solar energy powered to the closed cooling tower
Volt plate.Closed cooling tower is powered using solar energy, reduces consumption of the closed cooling tower to conventional electric energy, energy-conservation and ring
Protect.
The solar energy photovoltaic panel is connected by solar recharging management module with accumulator;The outfan Jing of the accumulator
Functional transformer is connected after adjusting with closed cooling tower.
Preferably, the inwall of the tower body 8 is additionally provided with silencing cotton structure.It is cold that the structure of silencing cotton advantageously reduces the closed
But the noise of the tower generation such as Water spray process, axial flow blower 17 in the course of the work.
With it is above-mentioned according to desirable embodiment of the present utility model as enlightenment, by above-mentioned description, related work people
Member can carry out various change and modification in the range of without departing from this utility model technological thought completely.This reality
The content being not limited to new technical scope in description, it is necessary to its technology is determined according to right
Property scope.
Claims (9)
1. the closed cooling tower of a kind of cycling use of water and automatic water supplement, it is characterised in that including tower body, located at tower body top
Air duct, located at the air inlet of tower body bottom tower wall, the water collection device for setting gradually from top to bottom, spray dress located at tower body inner chamber
Put, rustless steel heat exchange coil group, and in tower body bottom collecting-tank;Wherein
If the rustless steel heat exchange coil group includes dry tablet heat exchange coil, and the two ends of the rustless steel heat exchange coil group connect respectively
Connect a hot water inlet port and cold water outlet;The cold water outlet is provided with a temperature sensor;
The air duct includes demister and axial flow blower in air duct;
The water collection device includes some water collecting pieces, and the socket joint for playing interval fixation being arranged between adjacent two water collecting piece
Connector;
The spray equipment is connected by a spray pump with collecting-tank, forms a loop structure;Shown spray pump is located at and catchments
The side in pond;
Defecator is provided with the suction inlet of the spray pump, the defecator adopts the drainage screen of stainless steel;And institute
State and be additionally provided with by defecator a sewage draining exit;
The closed cooling tower also includes being connected with external source and for the water replanishing device of collecting-tank replenishment cycles water;With
And
The closed cooling tower also includes an electric control constant temperature control being connected with spray pump and temperature sensor by cable, wire
Cabinet processed.
2. closed cooling tower according to claim 1, it is characterised in that the air inlet is vertically provided with air-inlet grille;
The air-inlet grille is sequentially overlapped by least one mesh grille and is constituted;And
The mesh grille is in cellular and is made up of some grizzly bars being connected with each other and framework.
3. closed cooling tower according to claim 2, it is characterised in that the water collecting piece includes the connection located at center
Portion, and it is distributed in the left and right water-filtering part of connecting portion both sides;The connecting portion is in strip, and surface is arc;
The left and right water-filtering part is provided with the connecting hole for being suitable to be connected with socket joint connector;
At least two ribs that block water are arranged with the left and right water-filtering part upper surface, i.e., described left and right water-filtering part upper surface is in
M types are wavy.
4. closed cooling tower according to claim 3, it is characterised in that the cylinder top of the air duct is horizontally disposed to be had
First square tube and the second square tube of some vertical distributions;The cylinder top is additionally provided with and some is engaged with the first square tube two ends
Groove, i.e. the first square tube are inlaid in the groove, and the bottom surface of the second square tube contacts with the top surface of the first square tube;It is described to remove
Mist device is arranged on the top of axial flow blower.
5. closed cooling tower according to claim 4, it is characterised in that the heat exchange coil of the monolithic is serpentine coil
And using the serpentine configuration without longitudinal ream.
6. closed cooling tower according to claim 5, it is characterised in that the water replanishing device is included located at collecting-tank
The first moisturizing joint and the second moisturizing joint on pool wall;And
The first moisturizing joint and the second moisturizing joint are connected with the water side of a tee T;The water inlet of the tee T
End is connected with the water inlet pipe of external source;
The first moisturizing joint is also connected with a floating ball valve;The ball float of the floating ball valve is in collecting-tank;
The position of the first moisturizing joint is higher than the second moisturizing joint.
7. closed cooling tower according to claim 6, it is characterised in that apply on the heat exchange coil outer surface of the monolithic
It is covered with protective layer;The protective layer is corrosion-resistant and resistance to perforation protective layer.
8. closed cooling tower according to claim 7, it is characterised in that the closed cooling tower is also included located at tower
Top for the solar energy photovoltaic panel powered to the closed cooling tower.
9. closed cooling tower according to claim 8, it is characterised in that the solar energy photovoltaic panel passes through solar charging
Electric management module is connected with accumulator;The outfan of the accumulator is connected Jing after functional transformer regulation with closed cooling tower.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620985475.5U CN206113692U (en) | 2016-08-31 | 2016-08-31 | Cycling use of water and automatic water supply's closed type cooling tower |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201620985475.5U CN206113692U (en) | 2016-08-31 | 2016-08-31 | Cycling use of water and automatic water supply's closed type cooling tower |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206113692U true CN206113692U (en) | 2017-04-19 |
Family
ID=58513951
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201620985475.5U Expired - Fee Related CN206113692U (en) | 2016-08-31 | 2016-08-31 | Cycling use of water and automatic water supply's closed type cooling tower |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206113692U (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109286367A (en) * | 2018-08-24 | 2019-01-29 | 广东南控电力有限公司 | A kind of controllable temperature photovoltaic system |
CN110411076A (en) * | 2019-06-27 | 2019-11-05 | 江苏赐福科技有限公司 | A kind of ultra high efficiency evaporative condenser |
CN114234667A (en) * | 2021-12-24 | 2022-03-25 | 益冷和众科技(北京)有限公司 | Cooling tower and system for wastewater recycling |
CN114608346A (en) * | 2022-01-26 | 2022-06-10 | 山东泰王冷却设备有限公司 | Automatic heat sink of frequency conversion control of closed cooling tower |
-
2016
- 2016-08-31 CN CN201620985475.5U patent/CN206113692U/en not_active Expired - Fee Related
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109286367A (en) * | 2018-08-24 | 2019-01-29 | 广东南控电力有限公司 | A kind of controllable temperature photovoltaic system |
CN109286367B (en) * | 2018-08-24 | 2020-06-05 | 广东南控电力有限公司 | Temperature-controllable photovoltaic system |
CN110411076A (en) * | 2019-06-27 | 2019-11-05 | 江苏赐福科技有限公司 | A kind of ultra high efficiency evaporative condenser |
CN110411076B (en) * | 2019-06-27 | 2021-07-27 | 江苏赐福科技有限公司 | Super-efficient evaporative condenser |
CN114234667A (en) * | 2021-12-24 | 2022-03-25 | 益冷和众科技(北京)有限公司 | Cooling tower and system for wastewater recycling |
CN114608346A (en) * | 2022-01-26 | 2022-06-10 | 山东泰王冷却设备有限公司 | Automatic heat sink of frequency conversion control of closed cooling tower |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206113692U (en) | Cycling use of water and automatic water supply's closed type cooling tower | |
CN104244678B (en) | Method for controlling primary water loop heat pipe heat radiation system for equipment cabinet server | |
CN103743258B (en) | The dry closed cooling tower of a kind of water saving | |
CN105258549B (en) | A kind of water circulation evaporation and heat-exchange cooling condenser | |
CN105430998B (en) | A kind of control method of fluorine pump internal-circulation type server cabinet cooling system | |
CN105451509B (en) | A kind of fluorine pumps the control method of a loop server cabinet cooling system | |
CN202092479U (en) | Closed air cooling system for auxiliary machine circulating cooling water | |
CN106091728B (en) | Step cooling down water with composite construction prepares cooling tower | |
CN206113702U (en) | Novel closed type cooling tower | |
CN106052418A (en) | On-off switchable air cooling and water cooling composite cooling tower for air cooling radiator and operation mode | |
CN104132409B (en) | Evaporative cooling type water chilling unit adopting rotary water distribution | |
CN107543264A (en) | Handpiece Water Chilling Units are cooled down using the evaporation of plate fin type indirect evaporative cooler | |
CN205402997U (en) | Use plate -fin indirect evaporative cooler's evaporative cooling air -conditioning unit | |
CN102679480B (en) | Dew point indirect evaporation cooler with plate-tube combined structure | |
CN206019394U (en) | The step cooling down water combined with wind cooling temperature lowering by water-cooled cooling prepares cooling tower | |
CN107044695A (en) | Staggered form dew point evaporation cooling high-temperature handpiece Water Chilling Units | |
CN105972728B (en) | Standpipe indirectly-layering of drawing and pulling type filler sprays compound evaporative cooling air conditioning machine group | |
CN204757738U (en) | Circulative cooling tower | |
CN205261805U (en) | Evaporation formula condensing equipment based on separated heat pipe precooling | |
CN105928106B (en) | The cooling handpiece Water Chilling Units of capillary type enclosed evaporation | |
CN205036399U (en) | Heat transfer of mine return air is with diffusion tower | |
CN109827267A (en) | A kind of horizontal combined vertical plate cast two-stage indirect evaporating-cooling water cooler | |
CN106091488A (en) | Fin-tube type indirect evaporation air cooler | |
CN107036206B (en) | A kind of unpowered type Evaporative Cooling Air-conditioning System suitable for crow | |
CN205156672U (en) | Take precooling air cooler |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170419 Termination date: 20210831 |
|
CF01 | Termination of patent right due to non-payment of annual fee |