CN207103397U CN201720711286.3U CN201720711286U CN207103397U CN 207103397 U CN207103397 U CN 207103397U CN 201720711286 U CN201720711286 U CN 201720711286U CN 207103397 U CN207103397 U CN 207103397U
Authority
CN
China
Prior art keywords
frame
vibratory sieve
processing equipment
waste processing
disintegrating machine
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720711286.3U
Other languages
Chinese (zh)
Inventor
刘永强
刘纲领
杨得欣
孟雨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHENGZHOU ZHONGYI MINING MACHINERY CO Ltd
Original Assignee
ZHENGZHOU ZHONGYI MINING MACHINERY CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHENGZHOU ZHONGYI MINING MACHINERY CO Ltd filed Critical ZHENGZHOU ZHONGYI MINING MACHINERY CO Ltd
Priority to CN201720711286.3U priority Critical patent/CN207103397U/en
Application granted granted Critical
Publication of CN207103397U publication Critical patent/CN207103397U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02WCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO WASTEWATER TREATMENT OR WASTE MANAGEMENT
    • Y02W30/00Technologies for solid waste management
    • Y02W30/50Reuse, recycling or recovery technologies
    • Y02W30/58Construction or demolition [C&D] waste

Landscapes

  • Combined Means For Separation Of Solids (AREA)

Abstract

It the utility model is related to a kind of mobile construction waste processing equipment, including frame and the charging gear, disintegrating machine and the vibratory sieve that are arranged in frame, the frame has two spaced girders extended along frame length direction side by side, and the vibratory sieve is arranged between two girders and the lowest part of vibratory sieve is less than the top surface of frame.Compared to prior art, reduce the height of vibratory sieve, in the case of certain at the angle of inclination of connection disintegrating machine and the charging belt conveyer of vibratory sieve, the spacing that can further reduce between disintegrating machine and vibratory sieve, reduce the length of transfer formula building waste processing equipment, the length of mobile construction waste processing equipment is shorter, easy to use, and operating cost is relatively low.

Description

Mobile construction waste processing equipment
Technical field
It the utility model is related to a kind of mobile construction waste processing equipment.
Background technology
With the continuous quickening of urbanization process, the generation of building waste and discharge rate are also in rapid growth in city.Build Many discarded objects in building refuse are sorted, reject or crush after, regenerated resources can be used as to re-use mostly, it is such as useless Reinforcing bar, waste electric wire etc..There is the building waste processing equipment of movable type at present, for example, notification number is CN201423382Y, public affairs A kind of mobile construction waste treatment device disclosed in the Chinese utility model patent that day is 2010.03.17 is accused, including it is removable Frame and the feed hopper that is arranged in frame, the import of the outlet connection vibrosieve feeding machine of batcher, vibrosieve feed The import of the outlet connection disintegrating machine of material machine, the outlet of disintegrating machine connect vibratory sieve by two spaced material conveyors Import, vibratory sieve has aniseed outlet, first material outlet and second material outlet, and aniseed outlet passes through returning charge conveying Machine connects the import of disintegrating machine.Crushed in use, material in feed hopper enters in disintegrating machine, the material after crushing via Material conveyor is sent in vibratory sieve and sieved, and unqualified material exports from aniseed and discharges and returned to brokenly via returning charge conveyer Crushed in broken machine, qualified material is discharged from first, second material outlet.Shaken in existing mobile construction waste processing equipment Dynamic to sieve the upside for being arranged on frame top surface, vibratory sieve height is higher, due to the material conveyor between disintegrating machine and vibratory sieve Angle of inclination can not be excessive, causes the interval needs between disintegrating machine and vibratory sieve larger, mobile construction waste processing equipment Length it is longer, it has not been convenient to use.
Utility model content
The purpose of this utility model is to provide a kind of mobile construction waste processing equipment, to solve existing movement Length existing for formula building waste processing equipment is longer, it has not been convenient to the problem of using.
To achieve the above object, the technical scheme of mobile construction waste processing equipment of the present utility model is:It is portable Building waste processing equipment includes frame and the charging gear, disintegrating machine and the vibratory sieve that are arranged in frame, and the frame has The two spaced girders extended along frame length direction arranged side by side, the vibratory sieve is arranged between two girders and vibratory sieve Lowest part be less than frame top surface.
The disintegrating machine is arranged on the side towards vibratory sieve of charging gear, and the outlet of disintegrating machine is less than the top of frame Face.
Charging belt conveyer is provided between the disintegrating machine and vibratory sieve, the feed end of charging belt conveyer is arranged on The exit of disintegrating machine, discharge end are arranged on the entrance of vibratory sieve.
Mobile construction waste processing equipment includes self-unloading type deferrization device, and the frame is provided with pacifies for self-unloading type deferrization device The tramp iron separator support of dress, self-unloading type deferrization device are suspended above charging belt conveyer.
The vibratory sieve has the coarse fodder outlet for the discharge of unqualified material, and coarse fodder outlet is less than frame top surface.
Return conveyer conveyer is provided between the vibratory sieve and disintegrating machine, the feed end of return conveyer conveyer is arranged on The coarse fodder exit of vibratory sieve, discharge end are arranged on the entrance of disintegrating machine.
The charging gear includes raw material cabin and oscillating feeder, and the outlet of raw material cabin and the import of oscillating feeder connect Connect, oscillating feeder aligns backwards to the side of disintegrating machine with frame edge.
The beneficial effects of the utility model are:Mobile construction waste processing equipment includes frame, and frame is arranged side by side with two Spaced girder, vibratory sieve is arranged between two girders and the lowest part of vibratory sieve is less than the top surface of frame, reduces vibration The height of sieve, can be further in the case of certain at the angle of inclination of connection disintegrating machine and the charging belt conveyer of vibratory sieve The spacing reduced between disintegrating machine and vibratory sieve, reduce the length of transfer formula building waste processing equipment, compared to prior art, The length of mobile construction waste processing equipment is shorter, easy to use.
Brief description of the drawings
Fig. 1 is the structural representation of the specific embodiment of mobile construction waste processing equipment of the present utility model.
Embodiment
Embodiment of the present utility model is described further below in conjunction with the accompanying drawings.
The specific embodiment of mobile construction waste processing equipment of the present utility model, as shown in figure 1, including frame 10, Frame 10 is provided with tire and hydraulic leg 9, and tire is arranged on the left side of frame 10, and hydraulic leg 9 has two or more, each hydraulic pressure Supporting leg 9 is arranged at intervals along the length direction of frame 10.Feeding device, disintegrating machine 3 and vibration are sequentially provided with frame 10 from left to right Sieve 7, wherein, feeding device and disintegrating machine 3 are set close to the left side of frame 10, and vibratory sieve 7 is set close to the right side of frame 10.
The charging gear includes raw material cabin 1 and oscillating feeder 2, disintegrating machine 3 it is adjacent to be arranged on oscillating feeder 2 right Side;The outlet of raw material cabin 1 is directly connected to the import of oscillating feeder 2, and the outlet of oscillating feeder 2 is directly connected to disintegrating machine 3 Import, downside of the outlet in frame 10 of disintegrating machine 3.
The outlet of disintegrating machine 3 connects the import of vibratory sieve 7 by charging belt conveyer 5, and charging belt conveyer 5 is by a left side To the right, extension is tilted from the bottom to top;The discharge end of the upside of charging belt conveyer 5 is in the top of the import of vibratory sieve 7.
Mobile construction waste processing equipment includes self-unloading type deferrization device 11, and frame 10 is provided with removing for tramp iron separator installation Ironware support, self-unloading type deferrization device 11 by tramp iron separator holder suspension above charging belt conveyer 5, for collect it is broken after Material in scrap iron.
There is vibratory sieve 7 donor to accumulate the coarse fodder outlet of larger unqualified material discharge and the fines for qualified material discharge Outlet;Coarse fodder outlet is connected by the import of the upside of return conveyer conveyer 4 and disintegrating machine 3, return conveyer conveyer 4 by the right side extremely Left, inclination extension from the bottom to top.
The fines outlet of vibratory sieve 7 has two, and the outlet of respectively the first fines and the second fines export;First fines exports Place is provided with the first outfeed belt conveyor 6, and the second fines exit is provided with the second outfeed belt conveyor 8, the second outfeed belt Conveyer 8 is foldable.
It is provided with and is used in mobile construction waste processing equipment between disintegrating machine 3 and tramp iron separator support in frame 10 The hydraulic station 12 of all hydraulic element voltage supply, the multichannel for being used for carrying out hydraulic control is provided with frame 10 in the lower section of hydraulic station 12 Reversal valve 13.
In use, building waste enters oscillating feeder 2 by raw material cabin 1, oscillating feeder 2 uniformly gives material Disintegrating machine 3, disintegrating machine 3 crush to material, and the material after broken is transported to vibratory sieve 7 by charging belt conveyer 5 In;When material passes through self-unloading type deferrization device 11, the scrap iron in material is collected by self-unloading type deferrization device 11.
Vibratory sieve 7 sieves to the material of entrance, and unqualified material exports discharge via the coarse fodder of vibratory sieve 7, qualified Material is via the outlet of the first fines and the second fines outlet discharge;Pass through return conveyer conveyer from the material of coarse fodder outlet discharge 4 come back in disintegrating machine 3 and are crushed.Transported respectively by the first outfeed belt conveyor 6 from the material of two fineves outlet discharge Deliver to the first finished product stock ground, the second finished product stock ground is transported to by the second outfeed belt conveyor 8.
During use, frame 10, tire and hydraulic leg 9 support whole equipment, hydraulic station 12 and multiple directional control valve 13 regulations, control whole system, ensure normal, the high-efficiency operation of equipment.In transportation, frame 10 and tire part undertake The locomotive function of whole equipment.
Using mobile construction waste processing equipment of the present utility model, irony thing in building waste and its can be eliminated The construction material such as his debris, output sandstone, vibrosieve Tire-moved-type construction waste treatment device of the present utility model, knot Structure is compact, simple, and operation cost is low.

Claims (7)

1. mobile construction waste processing equipment, including frame and the charging gear, disintegrating machine and the vibratory sieve that are arranged in frame, It is characterized in that:The frame has the two spaced girders extended along frame length direction arranged side by side, and the vibratory sieve is set Put between two girders and the lowest part of vibratory sieve is less than the top surface of frame.
2. mobile construction waste processing equipment according to claim 1, it is characterised in that:The disintegrating machine be arranged on to Expect the side towards vibratory sieve of device, the outlet of disintegrating machine is less than the top surface of frame.
3. mobile construction waste processing equipment according to claim 2, it is characterised in that:The disintegrating machine and vibratory sieve Between be provided with charging belt conveyer, the feed end of charging belt conveyer is arranged on the exit of disintegrating machine, discharge end is set In the entrance of vibratory sieve.
4. mobile construction waste processing equipment according to claim 3, it is characterised in that:Mobile construction waste processing Equipment includes self-unloading type deferrization device, and the frame is provided with the tramp iron separator support for self-unloading type deferrization device installation, self-tipping type iron removaling Device is suspended above charging belt conveyer.
5. the mobile construction waste processing equipment according to any one of Claims 1-4, it is characterised in that:The vibration Sifter device has the coarse fodder outlet for the discharge of unqualified material, and coarse fodder outlet is less than frame top surface.
6. mobile construction waste processing equipment according to claim 5, it is characterised in that:The vibratory sieve and disintegrating machine Between be provided with return conveyer conveyer, the feed end of return conveyer conveyer is arranged on the coarse fodder exit of vibratory sieve, discharge end It is arranged on the entrance of disintegrating machine.
7. the mobile construction waste processing equipment according to any one of Claims 1-4, it is characterised in that:The feed Device includes raw material cabin and oscillating feeder, and the outlet of raw material cabin and the import of oscillating feeder connect, the back of the body of oscillating feeder Alignd to the side of disintegrating machine with frame edge.
CN201720711286.3U 2017-06-19 2017-06-19 Mobile construction waste processing equipment Active CN207103397U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720711286.3U CN207103397U (en) 2017-06-19 2017-06-19 Mobile construction waste processing equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720711286.3U CN207103397U (en) 2017-06-19 2017-06-19 Mobile construction waste processing equipment

Publications (1)

Publication Number Publication Date
CN207103397U true CN207103397U (en) 2018-03-16

Family

ID=61578162

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720711286.3U Active CN207103397U (en) 2017-06-19 2017-06-19 Mobile construction waste processing equipment

Country Status (1)

Country Link
CN (1) CN207103397U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109365060A (en) * 2018-12-03 2019-02-22 那健 A kind of civil engineering work material recuperating machines of environmental protection

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109365060A (en) * 2018-12-03 2019-02-22 那健 A kind of civil engineering work material recuperating machines of environmental protection
CN109365060B (en) * 2018-12-03 2021-02-19 浙江鹏盛建设集团有限公司 Civil engineering building material recovery unit of environmental protection

Similar Documents

Publication Publication Date Title
CN107952571B (en) A kind of production method of Machine-made Sand
CN103567209B (en) A kind of resourceful treatment system for decoration construction waste and processing method thereof
CN106733116B (en) A kind of crawler belt mobile jaw crushing screening station
CN202762516U (en) Granite machining system
CN102847702B (en) Tire-moved-type construction waste treatment device
CN207103398U (en) Mobile construction waste processing equipment
CN207103397U (en) Mobile construction waste processing equipment
CN104971878A (en) Sand screening machine for building
CN207592029U (en) A kind of asphalt-regenerating material Crushing & Screening Machineries
CN205128134U (en) Continuous broken sorting unit of raw coal
CN104689912B (en) Detachable nonferrous metal sorting system
CN206716421U (en) Coal material screening breaker
CN105689088B (en) The dry bone skeletal grain crusher of one-pass molding
CN215464748U (en) Second grade crushing and screening all-in-one
CN215087403U (en) Aggregate crushing and screening production line
CN215313072U (en) Machine-made sand production system for road and bridge construction
CN210058990U (en) Vehicle-mounted mobile intelligent dry separation coal separation device
CN213141862U (en) Broken screening production line of cobble
CN201728187U (en) Common rail sieving device of material piling and taking machine
CN203764371U (en) Crushing and transport system for deep mined ore
CN207446388U (en) Ball mill spits ore deposit Full-automatic circulation system
CN220195096U (en) Building type sand and stone aggregate integrated equipment capable of producing coarse and fine aggregate
CN202779141U (en) Tire type mobile construction waste disposal equipment
CN203695101U (en) Ore crushing and screening device
CN220744427U (en) Distributing vehicle buffering powder split hopper

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant