CN207092092U - A kind of steel-pipe pile piling machine suitable for beach - Google Patents

A kind of steel-pipe pile piling machine suitable for beach Download PDF

Info

Publication number
CN207092092U
CN207092092U CN201720656232.1U CN201720656232U CN207092092U CN 207092092 U CN207092092 U CN 207092092U CN 201720656232 U CN201720656232 U CN 201720656232U CN 207092092 U CN207092092 U CN 207092092U
Authority
CN
China
Prior art keywords
frame
guide rod
pile monkey
steel
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720656232.1U
Other languages
Chinese (zh)
Inventor
周剑雄
夏伟才
陈昌杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Asia Pacific Construction Supervision Consulting Co Ltd
Original Assignee
Hangzhou Asia Pacific Construction Supervision Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Asia Pacific Construction Supervision Consulting Co Ltd filed Critical Hangzhou Asia Pacific Construction Supervision Consulting Co Ltd
Priority to CN201720656232.1U priority Critical patent/CN207092092U/en
Application granted granted Critical
Publication of CN207092092U publication Critical patent/CN207092092U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

It the utility model is related to water conservancy construction technical field, and in particular to a kind of steel-pipe pile piling machine suitable for beach.Including pedestal, frame, hoist engine and pile monkey, hoist engine is set on pedestal, and frame is uprightly set and bottom is connected with pedestal;Pile monkey is connected by transmission rope with hoist engine, and pile monkey is hung in frame by transmission rope and fixed pulley;Frame is provided with the guide rod being oriented to pile monkey, and pile monkey is provided with the guide frame to match with guide rod, and pile monkey is coordinated by guide rod and guide frame to be slidably connected with guide rod, and adjusting rod is provided between frame and pedestal.The piling machine flexibility is preferable, the position that can be driven piles according to regulation is actually needed, and disclosure satisfy that the piling demand of certain angle;It is handling good, pile monkey sliding will not be caused out of control;Simple in construction, cost is relatively low, solves the problems, such as current large-scale piling machine in the good constructional difficulties of beach;It is simple to operate, save labour.

Description

A kind of steel-pipe pile piling machine suitable for beach
Technical field
It the utility model is related to water conservancy construction technical field, and in particular to a kind of steel-pipe pile piling machine suitable for beach.
Background technology
In architectural engineering Foundation Treatment project, piling is a common project under construction, and pile foundation is deep foundation Using a kind of most base forms, the stake and the cushion cap or apron piece of connection stake top that it is sunk in soil by several form.Stake Effect be that the load of upper building is delivered on the stronger soil layer of depths bearing capacity, or by the compacted reality of soft layer to carry The bearing capacity and compactness of high foundation soil.Man-hour requirement erecting scaffold on beach is applied in beach, in order to ensure scaffold Stable safety, it is necessary to the steel-pipe pile of a fixed-caliber squeezed into beach depth basic unit, the use of piling machine just must, but on beach Coat when being set to the steel-pipe pile of such as 89 millimeters of small size, because the location of piling is on beach, construction environment is multiple Miscellaneous, diameter of steel tube is small, and large-scale construction equipment is not suitable for, constructional difficulties.
The content of the invention
The purpose of this utility model is in order to which constructional difficulties are asked when solving to drive piles to small size steel-pipe pile on current beach A kind of topic, there is provided steel-pipe pile piling machine suitable for beach.
In order to reach above-mentioned purpose of utility model, the utility model uses following technical scheme:
A kind of steel-pipe pile piling machine suitable for beach, including pedestal, frame, hoist engine and pile monkey, hoist engine set base On seat, frame is uprightly set and bottom is connected with pedestal;Pile monkey is connected by transmission rope with hoist engine, and pile monkey by transmission rope and Fixed pulley is hung in frame;Frame is provided with the guide rod being oriented to pile monkey, and pile monkey is provided with what is matched with guide rod Guide frame, pile monkey is coordinated by guide rod and guide frame to be slidably connected with guide rod, and regulation is provided between frame and pedestal Bar.
Preferably, the guide frame includes the closing on pile monkey or semi-enclosed pilot hole, pilot hole Through pile monkey top surface and bottom surface, and pilot hole matches with guide rod.
Preferably, the guide frame is also led including being respectively arranged on the upper positioning disk at the top and bottom of pile monkey with To disk, upper positioning disk and lower positioning disk are located at the upper and lower opening of pilot hole respectively, and upper positioning disk is identical with lower guiding dish structure, Include disk seat and the directive wheel on disk seat or guiding pearl, guiding opinion or guiding pearl are around setting, formation and pilot hole phase With the targeting port passed through for guide rod.
Preferably, the guide frame also includes some array distributions in the guide wall pearl of pilot hole inwall, leads Match to stud locations and guide rod structure.
Preferably, the frame includes vertical rod and the cross bar at the top of vertical rod, transmission rope are hung on cross bar, It is rotatablely connected at the top of guide rod with cross bar, guide rod bottom and pedestal or the adjustable connection of bottom of the frame.
Preferably, the guide rod has two.
Preferably, the pilot hole is two, is symmetrical arranged on pile monkey.
Preferably, the guide rod is round bar or square bar.
Compared with prior art, beneficial effect is the utility model:Flexibility is preferable, can be beaten according to regulation is actually needed The position of stake, and disclosure satisfy that the piling demand of certain angle;It is handling good, pile monkey sliding will not be caused out of control;Structure letter Single, cost is relatively low, solves the problems, such as current large-scale piling machine in the good constructional difficulties of beach;It is simple to operate, save labour.
Brief description of the drawings
Fig. 1 is structural representation of the present utility model;
Fig. 2 is the structural representation of another angle of the utility model;
Fig. 3 is the structural representation of the utility model pile monkey;
Fig. 4 is the structural representation of positioning disk or lower positioning disk on the utility model;
Fig. 5 is another structural representation of positioning disk or lower positioning disk on the utility model;
Fig. 6 is the internal structure schematic diagram of the utility model pile monkey.
In figure:1 pedestal, 2 frames, 3 hoist engines, 4 pile monkeys, 5 transmission ropes, 6 fixed pulleys, 7 guide rods, 8 guide frames, 9 adjust Pole, 10 pilot holes, positioning disk on 11,12 times positioning disks, 13 disk seats, 14 directive wheels, 15 are oriented to pearls, and 16 targeting ports, 17 are oriented to Wall pearl, 18 vertical rods, 19 cross bars.
Embodiment
Explanation is further described to the technical solution of the utility model below by specific embodiment.
Embodiment:
A kind of steel-pipe pile piling machine suitable for beach, as depicted in figs. 1 and 2, including pedestal 1, frame 2, the and of hoist engine 3 Pile monkey 4, hoist engine 3 are set on pedestal 1, and frame 2 is uprightly set and bottom is connected with pedestal 1;Pile monkey 4 is by transmission rope 5 and elevator Machine 3 is connected, and pile monkey 4 is hung in frame 2 by transmission rope 5 and fixed pulley 6;Frame 2 is provided with what pile monkey 4 was oriented to Two guide rods 7, guide rod 7 are round bar or square bar, and pile monkey 4 is provided with the guide frame 8 to match with guide rod 7, and pile monkey 4 passes through Guide rod 7 and guide frame 8 coordinate to be slidably connected with guide rod 7, and adjusting rod 9 is provided between frame 2 and pedestal 1.
Adjusting rod 9 can adjust the angle between frame 2 and pedestal 1, and to adapt to different work requirements, pile monkey 4 exists It is raised in the presence of hoist engine 3, then after hoist engine 3 loses upward power to it, pile monkey 4 is under the guiding of guide rod 7 Make falling, the steel pipe below pile monkey is driven piles.
As shown in figure 3, the guide frame 8 includes the closing on pile monkey 4 or semi-enclosed pilot hole 10, pilot hole 10 run through the top surface of pile monkey 4 and bottom surface, and pilot hole 10 matches with guide rod 7.When pilot hole 10 is incomplete circular hole, it is It is semi-enclosed, now, side wall and the UNICOM of pilot hole 10 of pile monkey 4.
As shown in figure 3, the upper positioning disk 11 that the guide frame 8 also includes being respectively arranged on the top and bottom of pile monkey 4 is with Respectively at the upper and lower opening of pilot hole 10, upper positioning disk 11 is led with for positioning disk 12, upper positioning disk 11 and lower positioning disk 12 It is identical to the structure of disk 12, as shown in Figure 4 and Figure 5, directive wheel 14 or guiding pearl 15 including disk seat 13 and on disk seat 13, Directive wheel 14 is oriented to pearl 15 around setting, and forms the targeting port 16 for matching with pilot hole 10 and being passed through for guide rod 7.Guide rod 7 Through targeting port 16, in the presence of directive wheel 14 or guiding pearl 15 so that pile monkey 4 is slidably connected with guide rod 7, so as to reach The effect that guide rod 7 is guided pile monkey 4, now, as long as being carried out by adjusting the can of guide rod 4 to the whereabouts angle of pile monkey 4 Regulation, to reach the purpose of different angle piling.
As shown in fig. 6, the guide frame 8 also includes some array distributions in the guide wall pearl 17 of the inwall of pilot hole 10, Stud locations are oriented to the structure of guide rod 7 to match.It is equally to be used to form sliding effect to guide rod 7 to be oriented to pilaster 17, so as to Pile monkey 4 is oriented in guide rod 17.
On the structure of frame 2, as shown in Fig. 2 the frame 2 includes vertical rod 18 and the cross bar positioned at the top of vertical rod 18 19, transmission rope 5 is hung on cross bar 19, and the top of guide rod 7 is rotatablely connected with cross bar 19, the bottom of guide rod 7 and pedestal 1 or frame The adjustable connection in 2 bottoms.By the regulation that certain orientation is carried out to the bottom of guide rod 7, thus it is possible to vary the angle of guide rod 7, So as to realize the piling angle control to pile monkey 4.

Claims (8)

1. a kind of steel-pipe pile piling machine suitable for beach, it is characterised in that including pedestal(1), frame(2), hoist engine(3)With Pile monkey(4), hoist engine(3)Pedestal is set(1)On, frame(2)Upright setting and bottom and pedestal(1)It is connected;Pile monkey(4)By passing Running rope(5)With hoist engine(3)Connection, and pile monkey(4)Pass through transmission rope(5)And fixed pulley(6)Hang on frame(2)On;Frame (2)It is provided with to pile monkey(4)The guide rod being oriented to(7), pile monkey(4)It is provided with and guide rod(7)The guide frame of matching (8), pile monkey(4)Pass through guide rod(7)And guide frame(8)Cooperation and guide rod(7)It is slidably connected, frame(2)With pedestal(1) Between be provided with adjusting rod(9).
A kind of 2. steel-pipe pile piling machine suitable for beach according to claim 1, it is characterised in that the guide frame (8)Including located at pile monkey(4)On closing or semi-enclosed pilot hole(10), pilot hole(10)Through pile monkey(4)Top surface and bottom Face, and pilot hole(10)With guide rod(7)Match.
A kind of 3. steel-pipe pile piling machine suitable for beach according to claim 2, it is characterised in that the guide frame (8)Also include being respectively arranged on pile monkey(4)The upper positioning disk of top and bottom(11)With lower positioning disk(12), upper positioning disk(11)With Lower positioning disk(12)It is located at pilot hole respectively(10)Upper and lower opening at, upper positioning disk(11)With lower positioning disk(12)Structure phase Together, including disk seat(13)With located at disk seat(13)On directive wheel(14)Or it is oriented to pearl(15), directive wheel(14)Or it is oriented to pearl (15)Around setting, formation and pilot hole(10)Matching supplies guide rod(7)The targeting port passed through(16).
A kind of 4. steel-pipe pile piling machine suitable for beach according to Claims 2 or 3, it is characterised in that the guiding Structure(8)Also include some array distributions in pilot hole(10)The guide wall pearl of inwall(17), it is oriented to stud locations and guide rod (7)Structure matches.
A kind of 5. steel-pipe pile piling machine suitable for beach according to claim 1 or 2 or 3, it is characterised in that the machine Frame(2)Including vertical rod(18)With positioned at vertical rod(18)The cross bar at top(19), transmission rope(5)Hang on cross bar(19)On, it is oriented to Bar(7)Top and cross bar(19)Rotation connection, guide rod(7)Bottom and pedestal(1)Or frame(2)The adjustable connection in bottom.
6. a kind of steel-pipe pile piling machine suitable for beach according to claim 1 or 2 or 3, it is characterised in that described to lead To bar(7)There are two.
A kind of 7. steel-pipe pile piling machine suitable for beach according to Claims 2 or 3, it is characterised in that the guiding Hole(10)For two, in pile monkey(4)On be symmetrical arranged.
8. a kind of steel-pipe pile piling machine suitable for beach according to claim 1 or 2 or 3, it is characterised in that described to lead To bar(7)For round bar or square bar.
CN201720656232.1U 2017-06-07 2017-06-07 A kind of steel-pipe pile piling machine suitable for beach Expired - Fee Related CN207092092U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720656232.1U CN207092092U (en) 2017-06-07 2017-06-07 A kind of steel-pipe pile piling machine suitable for beach

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720656232.1U CN207092092U (en) 2017-06-07 2017-06-07 A kind of steel-pipe pile piling machine suitable for beach

Publications (1)

Publication Number Publication Date
CN207092092U true CN207092092U (en) 2018-03-13

Family

ID=61550649

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720656232.1U Expired - Fee Related CN207092092U (en) 2017-06-07 2017-06-07 A kind of steel-pipe pile piling machine suitable for beach

Country Status (1)

Country Link
CN (1) CN207092092U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109467369A (en) * 2018-12-29 2019-03-15 杭州亚太建设监理咨询有限公司 A kind of extrusion side wall concrete and preparation method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109467369A (en) * 2018-12-29 2019-03-15 杭州亚太建设监理咨询有限公司 A kind of extrusion side wall concrete and preparation method thereof

Similar Documents

Publication Publication Date Title
CN202300407U (en) Lifting platform for construction operation over shaft wall of vertical shaft
CN207092092U (en) A kind of steel-pipe pile piling machine suitable for beach
CN202299574U (en) Plug-in type communication base station lifting tower
CN105019670B (en) Precast concrete wall panel position regulator
CN111236616A (en) Horizontal guide rail walking hanging basket for high-rise construction
CN107096166A (en) The chair-type body-building equipment of Intelligent adjustment counterweight
CN202788610U (en) Down-hole hammer sleeve follow-up drilling machine
CN208455622U (en) A kind of quick pile driving equipment of architectural engineering
CN203938403U (en) A kind of Manual hanger
CN206336964U (en) A kind of support top formula lifting pipeline apparatus and system
CN214940110U (en) Negative pressure barrel type guide frame platform for pile sinking construction
CN204570690U (en) Pontoon pile driving plant
CN211478364U (en) Flow measuring device for hydraulic engineering
CN208684250U (en) One kind being based on the quick detachable boom hoisting of major structure of construction
CN207673018U (en) A kind of assembled-type house PC prefabricated components installation support fixed structure
CN108265707A (en) One kind can the multi-functional middle pick of tuning fetch earth and plant stake device and its construction method
CN202688997U (en) Dual-purpose long-screw full-automatic pile driver
CN106259064A (en) Cultivating system and cultural method
CN201923647U (en) Pipe kicking device of oil-field derrick pipe conveying machine
CN207047847U (en) One kind building pile driving equipment
CN207377503U (en) A kind of portable drilled grout hole platform of angle adjustable
CN206958386U (en) A kind of fire water-supply Pipe installing standpipe mounting bracket
CN206512706U (en) One kind can tuning it is multi-functional it is middle pick fetch earth plant stake device
CN206457788U (en) A kind of water conservancy lock for being easy to cleaning stands device for hoisting
CN203021211U (en) Slope surface crane equipment

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180313