CN207092045U - The stage apparatus of marine pile connection construction - Google Patents
The stage apparatus of marine pile connection construction Download PDFInfo
- Publication number
- CN207092045U CN207092045U CN201720888829.9U CN201720888829U CN207092045U CN 207092045 U CN207092045 U CN 207092045U CN 201720888829 U CN201720888829 U CN 201720888829U CN 207092045 U CN207092045 U CN 207092045U
- Authority
- CN
- China
- Prior art keywords
- steel
- pile
- horizontal
- construction
- stage apparatus
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Revetment (AREA)
Abstract
A kind of stage apparatus of marine pile connection construction, including:Sleeve on skirt jacket, the pile extension platform on sleeve, wherein, pile extension platform is mesa structure, the pile extension platform is by several horizontal I-steel, middle connection I-steel, brace I-steel and the first shelf pipe, the second shelf pipe, the 3rd shelf pipe and horizontal aisle, vertical aisle springboard connection composition.The utility model not only makes that workmen is simple, pile connection construction operation is safely completed on platform, solves shallow water skirt piles jacket pile connection construction shop problem;Moreover, also improving efficiency of construction, the construction period is reduced, has saved operating expenses.
Description
Technical field
Platform is the utility model is related to, more particularly to a kind of sea for marine skirt piles jacket pile connection construction operation connects
The stage apparatus of pile driving construction.Belong to ocean engineering field.
Background technology
In recent years, ocean engineering construction is developed rapidly, and various types of offshore production production platforms are also begun to towards large-scale
Change, synthesization, diversification direction are developed.In order to save the steel consumption amount for building jacket and piling bar, shallow water skirt piles jacket
Arise at the historic moment.Skirt piles jacket was all applied in deep water jacket in the past, using a piling bar, did not need pile extension.And shallow water conduit
Frame is then using a piling bar, it is necessary to pile extension.It is high limited due to hanging, and piling bar self-strength deficiency, therefore, it is necessary to piling bar is divided into
Multistage, and carry out marine pile extension operation.But due to there was only spacious waters above skirt piles jacket, it is not available for pile connection construction
Operating platform, also can not just complete this operation.
Utility model content
Main purpose of the present utility model is to overcome disadvantages mentioned above existing for prior art, and provides a kind of marine pile extension
The stage apparatus of construction, it not only makes, and workmen is simple, pile connection construction operation is safely completed on platform, solves shallow water
Skirt piles jacket pile connection construction shop problem;Moreover, also improving efficiency of construction, the construction period is reduced, has saved construction cost
With.
The purpose of this utility model is realized by following technical scheme:
A kind of stage apparatus of marine pile connection construction, it is characterised in that:Including:Sleeve on skirt jacket,
Pile extension platform on sleeve, wherein, pile extension platform is mesa structure, the pile extension platform be by several horizontal I-steel,
Centre connection I-steel, brace I-steel and the first shelf pipe, the second shelf pipe, the 3rd shelf pipe and horizontal aisle, is erected
Connect and form to aisle springboard.
Two block protection pasting boards are installed on the horizontal I-steel.
The oblique angle of the brace I-steel and horizontal I-steel is 45 degree;Brace I-steel and horizontal I-steel
Between reinforcement flange plate is installed.
The beneficial effects of the utility model:The utility model is because using above-mentioned technical proposal, it not only makes workmen
Simply, pile connection construction operation is safely completed on platform, solves shallow water skirt piles jacket pile connection construction shop problem;And
And efficiency of construction is also improved, the construction period is reduced, has saved operating expenses.
Brief description of the drawings
Fig. 1 is that the utility model structure I-steel is connected arrangement schematic top plan view with skirt piles jacket.
Fig. 2 is that the utility model I-steel is connected schematic side view with skirt piles jacket.
Fig. 3, which is that the utility model is horizontal, strengthens flange plate schematic diagram.
Fig. 4 is the utility model scaffold connection diagram.
Major Symbol explanation in figure:
1st, skirt piles jacket;2nd, sleeve;3rd, pasting board is protected;4th, horizontal I-steel;5th, middle connection I-steel;6th, underwater steel
Stake;7th, operating space;8th, brace I-steel;9th, flange plate is strengthened;10th, the first shelf pipe;11st, horizontal aisle springboard;12nd, erect
To aisle springboard;13rd, the second shelf pipe;14th, the 3rd shelf pipe.
Embodiment
As shown in Fig. 1-Fig. 4, the utility model includes:Sleeve 2 on skirt jacket 1, installed in sleeve 2
On pile extension platform, wherein, pile extension platform is mesa structure, and the pile extension platform is by horizontal (the present embodiment two of I-steel 4
Root), middle connection I-steel 5, brace I-steel 8 (the present embodiment is two) and (the present embodiment four of the first shelf pipe 10
Root), the second shelf pipe 13, the 3rd shelf pipe 14 (the present embodiment is four) and horizontal aisle 11, vertical aisle gang plank
12 and using welding manner connection composition.
Two block protection pasting boards 3 are provided with using welding manner on above-mentioned horizontal I-steel 4;The length of horizontal I-steel 4 is
Determined by the size of underwater piling bar 6 and its with the relative position of sleeve 2.
The oblique angle of above-mentioned brace I-steel 8 and horizontal I-steel 4 is 45 degree;Brace I-steel 8 and horizontal work
It is provided between word steel 4 and strengthens flange plate 9.
The position of the above-mentioned shelf 14 of horizontal connection I-steel 5 and the 3rd and the first shelf 10 is by the chi of underwater piling bar 6
Very little determination, in order to reserve operating space 7.Installed so as to complete a kind of stage apparatus for marine pile connection construction,
Workmen can start the pile connection construction work of underwater piling bar 6.
It is described above, only it is preferred embodiments of the present utility model, not the utility model is made any formal
Limitation, every any simple modification, equivalent change and modification made according to the technical essence of the utility model to above example,
Belong within the scope of technical solutions of the utility model.
Claims (3)
- A kind of 1. stage apparatus of marine pile connection construction, it is characterised in that:Including:Sleeve, peace on skirt jacket Pile extension platform on sleeve, wherein, pile extension platform is mesa structure, the pile extension platform be by several horizontal I-steel, in Between connect I-steel, it is brace I-steel and the first shelf pipe, the second shelf pipe, the 3rd shelf pipe and horizontal aisle, vertical Aisle springboard connection composition.
- 2. the stage apparatus of marine pile connection construction according to claim 1, it is characterised in that:Pacify on the horizontal I-steel Equipped with two block protection pasting boards.
- 3. the stage apparatus of marine pile connection construction according to claim 1, it is characterised in that:The brace I-steel with The oblique angle of horizontal I-steel is 45 degree;Reinforcement flange plate is installed between brace I-steel and horizontal I-steel.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720888829.9U CN207092045U (en) | 2017-07-21 | 2017-07-21 | The stage apparatus of marine pile connection construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720888829.9U CN207092045U (en) | 2017-07-21 | 2017-07-21 | The stage apparatus of marine pile connection construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207092045U true CN207092045U (en) | 2018-03-13 |
Family
ID=61545701
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720888829.9U Active CN207092045U (en) | 2017-07-21 | 2017-07-21 | The stage apparatus of marine pile connection construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207092045U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114382336A (en) * | 2021-12-28 | 2022-04-22 | 海洋石油工程股份有限公司 | Novel process for assisting jacket to install railing on sea |
CN117773440A (en) * | 2024-02-26 | 2024-03-29 | 广州文船重工有限公司 | Movable inner container tool for wind power jacket |
-
2017
- 2017-07-21 CN CN201720888829.9U patent/CN207092045U/en active Active
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114382336A (en) * | 2021-12-28 | 2022-04-22 | 海洋石油工程股份有限公司 | Novel process for assisting jacket to install railing on sea |
CN117773440A (en) * | 2024-02-26 | 2024-03-29 | 广州文船重工有限公司 | Movable inner container tool for wind power jacket |
CN117773440B (en) * | 2024-02-26 | 2024-04-19 | 广州文船重工有限公司 | Movable inner container tool for wind power jacket |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202530367U (en) | Deepwater complex geology foundation construction system | |
CN207092045U (en) | The stage apparatus of marine pile connection construction | |
CN101745748B (en) | Method for welding pile leg and pile shoe of drill platform | |
CN102134854A (en) | Slipway underwater pile foundation and construction method thereof | |
CN104805857A (en) | Detachable cyclic utilization bottomless steel jacket box and construction method thereof | |
CN202559371U (en) | Driving type independent column and independent pile sea anemometer tower foundation | |
CN106759340A (en) | Steel-pipe pile pile-pulling construction method and device in low spatial water | |
CN108330837B (en) | Set up the construction method of girder steel | |
CN204608812U (en) | One detachably recycles bottomless steel jacket box | |
CN111980049A (en) | Foundation device of deep riverbed mast type wharf crane and construction method | |
CN108018867B (en) | The method for realizing the construction of coastal waters beach column foot based on trestle method | |
CN208792357U (en) | A kind of control platform for the construction of marine jacket-type blower foundation | |
CN203034468U (en) | Novel cofferdam for deep water foundation construction | |
CN205604207U (en) | Novel jacket platform | |
CN205804182U (en) | A kind of land pebble and the novel combined work platforms in argillaceous sandstone district | |
CN202416320U (en) | Up-right frame for underwater steel pipe pile foundation in pilling process | |
CN103726505A (en) | Offshore wind plant wind turbine foundation | |
CN204000814U (en) | Steel casing is planted a platform | |
CN210134411U (en) | Steel-pipe pile diversion guiding device that divides water | |
CN210067284U (en) | Marine booster station cat ladder structure | |
CN204551495U (en) | The assembled lifting structure of a kind of Double-Wall Steel Boxed Cofferdam | |
CN209816899U (en) | Floating pile-stabilizing platform for construction of steel pipe piles of offshore jacket type fan foundation | |
CN202482771U (en) | T-beam installer | |
CN202899150U (en) | Draught fan base of offshore wind power station | |
CN207000767U (en) | It is easy to arrange the ship side extendable platform of underwater robot |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |