CN207079538U - A kind of upright high Retaining Wall Reinforcement and the ecological reconstruction structure in mountain channel - Google Patents

A kind of upright high Retaining Wall Reinforcement and the ecological reconstruction structure in mountain channel Download PDF

Info

Publication number
CN207079538U
CN207079538U CN201720277250.9U CN201720277250U CN207079538U CN 207079538 U CN207079538 U CN 207079538U CN 201720277250 U CN201720277250 U CN 201720277250U CN 207079538 U CN207079538 U CN 207079538U
Authority
CN
China
Prior art keywords
box
barricade
flower trough
prefabricated
retaining wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720277250.9U
Other languages
Chinese (zh)
Inventor
陈渠成
王军
刘小梅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Water Engineering Design and Research Institute Co Ltd
Original Assignee
Shanghai Water Engineering Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Water Engineering Design and Research Institute Co Ltd filed Critical Shanghai Water Engineering Design and Research Institute Co Ltd
Priority to CN201720277250.9U priority Critical patent/CN207079538U/en
Application granted granted Critical
Publication of CN207079538U publication Critical patent/CN207079538U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)

Abstract

Uprightly high Retaining Wall Reinforcement and the ecological reconstruction structure, including vertical type barricade of a kind of mountain channel disclosed in the utility model, it is characterised in that be provided with Ecotypic Stone Mesh-box barricade before the side near water of the vertical type barricade.Uprightly compared with the prior art, its improvement cost is greatly lowered high Retaining Wall Reinforcement and ecological reconstruction structure, while the influence in work progress to environment is also minimum for mountain channel of the present utility model, and the impact after building up to bio-diversity along the river reduces.

Description

A kind of upright high Retaining Wall Reinforcement and the ecological reconstruction structure in mountain channel
Technical field
Channel revetment technical field is the utility model is related to, uprightly high Retaining Wall Reinforcement and the life of more particularly to a kind of mountain channel State reconstruction structure.
Background technology
With social economy and the development of urbanization, urbanization population constantly increases, and the construction in rigid city be unable to do without river Stream is interspersed, urban river most concern and attention because the density of population in city receives, with the increasing of natural calamity More, design standard raising, urban river have been able to meet city operations demand.But mountain stream is due to naturally humane society Can etc. reason, washing away and being negligent of the protection and regulation to it year in year out, all there is hidden danger in shore protection barricade strength durable, can The Urban population life in downstream can be impacted.Mountain channel is due to the geology rock matter condition of uniqueness, its bank protection structure base This is vertical type (Gravity Retaining Wall), and the transformation for mountain area barricade exists only in the transformation of hard structure in the past, and barricade adds Height is reinforced or removed and rebuilds, and this way has Railway Project:One heightening and consolidation hard structure can produce shadow to monolithic stability Ring, mountain seism is more than Plain, and high barricade can be more easy to collapse.Two remove the new barricade of reconstruction, and excavation of foundation pit is excessive, to building along the river Influence too big.Three rigidity revetments do not have any benefit to river channel ecology, along the river landscape.
Utility model content
Technical problem to be solved in the utility model is above-mentioned present in existing mountain channel shore protection technology Deficiency and a kind of mountain channel uprightly high Retaining Wall Reinforcement and ecological reconstruction structure is provided, to reduce improvement cost and Construction on Environment Influence.
Technical problem to be solved in the utility model can be achieved through the following technical solutions:
A kind of mountain channel uprightly high Retaining Wall Reinforcement and ecological reconstruction structure, including vertical type barricade, it is characterised in that Ecotypic Stone Mesh-box barricade is provided with before the side near water of the vertical type barricade.
In a preferred embodiment of the present utility model, the Ecotypic Stone Mesh-box barricade includes being cast in the vertical type gear The reinforced concrete bottom plate of wall bottom and riverbed bottom and the plain concrete bed course that is cast on the reinforced concrete bottom plate and pile up described Ecotypic Stone Mesh-box on plain concrete bed course;The Ecotypic Stone Mesh-box gear coping is in step state, is placed with every grade of step surface pre- Assembled processed combines flower trough, and the elevation of the prefabricated assembled combination flower trough of most last layer, which reaches, calculates fifty year return period flood level.
In a preferred embodiment of the present utility model, the prefabricated assembled combination flower trough is spent by some prefabricated horizontal types Groove unit forms along water front arrangement, is connected between contiguous prefabricated horizontal type flower trough unit using box and pin mode.
In a preferred embodiment of the present utility model, in addition to one layer of prefabricated assembled combination flower trough topmost, remaining Also include some prefabricated vertical flower trough units in the prefabricated assembled combination flower trough of layer, at interval of several prefabricated horizontal type flower trough lists Member places a prefabricated vertical flower trough unit, and the outer end both sides of the prefabricated vertical flower trough unit are each provided with a rib, and two Individual rib respectively catches on the prefabricated horizontal type flower trough unit of adjacent both sides.
In a preferred embodiment of the present utility model, the reinforced concrete plate outer side in the Ecotypic Stone Mesh-box barricade bottom Be provided with Ecotypic Stone Mesh-box barricade town pin, the Ecotypic Stone Mesh-box barricade town pin using M10 starch air parcel barnacle into.
In a preferred embodiment of the present utility model, it is equipped with the riverbed before the Ecotypic Stone Mesh-box barricade town pin Ecotypic Stone Mesh-box layer, to prevent underearth stone to be washed.
In a preferred embodiment of the present utility model, the Ecotypic Stone Mesh-box layer height is 500mm.
By adopting the above-described technical solution, upright high Retaining Wall Reinforcement and the ecological reconstruction knot in mountain channel of the present utility model Compared with the prior art, its improvement cost is greatly lowered structure, while the influence in work progress to environment is also minimum, builds Reduce into the rear impact to bio-diversity along the river.
Brief description of the drawings
Fig. 1 is the utility model structure diagram.
Fig. 2 is the top view of the prefabricated assembled combination flower trough of the superiors in the utility model.
Fig. 3 is the top view of middle one layer of prefabricated assembled combination flower trough in the utility model.
Fig. 4 is the top view of bottom one layer of prefabricated assembled combination flower trough in the utility model.
Embodiment
Referring to Fig. 1, mountain channel uprightly high Retaining Wall Reinforcement and the ecological reconstruction structure, including vertical type barricade shown in figure 100, it is provided with Ecotypic Stone Mesh-box barricade 200 before the side near water of vertical type barricade 100.
Ecotypic Stone Mesh-box barricade 200 includes being cast in the He of reinforced concrete bottom plate 210 of the bottom of vertical type barricade 100 and riverbed bottom The plain concrete bed course 220 that is cast on reinforced concrete bottom plate 210 and pile up the Ecotypic Stone Mesh-box 230 on plain concrete bed course 220.
The top of Ecotypic Stone Mesh-box barricade 200 is in three-level step state, and prefabricated assembled group is placed with three-level step surface Flower trough 310,320,330 is closed, the elevation of the prefabricated assembled combination flower trough 310 of most last layer, which reaches, calculates fifty year return period flood Position.
Referring to Fig. 2, prefabricated assembled combination flower trough 310 is formed by some prefabricated horizontal type flower trough units 311 along water front arrangement, Connected between contiguous prefabricated horizontal type flower trough unit 311 using box and pin mode.
Referring to Fig. 3, middle one layer of prefabricated assembled combination flower trough 320 is by some prefabricated horizontal type flower trough units 321 and some Prefabricated vertical flower trough unit 322 is formed along water front arrangement, and box and pin mode is used between contiguous prefabricated horizontal type flower trough unit 321 Connection;A prefabricated vertical flower trough unit 322 is placed at interval of several prefabricated horizontal type flower trough units 321.Prefabricated vertical flower trough The outer end both sides of unit 322 are each provided with rib 322a, a 322b, and two ribs 322a, 322b are respectively by adjacent both sides Prefabricated horizontal type flower trough unit 321 is caught on.
Referring to Fig. 4, the prefabricated assembled combination flower trough 330 of basecoat is by some prefabricated horizontal type flower trough units 331 and some Prefabricated vertical flower trough unit 332 is formed along water front arrangement, and box and pin mode is used between contiguous prefabricated horizontal type flower trough unit 331 Connection;A prefabricated vertical flower trough unit 332 is placed at interval of several prefabricated horizontal type flower trough units 331.Prefabricated vertical flower trough The outer end both sides of unit 332 are each provided with rib 332a, a 332b, and two ribs 332a, 332b are respectively by adjacent both sides Prefabricated horizontal type flower trough unit 331 is caught on.
The outside of reinforced concrete bottom plate 210 of the bottom of Ecotypic Stone Mesh-box barricade 200 is provided with Ecotypic Stone Mesh-box barricade town pin 400, it is raw State gabion baffling town pin 400 using M10 starch air parcel barnacle into.The width of Ecotypic Stone Mesh-box barricade town pin 400 is 800mm.
Ecotypic Stone Mesh-box layer 500 is equipped with riverbed before Ecotypic Stone Mesh-box barricade town pin 400, to prevent that underearth stone from being rushed Brush.Ecotypic Stone Mesh-box layer height is 500mm, width 8m.

Claims (6)

1. a kind of mountain channel uprightly high Retaining Wall Reinforcement and ecological reconstruction structure, including vertical type barricade, it is characterised in that in institute Ecotypic Stone Mesh-box barricade is provided with before stating the side near water of vertical type barricade;
The Ecotypic Stone Mesh-box barricade includes being cast in the reinforced concrete bottom plate of the vertical type barricade bottom and riverbed bottom and poured Plain concrete bed course on the reinforced concrete bottom plate and pile up the Ecotypic Stone Mesh-box on the plain concrete bed course;The Ecotypic Stone Mesh-box gear Coping is in step state, and prefabricated assembled combination flower trough is placed with every grade of step surface, and most last layer is prefabricated assembled The elevation of combination flower trough, which reaches, calculates fifty year return period flood level.
2. upright high Retaining Wall Reinforcement and the ecological reconstruction structure in mountain channel as claimed in claim 1, it is characterised in that described pre- Assembled combination flower trough processed is formed by some prefabricated horizontal type flower trough units along water front arrangement, between contiguous prefabricated horizontal type flower trough unit Connected using box and pin mode.
3. upright high Retaining Wall Reinforcement and the ecological reconstruction structure in mountain channel as claimed in claim 2, it is characterised in that except most upper Outside the prefabricated assembled combination flower trough in one layer of face, some prefabricated vertical flower troughs are also included in the prefabricated assembled combination flower trough of remainder layer Unit, a prefabricated vertical flower trough unit, the prefabricated vertical flower trough list are placed at interval of several prefabricated horizontal type flower trough units The outer end both sides of member are each provided with a rib, and two ribs respectively catch on the prefabricated horizontal type flower trough unit of adjacent both sides.
4. upright high Retaining Wall Reinforcement and the ecological reconstruction structure in mountain channel as described in any one of claims 1 to 3 claim, Characterized in that, the reinforced concrete plate outer side in the Ecotypic Stone Mesh-box barricade bottom is provided with Ecotypic Stone Mesh-box barricade town pin, it is described Ecotypic Stone Mesh-box barricade town pin using M10 starch air parcel barnacle into.
5. upright high Retaining Wall Reinforcement and the ecological reconstruction structure in mountain channel as claimed in claim 4, it is characterised in that described Ecotypic Stone Mesh-box layer is equipped with riverbed before the pin of Ecotypic Stone Mesh-box barricade town, to prevent underearth stone to be washed.
6. upright high Retaining Wall Reinforcement and the ecological reconstruction structure in mountain channel as claimed in claim 5, it is characterised in that the life State gabion layer height is 500mm.
CN201720277250.9U 2017-03-21 2017-03-21 A kind of upright high Retaining Wall Reinforcement and the ecological reconstruction structure in mountain channel Expired - Fee Related CN207079538U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720277250.9U CN207079538U (en) 2017-03-21 2017-03-21 A kind of upright high Retaining Wall Reinforcement and the ecological reconstruction structure in mountain channel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720277250.9U CN207079538U (en) 2017-03-21 2017-03-21 A kind of upright high Retaining Wall Reinforcement and the ecological reconstruction structure in mountain channel

Publications (1)

Publication Number Publication Date
CN207079538U true CN207079538U (en) 2018-03-09

Family

ID=61427450

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720277250.9U Expired - Fee Related CN207079538U (en) 2017-03-21 2017-03-21 A kind of upright high Retaining Wall Reinforcement and the ecological reconstruction structure in mountain channel

Country Status (1)

Country Link
CN (1) CN207079538U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108374389A (en) * 2018-04-25 2018-08-07 广州市市政工程设计研究总院 A kind of the ecology structure and remodeling method of tidal reach vertical type embankment
CN109750629A (en) * 2019-01-25 2019-05-14 上海市水利工程设计研究院有限公司 A kind of high barrier wall structure of Eco-city river hard

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108374389A (en) * 2018-04-25 2018-08-07 广州市市政工程设计研究总院 A kind of the ecology structure and remodeling method of tidal reach vertical type embankment
CN109750629A (en) * 2019-01-25 2019-05-14 上海市水利工程设计研究院有限公司 A kind of high barrier wall structure of Eco-city river hard

Similar Documents

Publication Publication Date Title
US9915048B2 (en) Method for river/lake level regulation and water conservancy system
CN103821107B (en) Casing and plate combined ecological bank protection structure
CN204849680U (en) Novel ecological shore protection system
CN203795372U (en) Box body and inserted plate combined type ecological bank protection structure
CN207003363U (en) Barrier wall structure and channel revetment system
CN207079538U (en) A kind of upright high Retaining Wall Reinforcement and the ecological reconstruction structure in mountain channel
CN103243678A (en) Breakwater
CN207130765U (en) A kind of Construction of Civil Engineering retaining wall with greening and discharge structure
CN209722867U (en) Protective structure of hydraulic and hydroelectric engineering side slope
CN102912762A (en) Dam with pile groups and permeable frame and construction method of dam
CN208072332U (en) Water conservancy and hydropower baffle device for water
CN103758080B (en) Overhead type disappears unrestrained sightseeing platform structure
CN104695379A (en) Ecological river channel revetment structure
CN201671103U (en) Integral construction forming platform of underwater pier cap drilled pile
CN203668883U (en) Overhead type wave eliminating view platform structure
CN215630021U (en) Highway bridge construction foundation ditch protector
CN205502070U (en) A dual -purpose underground gallery structure
CN107653837A (en) The native compound dike of stone framework
CN209584969U (en) A kind of water conservancy construction protective slope structure
CN210049197U (en) Slope protection structure with secondary prevention soil erosion and water loss function
CN207597544U (en) A kind of high resiliency water conservancy chute
CN208501613U (en) Nearby Structure depth riverbed quaywall supporting construction
CN203256675U (en) Wall pile framework structure
CN209509556U (en) Underpin the constructing structure of no basement building underground space increasing layer
CN203256680U (en) Jetty

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180309