CN207062786U - A kind of construction bracket of continuous beam cantilever 0# blocks - Google Patents
A kind of construction bracket of continuous beam cantilever 0# blocks Download PDFInfo
- Publication number
- CN207062786U CN207062786U CN201721013498.0U CN201721013498U CN207062786U CN 207062786 U CN207062786 U CN 207062786U CN 201721013498 U CN201721013498 U CN 201721013498U CN 207062786 U CN207062786 U CN 207062786U
- Authority
- CN
- China
- Prior art keywords
- bar
- transverse horizontal
- construction
- fixed
- stupefied
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
The utility model discloses a kind of construction bracket of continuous beam cantilever 0# blocks, and the both sides of bridge pier along its length are separately installed with two temporary supports, and the bottom of temporary support is fixed on cushion cap;The top of temporary support sets a vertical equity bar being connected with bridge pier, and vertical equity bar is connected with pier shaft built-in fitting;Some height gradual increased vertical supporting bar from inside to outside is provided with vertical equity bar;Transverse horizontal bar is set above vertical supporting bar, and the both ends of transverse horizontal bar are separately fixed on the corresponding vertical supporting bar of two temporary supports of bridge pier homonymy;Set above transverse horizontal bar longitudinal brace master stupefied, transverse horizontal bar and longitudinal brace master it is stupefied between connected by voussoir.The utility model, which makes, implements safety simple, easy for construction, has saved construction cost, has improved the quality and efficiency of construction.
Description
Technical field
The utility model belongs to field of bridge construction, and in particular to a kind of construction bracket of continuous beam cantilever 0# blocks.
Background technology
With the fast development of China's infrastructure, continuous beam cantilever pouring construction method is superior because its ripe uniqueness
Property, it is increasingly used for the region of the support cast-in-place constructional difficulties such as cross a river stream, mountain valley, road.Poured in continuous beam cantilever
During construction, basis that 0# blocks are constructed as cantilever pouring, because of its size and quality is larger and its surrounding enviroment is complicated and changeable, easily
Cause safety and quality problems.
When cantilever pouring continuous beam 0# blocks are constructed, construction condition is typically poor, need to be complete in narrow and small high dummy section
Poured into prevention of mass concrete, and construction site geological conditions typically changes greatly.If using conventional construction support, it is necessary to 0# blocks
Neighbouring place is handled on a large scale, could strictly control the sedimentation of 0# blocks.Also, this method is using material is more, constructing accounts for
Ground is larger, and in the environment of geological condition complexity, narrow space, the diagonally disposed construction safety risk of steel pipe is larger, and branch be present
The problem of frame sedimentation is uneven, construction safety hidden danger is larger.
Utility model content
Purpose of utility model:The utility model purpose is in view of the shortcomings of the prior art, there is provided a kind of continuous beam cantilever
The construction bracket of 0# blocks.The utility model, which makes, implements safety simple, easy for construction, has saved construction cost, has improved construction
Quality and efficiency.
Technical scheme:The construction bracket of continuous beam cantilever 0# blocks described in the utility model, bridge pier along its length two
Side is separately installed with two temporary supports, and the bottom of temporary support is fixed on cushion cap;The top of temporary support set one with
The vertical equity bar of bridge pier connection, vertical equity bar are connected with pier shaft built-in fitting;Some height are provided with vertical equity bar
Gradual increased vertical supporting bar from inside to outside;Transverse horizontal bar, the both ends point of transverse horizontal bar are set above vertical supporting bar
It is not fixed on the corresponding vertical supporting bar of two temporary supports of bridge pier homonymy;Longitudinal brace master is set above transverse horizontal bar
It is stupefied, transverse horizontal bar and longitudinal brace master it is stupefied between connected by voussoir.
Further, it is fixed with shelf bracket between the temporary support and vertical equity bar.
Further, the bottom of the temporary support is welded and fixed by pre-embedded steel slab on cushion cap.
Further, the transverse horizontal bar at longitudinal stupefied contact position of brace master using U-bolt with being fixed.
Beneficial effect:(1)The utility model is less using material installation, Neng Gou less demanding to construction site condition
Narrow space carries out crossed construction, has saved cost, has shortened the engineering time, has improved efficiency of construction;
(2)Due to eliminating original primary load bearing steel pipe support, by temporary support, load is transferred to pier cap
On, avoid the support caused by Geological condition difference and settle non-uniform phenomenon, enhance working security;
(3)Because being not provided with rigid temporary support between pier coping portion and 0# block box beams, it is possible to achieve the lotus that bearing is born
It is loaded in the propulsion of cantilever casting construction progress and increases, avoids to greatest extent after beam body is closed up when contacting temporary support because of branch
Seat depression and the problem of produce larger structure second inner force.
Brief description of the drawings
Fig. 1 is the structure chart of the construction bracket of continuous cantilever beam 0# blocks described in the utility model;
Fig. 2 is Figure 1A-A profiles.
In figure, 1, cushion cap;2nd, bridge pier;3rd, temporary support;4th, shelf bracket;5th, vertical equity bar;6th, vertical supporting bar;7、
Transverse horizontal bar;8th, voussoir;9th, longitudinal brace master is stupefied.
Embodiment
Technical solutions of the utility model are described in detail below by accompanying drawing, but the scope of protection of the utility model
It is not limited to the embodiment.
Embodiment 1:A kind of construction bracket of continuous beam cantilever 0# blocks, as shown in figure 1, bridge pier 2 along its length two
Side is separately installed with two temporary supports 3, and the bottom of temporary support 3 is fixed on cushion cap 1;The top of temporary support 3 sets one
The vertical equity bar 5 that root is connected with bridge pier 2, vertical equity bar 5 are connected with pier shaft built-in fitting;Temporary support 3 and vertical equity bar 5
Between be fixed with shelf bracket 4;Some height gradual increased vertical supporting bar from inside to outside is provided with vertical equity bar 5
6;The top of vertical supporting bar 6 sets transverse horizontal bar 7, and the both ends of transverse horizontal bar 7 are separately fixed at 2 homonymy of bridge pier two temporarily
On the corresponding vertical supporting bar 6 of support 3;The top of transverse horizontal bar 7 sets longitudinal brace master stupefied 9, and transverse horizontal bar 7 and longitudinal direction are tiltedly
Connected between bar master stupefied 9 by voussoir 8.
The construction bracket of continuous beam cantilever 0# blocks described in the utility model be by it is lower from the upper vertical equity bar of consolidation in advance 5,
Shelf bracket 4, vertical supporting bar 6, transverse horizontal bar 7 and longitudinal brace master stupefied 9 are then placed, then on longitudinal brace master stupefied 9
The lumps of wood, bed die and Bian Mo are laid, so as to form complete 0# block construction supports and template system.
More specifically, the temporary support 3 uses material to be made up of Q235 spiral steel pipe, temporary support 3, which is supported on, holds
On platform 1, temporary support 3 is welded and fixed away from the side 15cm of cushion cap 1 with 700mm × 700mm pre-buried on cushion cap 1 × 20mm steel plates.Phase
[20 channel-section steel is welded and fixed, to strengthen the steadiness of 0# block construction supports by 2 at the middle part of adjacent two temporary supports 3.
[36 channel-section steel is made, and vertical equity bar 5 passes through pier shaft pre-embedded steel slab and bridge pier 2 for the use of vertical equity bar 52
It is welded to connect, surface of steel plate slightly concave 2-3cm into pier shaft, facilitates the construction of 0# blocks to terminate the outward appearance processing of rear steel plate surface.Steel plate is carried on the back
Face is welded with anchor bar, and the position of steel plate, the specification of size and anchor bar, size determine after design calculates.
[20 channel-section steel is made, and shelf bracket 4 welds with temporary support 3 and vertical equity bar 5 for the use of shelf bracket 42
Connection.
[36 channel-section steel is made, and bottom and the vertical equity bar 5 of vertical supporting bar 6 weld for the use of vertical supporting bar 62
Connection.
[36 channel-section steel is made, and the top of transverse horizontal bar 7 and vertical supporting bar 6 is welded for the use of transverse horizontal bar 72
Connection.
Longitudinal brace master stupefied 9 is made of Two bors d's oeuveres 25b channel-section steels, and length is with spacing depending on Bridge Design situation.
Transverse horizontal bar 7 prevents both sides cantilever extension from toppling with being fixed at stupefied 9 contact position of longitudinal brace master using U-bolt.It is horizontal
Two bors d's oeuveres 25b channel-section steels web is strengthened with 20mm steel plates to horizon bar 7 and stupefied 9 intersection of longitudinal brace master, spacing 10cm, strengthened
Scope is more than the stupefied 9 width 20cm of longitudinal brace master.10cm × 10cm lumps of wood, lumps of wood upper berth bamboo are placed on longitudinal brace master stupefied 9
Offset plate bed die and Bian Mo.
The voussoir 8 is formed using channel-section steel cutting processing, filling M15 mortars in voussoir 8.
Permanent bearing, the branch that the 0# blocks edge of a wing is carried using sizing punching block outer side mold are fixed between 0# blocks box beam and bridge pier 2
Frame, support is erected on Two bors d's oeuveres 25b channel-section steel along bridge to setting, spacing 90cm, support, while places installation flange template.
After construction, steel pipe guard rail and Dense mesh screen are set in the outer rim of longitudinal brace master stupefied 9 and the outside of set shaped steel formwork, with
Plan safety.
Precompressed is carried out by code requirement on the bed die that 0# blocks have been laid, to eliminate the inelastic deformation of construction bracket.
Treat that permanent bearing and pier shaft built-in fitting and assembling reinforcement are installed after the completion of precompressed, finally pour 0# block concretes.
As described above, although the utility model has been represented and described with reference to specific preferred embodiment, but it must not
It is construed to the limitation to the utility model itself.In the spirit and scope of the present utility model for not departing from appended claims and defining
Under the premise of, can various changes can be made in the form and details to it.
Claims (4)
- A kind of 1. construction bracket of continuous beam cantilever 0# blocks, it is characterised in that:Install respectively the both sides of bridge pier along its length There are two temporary supports, the bottom of temporary support is fixed on cushion cap;What the top setting one of temporary support was connected with bridge pier Vertical equity bar, vertical equity bar are connected with pier shaft built-in fitting;Be provided with vertical equity bar some height from inside to outside by Gradually increased vertical supporting bar;Transverse horizontal bar is set above vertical supporting bar, and the both ends of transverse horizontal bar are separately fixed at bridge On the corresponding vertical supporting bar of two temporary supports of pier homonymy;Set longitudinal brace master stupefied above transverse horizontal bar, transverse horizontal Connected between bar and longitudinal brace master are stupefied by voussoir.
- 2. the construction bracket of continuous beam cantilever 0# blocks according to claim 1, it is characterised in that:The temporary support is with indulging To being fixed with shelf bracket between horizon bar.
- 3. the construction bracket of continuous beam cantilever 0# blocks according to claim 1, it is characterised in that:The bottom of the temporary support End is welded and fixed by pre-embedded steel slab on cushion cap.
- 4. the construction bracket of continuous beam cantilever 0# blocks according to claim 1, it is characterised in that:The transverse horizontal bar with Fixed at longitudinal stupefied contact position of brace master using U-bolt.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721013498.0U CN207062786U (en) | 2017-08-14 | 2017-08-14 | A kind of construction bracket of continuous beam cantilever 0# blocks |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721013498.0U CN207062786U (en) | 2017-08-14 | 2017-08-14 | A kind of construction bracket of continuous beam cantilever 0# blocks |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207062786U true CN207062786U (en) | 2018-03-02 |
Family
ID=61514996
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721013498.0U Expired - Fee Related CN207062786U (en) | 2017-08-14 | 2017-08-14 | A kind of construction bracket of continuous beam cantilever 0# blocks |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207062786U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115262613A (en) * | 2022-08-15 | 2022-11-01 | 江苏海洋大学 | No. 0 block floor bracket cantilever type vibration damping concrete foundation attached to bearing platform |
WO2023165628A1 (en) * | 2022-09-16 | 2023-09-07 | 中铁七局集团郑州工程有限公司 | Curved girder base bearing apparatus with superposition of tied arch and continuous girder |
-
2017
- 2017-08-14 CN CN201721013498.0U patent/CN207062786U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115262613A (en) * | 2022-08-15 | 2022-11-01 | 江苏海洋大学 | No. 0 block floor bracket cantilever type vibration damping concrete foundation attached to bearing platform |
WO2023165628A1 (en) * | 2022-09-16 | 2023-09-07 | 中铁七局集团郑州工程有限公司 | Curved girder base bearing apparatus with superposition of tied arch and continuous girder |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202359506U (en) | Double hoop supporting system for pier column capping beam | |
CN102888815B (en) | The pouring construction method of a kind of wide-angle V-type pier and 0# block case beam | |
CN103866697B (en) | A kind of bridge pier and straining beam calf support method for synchronously constructing | |
CN202954299U (en) | Template support structure for large-angle V-shaped pier and No.0 block of continuous rigid framework bridge | |
CN102900230B (en) | Liftable reinforced concrete post-casting strip construction method | |
CN106592406A (en) | Through tied arch bridge and construction method thereof | |
CN203270461U (en) | Bailey beam support without buttress in soft foundation | |
CN102251481B (en) | Railway pier layered construction method and construction device | |
CN104727223A (en) | Annular platform for bridge pier stud construction and construction method | |
CN103882813A (en) | Corbel bracket platform for bridge pier and transverse straining beam synchronous construction and construction method of corbel bracket platform | |
CN107905114A (en) | A kind of construction method of large span Successive interference cancellation | |
CN207062786U (en) | A kind of construction bracket of continuous beam cantilever 0# blocks | |
CN106012851A (en) | Synchronous construction method of steel box girder and concrete pier studs | |
CN202659247U (en) | Back templates and combined steel die for tunnel inverted arch construction | |
CN102733307B (en) | Method for constructing cast-in-place beam falsework | |
CN103233426A (en) | Bailey beam support free of buttress in soft foundation and supporting method thereof | |
CN203248170U (en) | Lining trolley for secondary lining construction of pedestrian crosswalk | |
CN105908638B (en) | It is a kind of to turn rigid frame bridge steel box-girder and the construction method of concrete pier consolidation | |
CN104929047A (en) | V-shaped pier outer support construction method | |
CN111910520B (en) | Construction method of high-speed inclined leg crossing rigid frame overpass | |
CN204780635U (en) | Super wide nonprismatic continuous beam 0# piece concreties and relieves construction structures | |
CN205276694U (en) | Hang bench | |
CN105887922B (en) | A kind of method that inwall construction is carried out using truss support device | |
CN207685855U (en) | A kind of anti-anti-floating large steel moulding plate device that inclines of cast-in-place concrete retaining wall | |
CN202577158U (en) | Hyperbolic cable tower cross beam adjusting bracket |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180302 |
|
CF01 | Termination of patent right due to non-payment of annual fee |