CN207032521U - A kind of toilet threshold stone waterproof construction - Google Patents
A kind of toilet threshold stone waterproof construction Download PDFInfo
- Publication number
- CN207032521U CN207032521U CN201720877852.8U CN201720877852U CN207032521U CN 207032521 U CN207032521 U CN 207032521U CN 201720877852 U CN201720877852 U CN 201720877852U CN 207032521 U CN207032521 U CN 207032521U
- Authority
- CN
- China
- Prior art keywords
- waterproof
- layer
- laying
- threshold stone
- cement mortar
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Abstract
The utility model discloses a kind of toilet threshold stone waterproof construction, including threshold stone, the first cement mortar adhered layer, the second cement mortar adhered layer, fish tail and waterproof layer, waterproof layer, structure of capital construction layer;Also include the pre- laying of waterproof, it includes:The pre- laying of first waterproof, it is located at the lower section of the first cement mortar adhered layer and the second cement mortar adhered layer;The pre- laying of second waterproof, it forms one with the pre- laying of the first waterproof, and positioned at the top of the pre- laying of the first waterproof, and between the first cement mortar adhered layer and the second cement mortar adhered layer, the contour shape of the longitudinal section of the pre- laying of second waterproof is in inverted V-shaped, waterproof layer is laid on the upper surface of the pre- laying of the first waterproof and the pre- laying of the second waterproof, is located at the lower section of threshold stone at the top of the pre- laying of the second waterproof, and marine glue is coated between top and threshold stone lower surface.The pre- laying of second waterproof coordinates waterproof layer on its side and the marine glue effectively to prevent the steam in toilet from leaking into floor in room.
Description
Technical field
The utility model belongs to buildings waterproof technical field of structures, is to be related to a kind of door for toilet specifically
Sill stone waterproof construction designs.
Background technology
The ground that toilet is laundry, has a bath and washes one's face and rinses one's mouth, so unrestrained regimen condition often occurs in ground, occur in short-term when serious
Between ponding.Therefore, it is necessary to carry out water-proofing treatment to the ground of toilet, such as waterproof is laid below the floor tile of toilet
Layer, when water between the brickwork joint of toilet floor tile from when being seeped into below floor tile, because there is the presence of waterproof layer, water will not be seeped into downstairs,
Play certain waterproof action.But during water saturation below floor tile can afterflow to toilet doorway.If metope and health
Between outside region do not carry out waterproof measure, current would generally be inhaled on metope, cause metope emulsion paint or wallpaper to be grown
Phase is in dampness, causes the peeling and mouldy of coming off in the course of time.Furthermore if the room outside toilet is using solid wood
Plate, because wood materials are easy to absorb moisture, over time, the easily mouldy blackening of wood floors, influence U.S.s of room floors
The property seen, severe patient there is also musty.
To avoid the water of toilet from penetrating into room floor, common practice is at present:In toilet and room floors
Threshold stone is set up in joint portion, and takes the mode of wet-laying, is applied and brushed one times with surrounding of the waterproof material along threshold stone, and in threshold
The waterproof material of stone and the joint portion brushing certain altitude of door girder construction, to prevent the water of toilet from being inhaled on metope.It is this
Way can play certain waterproof effect really, but when the water accumulation of accomodation ground is excessive, waterproof material can not yet
Good interception function is played, the water that still there can be toilet crosses threshold stone and the waterproof material brushed with penetrating into room
The situation of plate.
Chinese patent notification number CN202990369 discloses a kind of toilet threshold stone waterstop device, by health
Between the junction of earth construction and threshold stone set up the waterstop formed using pea gravel concreten, and by pea gravel concreten waterstop
It is arranged between basic unit and waterproof layer, so as to solve the waterproof problem of waterproof layer lower floor well.But for anti-
Any water-proofing treatment is not done between water layer and threshold stone, finds still to have part water in practice along threshold stone with infiltrating into room
Face.And mentioned in the construction method:After pea gravel concreten sealing belt construction is completed 7 days, waterproof material is smeared, completes threshold stone
Construction operation.It can be seen that the construction period that the waterproofing process needs is longer, it is unsuitable for surface construction in large area.
The content of the invention
The utility model provides a kind of toilet threshold stone waterproof construction, solves ponding in existing toilet along threshold
The problem of stone seeps water, the reliability of waterproof at toilet threshold is improved, and it is fairly simple to construct.
In order to solve the above technical problems, the utility model is achieved using following technical scheme:
A kind of toilet threshold stone waterproof construction, including threshold stone, the first cement mortar below the threshold stone
Adhered layer, the second cement mortar adhered layer, fish tail and waterproof layer, waterproof layer, structure of capital construction layer below toilet floor tile;Also
Including:The pre- laying of waterproof, it includes:The pre- laying of first waterproof, it is located at the first cement mortar adhered layer and described second
The lower section of cement mortar adhered layer, the waterproof layer and fish tail and waterproof layer are laid on the pre- laying of the first waterproof and described first
Between cement mortar adhered layer, the second cement mortar adhered layer;The pre- laying of second waterproof, itself and the pre- laying shape of first waterproof
Integrally, and positioned at the top of the pre- laying of the first waterproof, and between the first cement mortar adhered layer and the second cement
Between mortar adhered layer, the waterproof layer is laid on the pre- laying of the second waterproof and the first cement mortar adhered layer, the
Between two cement mortar adhered layers;The contour shape of the longitudinal section of the pre- laying of second waterproof is in inverted V-shaped, the waterproofing protection
Layer is laid on waterproof layer and the first mortar adhered layer, the stickup of the second cement mortar in addition at the top of the pre- laying of second waterproof
Between layer, the top is located at the lower section of the threshold stone, and waterproof is coated between the top and threshold stone lower surface
Glue.
For the toilet part by moisture barrier within threshold stone as early as possible, the top of the setting pre- laying of the second waterproof
The seaming position of the neighbouring threshold stone and toilet floor tile;The marine glue extends from the top of the pre- laying of the second waterproof
To described seaming position, the waterproof surface of threshold stone lower surface is which increased, strengthens waterproof effect.
Preferably, threshold stone 2 ~ 3mm of lower surface described in the distance from top of the pre- laying of the second waterproof.
Preferred scheme is similarly, the height of the pre- laying of the second waterproof is between 3 ~ 5cm;The pre- laying of second waterproof
Longitudinal section the widest part width between 3 ~ 5cm.
The top surface of the pre- laying of the first waterproof in the present embodiment below the second cement mortar adhered layer is formed tiltedly
Face, and from the inside of a lateral toilet of the neighbouring threshold stone in overbank from high to low.It can make toilet
The trend of the oriented toilet internal flow of water storage under floor tile, ensure that bathroom door oral area divides relatively dry, reduce waterproof difficulty,
Strengthen waterproof effect.
To reduce the first cement mortar adhered layer as far as possible on the premise of firmly installation toilet floor tile is ensured
Reservoir storage, the present embodiment preferably the distance between lower surface of top surface and the toilet floor tile of the pre- laying of the first waterproof 3 ~
Between 5cm.
Structure of capital construction layer described in the present embodiment includes the Part I and position below the pre- laying of the first waterproof
In the Part II in the room abutted with the threshold stone below floor, the Part II is higher than Part I;It is described anti-
The pre- laying of water also overlays layer including the 3rd waterproof, and it forms one with the pre- laying of the first waterproof, and anti-positioned at described first
The top of the pre- laying of water, and between Part II between the structure of capital construction layer and the first cement mortar adhered layer.Increase
Add the flatness of the structure of capital construction layer Part II vertical plane, it is easier to lay waterproof layer in its right flank.
It is anti-described in specially overlaying and be equipped between layer and the first cement mortar adhered layer in the 3rd waterproof
Water layer and fish tail and waterproof layer.It can stop that the steam of the first mortar adhered layer enters the Part II of structure of capital construction layer.
3rd waterproof described in the present embodiment overlays the lower section that layer is located at the threshold stone, and layer is overlay in the 3rd waterproof
Top surface be equipped with waterproof layer, and be laid on the 3rd waterproof and overlay the waterproof layer of layer top surface and glued from first cement mortar
The structure of capital construction layer Part II top surface extension under floor into the room of the position of paste layer, and more than ground in the room
The seaming position of plate and threshold stone.This structure makes that the 3rd waterproof overlays layer top surface and the top surface of structure of capital construction layer Part II is formed
Waterproof surface.
To strengthen waterproof effect, in the threshold stone and it is laid on the 3rd waterproof and overlays between the waterproof layer of layer top surface
And it is coated with the threshold stone and the room under floor between the waterproof layer of structure of capital construction layer Part II top surface
Marine glue.It is with reference to described in can stopping the waterproof surface for the top surface that the 3rd waterproof overlays layer top surface and structure of capital construction layer Part II
Steam in first cement mortar adhered layer penetrates into floor in room along threshold stone lower surface.
The utility model having the beneficial effect that compared with prior art:
The pre- laying of second waterproof coordinates at the top of waterproof layer on its side and the pre- laying of second waterproof and described
Marine glue between threshold stone lower surface can effectively prevent the water storage in the second cement mortar adhered layer from crossing described second
The pre- laying of waterproof reaches the first cement mortar adhered layer, and so as to leak into floor in room, this structure is by setting one
The pre- laying of the second waterproof of inverted V-shaped, the seepage of steam is effectively prevented, structure and technique are all very simple, strong operability, are adapted to
Promote the use of on a large scale.
Brief description of the drawings
Fig. 1 be the utility model proposes toilet threshold stone waterproof construction a kind of embodiment structural representation;
Fig. 2 is the enlarged drawing in A portions in Fig. 1.
In figure
1 structure of capital construction layer Part I;The 2 first pre- layings of waterproof;3 waterproof layers;4 fish tail and waterproof layers;5 second cement mortar
Adhered layer;6 toilet floor tiles;The 7 second pre- layings of waterproof;8 marine glues;9 first cement mortar adhered layers;10 threshold stones;Rooms 11
Interior floor;12 Dampproof floor board pads;13 the 3rd waterproofs overlay layer;14 structure of capital construction layer Part II.
Embodiment
Specific embodiment of the present utility model is described in more detail below in conjunction with the accompanying drawings.
1 and accompanying drawing 2 referring to the drawings, the utility model provide a kind of toilet threshold stone waterproof construction, and the structure includes door
Sill stone 10, the first cement mortar adhered layer 9, the second cement mortar adhered layer 5, waterproof layer 3, waterproof layer protective layer 4, structure of capital construction
Layer;Also include the pre- laying of waterproof, it includes the pre- laying 2 of the first waterproof, the pre- laying 7 of the second waterproof.The pre- laying 2 of first waterproof
Positioned at the lower section of the first cement mortar adhered layer 9 and the second cement mortar adhered layer 5, the pre- laying of the second waterproof
7 form one with the pre- laying 2 of first waterproof, and positioned at the top of the pre- laying 2 of first waterproof, and between described first
Between the cement mortar adhered layer 5 of cement mortar adhered layer 9 and second.Overlay in the pre- waterproof of laying 2 and second of first waterproof
The upper surface laying waterproof layer 3 of layer 7, lays on the waterproof layer in addition to the waterproof layer at the top of the pre- laying 7 of second waterproof
Fish tail and waterproof layer 4, marine glue is coated between the top of the pre- laying 7 of second waterproof and the lower surface of threshold stone 10,
The waterproof layer at the pre- top of laying 7 of second waterproof is set directly to be connected with marine glue 8.The pre- laying 2 of first waterproof combines it
The waterproof layer 3 on surface prevents the downward seepage of water storage in its second cement mortar adhered layer 5 above, the pre- laying of the second waterproof
7 with reference to the marine glue between the waterproof layer 3 on its surface and the pre- top of laying 7 of second waterproof and the lower surface of threshold stone 10
Prevent the water storage in the second cement mortar adhered layer 5 from permeating the pre- laying 7 of the second waterproof to first cement mortar to paste
Layer 9, so as to prevent its steam from infiltrating into timber floor 11, ensure that waterproof effect, and construction is simple.
For stopping the steam in toilet as early as possible, the top of the pre- laying 7 of second waterproof is arranged on neighbour
The seaming position of the nearly threshold stone 10 and toilet floor tile 6.Pushed up for the increase lower surface of threshold stone 10 in the pre- laying 7 of the second waterproof
Waterproof surface near portion, the marine glue 8 at the pre- top of laying 7 of second waterproof is extended into the seam position from its described top
Put.For increase threshold stone 10 and the seam crossing of toilet floor tile 6 it is attractive in appearance, connect around the threshold stone 10 with toilet floor tile
Marine glue is coated with seam.
Preferably, threshold stone 2 ~ 3mm of lower surface described in the distance from top of the pre- laying of the second waterproof.
Equally preferably, the height of the pre- laying of the second waterproof is between 3 ~ 5cm;Second waterproof is overlay
The width of the widest part of the longitudinal section of layer is between 3 ~ 5cm.
To adapt to toilet warterproof needs, the structure of capital construction layer includes two parts, and structure of capital construction layer Part I 1 is located at
The lower section of the pre- laying 2 of first waterproof, structure of capital construction layer Part II 14 are located at ground in the room of the threshold stone 10 adjoining
The lower section of plate 11, the Part II 14 are higher than Part I 1.Spread using the indentation space of the structure of capital construction layer Part I 1
If toilet waterproofing structure and forming toilet less than the physical features in room, to avoid the water in toilet outflow is defended from surface
So as to flowing in room between life.
Further, the pre- laying 2 of first waterproof is located at the top of the structure of capital construction layer Part I 1, and it is located at
The top surface of the part of the lower section of second cement mortar adhered layer 5 forms inclined-plane, and the inclined-plane is lateral from neighbouring threshold stone 10 1
In trend from high to low inside toilet, make steam in toilet in the second mortar adhered layer 5 along the pre- laying 2 of the first waterproof
Top surface is flowed to inside toilet at toilet threshold stone 10, bathroom door is kept relatively dry, reduces waterproof difficulty.It is preferred that
, the distance between the top surface of the pre- laying 2 of the first waterproof and the lower surface of toilet floor tile 6 make toilet between 3 ~ 5cm
Floor tile 6 is firmly installed by the second cement mortar adhered layer 5, and the water storage in the second cement mortar adhered layer is minimum.
To prevent the steam in the first cement mortar adhered layer 9 from penetrating into structure of capital construction layer Part II 14, the waterproof
Pre- laying sets the 3rd waterproof to overlay layer 13, and its laying 2 pre- with the first waterproof forms one, and is overlay positioned at first waterproof
The top of layer 2, and between the structure of capital construction layer Part II 14 and the first cement mortar adhered layer 9.Described
3rd waterproof overlays and lays waterproof layer 3 and fish tail and waterproof layer 4 successively between layer 13 and the first mortar adhered layer 9, described
3rd waterproof overlays the top surface of layer 13 laying waterproof layer 3, and is laid on the 3rd waterproof and overlays the waterproof layer of the top surface of layer 13 from institute
Position 11 times structure of capital construction layer Part II top surface extensions in floor into the room of the first cement mortar adhered layer 9 are stated, and
More than the seaming position of floor 11 and threshold stone 10 in the room.
Further, the waterproof layer for overlaying the top surface of layer 13 with being laid on the 3rd waterproof in the lower surface of threshold stone 10
Between and the lower surface of threshold stone 10 and the room under floor structure of capital construction layer Part II top surface waterproof layer it
Between be coated with marine glue, prevent steam in the first cement mortar adhered layer 9 along the lower surface of threshold stone 10 and the three proofings
Gap and the lower surface of threshold stone 10 and the upper table of structure of capital construction layer Part II 14 between the top surface waterproof layer of the pre- laying 13 of water
Gap between the waterproof layer of face penetrates into floor 11 in room, is the second waterproof barrier of toilet threshold stone waterproof construction.
Certainly, it is to be also not limited to the example above to limitation of the present utility model, the utility model that described above, which is not,
The variations, modifications, additions or substitutions that those skilled in the art are made in essential scope of the present utility model,
Also the scope of protection of the utility model should be belonged to.
Claims (10)
1. a kind of toilet threshold stone waterproof construction, including threshold stone, the first cement mortar below the threshold stone are glued
Paste layer, the second cement mortar adhered layer, fish tail and waterproof layer, waterproof layer, structure of capital construction layer below toilet floor tile;It is special
Sign is, in addition to:
The pre- laying of waterproof, it includes:
The pre- laying of first waterproof, it is located under the first cement mortar adhered layer and the second cement mortar adhered layer
Side, the waterproof layer and fish tail and waterproof layer are laid on the pre- laying of the first waterproof and the first cement mortar adhered layer, the
Between two cement mortar adhered layers;
The pre- laying of second waterproof, it forms one with the pre- laying of the first waterproof, and positioned at the pre- laying of the first waterproof
Top, and between the first cement mortar adhered layer and the second cement mortar adhered layer, the waterproof layer is laid on institute
State between the pre- laying of the second waterproof and the first cement mortar adhered layer, the second cement mortar adhered layer;Second waterproof
The contour shape of the longitudinal section of pre- laying is in inverted V-shaped, and the fish tail and waterproof layer is laid on except at the top of the pre- laying of second waterproof
Outside waterproof layer and the first mortar adhered layer, the second cement mortar adhered layer between, the top is located at the threshold stone
Lower section, and marine glue is coated between the top and threshold stone lower surface.
2. threshold stone waterproof construction in toilet according to claim 1, it is characterised in that the pre- laying of the second waterproof
Top is adjacent to the seaming position of the threshold stone and toilet floor tile, and the marine glue is from the top of the pre- laying of the second waterproof
Extend to described seaming position.
3. threshold stone waterproof construction in toilet according to claim 1, it is characterised in that the pre- laying of the second waterproof
Threshold stone 2 ~ 3mm of lower surface described in distance from top.
4. threshold stone waterproof construction in toilet according to claim 1, it is characterised in that the pre- laying of the second waterproof
Height is between 3 ~ 5cm;The width of the widest part of the longitudinal section of the pre- laying of the second waterproof is between 3 ~ 5cm.
5. threshold stone waterproof construction in toilet according to claim 1, it is characterised in that positioned at second cement mortar
The top surface of the pre- laying of the first waterproof below adhered layer forms inclined-plane, and out of, the neighbouring threshold stone a lateral toilet
Portion is in overbank from high to low.
6. threshold stone waterproof construction in toilet according to claim 5, it is characterised in that the pre- laying of the first waterproof
The distance between lower surface of top surface and toilet floor tile is between 3 ~ 5cm.
7. threshold stone waterproof construction in toilet according to any one of claim 1 to 6, it is characterised in that
The structure of capital construction layer include Part I below the pre- laying of the first waterproof and positioned at the threshold stone
Part II in adjacent room below floor, the Part II are higher than Part I;
The pre- laying of waterproof also overlays layer including the 3rd waterproof, and it forms one with the pre- laying of the first waterproof, and is located at
The top of the pre- laying of first waterproof, and the Part II between the structure of capital construction layer is pasted with first cement mortar
Between layer.
8. threshold stone waterproof construction in toilet according to claim 7, it is characterised in that overlay layer in the 3rd waterproof
Described waterproof layer and fish tail and waterproof layer are equipped between the first cement mortar adhered layer.
9. threshold stone waterproof construction in toilet according to claim 8, it is characterised in that the 3rd waterproof overlays layer position
In the lower section of the threshold stone, waterproof layer is equipped with the top surface that the 3rd waterproof overlays layer, and be laid on the three proofings
The waterproof layer of the pre- laying top surface of water structure of capital construction under floor into the room from the position of the first cement mortar adhered layer
The extension of layer Part II upper surface, and more than floor in the room and the seaming position of threshold stone.
10. threshold stone waterproof construction in toilet according to claim 9, it is characterised in that in the threshold stone and laying
The capital construction knot under floor between the 3rd waterproof overlays the waterproof layer of layer top surface and in the threshold stone and the room
Marine glue is coated between the waterproof layer of structure layer Part II top surface.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720877852.8U CN207032521U (en) | 2017-07-19 | 2017-07-19 | A kind of toilet threshold stone waterproof construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720877852.8U CN207032521U (en) | 2017-07-19 | 2017-07-19 | A kind of toilet threshold stone waterproof construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207032521U true CN207032521U (en) | 2018-02-23 |
Family
ID=61464882
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720877852.8U Expired - Fee Related CN207032521U (en) | 2017-07-19 | 2017-07-19 | A kind of toilet threshold stone waterproof construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207032521U (en) |
-
2017
- 2017-07-19 CN CN201720877852.8U patent/CN207032521U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104047356B (en) | A kind of antiseep is bathed between defending and Antiseep method | |
CN104100011A (en) | Toilet floor heating waterproof construction method and toilet floor heating waterproof system | |
CN106284706A (en) | The construction method of external wall outer insulation rock cotton board | |
CN108487481A (en) | A kind of antiseep assembled water stopping thresholds and its construction method | |
CN206205167U (en) | A kind of indoor toilets threshold stone water proof structure | |
CN109750758A (en) | The construction method that prefabricated sandwich heat preservation shear wall exterior wall is laterally stitched and vertically stitched | |
CN207110817U (en) | Toilet threshold waterproof construction | |
CN204531883U (en) | Shower house dash threshold constructs | |
CN206070602U (en) | Resistance to plucking pile head node waterproof structure | |
CN207032521U (en) | A kind of toilet threshold stone waterproof construction | |
CN206205168U (en) | A kind of bathroom door pin waterproof treatment structure | |
CN206220272U (en) | Ground hot water lays heating toilet doorway sealing damp proof insulation construction | |
CN206844380U (en) | A kind of waterproof wall body structure | |
CN211286064U (en) | Waterproof construction structure of kitchen guarding ground | |
CN205676931U (en) | A kind of basement waterproofing base plate | |
CN104818835B (en) | Toilet threshold stone waterproof structure and construction method | |
CN207714385U (en) | A kind of mixing pile cut-pff wall and bottom plate connecting structure | |
CN207988424U (en) | A kind of moisture-proof ground of rubble drainage layer draining | |
CN206233388U (en) | A kind of waterproof system of toilet | |
CN208167997U (en) | Waterproof construction at a kind of toilet threshold | |
CN211548589U (en) | Dampproofing structure in bathroom | |
CN209653773U (en) | A kind of shower cabinet threshold water-retaining structure | |
CN209260932U (en) | A kind of accomodation ground seepage-proof structure | |
CN210767273U (en) | Node processing structure at separation position of shower room and washing room | |
CN204609233U (en) | Washroom threshold stone waterproof construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180223 Termination date: 20210719 |