CN207027896U - Ash system under well head not decoupling device screw delivery pump - Google Patents

Ash system under well head not decoupling device screw delivery pump Download PDF

Info

Publication number
CN207027896U
CN207027896U CN201720915586.3U CN201720915586U CN207027896U CN 207027896 U CN207027896 U CN 207027896U CN 201720915586 U CN201720915586 U CN 201720915586U CN 207027896 U CN207027896 U CN 207027896U
Authority
CN
China
Prior art keywords
casing
ash
conveying worm
mixer
well head
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720915586.3U
Other languages
Chinese (zh)
Inventor
庆文奎
刘波
孟方
张坤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Coal No 5 Construction Co Ltd
Original Assignee
China Coal No 5 Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Coal No 5 Construction Co Ltd filed Critical China Coal No 5 Construction Co Ltd
Priority to CN201720915586.3U priority Critical patent/CN207027896U/en
Application granted granted Critical
Publication of CN207027896U publication Critical patent/CN207027896U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Processing Of Solid Wastes (AREA)

Abstract

The utility model announces ash system under a kind of well head not decoupling device screw delivery pump, belongs to technical field of engineering machinery.Mixer side is connected with mixer storage bin, and removable flat car is provided with conveying worm;Conveying worm includes the casing of tubular, and feeding mouth is offered above casing one end, feed opening is offered below the casing other end;Spiral reamer is installed in casing;Drive device is provided with one end of casing feeding mouth, drive device is connected by shaft coupling with spiral reamer;The feed opening of conveying worm is connected with rotatable chute.Under the utility model well head during concrete, ash can is not plucked, avoiding personnel, ash can topple over danger of hurting sb.'s feelings when pushing away ash can;Ground staff take it is less, time end, labor strength is smaller, safe to use, and operating efficiency is high;Easy to maintenance, cost is relatively low.

Description

Ash system under well head not decoupling device screw delivery pump
Technical field
Technical field of engineering machinery is the utility model is related to, ash system under specifically a kind of well head not decoupling device screw delivery pump System.
Background technology
Shandong Gold Group Co., Ltd. Xincheng Gold Ore picks up 8000t/d extension projects Teng man returnairshaft and is located at new city It is only straight positioned at Jincheng Town, Laizhou City, Shandong Province new city village Dong0.5kmChu, pit shaft away from Xincheng Gold Mine 3.5km in gold mine Teng Jia mining areas Footpath 7.0m, pit shaft normal reach lining thickness are 300mm (- 605m is with epimere) and 400mm (- 605m is with hypomere), wellhead ground mark Height+11.83m, shaft bottom absolute altitude -1135m;- 225m, -425m, -620m are provided with rest chamber, and -720m is provided with unilateral ingate, - 820m, -920m, -1020m, -1120m are provided with bilateral ingate, are provided with and detour at ingate.The pit shaft preliminary shaft designs double-deck well Wall strength grade of concrete is C30, and well bore and ingate single layer well wall strength grade of concrete are C25.Well head nearby builds stirring Stand, stand 2 MP1500 type forced action type concrete mixers of interior arrangement and 2 sets of PLD1600 type concrete proportioning machines, offer coagulation is poured for pit shaft Soil.Need one to lay track in well head side closure plate according to conventional construction, place flat car, manpower is bulldozed wooden handcart, arrives Lower ash can is linked up with again on Manhole closing disk trapdoor, and construction period is comparatively laborious, and process is more, and ground staff is more.Secondly A belt conveyor is put in well head side, and belt feeder front end is stretched out mixer discharging opening in the upper edge of bottom discharge bucket, rear end, mixed Solidifying soil is transported in bottom discharge bucket through belt feeder, and after well-bucket chengman, belt feeder is retreated to beyond trapdoor, then transfers bottom The formula well-bucket of unloading completes lower ash work, and occupancy well head space is big, and movable belt conveyor is wasted time and energy.
The content of the invention
In order to solve the above technical problems, the utility model provides ash system under a kind of well head not decoupling device screw delivery pump.
The utility model is by the following technical programs:Ash system under a kind of well head not decoupling device screw delivery pump, including stirring Machine, mixer side are connected with mixer storage bin, in addition to a conveying worm, are provided with conveying worm removable Flat car;The conveying worm includes the casing of tubular, and feeding mouth is offered above casing one end, is opened below the casing other end Provided with feed opening;Spiral reamer is installed, the both ends of spiral reamer pass through front end bearings, rear axle respectively in the casing Support is held to be rotatably connected with casing both ends;Drive device is provided with one end of casing feeding mouth, drive device passes through shaft coupling It is connected with spiral reamer;The feed opening of the conveying worm is connected with rotatable chute.
It is further:The spiral reamer share it is multiple, between adjoining spiral reamer pass through intermediate bearing support connection; The intermediate bearing is supported and fixed in casing.
The mixer shares two, and the mixer storage bin is arranged between two mixers;The mixer peace Equipped with stirring system stock shelf.
The utility model transports concrete from a conveying worm to ash can, and conveying worm is fixed on removable flat board Che Shang, pulled out when beating grey, not the used time return to below mixer, rotatable chute is installed in conveying worm front end, can be in spiral shell Revolve in the case that conveyer does not move respectively to ash under two ash cans, the blanking of conveying worm rear end face mixer storage bin Mouthful.
Compared with the mode for being bulldozed wooden handcart:
(1) ash can is not plucked during concrete under the utility model well head, avoiding personnel, ash can topple over wound when pushing away ash can People is dangerous;
(2) discharging is carried out using conveying worm, ground staff takes less;If using double-hook hoisting, a spiral shell is placed Revolve conveyer, user of service is 3 people, according to pushing away ash can, at least 8 people, it is necessary to push away grey narrow-necked earthen jar, steady narrow-necked earthen jar, labor intensity it is larger and It is dangerous;
(3) time is saved for rapid construction, using conveying worm discharging, carried from grey narrow-necked earthen jar and put well head to dress ash to lower narrow-necked earthen jar only 1-2 minutes are needed, are substantially reduced in time, and use is bulldozed wooden handcart, this procedure at least wants 10 minutes, it is seen that spiral Conveyer greatlys save the time.
Compared with the mode of belt conveyor:
(1) belt conveyor preparation needs 10 people to complete, as long as the people of conveying worm preparation 2 completes, It is big to save personnel;
(2) occupied little space with Belt Conveying ratio;Safeguard and maintenance is few;Winter construction will not elephant hide band equally go out to freeze;
(3) use cost is low, it is not necessary to changes important accessory, one pit shaft of belt feeder needs to change 4-5 belt feeder;
(4) time is short, and belt conveyor needs 15-20 times minute, and conveying worm only needs 1 minute just Can be ready in place.
Brief description of the drawings
Fig. 1 is the utility model structure diagram;
Fig. 2 is top view in Fig. 1;
Fig. 3 is screw conveyer structure schematic diagram.
In figure:1st, stirring system stock shelf;2nd, mixer;3rd, mixer storage bin;4th, conveying worm;4-1, front end axle Hold support;4-2, spiral reamer;4-3, casing;4-4, intermediate bearing support;4-5, rear end bearing support;4-6, shaft coupling;4- 7th, drive device;4-8, feed opening;4-9, feeding mouth;5th, it may move flat car;6th, rotatable chute;7th, ash can.
Embodiment
It is a specific embodiment of the present utility model below, in conjunction with accompanying drawing, the utility model is described in further detail.
As shown in figure 1, ash system under a kind of well head not decoupling device screw delivery pump, two mixers 2 are positioned opposite, at two One mixer storage bin 3 is installed, the material that mixer 2 processes enters in mixer storage bin 3, stirring between mixer 2 The lower section of machine storage bin 3 offers discharging opening.Each mixer 2 is provided with a stirring system stock shelf 1, stirring system feeding Frame 1 is used for the transferring raw material of mixer 2.A conveying worm 4 is provided with below mixer storage bin 3, under conveying worm 4 Removable flat car 5 is installed, removable flat car 5 is used for drive the movement transposition of conveying worm 4.
In conjunction with shown in Fig. 2, conveying worm 4 includes columnar casing 4-3, offered above casing 4-3 right-hand members into Feed opening 4-8 is offered below material mouth 4-9, casing 4-3 left end;In use, feeding mouth 4-9 and mixer storage bin 3 discharging Mouth is relative, for receiving the material processed in mixer storage bin 3.It is concentric in casing 4-3 that two spiral hinges are installed Knife 4-2, spiral reamer 4-2 both ends support 4-5 and casing 4-3 both ends can by front end bearings 4-1, rear end bearing respectively Rotation connection;4-4 connections are supported by intermediate bearing between two spiral reamer 4-2, intermediate bearing support 4-4 is fixed on casing 4- Upside in 3.Drive device 4-7 is provided with casing 4-3 right-hand members, drive device 4-7 is connected by shaft coupling 4-6 and spiral reamer 4-2 Connect;Drive device 4-7 drives spiral reamer 4-2 to rotate, and then material is transported from right to left.
The feed opening 4-8 of conveying worm 4 is connected with rotatable chute 6, and ash can 7 is placed in the rotatable lower section of chute 6.It can revolve It is rotatable in the range of certain angle to turn chute 6 so that, can be into different ash cans 7 in the case that conveying worm 4 is motionless Unload material.
Concrete operation step:
(1) after underground, which possesses, beats grey condition and after the object such as hanging scaffold ash divider all transfers to underground, bottom-dump is hung Bucket is transported to well head, and well-bucket is delivered on trapdoor using electric block, and well-bucket then is lifted into 0.2 meter or so height with lifting gib head Degree, sets the position of well-bucket, falls well-bucket, seat is on well lid;
(2) conveying worm is pushed into that discharge position can be gone up, the rotatable trough outlet in front end makes from ash can upper limb 100mm Concrete is fairly fallen in well-bucket, and the feeding mouth of rear end is in the discharging opening lower end of mixer storage bin;
(3) drive device is opened, starts conveying worm, then puts ash, treats that the bottom discharge bucket in ash can is also surplus 0.2 meter Gao Shi, mixer storage bin is closed, stopping puts ash, conveying worm inner concrete has been sent, and stops conveying worm, then will Rotatable chute, which is removed, to be hung up properly, and prevents tank cap collision chute front;
(4) after ensuring that above and below tank cap is safe and punctual, signalman sends signal, and bottom discharge bucket is carried to underground;
(5) as long as ash moves to chute the repetition aforesaid operations suitable for reading of ash can under another ash can;
(6) after beating ash and terminating, conveying worm is released into mixer, rinsed well with water, all bearing portions are yellow Oil is safeguarded, is easy to next use.
Construction effect:
(1) maintenance, particularly each bearing portions are strengthened, each use finishes, it is necessary to maintenance in time;
(2) bulky grain stirring material transport is realized;
(3) quality of winter construction concrete is improved;
(4) when unsnatching ash every time and be pushed into beyond trapdoor, it is necessary to ensure that safe distance, prevent narrow-necked earthen jar cap from bumping against belt feeder;
(5) Basis was being constructed 1000 meters in pit shaft, only carried out once small-scale maintenance;
(6) conveying worm is suitable for reading is blocked with mesh sheet in operation by personnel, prevents from falling into during personnel's maloperation;
(7) to be cleared up in time after the completion of use prevents residual concrete caking from influenceing to use next time;
(8) in use, conveying worm wants timely fixation afterwards in place, prevents coaster.
Using wanting locked in time when completing to restore, human users and flat car automatic running are prevented, influences normal construction, Bring potential safety hazard.

Claims (3)

1. ash system under a kind of well head not decoupling device screw delivery pump, including mixer (2), mixer (2) side is connected with stirring Machine storage bin (3), it is characterised in that:
Also include a conveying worm (4), removable flat car (5) is installed under conveying worm (4);
The conveying worm (4) includes the casing (4-3) of tubular, and feeding mouth (4-9) is offered above casing (4-3) one end, Feed opening (4-8) is offered below casing (4-3) other end;Spiral reamer (4-2), spiral are installed in the casing (4-3) The both ends of reamer (4-2) can be turned by front end bearings (4-1), rear end bearing support (4-5) with casing (4-3) both ends respectively Dynamic connection;Drive device (4-7) is provided with one end of casing (4-3) feeding mouth (4-9), drive device (4-7) passes through shaft coupling (4-6) is connected with spiral reamer (4-2);
The feed opening (4-8) of the conveying worm (4) is connected with rotatable chute (6).
2. ash system under well head not decoupling device screw delivery pump according to claim 1, it is characterised in that:The spiral reamer (4-2) is shared multiple, supports (4-4) to connect by intermediate bearing between adjoining spiral reamer (4-2);The intermediate bearing support (4-4) is fixed in casing (4-3).
3. ash system under well head not decoupling device screw delivery pump according to claim 1, it is characterised in that:The mixer (2) two are shared, the mixer storage bin (3) is arranged between two mixers (2);The mixer (2), which is provided with, stirs Mix system stock shelf (1).
CN201720915586.3U 2017-07-26 2017-07-26 Ash system under well head not decoupling device screw delivery pump Active CN207027896U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720915586.3U CN207027896U (en) 2017-07-26 2017-07-26 Ash system under well head not decoupling device screw delivery pump

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720915586.3U CN207027896U (en) 2017-07-26 2017-07-26 Ash system under well head not decoupling device screw delivery pump

Publications (1)

Publication Number Publication Date
CN207027896U true CN207027896U (en) 2018-02-23

Family

ID=61462647

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720915586.3U Active CN207027896U (en) 2017-07-26 2017-07-26 Ash system under well head not decoupling device screw delivery pump

Country Status (1)

Country Link
CN (1) CN207027896U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107471452A (en) * 2017-07-26 2017-12-15 中煤第五建设有限公司 Ash system under a kind of well head not decoupling device screw delivery pump

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107471452A (en) * 2017-07-26 2017-12-15 中煤第五建设有限公司 Ash system under a kind of well head not decoupling device screw delivery pump

Similar Documents

Publication Publication Date Title
US8388831B2 (en) Compact slurry preparation system for oil sand
CN207027896U (en) Ash system under well head not decoupling device screw delivery pump
CN205466758U (en) Discharging device and dry -mixed mortar remove silo for silo
CN107471452A (en) Ash system under a kind of well head not decoupling device screw delivery pump
CN101462817A (en) Sludge sterilization system
CN108177252A (en) A kind of application method for the three-in-one stirring complexes for producing three kinds of engineering material
CN201419442Y (en) Storage tank with agitating device for mortar to be mixed
CA2480122C (en) Compact slurry preparation system for oil sand
CA2469326A1 (en) Oil sand conditioning process and apparatus
CN108003900A (en) A kind of closed petroleum coke dehydration, storage and handling facility
CN2848661Y (en) Multifunction concrete agitating transporting car
CN212197233U (en) A cloth turns over throws all-in-one for organic solid useless aerobic fermentation
CN110280570A (en) A kind of solid waste decomposition apparatus
CN208054269U (en) Bucket elevator
CN208789043U (en) A kind of screw extruder mixing blanking component
CN207446388U (en) Ball mill spits ore deposit Full-automatic circulation system
CN206082232U (en) Water treatment dry powder charge device
CN205743781U (en) Drilling wastes solidification automatic feeding device
CN205739554U (en) Feeding-distribution device on bifurcated funnel
CN206487472U (en) A kind of pit shaft pours device
CN205916808U (en) Standdle carrier railway carriage or compartment doffer on loading funnel
CN108193579A (en) A kind of pitch cold-repairing material proportioner
CN107447986A (en) A kind of construction method of concrete chute device and the chute device
CN204502838U (en) Lifting type mixer
CN206215159U (en) For the conveying device of phenol cyanogen sludge feed proportioning system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant