CN207017294U - Equipment anchor bolt buries the construction tool of reserving hole - Google Patents
Equipment anchor bolt buries the construction tool of reserving hole Download PDFInfo
- Publication number
- CN207017294U CN207017294U CN201720969719.5U CN201720969719U CN207017294U CN 207017294 U CN207017294 U CN 207017294U CN 201720969719 U CN201720969719 U CN 201720969719U CN 207017294 U CN207017294 U CN 207017294U
- Authority
- CN
- China
- Prior art keywords
- steel
- hole
- reinforcement cage
- pore
- steel reinforcement
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Foundations (AREA)
Abstract
The utility model discloses the construction tool that a kind of equipment anchor bolt buries reserving hole, this frock includes the pore-forming pipe and steel reinforcement cage matched with reserving hole, some steel rings of steel reinforcement cage including spaced and parallel arrangement, located at some vertical reinforcing bars of some steel ring outer rings and the cross reinforcing rods located at bottom steel rib ring inner ring, pore-forming pipe sealing two ends and sink to steel reinforcement cage from steel reinforcement cage top surface.This frock effectively improves the success rate of hole indwelling, can indwelling construction operation that is economic, quick, being efficiently completed anchor bolt box hole, ensure the installation quality of equipment.
Description
Technical field
It the utility model is related to the construction tool that a kind of equipment anchor bolt buries reserving hole.
Background technology
With the further development of process of industrialization, traditional small workshop mode factory is gradually eliminated, large-scale environment-friendly type
Industrial enterprise further flourishes, and all industrial premises will carry out the installations of large number quipments when building, in work progress
Because equipment installation and Equipment Foundations can not be constructed simultaneously, it is therefore necessary to reserve equipment anchor bolt when Equipment Foundations are constructed
Hole, after equipment installs carrying out back-grouting again to the hole of burial equipment foundation bolt is fixed.
The indwelling of hole for convenience in work progress, generally use reserves timber, plank sheathing makes reserving hole, prefabricated
The mode indwelling hole such as concrete blinding, preset bellows;Flitch, i.e., be embedded to by so-called reserved timber before concreting
To relevant position, its shortcoming is that position is not fixed easily, and timber causes hole to collapse when extracting;So-called plank sheathing makes preformed hole
Hole, i.e., with template construct into being not to be fixed easily with reserving hole size identical core, its shortcoming, core is not easily taken out;It is so-called
Precast concrete form, i.e., the prefabricated board of a prefabricated grade higher than base concrete intensity, its shortcoming are installation edge joint positions in advance
Spillage is easily caused, installation is heavy;So-called preset bellows, i.e., prefabricated bellows carry out the indwelling of reserving hole, and its shortcoming is
Trouble is taken out, cost is higher.
The content of the invention
Technical problem to be solved in the utility model is to provide the construction that a kind of equipment anchor bolt buries reserving hole
Frock and method, this frock and method overcome the defects of traditional hole indwelling mode, effectively improve the success rate of hole indwelling,
Can indwelling construction operation that is economic, quick, being efficiently completed anchor bolt box hole, ensure the installation quality of equipment.
In order to solve the above technical problems, the utility model device foundation bolt bury reserving hole construction tool include with
Reserving hole external diameter, the pore-forming pipe and steel reinforcement cage of depth matching, some steel rings of the steel reinforcement cage including spaced and parallel arrangement,
Located at some vertical reinforcing bars of some steel ring outer rings and the cross reinforcing rod located at bottom steel rib ring inner ring, the pore-forming
Pipe sealing two ends and sink to the steel reinforcement cage from the steel reinforcement cage top surface.
Further, the steel reinforcement cage internal diameter is more than 3~5mm of the pore-forming pipe external diameter, and the pore-forming tube top face is higher than described
50~70mm of steel reinforcement cage top surface.
Further, when hole aperture is less than 150mm, the vertical reinforcing bar is three, when hole aperture is more than 150mm
When, often increase 80mm and add a vertical reinforcing bar more;When hole depth is less than 300mm, the steel ring is twice, works as hole
When depth is more than 300mm, one of steel ring is set every 200mm.
Further, this frock also includes two hangers, and described two hangers are symmetrically set in the pore-forming tube top face outer ring.
The construction tool that reserving hole is buried due to the utility model device foundation bolt employs above-mentioned technical proposal, i.e.,
This frock includes the pore-forming pipe and steel reinforcement cage that matchs with reserving hole, some steel rings of the steel reinforcement cage including spaced and parallel arrangement,
Located at some vertical reinforcing bars of some steel ring outer rings and the cross reinforcing rod located at bottom steel rib ring inner ring, the end seal of pore-forming pipe two
Mouthful and sink to steel reinforcement cage from steel reinforcement cage top surface.This frock overcomes the defects of traditional hole indwelling mode, effectively improves hole
The success rate of indwelling, can indwelling construction operation that is economic, quick, being efficiently completed anchor bolt box hole, ensure equipment
Installation quality.
Brief description of the drawings
The utility model is described in further detail with embodiment below in conjunction with the accompanying drawings:
Fig. 1 is the construction tool structural representation that the utility model device foundation bolt buries reserving hole;
Fig. 2 is reinforcement cage structure schematic diagram in this frock;
Fig. 3 is pore-forming pipe and shackle structure schematic diagram in this frock.
Embodiment
As shown in Figure 1, Figure 2 and Figure 3, the utility model device foundation bolt buries the construction tool of reserving hole to embodiment
Including the pore-forming pipe 1 and steel reinforcement cage 2 matched with reserving hole external diameter, depth, if the steel reinforcement cage 2 includes spaced and parallel arrangement
Dry steel ring 21, some vertically reinforcing bar 22 and the crosses located at bottom steel rib ring inner ring located at some outer rings of steel ring 21
Reinforcing rod 23, the sealing two ends of pore-forming pipe 1 and sinks to the steel reinforcement cage 2 from the top surface of steel reinforcement cage 2.
Preferably, the internal diameter of steel reinforcement cage 2 is more than the 3~5mm of external diameter of pore-forming pipe 1, and the top surface of pore-forming pipe 1 is higher than institute
State the 50~70mm of top surface of steel reinforcement cage 2.
Preferably, when hole aperture is less than 150mm, the vertical reinforcing bar 22 is three, when hole aperture is more than 150mm
When, often increase 80mm and add a vertical reinforcing bar 22 more;When hole depth is less than 300mm, the steel ring 21 is twice, when
When hole depth is more than 300mm, one of steel ring 21 is set every 200mm.The steel ring 21 of steel reinforcement cage 2 and vertically reinforcing bar 22
Setting is defined by the rigidity of steel reinforcement cage 2 and stability, to ensure reliable pore-forming.
Preferably, this frock also includes two hangers 3, and described two hangers 3 are symmetrically set in outside the top surface of pore-forming pipe 1
Circle.
The construction method for realizing the embedded reserving hole of equipment anchor bolt using above-mentioned frock comprises the following steps:
Step 1: determining reserving hole position and type, including hole aperture and depth according to construction drawing, make and pre-
Box out hole matching any of the above-described frock;
Step 2: the steel reinforcement cage of frock is welded on to the reserving hole position of banded good reinforcement foundation, steel reinforcement cage
The steel ring of top surface is with reinforcement foundation with high, it is ensured that reinforcing bar cage location is errorless and after firmly installing, by pore-forming pipe from reinforcing bar cage top
Face is sunk in steel reinforcement cage;The steel reinforcement cage of welding forms an entirety with reinforcement foundation, avoids the shift in position of steel reinforcement cage;
Step 3: carrying out concreting to reinforcement foundation, after concrete initial set, pore-forming pipe is taken out of concrete
Go out, after concrete setting shaping, the hole that pore-forming pipe is formed in concrete is that equipment anchor bolt buries reserving hole.
Preferably, when the pore-forming pipe takes out out of concrete, two, pore-forming tube top face hanger is held, and pore-forming pipe is light
Turn gently to carry, until pore-forming pipe takes out.
Pore-forming pipe can be made by PVC plastic pipe in this frock, and hole can be filled out PVC plastic pipe using woven bag plug up and down
Closure is realized in PVC plastic pipe, or the closing PVC plastic mouth of pipe is wound with adhesive tape, prevents coagulation in concreting process
Soil is poured into PVC plastic pipe, and the hanger in pore-forming tube top face can use iron wire bending fixation to form.Concrete initial set in construction method
It is general about 2 hours or so, the time should be specifically determined according to factors such as temperature during concreting, weather, wind-force, pore-forming pipe takes
During going out, if finding, concrete strength is not up to pre-hardening state and should stopped operation, and avoids causing hole to damage, treats coagulation soil matrix
After this coagulation forming, pore-forming pipe, which takes out, to cause hole to damage, and the pore-forming pipe of taking-up can be used for next construction operation, only need to make
Make supporting steel reinforcement cage.
This frock is primarily adapted for use in the embedded reserving hole of M6~M48 foundation bolt, is applied to depth in length direction
Foundation bolt less than 1.3m buries the indwelling of reserving hole, can it is economical, quick, be efficiently completed anchor bolt box hole
Indwelling construction operation, ensure the installation quality of equipment.
Claims (4)
1. a kind of equipment anchor bolt buries the construction tool of reserving hole, it is characterised in that:This frock includes and reserving hole
External diameter, the pore-forming pipe and steel reinforcement cage of depth matching, the steel reinforcement cage include some steel rings of spaced and parallel arrangement, located at described
Some vertical reinforcing bars of some steel ring outer rings and the cross reinforcing rod located at bottom steel rib ring inner ring, the end seal of pore-forming pipe two
Mouthful and sink to the steel reinforcement cage from the steel reinforcement cage top surface.
2. equipment anchor bolt according to claim 1 buries the construction tool of reserving hole, it is characterised in that:The steel
Muscle cage internal diameter is more than 3~5mm of the pore-forming pipe external diameter, and the pore-forming tube top face is higher than 50~70mm of the steel reinforcement cage top surface.
3. equipment anchor bolt according to claim 1 or 2 buries the construction tool of reserving hole, it is characterised in that:When
When hole aperture is less than 150mm, the vertical reinforcing bar is three, when hole aperture is more than 150mm, often increases 80mm and adds more
A piece vertical reinforcing bar;When hole depth is less than 300mm, the steel ring is twice, when hole depth is more than 300mm, often
Every 200mm, one of steel ring is set.
4. equipment anchor bolt according to claim 3 buries the construction tool of reserving hole, it is characterised in that:This frock
Also include two hangers, described two hangers are symmetrically set in the pore-forming tube top face outer ring.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720969719.5U CN207017294U (en) | 2017-08-04 | 2017-08-04 | Equipment anchor bolt buries the construction tool of reserving hole |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720969719.5U CN207017294U (en) | 2017-08-04 | 2017-08-04 | Equipment anchor bolt buries the construction tool of reserving hole |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207017294U true CN207017294U (en) | 2018-02-16 |
Family
ID=61477801
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720969719.5U Expired - Fee Related CN207017294U (en) | 2017-08-04 | 2017-08-04 | Equipment anchor bolt buries the construction tool of reserving hole |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207017294U (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108951683A (en) * | 2018-07-18 | 2018-12-07 | 中铁广州工程局集团有限公司 | A kind of prefabricated cushion cap of land superposed type and its production and installation method |
CN108978699A (en) * | 2018-07-18 | 2018-12-11 | 中铁广州工程局集团有限公司 | Land integral prefabricated bearing platform and production and installation method thereof |
CN109083184A (en) * | 2018-07-18 | 2018-12-25 | 中铁广州工程局集团有限公司 | A kind of prefabricated cushion cap of land sectional type and its production and installation method |
CN109137990A (en) * | 2018-07-18 | 2019-01-04 | 中铁广州工程局集团有限公司 | A kind of prefabricated cushion cap of land delay-pour joint sectional type and its production and installation method |
CN109386009A (en) * | 2017-08-04 | 2019-02-26 | 上海宝冶集团有限公司 | Equipment anchor bolt buries the construction tool and method of reserving hole |
-
2017
- 2017-08-04 CN CN201720969719.5U patent/CN207017294U/en not_active Expired - Fee Related
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109386009A (en) * | 2017-08-04 | 2019-02-26 | 上海宝冶集团有限公司 | Equipment anchor bolt buries the construction tool and method of reserving hole |
CN108951683A (en) * | 2018-07-18 | 2018-12-07 | 中铁广州工程局集团有限公司 | A kind of prefabricated cushion cap of land superposed type and its production and installation method |
CN108978699A (en) * | 2018-07-18 | 2018-12-11 | 中铁广州工程局集团有限公司 | Land integral prefabricated bearing platform and production and installation method thereof |
CN109083184A (en) * | 2018-07-18 | 2018-12-25 | 中铁广州工程局集团有限公司 | A kind of prefabricated cushion cap of land sectional type and its production and installation method |
CN109137990A (en) * | 2018-07-18 | 2019-01-04 | 中铁广州工程局集团有限公司 | A kind of prefabricated cushion cap of land delay-pour joint sectional type and its production and installation method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207017294U (en) | Equipment anchor bolt buries the construction tool of reserving hole | |
CN104452749B (en) | The constructional method of a kind of reinforced concrete cast-in-situ pile tube | |
CN104895092A (en) | Method for using inner-support temporary latticed column as permanent structure column | |
CN103993598B (en) | One is drawn hole and is implanted cloth bag crushed stone grouting pile and construction method | |
CN202644519U (en) | Special fixing clamp for preventing reinforcement cage of cast-in-situ bored pile from floating upward | |
CN111042213A (en) | Construction method for replacing raft split heads with anti-floating anchor rods for supporting | |
CN109386009A (en) | Equipment anchor bolt buries the construction tool and method of reserving hole | |
CN107542086B (en) | Anchor cable construction method for filling slope | |
CN203821381U (en) | Rectangular pre-stressed filling pile | |
CN204959787U (en) | Novel tower crane combination formula basis | |
CN104005414B (en) | Large-size rebar cast in place concrete pile supports the constructional method of column | |
CN106400783A (en) | Construction method for manufacturing cast-in-place pile through unfolded type reinforcement cage | |
CN204676533U (en) | A kind of soil-nail wall support system based on the recyclable technique of assembling | |
CN101514551B (en) | Artificial excavating pile reinforcing cage vertical colligation and installation method | |
CN110820728A (en) | Cast-in-situ bored pile construction method for penetrating underground deep-buried waste pipeline | |
JP2017155478A (en) | Earth retaining preceding method of using adjustable wale | |
CN102094419A (en) | Method for forming drilled pile in foundation with silty sand layer | |
JP6757003B2 (en) | Construction method of double pipe pile and double pipe pile | |
CN105178356A (en) | Setting-up construction method for vertical joint bars of columns in reverse building method | |
CN114960715A (en) | Underground engineering surge treatment device and control method | |
CN212688926U (en) | Resistance to plucking device suitable for precast tubular pile | |
CN103924595B (en) | A kind of hollow pipe column underwater casting self-floating inner formwork system | |
CN204282348U (en) | A kind of reinforced concrete cast-in-situ pile tube | |
CN208701748U (en) | Integrated vertical supporting system in reverse construction stage | |
CN203924043U (en) | A kind of bamboo concrete stake |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180216 |
|
CF01 | Termination of patent right due to non-payment of annual fee |