JP2017155478A - Earth retaining preceding method of using adjustable wale - Google Patents

Earth retaining preceding method of using adjustable wale Download PDF

Info

Publication number
JP2017155478A
JP2017155478A JP2016039478A JP2016039478A JP2017155478A JP 2017155478 A JP2017155478 A JP 2017155478A JP 2016039478 A JP2016039478 A JP 2016039478A JP 2016039478 A JP2016039478 A JP 2016039478A JP 2017155478 A JP2017155478 A JP 2017155478A
Authority
JP
Japan
Prior art keywords
earth retaining
construction method
wale
support
outer cylinder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2016039478A
Other languages
Japanese (ja)
Other versions
JP6068774B1 (en
Inventor
前田 英樹
Hideki Maeda
英樹 前田
亮一 菊田
Ryoichi Kikuta
亮一 菊田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NIPPON SPEED SHORE
NIPPON SUPIIDE SHIYOA KK
Original Assignee
NIPPON SPEED SHORE
NIPPON SUPIIDE SHIYOA KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NIPPON SPEED SHORE, NIPPON SUPIIDE SHIYOA KK filed Critical NIPPON SPEED SHORE
Priority to JP2016039478A priority Critical patent/JP6068774B1/en
Application granted granted Critical
Publication of JP6068774B1 publication Critical patent/JP6068774B1/en
Publication of JP2017155478A publication Critical patent/JP2017155478A/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

PURPOSE: To provide an earth retaining preceding method of using an adjustable wale without using a permanent beam.CONSTITUTION: The present invention written in a Claim 1 is an earth retaining preceding method for supporting a sheet pile along an excavation groove by a timbering constituted of a pair of wales and a plurality of struts installed between both wales, and after installing the timbering, a lower beam material is installed in a lower end part of the sheet pile, and next, the strut of the upper timbering is removed, and after installing a pipe body in the excavation groove, the strut is installed again in the upper timbering, and next, the lower beam material is removed. The present invention written in a Claim 2 uses a freely expandable wale. In the present invention written in a Claim 3, the wale is constituted of an outer cylinder and an inner cylinder slidable in the outer cylinder.SELECTED DRAWING: Figure 6

Description

本発明は土留め先行工法に関し、より詳しくは水道管等の長尺の管体を埋設する際に使用する捨て梁を、回収可能とする土留め先行工法に関する。   The present invention relates to an earth retaining prior construction method, and more particularly, to an earth retaining prior construction method that makes it possible to collect a discarded beam used when embedding a long pipe body such as a water pipe.

小規模な溝掘削作業を伴う上下水道工事等においては、溝掘削作業及び溝内作業中における土砂崩壊に伴う労働災害を防ぐため、溝内での作業に先行して土留め支保工を設置するのが通常である。   For waterworks and sewerage work involving small-scale trench excavation work, in order to prevent occupational accidents associated with sediment collapse during trench excavation work and in-groove work, a soil retaining support will be installed prior to the work in the trench. It is normal.

具体的にはドラグショベルによって掘削(素掘り)し、その後、軽量鋼矢板を掘削面に張りつけるように建て込み、腹起し、切梁を取り付けて土留め支保工を組み立てるものである。   Specifically, it is excavated (raw digging) with a drag shovel, and then built with light steel sheet piles attached to the excavated surface, erected, and attached with beams to assemble a retaining support.

このように溝内での作業に先行して土留め支保工を設置する土留め先行工法において、支保工の設置後水道管等の長尺の管体を埋設する工程を、以下図面を参照しながら概説する。   In this way, the process of embedding long pipes such as water pipes after the installation of the support works in the pre-installation work method for installing the support works prior to the work in the groove, with reference to the drawings below. While outline.

図11は掘削溝Fに支保工1を設置した状態を示すものである。掘削溝Fの対向する壁面に沿ってそれぞれ矢板2を打ち込み、矢板2に接して角パイプ状の腹起し3を設置し、対向する腹起し3,3間にわたってジャッキを利用して複数本の切梁4を配設することで一組の支保工1を形成し、かかる支保工1を複数段矢板2,2間に配設することで土留めを行うものである。なお、図12においては上下二段に支保工1を配設してある。   FIG. 11 shows a state where the support work 1 is installed in the excavation groove F. FIG. The sheet piles 2 are driven along the opposing wall surfaces of the excavation groove F, the square pipe-like ridges 3 are installed in contact with the sheet piles 2, and a plurality of jacks are used between the opposed ridges 3 and 3. A pair of supporting works 1 is formed by arranging the cut beams 4, and the supporting works 1 are arranged between a plurality of step sheet piles 2 and 2 for earth retaining. In addition, in FIG. 12, the support work 1 is arrange | positioned at two steps up and down.

上記の通り支保工1を設置した後、水道管等の長尺の管体5に玉掛け用ワイヤロープ6を巻回し、荷重に応じたフックを用いて図示しないドラグショベルで掘削溝Fに吊り降ろすものである。この際、長尺の管体5を水平を保持して吊り降ろそうとすると、管体5が支保工1を構成する切梁4に当接してしまい、管体5を吊り降ろすことが出来ない場合がある。   After the support 1 is installed as described above, the sling wire rope 6 is wound around a long pipe body 5 such as a water pipe, and is suspended in the excavation groove F with a drag shovel (not shown) using a hook corresponding to the load. Is. At this time, if the long tubular body 5 is to be suspended while being kept horizontal, the tubular body 5 comes into contact with the cut beam 4 constituting the support 1 and the tubular body 5 cannot be suspended. There is a case.

かような場合、図12に示すように矢板2の下端付近に、まず捨て梁7を設置し補強したうえで、図13に示すように、管体5の吊り降ろしの邪魔になる切梁4、すなわち上段の支保工1aを構成する切梁4のうち、中央部に存する二本の切梁4を取り外す。   In such a case, as shown in FIG. 12, a discarded beam 7 is first installed and reinforced near the lower end of the sheet pile 2, and then a cut beam 4 that hinders the suspension of the tubular body 5 as shown in FIG. That is, the two beams 4 existing in the center are removed from the beams 4 constituting the upper support 1a.

次いで図14に示すように、管体5を下段の支保工1bの上部まで吊り降ろしたうえで、上記取り外した上段の支保工1aの切梁4を再度設置し、補強する。   Next, as shown in FIG. 14, after the pipe body 5 is hung down to the upper part of the lower support 1b, the cut beam 4 of the removed upper support 1a is installed again and reinforced.

次いで図15に示すように、下段の支保工1bを構成する切梁4のうち、管体5に当接するすることで吊り降ろしの邪魔になる切梁4を取り外し、かかる状態で掘削溝Fの下端まで管体5を吊り降ろすものである。   Next, as shown in FIG. 15, among the beams 4 constituting the lower support 1 b, the beams 4 that are hindered from being suspended are removed by coming into contact with the pipe body 5, and in this state, The pipe body 5 is suspended to the lower end.

かかる工法においては、捨て梁7は管埋設工事完了後も回収せず、そのまま土中に放置するのが通常である。   In such a construction method, the discarded beam 7 is usually left in the soil as it is without being collected even after the pipe burying work is completed.

特許文献1には、掘削溝内での作業の邪魔になる切梁をなくすため、矢板上部に上梁を設置する工法が開示されている。   Patent Document 1 discloses a construction method in which an upper beam is installed on an upper portion of a sheet pile in order to eliminate a cutting beam that hinders the work in the excavation groove.

特開平9−291562号公報JP-A-9-291562

従来の土留め先行工法では、上記の通り捨て梁を使用する場合があり、作業コストが大幅に上昇してしまう。また省資源の観点からも問題が多い。そこで本発明は吊り降ろし時に切梁が邪魔になるような長尺の管体を埋設する場合でも、捨て梁を使用しないでも済み、したがって当該捨て梁を埋設放棄しないで済む土留め先行工法を提供することを目的とする。   In the conventional earth retaining prior construction method, abandoned beams may be used as described above, resulting in a significant increase in work costs. There are also many problems from the viewpoint of resource saving. Therefore, the present invention provides a soil retaining preceding construction method that does not require the use of a discarded beam even when a long pipe body that obscures a cut beam during suspension is used, and therefore does not require the abandoned abandoned buried beam. The purpose is to do.

また、従来工法において、捨て梁として木材を使用する場合が多いが、木材を使用すると埋設放置したのちに腐敗し、管体の下に間隙が出来てしまう場合がある。かかる状態に至ると陥没の原因ともなりかねない。   Also, in the conventional construction method, wood is often used as a discarded beam, but if wood is used, it may rot after being buried and leave a gap under the tube. Such a situation can cause depression.

また、管路が長いと捨て梁も多く必要となり、材料費が高騰すると共に、木材の大量使用が環境にも悪影響を及ぼしかねない。   In addition, if the pipe line is long, a lot of discarded beams are required, so that the material cost increases, and a large amount of wood may adversely affect the environment.

また、長尺の管体を埋設する場合には、管体の長さに応じた長さの腹起しを用いることが好ましい。すると種々の長さの腹起しを敷設場所に搬入しておくことが必要となる。とすれば搬入する腹起しの本数も多数にならざるを得ず、運搬量が多くなってしまうという難点がある。本発明は、かかる問題点も解消可能な土留め先行工法を提供することを目的とする。   Moreover, when embedding a long tubular body, it is preferable to use an erection of a length corresponding to the length of the tubular body. Then, it is necessary to carry various lengths of erections to the laying place. If this is the case, there will be a large number of erections to be carried in, and there will be a problem that the carrying amount will increase. An object of the present invention is to provide an earth retaining prior construction method that can solve such problems.

上記の目的を達成する本考案の構成は以下の通りである。   The configuration of the present invention that achieves the above object is as follows.

(1) 請求項1に記載の発明は、一対の腹起しと、両腹起しの間に設置される複数の切梁とで構成される支保工で掘削溝に沿った矢板を支持する土留め先行工法において、支保工の設置後、下梁材を矢板の下端部に設置し、次いで上部支保工の切梁を撤去し、管体を掘削溝に設置した後、上部支保工に再度切梁を設置し、次いで下梁材を撤去する。   (1) The invention according to claim 1 supports the sheet pile along the excavation groove by a support construction composed of a pair of erections and a plurality of beams installed between the erections. In the earth retaining prior construction method, after the support work is installed, the lower beam material is installed at the lower end of the sheet pile, then the upper support work beam is removed, the pipe is installed in the excavation groove, and then the upper support work is re-established. Cut the beam and then remove the lower beam.

(2) 請求項2に記載の発明は、請求項1記載の土留め先行工法において、伸縮自在な腹起しを使用するものである。   (2) The invention described in claim 2 uses a stretchable erection in the earth retaining preceding construction method described in claim 1.

(3) 請求項3に記載の発明は、請求項2に記載の土留め先行工法において、腹起しを、外筒と該外筒内を摺動可能な内筒とで構成した。   (3) The invention described in claim 3 is the earth retaining prior construction method described in claim 2, wherein the upset is configured by an outer cylinder and an inner cylinder that can slide in the outer cylinder.

上記のように構成される本発明が、如何に作用して課題を解決するかを図面を参照しながら概説する。   It will be outlined with reference to the drawings how the present invention configured as described above works to solve the problems.

図4はドラグショベル等によって掘削した掘削溝Fに支保工10a、10bを設置した状態を示すものである。掘削溝Fの対向する壁面に沿ってそれぞれ矢板2を打ち込み、矢板2に接して腹起し20を設置し、対向する腹起し20,20間にわたってジャッキを利用して複数本の切梁4を配設することで支保工10a、10bを形成し土留めを行うものである。   FIG. 4 shows a state where the supporting works 10a and 10b are installed in the excavation groove F excavated by a drag shovel or the like. The sheet piles 2 are driven along the opposing wall surfaces of the excavation groove F, the flank 20 is installed in contact with the sheet pile 2, and a plurality of beams 4 using a jack between the opposed flank 20, 20. The supporting works 10a and 10b are formed by disposing the structure, and earthing is performed.

この際腹起し20を伸縮自在なものとすれば、掘削溝の長さに応じて適宜な長さのアジャスタブルな腹起しを設置することが可能となるのである。また、長さ調整が可能なことから従来工法のように様々な長さの腹起しを敷設場所に搬入しておく必要もない。更には腹起しを短い状態にして掘削溝に搬入することが可能であり、クレーンが入れないような狭い現場でも、土留支保工及び土留壁の設置が可能となる。   At this time, if the erection 20 is telescopic, an adjustable erection having an appropriate length can be installed according to the length of the excavation groove. In addition, since the length can be adjusted, it is not necessary to carry various erections of various lengths to the laying place as in the conventional construction method. Furthermore, it can be carried into the excavation groove with a short erection, and it is possible to install a retaining wall and a retaining wall even in a narrow site where a crane cannot enter.

また、請求項3にかかる発明では、腹起しの製造コストを抑えることが可能という効果も有する。すなわち、支保工を構成する腹起しには、その中央部に、両端部に比してより大きな土圧がかかる。一方、請求項3に記載の腹起し20は、図8に示すように太い外筒21と該外筒21内を摺動可能な内筒22とで構成してある。つまり中央部により大きな土圧に対する耐久性を有する太い外筒21が存することから、両端に存し、かかる負荷が小さい内筒22は外筒21に比して強度の小さい素材で形成可能である。つまりは、製造コストの抑制が可能となるのである。   Moreover, in the invention concerning Claim 3, it also has the effect that the manufacturing cost of an angry rise can be suppressed. That is, a greater earth pressure is applied to the central part of the erection that constitutes the support structure than to both ends. On the other hand, as shown in FIG. 8, the erection 20 according to the third aspect includes a thick outer cylinder 21 and an inner cylinder 22 slidable in the outer cylinder 21. That is, since the thick outer cylinder 21 having durability against a large earth pressure exists in the central portion, the inner cylinder 22 that exists at both ends and has a small load can be formed of a material having a lower strength than the outer cylinder 21. . That is, the manufacturing cost can be suppressed.

図5は上記の通り支保工10を設置した掘削溝Fに下梁材30を設置し、土留め補強を行ったうえで、矢板の上部や中間部に設置した支保工10a、10bの切梁4のうち、管体5の吊降ろしの邪魔になる切梁4を撤去した状態を示すものである。下梁材30で土留め補強されていることから切梁4を撤去しても土砂崩壊の恐れが無く、安全に作業が可能となるものである。また、図示されているように管体5と当接する可能性のある切梁4が撤去されていることから、長尺の管体5であっても、水平を保持したまま吊り降ろすことが可能となるのである。   FIG. 5 shows that the lower beam material 30 is installed in the excavation groove F in which the support work 10 is installed as described above and the earth retaining is reinforced, and then the cut beams of the support works 10a and 10b installed on the upper and middle portions of the sheet pile. 4 shows a state in which the cut beam 4 that hinders the suspension of the pipe body 5 is removed. Since the earth retaining material is reinforced by the lower beam material 30, there is no fear of landslide even if the cut beam 4 is removed, and the work can be performed safely. Further, as shown in the drawing, since the cut beam 4 that may come into contact with the tube body 5 has been removed, even a long tube body 5 can be suspended while being kept horizontal. It becomes.

図6に示すように管体5を水平を保持したまま掘削溝Fに吊り降ろしたのち、支保工10a、10bに再び切梁4を設置し、土留め補強を行ったうえで、最終的に図7に示すように下梁材30を撤去し、管体5を地表面に設置するものである。このように本発明によれば下梁材30の回収が可能であり、従来例のようにそのまま放置埋設する、いわゆる捨て梁とする必要がないのである。つまりは、材料費の高騰を招くことも無く、捨て梁として木材を使用した場合のような陥没の恐れも無く、環境への悪影響も可及的に抑制可能となるのである。   As shown in FIG. 6, after suspending the pipe body 5 in the excavation groove F while keeping the horizontal, the cut beam 4 is installed again in the support works 10a and 10b, and after the earth retaining is reinforced, finally As shown in FIG. 7, the lower beam member 30 is removed, and the tubular body 5 is installed on the ground surface. As described above, according to the present invention, the lower beam material 30 can be collected, and it is not necessary to use a so-called abandoned beam that is left as it is as in the conventional example. In other words, there is no increase in material costs, there is no fear of sinking when wood is used as a discarded beam, and adverse effects on the environment can be suppressed as much as possible.

以上の通り、本発明は下梁材を設置することで一時的に上段支保工の土圧負担を軽減させ、管体を水平に吊り降ろすための開口部寸法の確保を目的とした工法であり、管体の布設工程の途中に当該下梁材の撤去を可能とした工法である。この工法において伸縮自在な腹起しを使用することで、管体に合わせた適切なサイズの支保工を効率的に提供することが可能となるものである。   As described above, the present invention is a construction method for temporarily reducing the earth pressure burden of the upper support by installing the lower beam material, and securing the opening dimension for hanging the pipe horizontally. In this construction method, the lower beam material can be removed during the pipe laying process. By using a stretchable erection in this construction method, it is possible to efficiently provide a support having an appropriate size according to the tubular body.

支保工の設置工程を示す説明図Explanatory drawing showing the installation process of support construction 支保工の設置工程を示す説明図Explanatory drawing showing the installation process of support construction 支保工の設置工程を示す説明図Explanatory drawing showing the installation process of support construction 完成した支保工を示す説明図Explanatory drawing showing completed support work 管体の吊り降ろし工程を示す説明図Explanatory drawing showing the process of hanging the pipe 管体の吊り降ろし工程を示す説明図Explanatory drawing showing the process of hanging the pipe 管体の吊り降ろし工程を示す説明図Explanatory drawing showing the process of hanging the pipe 腹起しの説明図Explanatory diagram of upset 腹起しの説明図Explanatory diagram of upset 腹起しの説明図Explanatory diagram of upset 従来工法を示す説明図Explanatory drawing showing the conventional method 従来工法を示す説明図Explanatory drawing showing the conventional method 従来工法を示す説明図Explanatory drawing showing the conventional method 従来工法を示す説明図Explanatory drawing showing the conventional method 従来工法を示す説明図Explanatory drawing showing the conventional method

以下、図面を参照して本発明の土留め先行工法の実施の形態の一例を概説する。なお、本発明の実施の形態は、下記の実施形態に何ら限定されることはなく、本発明の技術的範囲に属する限り種々の形態を採りうる。   Hereinafter, an example of an embodiment of the earth retaining prior method of the present invention will be outlined with reference to the drawings. The embodiment of the present invention is not limited to the following embodiment, and can take various forms as long as they belong to the technical scope of the present invention.

まず、図1に示すように図示しないドラグショベル等で地盤を所定深さまで掘削して、掘削溝Fを形成する。設定間隔をおいて掘削溝Fの対向する側面に沿ってそれぞれ矢板2,2を打ち込む。次いで、角パイプ状の腹起し20をチェーン等で掘削溝F内に吊り降ろした後、掘削溝F内において、対向する腹起し20,20間にわたってジャッキを利用して複数本の切梁4を配設する(図2参照)。   First, as shown in FIG. 1, the ground is excavated to a predetermined depth with a drag shovel or the like (not shown) to form an excavation groove F. The sheet piles 2 and 2 are driven along the opposite side surfaces of the excavation groove F at a set interval. Next, after the rectangular pipe-like erection 20 is suspended in the excavation groove F by a chain or the like, a plurality of slabs are used in the excavation groove F using a jack between the opposing erections 20 and 20. 4 is disposed (see FIG. 2).

その後、腹起し20の外側において、設定間隔をおいて打ち込まれた一方の矢板2から他方の矢板2にかけて一部重なり合うように矢板2を上方から順次差し込んで打ち込むことにより、掘削溝Fの土留めを行うものである(図3参照)。   After that, outside of the erection 20, the sheet pile 2 is sequentially inserted from the upper side so as to partially overlap from one sheet pile 2 driven at a set interval to the other sheet pile 2, thereby driving the soil of the excavation groove F. The fastening is performed (see FIG. 3).

以上の工程で図4に示すように土留め作業が完了するものである。なお図中支保工は10a,10bの上下二段に設けられているが、土圧によっては一段あるいは三段以上に設けることもある。   The earth retaining work is completed by the above steps as shown in FIG. In addition, although the support work is provided in the upper and lower two stages of 10a and 10b in the figure, it may be provided in one or more stages depending on earth pressure.

次いで図5に示すように下梁材30を設置し、上部に存する支保工10a,10bの切梁4のうち、管体5の吊り降ろしの邪魔になるものを撤去する。下梁材30は対向する腹起し20,20間にわたってジャッキを利用して配設されるものである。
次いで図6に示すように、管体5に玉掛け用ワイヤロープ6を巻回し、荷重に応じたフックを用いて図示しないドラグショベルで掘削溝Fに吊り降ろし、上部の支保工10a,10bに再度切梁4を配設する。なお、この段階では管体5は地面にまで降ろしていない。地面まで降ろすと下梁材30の撤去が困難となるからである。
Next, as shown in FIG. 5, the lower beam member 30 is installed, and among the cut beams 4 of the support works 10 a and 10 b existing at the upper part, those that obstruct the suspension of the pipe body 5 are removed. The lower beam member 30 is disposed between jacks 20 and 20 facing each other using a jack.
Next, as shown in FIG. 6, a slinging wire rope 6 is wound around the pipe body 5 and is suspended in the excavation groove F by a drag shovel (not shown) using a hook corresponding to the load, and is again attached to the upper support works 10a and 10b. A cutting beam 4 is disposed. At this stage, the tube 5 is not lowered to the ground. This is because it is difficult to remove the lower beam member 30 when it is lowered to the ground.

かかる状態から、下梁材30を撤去し、管体5を地面にまで降ろした状態を示すのが図7である。   FIG. 7 shows a state in which the lower beam member 30 is removed from this state and the tubular body 5 is lowered to the ground.

なお、本発明に使用する腹起し20は伸縮しない角パイプ状のものでも構わないが、請求項2、請求項3にかかる発明においては、図8乃至図10に示すように伸縮自在なものを採用している。すなわち、腹起し20は、図9に示すように角パイプ状の外筒21及び内筒22より成る。外筒21及び内筒22の上面にはそれぞれ複数のピン孔21a、22aが設けられており、図8や図10に示すようにピン孔21a、22aの位置を合わせたうえで、両者を貫通する形態で連結ピン40を差込むことで外筒21と内筒22を固定するものである。むろんこれは一例であり、例えば外筒と内筒とをボルト・ナット等の緊締金具で固定しても良い。   The belly ridge 20 used in the present invention may be a rectangular pipe that does not expand or contract. However, in the inventions according to claims 2 and 3, the one that can expand and contract as shown in FIGS. Is adopted. That is, the erection 20 includes a square pipe-shaped outer cylinder 21 and an inner cylinder 22 as shown in FIG. A plurality of pin holes 21a and 22a are provided on the upper surfaces of the outer cylinder 21 and the inner cylinder 22, respectively, and after the positions of the pin holes 21a and 22a are aligned as shown in FIGS. The outer cylinder 21 and the inner cylinder 22 are fixed by inserting the connecting pin 40 in such a form. Of course, this is only an example. For example, the outer cylinder and the inner cylinder may be fixed with a fastening metal fitting such as a bolt or nut.

上記のように構成される腹起し20は、内筒22を出し入れすることで伸縮可能なものであり、開削寸法への適応性が向上するものである。なお、腹起こし20の大きさ及び素材は、受け止める土留壁の面積及びこれが受ける土圧等を考慮して決定すればよい。  The abdominal ridge 20 configured as described above can be expanded and contracted by taking in and out the inner cylinder 22, and the adaptability to the cut dimensions is improved. Note that the size and material of the erection 20 may be determined in consideration of the area of the retaining wall to be received and the earth pressure received by the wall.

10・・支保工
20・・腹起し 21・・外筒 22・・内筒
30・・下梁材
10. · Supporting work 20 · · Raising 21 · · Outer tube 22 · · · Inner tube 30 · · Lower beam material

Claims (3)

一対の腹起しと、両腹起しの間に設置される複数の切梁とで構成される支保工で掘削溝に沿った矢板を支持する土留め先行工法であって、
支保工の設置後、下梁材を矢板の下端部に設置し、次いで上部支保工の切梁を撤去し、管体を掘削溝に設置した後、上部支保工に再度切梁を設置し、次いで下梁材を撤去することを特徴とする土留め先行工法。
It is a soil retaining precedent construction method that supports a sheet pile along a digging groove with a support structure composed of a pair of erections and a plurality of beams installed between both erections,
After installing the support work, install the lower beam material at the lower end of the sheet pile, then remove the upper support work cut beam, install the pipe in the excavation groove, then install the cut beam again in the upper support work, Next, the earth retaining prior construction method characterized by removing the lower beam material.
伸縮自在な腹起しを使用することを特徴とする請求項1記載の土留め先行工法。   2. The earth retaining prior construction method according to claim 1, wherein a stretchable uplift is used. 腹起しを、外筒と該外筒内を摺動可能な内筒とで構成した請求項2に記載の土留め先行工法。   The earth retaining prior construction method according to claim 2, wherein the erection is constituted by an outer cylinder and an inner cylinder slidable in the outer cylinder.
JP2016039478A 2016-03-01 2016-03-01 Earth retaining prior construction method using adjustable erection Active JP6068774B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2016039478A JP6068774B1 (en) 2016-03-01 2016-03-01 Earth retaining prior construction method using adjustable erection

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2016039478A JP6068774B1 (en) 2016-03-01 2016-03-01 Earth retaining prior construction method using adjustable erection

Publications (2)

Publication Number Publication Date
JP6068774B1 JP6068774B1 (en) 2017-01-25
JP2017155478A true JP2017155478A (en) 2017-09-07

Family

ID=57890543

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2016039478A Active JP6068774B1 (en) 2016-03-01 2016-03-01 Earth retaining prior construction method using adjustable erection

Country Status (1)

Country Link
JP (1) JP6068774B1 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6178030B1 (en) * 2017-02-28 2017-08-09 日本スピードショア株式会社 Prior construction method for earth retaining of excavation groove and supporting device used for the construction method
CN110965581A (en) * 2019-12-12 2020-04-07 中铁十二局集团第二工程有限公司 Protection construction method for underground pipeline in subway construction
CN114293567A (en) * 2021-12-27 2022-04-08 北京建工四建工程建设有限公司 Construction method for improving bearing capacity of natural foundation by embedding basic raft plates into slope protection piles

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS59167833U (en) * 1983-04-22 1984-11-10 日本電信電話株式会社 belly-up member
JPS6088725A (en) * 1983-10-20 1985-05-18 Osaka Gas Co Ltd Sheathing work of excavated trench
JPH08128043A (en) * 1993-07-31 1996-05-21 Kita Nippon Kenzai Lease Kk Turning strut for ditch excavation earth retaining
JP3325156B2 (en) * 1995-04-06 2002-09-17 日鐵建材工業株式会社 Soil support method and structure in excavation trench
JPH0989159A (en) * 1995-09-22 1997-03-31 Kawasaki Steel Corp Pipe line laying method, timbering method, and timbering assembling body
JP2004076490A (en) * 2002-08-21 2004-03-11 Jfe Engineering Kk Earth retaining member of trench and earth retaining method
JP2007092496A (en) * 2005-09-28 2007-04-12 Nippon Supiide Shiyoa Kk Polygonal frame body earth retaining for excavation groove

Also Published As

Publication number Publication date
JP6068774B1 (en) 2017-01-25

Similar Documents

Publication Publication Date Title
JP6010070B2 (en) Temporary closing method for existing underwater structures
JP5057223B2 (en) Temporary wall construction method using steel segments
JP6068774B1 (en) Earth retaining prior construction method using adjustable erection
CN104652418A (en) Continuous wall underground pipeline position construction method
KR100821663B1 (en) Construction method of Top-down concrete slab
CN105544603A (en) Construction method for underground pipeline reinforcement
KR100989946B1 (en) Construction method for under-ground structure construction using t-shaped guider with lagged flanges
JP2008133596A (en) Scaffold for vertical shaft, and method for assembly and removal thereof
CN105604064A (en) Construction method of comprehensive pipeline protection system supporting system
KR20150025409A (en) the tunnel structure using the small diameter steel pipe and the construction method thereof
JP2007023579A (en) Construction method of underground structure skeleton
JP6452299B2 (en) Construction method of steel pipe sheet pile foundation for temporary closing and combined use
CN108798508B (en) Pile hole excavating method
JP2004332202A (en) Method for constructing shaft by using liner plate
JP6178030B1 (en) Prior construction method for earth retaining of excavation groove and supporting device used for the construction method
JP2011246910A (en) Construction method of underground structure
JP6757003B2 (en) Construction method of double pipe pile and double pipe pile
KR101249660B1 (en) Earth pressure supporting method of walls trench applying construction of none- excavation underground structure
CN111794343B (en) Construction method for connecting pipeline ditch with integrated sewer
CN113089654A (en) Construction process of hole digging pile in complex soil layer and steel casing for construction
CN213477098U (en) Shaft concrete guide cutting structure
CN204401648U (en) Circular Pit inwall reinforcing cage binding stand
JP7153603B2 (en) Construction method of underground structure
CN212927135U (en) Ground is wall body rope saw cutting construction structures even
CN203925503U (en) A kind of upper pipe working well attending device

Legal Events

Date Code Title Description
TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20161206

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20161225

R150 Certificate of patent or registration of utility model

Ref document number: 6068774

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250