CN207004538U - The additional fixing structure of loess tunnel - Google Patents

The additional fixing structure of loess tunnel Download PDF

Info

Publication number
CN207004538U
CN207004538U CN201720581516.9U CN201720581516U CN207004538U CN 207004538 U CN207004538 U CN 207004538U CN 201720581516 U CN201720581516 U CN 201720581516U CN 207004538 U CN207004538 U CN 207004538U
Authority
CN
China
Prior art keywords
tunnel
loess
straining beam
concrete structure
straining
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720581516.9U
Other languages
Chinese (zh)
Inventor
袁文帅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Polytechnic Normal University
Original Assignee
Guangdong Polytechnic Normal University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Polytechnic Normal University filed Critical Guangdong Polytechnic Normal University
Priority to CN201720581516.9U priority Critical patent/CN207004538U/en
Application granted granted Critical
Publication of CN207004538U publication Critical patent/CN207004538U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of additional fixing structure of loess tunnel, including the straining beam laid along tunnel width direction on the loess surface of tunnel upper, the 50cm of straining beam 40 Loess Surface structure is above on the outside of the straining beam at the both ends in length of tunnel direction, there is gunite concrete structure in the medial surface towards straining beam of Loess Surface structure, gunite concrete structure is combined closely with straining beam, the casting concrete structure that thickness is 10cm is connected between per two adjacent straining beams, the top surface of casting concrete structure and the either flush of straining beam, and casting concrete structure, straining beam collectively forms tunnel top gutter with gunite concrete structure.The additional fixing structure of loess tunnel of the present utility model can make tunnel top support the rainwater on the soil body along the quick drainage in ditch, ensure that the water in the range of support of tunnel can be excluded quickly, prevent water from penetrating into tunnel top loess, so as to ensure that safety for tunnel engineering and operation tunnel safety.

Description

The additional fixing structure of loess tunnel
Technical field
It the utility model is related to building structure technology field, more particularly to a kind of additional fixing structure of loess tunnel.
Background technology
The settlement by soaking of loess is a kind of special engineering geological property of loess.Loess has in deadweight or outside loading Under, structure destroys rapidly the property for occurring to sink suddenly after by water-soaked.Harm of the collapsibility of loess to Human dried bloodstains is non- Chang great, often damage building, channel, storehouse bank.Therefore, when being built in Collapsible Loess District, to pay special attention to The infiltration of water is prevented, to ensure safety for tunnel engineering and operation tunnel safety, but current loess support reinforcement structure and is paid no attention to Think, however it remains potential safety hazard.
Utility model content
The purpose of this utility model is to provide a kind of additional fixing structure of loess tunnel, makes the rain on the tunnel top support soil body Water is along the quick drainage in ditch, it is ensured that and the water in the range of support of tunnel can be excluded quickly, prevent water from penetrating into tunnel top loess, So as to ensure that safety for tunnel engineering and operation tunnel safety.
To achieve the above object, the utility model provides a kind of additional fixing structure of loess tunnel, and the ruggedized construction includes edge The straining beam of the loess surface that with massif landforms is adapted laying of the tunnel width direction in tunnel upper, straining beam is in tunnel Length direction is spacedly distributed, and is above straining beam 40-50cm's on the outside of the straining beam at the both ends in length of tunnel direction Loess Surface structure, there are gunite concrete structure, gunite concrete knot in the medial surface towards straining beam of Loess Surface structure Structure is combined closely with straining beam, and the casting concrete knot that thickness is 10cm is connected between every two adjacent straining beams Structure, the top surface of casting concrete structure and the either flush of straining beam, and casting concrete structure, straining beam and gunite concrete Structure collectively forms tunnel top gutter, and multiple straining beams being spacedly distributed are provided with along the vertical of length of tunnel direction laying Binder, vertical binder are spacedly distributed along tunnel width direction, and vertical binder is provided with the equitant position of straining beam stretches into loess Interior hole, reinforcing bar is provided with hole, the upper end of reinforcing bar is fixedly connected with vertical binder and straining beam, and the lower end of reinforcing bar is fixed on loess It is interior.
As further improvement of the utility model, reinforcing bar guard member is cased with the reinforcing bar in hole.
Compared with prior art, loess tunnel of the present utility model additional fixing structure has the beneficial effect that:
(1) bolt anchorage is used outside tunnel, the support of anchor pole end uses binder, and the binder tunnel top soil body is set along massif landforms Put, binder both sides extend out 500mm, make tunnel top support soil body rainwater to be formed along support beam and expansion both sides concrete structure The quick drainage in ditch, it is ensured that water of the surface water in the range of support of tunnel can be excluded quickly, prevent terrestrial reference water penetrate into tunnel top Portion's loess, so as to ensure that safety for tunnel engineering and operation tunnel safety.
(2) using reinforcing bar guard member reinforcing bar can be avoided to be contacted with hole inwall, so as to extend the service life of reinforcing bar.
It will be become more fully apparent by following description and with reference to accompanying drawing, the utility model, these accompanying drawings are used to explain this The embodiment of utility model.
Brief description of the drawings
Fig. 1 is the elevation of the additional fixing structure of loess tunnel.
Fig. 2 is the plan of the additional fixing structure of loess tunnel.
Embodiment
Embodiment of the present utility model described with reference now to accompanying drawing, similar element numbers represent similar member in accompanying drawing Part.
Fig. 1-2 is refer to, the additional fixing structure of described loess tunnel is included along the width of tunnel 1 above tunnel 1 The surface of loess 2 laying straining beam 3, straining beam 3 is spacedly distributed in the length direction of tunnel 1, positioned at the length direction of tunnel 1 The outside of the straining beam 3 at both ends is above straining beam 340-50cm Loess Surface structure a, in Loess Surface structure a direction The medial surface of straining beam 3 has gunite concrete structure 4, and gunite concrete structure 4 is combined closely with straining beam 3, per adjacent two The casting concrete structure 5 that thickness is 10cm, top surface and the horizontal stroke of casting concrete structure 5 are connected between individual straining beam 3 The either flush of binder 3, and casting concrete structure 5, straining beam 3 collectively form tunnel top row with gunite concrete structure 4 Ditch 6, so as to make the rainwater on the top loess 2 of tunnel 1 along 6 quick drainage of gutter, it is ensured that in the range of the support of tunnel 1 Rainwater can quickly exclude, prevent rainwater penetrate into the top loess of tunnel 1, so as to ensure that the construction safety in tunnel 1 and operation tunnel Road safety.Multiple straining beams 3 being spacedly distributed be provided with along the length direction of tunnel 1 lay vertical binder 7, indulge binder 7 along The width of tunnel 1 is spacedly distributed, and vertical binder 7 is provided with the hole 8 stretched into loess 2, hole 8 with 3 equitant position of straining beam Interior to be provided with reinforcing bar 9, the upper end of reinforcing bar 9 is fixedly connected with vertical binder 7 and straining beam 3, and the lower end of reinforcing bar 9 is fixed in loess 2, is made It is firm, firm to obtain ruggedized construction.Reinforcing bar guard member 10 is cased with reinforcing bar 9 in hole 8, reinforcing bar can be avoided to be connect with hole inwall Touch, so as to extend the service life of reinforcing bar.
The utility model is described above in association with most preferred embodiment, but the utility model is not limited to the above and taken off The embodiment shown, and the various modifications carried out according to essence of the present utility model, equivalent combinations should be covered.

Claims (2)

  1. A kind of 1. additional fixing structure of loess tunnel, it is characterised in that:The ruggedized construction is included along tunnel width direction in tunnel The straining beam of the loess surface being adapted with the massif landforms laying of top, straining beam are spacedly distributed in length of tunnel direction, Straining beam 40-50cm Loess Surface structure is above on the outside of the straining beam at the both ends in length of tunnel direction, in loess The medial surface towards straining beam of slope structure has gunite concrete structure, and gunite concrete structure is combined closely with straining beam, The casting concrete structure that thickness is 10cm, the top of casting concrete structure are connected between per two adjacent straining beams Face and the either flush of straining beam, and casting concrete structure, straining beam and gunite concrete structure collectively form tunnel top Gutter, multiple straining beams being spacedly distributed are provided with the vertical binder laid along length of tunnel direction, indulge binder along tunnel Width is spacedly distributed, and vertical binder is provided with the hole stretched into loess with the equitant position of straining beam, and reinforcing bar is provided with hole, The upper end of reinforcing bar is fixedly connected with vertical binder and straining beam, and the lower end of reinforcing bar is fixed in loess.
  2. 2. the additional fixing structure of loess tunnel as claimed in claim 1, it is characterised in that:Reinforcing bar guarantor is cased with reinforcing bar in hole Guard.
CN201720581516.9U 2017-05-23 2017-05-23 The additional fixing structure of loess tunnel Expired - Fee Related CN207004538U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720581516.9U CN207004538U (en) 2017-05-23 2017-05-23 The additional fixing structure of loess tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720581516.9U CN207004538U (en) 2017-05-23 2017-05-23 The additional fixing structure of loess tunnel

Publications (1)

Publication Number Publication Date
CN207004538U true CN207004538U (en) 2018-02-13

Family

ID=61444632

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720581516.9U Expired - Fee Related CN207004538U (en) 2017-05-23 2017-05-23 The additional fixing structure of loess tunnel

Country Status (1)

Country Link
CN (1) CN207004538U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107100646A (en) * 2017-05-23 2017-08-29 梁美欣 The additional fixing structure of loess tunnel

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107100646A (en) * 2017-05-23 2017-08-29 梁美欣 The additional fixing structure of loess tunnel

Similar Documents

Publication Publication Date Title
CN102128035B (en) Construction method of bilateral biased small-clear distance tunnel
KR20100087858A (en) Retaining wall using anchor and concrete panel and its construction method
CN108755709A (en) A kind of open-pit slope antiseepage drainage system
CN204356615U (en) Permeable pavement structure
CN104653195A (en) Gully landform tunnel portal structure and construction method thereof
CN210262555U (en) Light soil road structure
CN207004538U (en) The additional fixing structure of loess tunnel
CN205617390U (en) A softer side of sears layer excavation supporting system for loess area
KR101326574B1 (en) Foundation structure for pillar
KR101698758B1 (en) A reinforcment grid structure
CN104314104B (en) Deformation joint setting method for oblique crossing with underground box culvert
CN203668978U (en) Anti-floating structure for subway tunnel
CN107100646A (en) The additional fixing structure of loess tunnel
CN105755919A (en) Widened highway old embankment side slope seepage treatment structure
CN208885303U (en) A kind of cap excavation method pipe gallery supporting construction
CN104947694A (en) Earth slope grouting reinforcement construction method
KR100440091B1 (en) Structure of Block type retaining wall and Construction Method thereof
KR20140042371A (en) The installation structure for the aritificial wall of the nature stone shape to use anchor
CN207003605U (en) Reinforced buried concrete pumping equipment
CN206625107U (en) A kind of new road discharge structure
CN108951618A (en) A kind of pile-anchor retaining device and its construction method
CN101228322B (en) A method for tunnel construction
CN211174131U (en) Tunnel is showy supporting construction that buries of highway down
KR101657279B1 (en) Permanent embedded anchor type slope ditch water way and slope ditch water way construction method using thereof
CN204589954U (en) A kind ofly punish the internal drainage ecosystem that side slope rainwater causes calamity unstability

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180213

Termination date: 20180523