CN211174131U - Tunnel is showy supporting construction that buries of highway down - Google Patents

Tunnel is showy supporting construction that buries of highway down Download PDF

Info

Publication number
CN211174131U
CN211174131U CN201921587613.4U CN201921587613U CN211174131U CN 211174131 U CN211174131 U CN 211174131U CN 201921587613 U CN201921587613 U CN 201921587613U CN 211174131 U CN211174131 U CN 211174131U
Authority
CN
China
Prior art keywords
layer
tunnel
stones
building
laying bricks
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201921587613.4U
Other languages
Chinese (zh)
Inventor
李峰
梁德礼
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guizhou Province Transporation Construction Consulting Supervision Co ltd
Original Assignee
Guizhou Province Transporation Construction Consulting Supervision Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guizhou Province Transporation Construction Consulting Supervision Co ltd filed Critical Guizhou Province Transporation Construction Consulting Supervision Co ltd
Priority to CN201921587613.4U priority Critical patent/CN211174131U/en
Application granted granted Critical
Publication of CN211174131U publication Critical patent/CN211174131U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model discloses a wear shallow supporting construction that buries of highway under tunnel relates to the shallow technical field that buries in tunnel, including building the layer by laying bricks or stones, one side fixedly connected with waterproof layer of building the layer by laying bricks or stones, one side fixedly connected with tunnel layer of waterproof layer, one side fixedly connected with stock of building the layer by laying bricks or stones, one side of building the layer by laying bricks or stones has been seted up the side and has been pour the hole, the top of building the layer by laying bricks or stones has been seted up the top and has been. According to the tunnel underpass highway shallow-buried supporting structure, the supporting effect of the supporting structure is better through the matching arrangement of the cross beam, the inner supporting plate, the fixed column and the outer supporting plate, and meanwhile, the bidirectional supporting is carried out on a highway subgrade and a tunnel, so that the problem that the existing bidirectional supporting structure is lacked is solved; through the cooperation setting of the anchor rod, the side pouring hole, the top pouring hole and the fixed column, the pouring of the concrete can be more convenient, meanwhile, the reasonable structure is maintained, and the problem that the existing concrete pouring is not convenient enough and is lack of the stable structure is solved.

Description

Tunnel is showy supporting construction that buries of highway down
Technical Field
The utility model relates to a shallow technical field that buries in tunnel specifically is a tunnel is worn highway under and is shallowly buried supporting construction.
Background
The tunnel is a huge branch system on the highway engineering. According to the investigation of construction data of a large number of tunnel projects, a tunnel or a section with an upper covering layer which is 2 times as short as a tunnel hole is a shallow buried tunnel, and meanwhile, the excavation construction of a shallow buried section project and a hole reinforcing section is carried out by selecting an excavation method and a supporting mode according to the factors of geological conditions, the influence of surface deep subsidence on ground buildings, construction safety guarantee and the like. Shallow tunnel burial means that the tunnel section with the upper covering layer of the tunnel, which is 2 times less than the tunnel hole, belongs to the shallow tunnel burial section. The tunnel is a structure built for passing through mountains when roads or railways are obstructed by mountains, and generally comprises a main structure and auxiliary structures, wherein the main structure comprises a hole door and a hole body lining, and the auxiliary structures mainly comprise systems for tunnel water supply and drainage, ventilation, illumination, power supply and the like. The excavation construction and the support are carried out in a shallow-buried and opening reinforced section, the excavation construction and the support are selected according to the geological conditions, the influence of surface subsidence on ground buildings, the construction safety guarantee and other factors, the construction effect and the engineering cost are considered, the tunnel shallow-buried section and the opening reinforced section are determined and are usually positioned in surrounding rocks with weak, broken and extremely short self-stabilizing time, if the construction method and the support mode are improper, roof collapse or harmful subsidence of the surface is easy to happen, and the safety of the building is endangered when the building exists on the surface. Therefore, measures such as supporting and then excavating or sub-excavating should be adopted to prevent instability caused by excavating work or harmful subsidence of the ground surface.
The existing tunnel underpass highway shallow-buried supporting structure product has the following defects:
1. when the tunnel is supported, the highway subgrade cannot be effectively supported, and a bidirectional supporting structure is lacked;
2. concrete pouring is not convenient enough, and a stable maintaining structure is lacked after pouring.
SUMMERY OF THE UTILITY MODEL
Technical problem to be solved
Not enough to prior art, the utility model provides a tunnel is worn shallow supporting structure that buries of highway down, it has the crossbeam to peg graft through the inside on masonry layer, can carry out effectual support to highway's road bed, be provided with the inside backup pad in one side on tunnel layer, at the top fixedly connected with fixed column on masonry layer, the outer backup pad of one end fixedly connected with of fixed column, the fixed column runs through masonry layer, the waterproof layer, tunnel layer, one side on masonry layer has been seted up the side and has been pour the hole, the top on masonry layer has been seted up the top and has been pour the hole. The problems set forth in the above background art are solved.
(II) technical scheme
In order to achieve the above purpose, the utility model discloses a following technical scheme realizes: the utility model provides a wear shallow supporting construction that buries of highway under tunnel, includes the masonry layer, one side fixedly connected with waterproof layer on masonry layer, one side fixedly connected with tunnel layer of waterproof layer, one side fixedly connected with stock on masonry layer, the hole is pour to the side has been seted up to one side on masonry layer, the hole is pour on the top has been seted up on masonry layer's top, it has the crossbeam to peg graft in masonry layer's inside, one side in tunnel is provided with the inner support plate, the top fixedly connected with fixed column on masonry layer, the one end fixedly connected with outer support plate on masonry layer is kept away from to the fixed column, the one end fixedly connected with fixed block of outer support plate is kept away from to.
Optionally, the thickness of the masonry layer is greater than that of the waterproof layer, and the masonry layer is made of masonry stones.
Optionally, a waterproof plate is arranged on one side of the waterproof layer, and the waterproof layer is connected with the tunnel layer through concrete pouring.
Optionally, the anchor rods penetrate through the masonry layer and the waterproof layer, the two anchor rods form a group, and the inclination angle of the anchor rods is forty-five degrees.
Optionally, the two side pouring holes form a group, and the side pouring holes penetrate through the masonry layer, the waterproof layer and the tunnel layer.
Optionally, the length of the cross beam is the same as the diameter of the waterproof layer, and the number of the cross beams is two.
Optionally, every three fixing columns form a group, and the fixing columns penetrate through the masonry layer, the waterproof layer and the tunnel layer.
(III) advantageous effects
The utility model provides a tunnel is worn shallow supporting construction that buries of highway down possesses following beneficial effect:
1. this pass shallow supporting construction that buries of highway under tunnel, it has the crossbeam to peg graft through the inside on masonry layer, can carry out effectual support to the road bed of highway, prevent that the road bed of highway from collapsing, one side through at tunnel layer is provided with the inner support plate, top fixedly connected with fixed column at masonry layer, the one end fixedly connected with outer backup pad of fixed column, the fixed column runs through masonry layer, the waterproof layer, tunnel layer, the fixed column passes through concrete placement and tunnel and ground fixed connection, it is better to strut the effect, through inner support plate and outer backup pad, can have a two-way supporting effect, through the crossbeam, the inner support plate, the fixed column, the cooperation setting of outer backup pad, can make supporting construction's supporting effect better, to highway road bed and tunnel two-way support simultaneously, the condition that has the current two-way supporting construction that lacks has been solved.
2. This tunnel is worn shallow supporting construction that buries of highway down, it pours the hole to have seted up the side through the one side of building by laying bricks or stones the layer, the top of building by laying bricks or stones the layer has been seted up and has been pour the hole and the top is poured the hole and run through building by laying bricks or stones the layer, the waterproof layer, the tunnel layer, it is more convenient to make pouring of concrete, cooperation through fixed column and stock, can make the concrete after pouring have the maintenance structure, the structure is firmer, through the stock, the hole is pour to the side, the hole is poured on the top, the cooperation setting of fixed column, it is more convenient to make pouring of concrete, simultaneously, there is reasonable maintenance structure, the current concrete placement condition that lacks stable maintenance structure simultaneously convenient inadequately.
Drawings
FIG. 1 is a schematic structural view of the present invention;
fig. 2 is a schematic front view of the structure of the present invention;
fig. 3 is a schematic side view of the present invention.
In the figure: 1-masonry layer, 2-waterproof layer, 3-tunnel layer, 4-anchor rod, 5-side pouring hole, 6-top pouring hole, 7-beam, 8-inner supporting plate, 9-fixing column, 10-outer supporting plate and 11-fixing block.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Referring to fig. 1 to 3, the present invention provides a technical solution: the utility model provides a wear shallow supporting construction that buries of highway under tunnel, including masonry layer 1, one side fixedly connected with waterproof layer 2 of masonry layer 1, one side fixedly connected with tunnel layer 3 of waterproof layer 2, one side fixedly connected with stock 4 of masonry layer 1, hole 5 has been built to the side has been seted up to one side of masonry layer 1, hole 6 has been built on the top has been seted up to the top of masonry layer 1, it has crossbeam 7 to peg graft in the inside of masonry layer 1, one side of tunnel layer 3 is provided with interior backup pad 8, the top fixedly connected with fixed column 9 of masonry layer 1, the one end fixedly connected with outer backup pad 10 of masonry layer 1 is kept away from to fixed column 9, the one end fixedly connected with fixed block 11 of outer backup pad 10.
As an optimal technical solution of the utility model: from the right, the thickness of the masonry layer 1 is greater than that of the waterproof layer 2, the masonry layer 1 is made of masonry stones, the structure of the masonry layer 1 is firmer, one side of the waterproof layer 2 is provided with a waterproof plate, the waterproof layer 2 is connected with the tunnel layer 3 through concrete pouring, the waterproof layer 2 is connected with the tunnel layer 3 more tightly and seamlessly, the anchor rods 4 penetrate through the masonry layer 1 and the waterproof layer 2, the anchor rods 4 form a group, the inclination angle of the anchor rods 4 is forty-five degrees, the anchor rods 4 can enable the side structure of the tunnel to be firmer and can maintain and fix concrete after the concrete is poured, the side pouring holes 5 form a group, the side pouring holes 5 penetrate through the masonry layer 1, the waterproof layer 2 and the tunnel layer 3 and perform the concrete pouring work towards the two sides of the tunnel through the side pouring holes 5, the length of the cross beams 7 is the same as that of the waterproof layer 2, and the, crossbeam 7 makes the top layer structure in tunnel more stable to support the road bed of highway, every three of fixed column 9 is a set of, and fixed column 9 runs through masonry layer 1, waterproof layer 2, tunnel layer 3, can make the connection on three layer more secret, and makes the contact between ground and the tunnel main part inseparabler.
When the user uses, build by laying bricks or stones earlier, install crossbeam 7 simultaneously, insert stock 4, pour the hole 5 through the side and carry out pouring of concrete, installation waterproof layer 2 and tunnel layer 3, insert fixed column 9, install interior backup pad 8 and outer backup pad 10, finish pouring, fixed column 9 and stock are stayed and are maintained and strut in the tunnel main part.
In conclusion, when the tunnel passes through the shallow supporting structure of the expressway, when in use, the crossbeam 7 is inserted into the masonry layer 1, the roadbed of the expressway can be effectively supported, the roadbed of the expressway is prevented from collapsing, the inner supporting plate 8 is arranged on one side of the tunnel layer 3, the fixed column 9 is fixedly connected to the top of the masonry layer 1, the outer supporting plate 10 is fixedly connected to one end of the fixed column 9, the fixed column 9 penetrates through the masonry layer 1, the waterproof layer 2 and the tunnel layer 3, the fixed column 9 is fixedly connected with the tunnel and the rock soil through concrete pouring, the supporting effect is better, the inner supporting plate 8 and the outer supporting plate 10 can have a bidirectional supporting effect, the crossbeam 7, the inner supporting plate 8, the fixed column 9 and the outer supporting plate 10 are matched, the supporting effect of the supporting structure can be better, and the expressway roadbed and the tunnel can be bidirectionally supported, the problem that the existing bidirectional supporting structure is lacked is solved; through having seted up the side in one side of masonry layer 1 and having pour hole 5, the top of masonry layer 1 has been seted up and has been pour hole 6, hole 5 is pour with the top and pour hole 6 and run through masonry layer 1, waterproof layer 2, tunnel layer 3, it is more convenient to make pouring of concrete, cooperation through fixed column 9 and stock 4, can make the concrete after pouring have the maintenance structure, the structure is more firm, through stock 4, hole 5 is pour to the side, top is poured hole 6, the cooperation setting of fixed column 9, it is more convenient to make pouring of concrete, simultaneously, there is reasonable maintenance structure, current concrete placement is convenient not to lack the stable condition of maintaining the structure simultaneously inadequately.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (7)

1. The utility model provides a tunnel is worn shallow supporting construction that buries of highway down which characterized in that: including building by laying bricks or stones layer (1), one side fixedly connected with waterproof layer (2) of building by laying bricks or stones layer (1), one side fixedly connected with tunnel layer (3) of waterproof layer (2), one side fixedly connected with stock (4) of building by laying bricks or stones layer (1), side pouring hole (5) have been seted up to one side of building by laying bricks or stones layer (1), top pouring hole (6) have been seted up at the top of building by laying bricks or stones layer (1), it has crossbeam (7) to peg graft in the inside of building by laying bricks or stones layer (1), one side of tunnel layer (3) is provided with interior support plate (8), the top fixedly connected with fixed column (9) of building by laying bricks or stones layer (1), the one end fixedly connected with outer backup pad (10) of building by laying bricks or stones layer (1) is kept away from fixed column (9), the one end.
2. The shallow supporting structure of tunnel underpass highway according to claim 1, wherein: the thickness of the masonry layer (1) is larger than that of the waterproof layer (2), and the masonry layer (1) is made of masonry stones.
3. The shallow supporting structure of tunnel underpass highway according to claim 1, wherein: and a waterproof plate is arranged on one side of the waterproof layer (2), and the waterproof layer (2) is connected with the tunnel layer (3) through concrete pouring.
4. The shallow supporting structure of tunnel underpass highway according to claim 1, wherein: the anchor rods (4) penetrate through the masonry layer (1) and the waterproof layer (2), the two anchor rods (4) form a group, and the inclination angle of the anchor rods (4) is forty-five degrees.
5. The shallow supporting structure of tunnel underpass highway according to claim 1, wherein: the side pouring holes (5) are two in one group, and the side pouring holes (5) penetrate through the masonry layer (1), the waterproof layer (2) and the tunnel layer (3).
6. The shallow supporting structure of tunnel underpass highway according to claim 1, wherein: the length of the cross beams (7) is the same as the diameter of the waterproof layer (2), and the number of the cross beams (7) is two.
7. The shallow supporting structure of tunnel underpass highway according to claim 1, wherein: every three fixing columns (9) form a group, and the fixing columns (9) penetrate through the masonry layer (1), the waterproof layer (2) and the tunnel layer (3).
CN201921587613.4U 2019-09-23 2019-09-23 Tunnel is showy supporting construction that buries of highway down Expired - Fee Related CN211174131U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921587613.4U CN211174131U (en) 2019-09-23 2019-09-23 Tunnel is showy supporting construction that buries of highway down

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921587613.4U CN211174131U (en) 2019-09-23 2019-09-23 Tunnel is showy supporting construction that buries of highway down

Publications (1)

Publication Number Publication Date
CN211174131U true CN211174131U (en) 2020-08-04

Family

ID=71794112

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921587613.4U Expired - Fee Related CN211174131U (en) 2019-09-23 2019-09-23 Tunnel is showy supporting construction that buries of highway down

Country Status (1)

Country Link
CN (1) CN211174131U (en)

Similar Documents

Publication Publication Date Title
CN106907159B (en) Shallow-buried underground excavation subway station separated open type structure and construction method thereof
CN105041349B (en) A kind of excavating construction method that station is digged on the basis of Subway Tunnel shield tunnel
CN107675628B (en) It is worn on urban road frame bridge and wears railway in operation jacking construction method under operated subway
CN102505695B (en) Construction method for deep foundation pit of three-dimensional garage
CN101775987B (en) Zero spacing construction method for overlapping part of upper main tunnel and lower main tunnel of underground overpass
CN110318770A (en) A kind of hazy start tunneling method of vcehicular tunnel
CN108103871B (en) Construction method of roadbed foam concrete filling technology adjacent to existing subway facility
CN108868778A (en) A kind of Large Underground Structure no-dig technique construction method
CN104831734A (en) Construction method of jet-grouting pile and composite soil-nailed wall support for deep foundation pit construction
CN108252329A (en) The assembled pipe gallery and its construction method of building enclosure load
CN107724236A (en) A kind of Tunnel-Type Anchorage of Suspension Bridge combination anchor and method of construction
CN108412016A (en) Underground tube body assures construction method
CN101838957B (en) Integral type T-shaped outer cantilever roads and construction method thereof
CN110004991A (en) Underground structure anti-floating system and construction method based on raised type tangs plate
CN206219897U (en) Medium-and low-speed maglev two-wire excavation location pile foundation combined type support rail beam transition section structure
CN208380578U (en) Precast construction in a kind of roads and tunnels
CN107339109A (en) The construction method of existing road is worn under super Shallow tunnel with large cross-section
CN109487793A (en) Inner support of pile foundation pit permanent support structure is perfused in a kind of solid matter under complex environment
CN113529752A (en) Construction method for ecologically treating tunnel entrance and exit structure by using foam concrete
CN112983461A (en) Construction method for bias tunnel portal in slope volume
CN111560959A (en) Excavation and supporting method for shield starting well foundation pit adjacent to subway
CN211174131U (en) Tunnel is showy supporting construction that buries of highway down
CN106283966A (en) Medium-and low-speed maglev single line embankment location detached pier pillar support rail beam transition section structure
CN110905529A (en) Construction method of loess tunnel penetrating through landslide mass
KR100509707B1 (en) None open cut tunnelling of arch type with hume pipe and con'c rib

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200804