CN206973054U - A kind of gas tube support of adjustment height - Google Patents
A kind of gas tube support of adjustment height Download PDFInfo
- Publication number
- CN206973054U CN206973054U CN201720900975.9U CN201720900975U CN206973054U CN 206973054 U CN206973054 U CN 206973054U CN 201720900975 U CN201720900975 U CN 201720900975U CN 206973054 U CN206973054 U CN 206973054U
- Authority
- CN
- China
- Prior art keywords
- bridle
- gas tube
- supporting leg
- bar hole
- tube support
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Abstract
A kind of gas tube support of adjustment height of the utility model, belong to gas tube support technology field;Technical problem to be solved is:It is simple in construction to provide one kind, can arbitrarily adjust undertaking depth of beam, the gas tube support of labour-saving adjustment height is set;Solve technical scheme that the technical problem uses for:The side of supporting leg prolongs axial direction and is provided with one section of bar hole, and the both ends for heightening bridle are welded with threaded installation plug, after installation plug insertion bar hole, pad is enclosed on installation plug and is connected with fixing bolt;It is further fixedly arranged on the downside of bar hole and heightens bolt;The hole inward flange of bar hole is additionally provided with one layer of tread plate;Supporting leg is provided with least two through holes with heightening the surface of bridle, and one layer of waste and old belt is covered in into supporting leg and heightens the surface of bridle, and fixed belt bolt is connected through through hole with waste and old belt;The utility model is applied in gas tunnel.
Description
Technical field
A kind of gas tube support of adjustment height of the utility model, belong to gas tube support technology field.
Background technology
During extraction coal mine gas, first to gather region to coal seam and gas and drill, and drilling is connected with dedicated line,
The gas in coal seam and goaf is evacuated to ground with gas pumping equipment, is used or is emitted into total return.
The main pipeline caliber of gas pumping equipment is larger at present, and the support of pipelines typically used is supported along main entry bottom plate cloth
Put, traditional support of pipelines is all fixed, it is impossible to regulation height, because roadway floor is tunneled thus had along seat earth mostly
Height rises and falls, and must add stow-wood or cushion block to be in close contact support and pipeline, set complicated and support effect bad.
The content of the invention
In order to solve the above-mentioned technical problem, the utility model provides a kind of simple in construction, can arbitrarily adjust undertaking depth of beam,
The gas tube support of labour-saving adjustment height is set.
In order to realize above-mentioned technical proposal, the technical solution of the utility model is:Including supporting leg, bridle is heightened, institute
The side for stating supporting leg prolongs axial direction and is provided with one section of bar hole, and the both ends for heightening bridle are welded with threaded peace
Plug, after installation plug insertion bar hole, pad is enclosed on installation plug and is connected with fixing bolt;
It is further fixedly arranged on the downside of the bar hole and heightens bolt.
The hole inward flange of the bar hole is additionally provided with one layer of tread plate.
The supporting leg is provided with least two through holes with heightening the surface of bridle, and one layer of waste and old belt is covered in into branch
Support leg and the surface for heightening bridle, and fixed belt bolt is connected through through hole with waste and old belt.
The earth terminal of the supporting leg is additionally provided with support feet.
The beneficial effects of the utility model are:The utility model passes through setting on the basis of existing gas tube support
It is height adjustable to heighten bridle, gas tube bracket adjustment bearing height is solve thed problems, such as, pipeline is set more
Simply, use heightens that bridle is simple in construction, and stable connection is easy to use.
Brief description of the drawings
Fig. 1 is structural representation of the present utility model;
Fig. 2 is the enlarged drawing that the utility model heightens bridle one end;
In figure:1 be supporting leg, 2 for heighten bridle, 3 be bar hole, 4 be installation plug, 5 be fixing bolt, 6 be tune
High bolt, 7 be tread plate, 8 be waste and old belt, 9 be fixed belt bolt, 10 be support feet.
Embodiment
As described in Figure 1, the gas tube support of a kind of adjustment height of the utility model, including supporting leg 1, heighten bridle
2, the side of the supporting leg 1 prolongs axial direction and is provided with one section of bar hole 3, and the both ends for heightening bridle 2 are welded with band
The installation plug 4 of screw thread, will installation plug 4 insert bar hole 3 after, by pad be enclosed on installation plug 4 on and with the phase of fixing bolt 5
Even;
The downside of the bar hole 3, which is further fixedly arranged on, heightens bolt 6.
The hole inward flange of the bar hole 3 is additionally provided with one layer of tread plate 7.
The supporting leg 1 is provided with least two through holes with heightening the surface of bridle 2, and one layer of waste and old belt 8 is covered
It is connected in supporting leg 1 and the surface for heightening bridle 2, and by fixed belt bolt 9 through through hole with waste and old belt 8.
The earth terminal of the supporting leg 1 is additionally provided with support feet 10.
The utility model is specifically a kind of gas tube support of adjustable supporting height, and gas pipeline is laid in tunnel
When use;Between gas tube first is placed on into supporting leg 1, then gas tube is docked using pipeline docking machine, completed
Bolt 6 is heightened afterwards, makes to heighten bridle 2 and gas tube close contact, then pretension heightens bolt 6, makes to heighten undertaking
Beam 2 provides a upward pressure to gas tube, pipeline weight is entirely applied on support, now ensures all to heighten bridle
2 is contour, and fixing bolt 5 is tightened after determining height, withdraws from the docking machine of gas tube, completes the frame of this section of gas tube immediately
If.
Described to heighten the both ends welded and installed plug 4 of bridle 2, the diameter of installation plug 4 is less than the width of bar hole 3, made
Installation plug 4 can be tightly fixed to fixing bolt 5 and pad on bar hole 3, increase tread plate 7 is auxiliary with heightening bolt 6
Help fixation that fixed effect can be made more preferable.
The supporting leg 1, bridle 2 and the surface of tube contacts are provided with waste and old belt 8, to protect gas tube table
Face antirust coat is not scratched, and waste and old belt 8 is fixed on bridle and supporting leg by fixed belt bolt 9.
The characteristics of the utility model, is, can directly be transformed on general gas tube bracket basis, to make support
Heighten bridle 2 and be arranged to adjustable type, it is necessary to open a bar hole 3 in the upper end correct position of supporting leg 1, and in bar hole 3
Lower section welds one group and heightens bolt 6,, can also be in support feet except increasing support feet 10 to increase the lifting surface area of supporting leg 1
10 top a small distance weld a rectangular steel plates.
Finally it should be noted that:Various embodiments above is only to illustrate the technical solution of the utility model, rather than it is limited
System;Although the utility model is described in detail with reference to foregoing embodiments, one of ordinary skill in the art should
Understand:It can still modify to the technical scheme described in foregoing embodiments, either to which part or whole
Technical characteristic carries out equivalent substitution;And these modifications or replacement, the essence of appropriate technical solution is departed from this practicality newly
The scope of each embodiment technical scheme of type.
Claims (4)
- A kind of 1. gas tube support of adjustment height, it is characterised in that:Including supporting leg(1), heighten bridle(2), it is described Supporting leg(1)Side prolong axial direction and be provided with one section of bar hole(3), it is described to heighten bridle(2)Both ends be welded with band The installation plug of screw thread(4), plug will be installed(4)Insert bar hole(3)Afterwards, pad is enclosed on installation plug(4)Go up and with consolidating Determine bolt(5)It is connected;The bar hole(3)Downside be further fixedly arranged on and heighten bolt(6).
- A kind of 2. gas tube support of adjustment height according to claim 1, it is characterised in that:The bar hole(3) Hole inward flange be additionally provided with one layer of tread plate(7).
- A kind of 3. gas tube support of adjustment height according to claim 2, it is characterised in that:The supporting leg(1) With heightening bridle(2)Surface be provided with least two through holes, by one layer of waste and old belt(8)It is covered in supporting leg(1)With tune High bridle(2)Surface, and will fixed belt bolt(9)Through through hole and waste and old belt(8)It is connected.
- A kind of 4. gas tube support of adjustment height according to claim 3, it is characterised in that:The supporting leg(1) Earth terminal be additionally provided with support feet(10).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720900975.9U CN206973054U (en) | 2017-07-24 | 2017-07-24 | A kind of gas tube support of adjustment height |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720900975.9U CN206973054U (en) | 2017-07-24 | 2017-07-24 | A kind of gas tube support of adjustment height |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206973054U true CN206973054U (en) | 2018-02-06 |
Family
ID=61397433
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720900975.9U Expired - Fee Related CN206973054U (en) | 2017-07-24 | 2017-07-24 | A kind of gas tube support of adjustment height |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206973054U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111336316A (en) * | 2020-03-25 | 2020-06-26 | 章耀尹 | Long-distance oil-gas pipeline laying, installing and constructing equipment |
CN116642063A (en) * | 2023-07-24 | 2023-08-25 | 山西中威建元科技有限公司 | Hydraulic pipeline supporting and connecting mechanism for hydraulic engineering |
-
2017
- 2017-07-24 CN CN201720900975.9U patent/CN206973054U/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111336316A (en) * | 2020-03-25 | 2020-06-26 | 章耀尹 | Long-distance oil-gas pipeline laying, installing and constructing equipment |
CN116642063A (en) * | 2023-07-24 | 2023-08-25 | 山西中威建元科技有限公司 | Hydraulic pipeline supporting and connecting mechanism for hydraulic engineering |
CN116642063B (en) * | 2023-07-24 | 2023-11-07 | 山西中威建元科技有限公司 | Hydraulic pipeline supporting and connecting mechanism for hydraulic engineering |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN100501124C (en) | Construction method for tunnel contact passage in shield section of underground railway | |
CN206973054U (en) | A kind of gas tube support of adjustment height | |
JP4715610B2 (en) | Construction method inside tunnel | |
CN104265306B (en) | A kind of municipal administration shield tunnel | |
CN101907202A (en) | Portable support type jack-based pipe installation construction method | |
CN105822330A (en) | GFRP tube concrete support for underground engineering supporting and construction technology thereof | |
CN206052702U (en) | A kind of foundation bolt mounting structure | |
CN207079617U (en) | A kind of roller-coaster foundation structure | |
CN108988215A (en) | High pressure electric cable with large cross-section route can right position height adjustment laying engineering method | |
US1646423A (en) | Cradle for hydraulic pipe lines | |
CN102444275A (en) | Silo flexible slip form torsion resistance construction device | |
CN105064217B (en) | A kind of bridge coping bed die leakproof sizing device | |
CN108729931B (en) | Tunnel inverted arch repairing secondary lining reinforcing structure and construction method | |
CN205863852U (en) | The installation auxiliary of a kind of enclosed busbar adjusts frock | |
CN106088143B (en) | Construction method for comprehensive pipe rack drainage pipeline buttress | |
CN205954730U (en) | Major diameter down --hole hammer construction drill way positioner | |
CN104631496B (en) | Temporary access road above a kind of ballast water tank water and the installation method of this passage | |
CN204828929U (en) | Vertical hot and cold water pipeline supporting assembly of high -rise building | |
CN203702172U (en) | Arch-shaped lining roof steel formwork supporting system | |
CN208830341U (en) | A kind of electric power pylon foundation reinforcing structure | |
CN202882954U (en) | U-shaped steel support | |
CN205399092U (en) | A reservation station track recess fixing device of rolling stock section for rail | |
CN218935518U (en) | Pipeline supporting device | |
CN204530759U (en) | Occasional passage above a kind of ballast water tank water | |
CN205954434U (en) | Tunnel or for pipeline boardwalk |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180206 Termination date: 20180724 |
|
CF01 | Termination of patent right due to non-payment of annual fee |