CN206971931U - A kind of prefabricated assembled isolated column - Google Patents
A kind of prefabricated assembled isolated column Download PDFInfo
- Publication number
- CN206971931U CN206971931U CN201720758868.7U CN201720758868U CN206971931U CN 206971931 U CN206971931 U CN 206971931U CN 201720758868 U CN201720758868 U CN 201720758868U CN 206971931 U CN206971931 U CN 206971931U
- Authority
- CN
- China
- Prior art keywords
- column
- fixed
- embedded bolt
- support plate
- embedded
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Abstract
The utility model provides a kind of prefabricated assembled isolated column, including arc railing, horizon bar, column, connector, nut, vertical reinforcement concrete foundation, support plate, pre-embedded bolt, horizontal reinforcement, the end of upper and lower two horizon bars is fixed on column by connector, with certain gradient during the horizon bar installation, match with the radian of arc railing, some arc railings are fixed on up and down on two horizon bars, the column bottom is fixed with support plate, and the support plate is fixed with pre-embedded bolt by nut;The pre-embedded bolt is embedded in vertical reinforcement concrete foundation, and positioned by horizontal reinforcement in advance, and pre-embedded bolt bottom sets diameter of bolt 5d horizontal bent anchor.Pipeline rigid support of the present utility model is by the prefabricated of component, and guardrail on-site consolidation, dismounting recycling is easy for construction simple, without secondary outfit auxiliary facility, greatly reduces the waste of resource, realizes that green construction convenience and high-efficiency saves requirement attractive in appearance.
Description
Technical field
It the utility model is related to a kind of prefabricated assembled isolated column.
Background technology
With developing rapidly for China's building, the prefabricated assembled component of green construction also gradually occurs from the design of people
In our real life, its simple and convenient green theory is also increasingly taken seriously.
At present, job site is often essentially the form that steel tube fastener adds Dense mesh screen with isolated column, and steel pipe is heavy and base adds
Gu it is comparatively laborious, potential safety hazard be present;Tube material is set up to be set up according to scene and requires also to need to carry out secondary cut, sets up completion
Also need brushing antirust paint afterwards, workload is greatly and unsightly.
Utility model content
The purpose of this utility model is to provide a kind of prefabricated assembled isolated column, meets job site green construction, with
Reach convenience and high-efficiency and save requirement attractive in appearance.
To reach above-mentioned purpose, the utility model adopts the following technical scheme that:
A kind of prefabricated assembled isolated column, including arc railing, horizon bar, column, connector, nut, vertical reinforcement mix
Solidifying earth foundation, support plate, pre-embedded bolt, horizontal reinforcement, the end of upper and lower two horizon bars are fixed on column by connector,
With certain gradient during the horizon bar installation, match with the radian of arc railing, some arc railings are fixed
On upper and lower two horizon bars, the column bottom is fixed with support plate, and the support plate is fixed with pre-embedded bolt by nut;
The pre-embedded bolt is embedded in vertical reinforcement concrete foundation, and positioned by horizontal reinforcement in advance, and pre-embedded bolt bottom sets spiral shell
Bolt diameter 5d horizontal bent anchor.
The installation of the column is installed according to vertical with azimuth mode number, and column and vertical reinforcement concrete foundation are set
Put spacing row is carried out according to the requirement for height of guardrail and set.
Compared with prior art, the utility model has the following advantages:
Pipeline rigid support of the present utility model passes through the prefabricated of component, guardrail on-site consolidation, dismounting recycling, construction
It is convenient and simple, without secondary outfit auxiliary facility, the waste of resource is greatly reduced, realizes that green construction convenience and high-efficiency energy-conservation is beautiful
The requirement of sight.
Brief description of the drawings
Fig. 1 is the column profile of the prefabricated assembled isolated column of the utility model embodiment.
Fig. 2 is the node overview of the prefabricated assembled isolated column of the utility model embodiment.
Fig. 3 is the balustrade units figure of the prefabricated assembled isolated column of the utility model embodiment.
Embodiment
To enable above-mentioned purpose of the present utility model, feature and advantage more obvious understandable, below in conjunction with the accompanying drawings specifically
The utility model is described in further detail.
As shown in Figure 1 to Figure 3, a kind of prefabricated assembled isolated column, including arc railing 1, horizon bar 2, column 3, connection
Part 4, nut 5, vertical reinforcement concrete foundation 6, support plate 7, pre-embedded bolt 8, horizontal reinforcement 9, the end of upper and lower two horizon bars 2
Portion is fixed on column 3 by connector 4, with certain gradient when the horizon bar 2 is installed, the arc with arc railing 1
Degree matches, and some arc railings 1 are fixed on up and down on two horizon bars 2, and the bottom of column 3 is fixed with support plate 7,
The support plate 7 is fixed with pre-embedded bolt 8 by nut 5;The pre-embedded bolt 8 is embedded in vertical reinforcement concrete foundation 6 in advance,
And positioned by horizontal reinforcement 9, the bottom of pre-embedded bolt 8 sets diameter of bolt 5d horizontal bent anchor.
First according to condition of construction and set up requirement before construction, selection is suitable lay foundation type and size place carry out it is pre-
System, scene carry out the excavation of foundation pit as requested, after the completion of carry out vertical reinforcement concrete foundation back bury soil pressure real, so
The installation of vertical rod 3 is carried out afterwards, finally carries out the assembly of arc railing 1.
Claims (1)
1. a kind of prefabricated assembled isolated column, it is characterised in that including arc railing(1), horizon bar(2), column(3), connection
Part(4), nut(5), vertical reinforcement concrete foundation(6), support plate(7), pre-embedded bolt(8), horizontal reinforcement(9), upper and lower two
Root horizon bar(2)End pass through connector(4)It is fixed on column(3)On, the horizon bar(2)Incline during installation with certain
Gradient, with arc railing(1)Radian match, some arc railings(1)It is fixed on two horizon bars up and down(2)On,
The column(3)Bottom is fixed with support plate(7), the support plate(7)With pre-embedded bolt(8)Pass through nut(5)It is fixed;It is described
Pre-embedded bolt(8)It is embedded in vertical reinforcement concrete foundation in advance(6)In, and pass through horizontal reinforcement(9)Positioning, pre-embedded bolt(8)Bottom
Portion sets diameter of bolt 5d horizontal bent anchor.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720758868.7U CN206971931U (en) | 2017-06-28 | 2017-06-28 | A kind of prefabricated assembled isolated column |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720758868.7U CN206971931U (en) | 2017-06-28 | 2017-06-28 | A kind of prefabricated assembled isolated column |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206971931U true CN206971931U (en) | 2018-02-06 |
Family
ID=61406175
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720758868.7U Expired - Fee Related CN206971931U (en) | 2017-06-28 | 2017-06-28 | A kind of prefabricated assembled isolated column |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206971931U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110512945A (en) * | 2019-09-05 | 2019-11-29 | 上海建工二建集团有限公司 | A kind of vertical lever fixing apparatus and installation method of safe protective railing |
-
2017
- 2017-06-28 CN CN201720758868.7U patent/CN206971931U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110512945A (en) * | 2019-09-05 | 2019-11-29 | 上海建工二建集团有限公司 | A kind of vertical lever fixing apparatus and installation method of safe protective railing |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105155572A (en) | Cast-in-place pre-stressed anchor cable draught fan foundation system and construction method thereof | |
CN103225422A (en) | Existing masonry structure using light steel structure direct storey-adding technology and construction method of existing masonry structure | |
CN204401650U (en) | Square longitudinally connection prestressed assembly formula underground pipe gallery | |
CN206157913U (en) | Assembled square steel tube concrete post and girder steel connected node | |
CN206971931U (en) | A kind of prefabricated assembled isolated column | |
CN202117072U (en) | Assembled type base for power transmission line iron tower | |
CN202117073U (en) | Eccentric assembly type foundation of transmission line tower | |
JP2011144567A (en) | Block for civil engineering work | |
CN206769200U (en) | First wear formula post stretching vertical prestressing cast-in-place concrete rod structure | |
CN107100322A (en) | Post stretching vertical prestressing cast-in-place concrete rod structure and construction method | |
CN207934185U (en) | A kind of detachably prefabricated assembled concrete-filled steel square tubular column and girder steel combined joint | |
CN1737288A (en) | Fixing device and building method for outer decorative stone curtain wall of steel pipe truss tower | |
CN207633795U (en) | A kind of foundation pit suspension lane device | |
CN207619987U (en) | A kind of prefabricated foundation pit enclosure structure of environment-friendly type underground garage | |
CN205444455U (en) | Adopt environment -friendly type wall body's building window subassembly structure | |
CN204457079U (en) | Enclosure upright post | |
CN203201172U (en) | Existing masonry structure adopting technology of directly increasing layers by lightweight steel construction | |
CN201943071U (en) | Implantable steel tube anchor rod with stabs | |
WO2014205918A1 (en) | Counterweight type solar rack | |
CN206769198U (en) | Separate combination type armored concrete prefabricated section anchored end supporting construction | |
CN201883422U (en) | Fabricated steel guide wall for underground continuous wall | |
CN205444443U (en) | Adopt environment -friendly type wall body's building window subassembly structure | |
CN205276147U (en) | Corrugated steel pipe culvert entrance to a cave | |
CN206204985U (en) | A kind of environment-friendly type assembled grouting behind shaft or drift lining steel cylinder pile foundation | |
CN205935186U (en) | Hang foot building formula movable dwelling |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180206 Termination date: 20180628 |
|
CF01 | Termination of patent right due to non-payment of annual fee |