CN206971764U - The purlin crane system of Steel Structure Installation - Google Patents

The purlin crane system of Steel Structure Installation Download PDF

Info

Publication number
CN206971764U
CN206971764U CN201720643105.8U CN201720643105U CN206971764U CN 206971764 U CN206971764 U CN 206971764U CN 201720643105 U CN201720643105 U CN 201720643105U CN 206971764 U CN206971764 U CN 206971764U
Authority
CN
China
Prior art keywords
purlin
slide rail
construction
steel structure
track
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720643105.8U
Other languages
Chinese (zh)
Inventor
罗靖
郭伟光
邓明胜
朱建
杨湘泰
许宏雷
李昭昭
陈晨
张�浩
刘坚根
赵鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
China Construction New Zealand Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
China Construction New Zealand Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd, China Construction New Zealand Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201720643105.8U priority Critical patent/CN206971764U/en
Application granted granted Critical
Publication of CN206971764U publication Critical patent/CN206971764U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

A kind of purlin crane system of Steel Structure Installation is the utility model is related to, including:A pair of slide rails of the branch above steel construction;Track support body on a pair of described slide rails is set up in, the track support body is slidedly arranged on corresponding slide rail;The hanging basket being slidedly arranged on the track support body;And it is slidedly arranged on the crane on the track support body.Purlin crane system provided by the utility model, above steel construction and removable regulation hanging basket and the crane of removable regulation are located at by branch, realize while provide operating platform for Construction of Steel Structure, additionally it is possible to direct handling steel member, lifting operation is carried out without using tower crane.Operating platform is provided using hanging basket, solves the problems, such as to need to repeat Mobile operating platform in existing Construction of Steel Structure, purlin crane system of the present utility model can reduce labour demand, greatly improve efficiency of construction and quality, cost-effective.

Description

The purlin crane system of Steel Structure Installation
Technical field
Field of steel structure construction is the utility model is related to, refers in particular to a kind of purlin crane system of Steel Structure Installation.
Background technology
As social senilization's degree is constantly deepened, China's labour market supplies gradual atrophy in recent years, labour into This is rapid soaring, makes a general survey of each developed country's development course in the world, China future architecture market must be from labor-intensive to technology Intensity transformation, China are currently carrying forward vigorously building industrialization reform, and this is also uniquely going out for future architecture industry development Road.
Rapid with labour market price rises, and construction material cost proportion shared in project construction will be more next Lower, especially steel production capacity in China's is seriously superfluous in recent years, and low level is kept relatively steady by price of steel product within following a period of time Fixed, steel building will be further developed, and compared with traditional construction installation method, technological innovation can be improved further Steel Structure Installation speed of application, safety and quality, the economic benefit and social benefit of steel building will highlight significantly.
The construction of existing steel building is used factory is pre-splicing or on-site consolidation, recycles tower crane lifting then to exist High-altitude is spliced to form, and needs to set operating platform on completed steel construction when high-altitude is spliced, operation is provided for workmen Space, complete to be further continued for concatenation construction on the Rotating fields, it is necessary to which operating platform is moved to after a Rotating fields are completed in construction, And need to lift steel member by tower crane in work progress, such construction method is less efficient, labour demand compared with Height, cost are also higher.
Utility model content
The defects of the purpose of this utility model is to overcome prior art, there is provided a kind of purlin of Steel Structure Installation, which is hung, is System, solve to need to repeat Mobile operating platform in existing Construction of Steel Structure and whole process of constructing needs tower crane to be lifted and existed Construction method is less efficient, the problem of labour demand is higher and cost is also higher.
Realizing the technical scheme of above-mentioned purpose is:
The utility model provides a kind of purlin crane system of Steel Structure Installation, including:
A pair of slide rails of the branch above steel construction;
Track support body on a pair of described slide rails is set up in, the track support body is slidedly arranged on corresponding slide rail;
The hanging basket being slidedly arranged on the track support body;And
The crane being slidedly arranged on the track support body.
Purlin crane system provided by the utility model, above steel construction and removable regulation hanging basket and removable is located at by branch The crane of dynamic regulation, realize while provides operating platform for Construction of Steel Structure, additionally it is possible to directly handling steel member, without making Lifting operation is carried out with tower crane.Operating platform is provided using hanging basket, solve needs to repeat to move in existing Construction of Steel Structure The problem of operating platform, purlin crane system of the present utility model can reduce labour demand, greatly improve efficiency of construction and quality, It is cost-effective.
The utility model Steel Structure Installation purlin crane system further improvement is that, the track support body includes relative A pair of guide rails of setting and the spacing bearing for being installed on the rail end, the bottom of the guide rail is formed with the first track, institute State cunning on the first track and set the hanging basket.
The utility model Steel Structure Installation purlin crane system further improvement is that, first track is in inverted T-shaped Structure, including be fixedly arranged on the guide rail bottom riser and with riser transverse slat connected vertically;
Liftable hoisting structure is connected with the top of the hanging basket, movement is fixedly connected with the top of the hoisting structure Mechanism, the travel mechanism are slidedly arranged on the transverse slat.
The utility model Steel Structure Installation purlin crane system further improvement is that, set on described a pair of guide rails There is the second track above first track;
Crane hanging is between a pair of guide rails and being slidedly arranged on corresponding second track.
The utility model Steel Structure Installation purlin crane system further improvement is that, the crane is provided with liftable Hoisting mechanism.
The utility model Steel Structure Installation purlin crane system further improvement is that, the bottom of described a pair of guide rails Purlin rail drive mechanism is installed with, the purlin rail drive mechanism is located at the both ends of the guide rail and is slidedly arranged on corresponding slide rail, leads to Crossing the purlin rail drive mechanism drives the guide rail to be moved along the slide rail.
The utility model Steel Structure Installation purlin crane system further improvement is that, the slide rail includes multiple removable The slide rail beam of connection is unloaded, by adjusting the length adaptation of the quantity of the slide rail beam and the slide rail in the steel construction The length of construction area.
The utility model Steel Structure Installation purlin crane system further improvement is that, in addition to branch is located at a pair of slide rails Both ends at reinforcement;
The end of each slide rail beam is equipped with the reserved connecting plate for being connected with the reinforcement;
The end of the reinforcement is resisted against the slide rail beam at extreme, and is fixed with corresponding reserved connecting plate Connection.
The utility model Steel Structure Installation purlin crane system further improvement is that, the reinforcement include it is multiple can The joggle beam of dismantling connection, by adjusting the length adaptation of the quantity of the joggle beam and the reinforcement in the steel knot The width of the construction area of structure.
The utility model Steel Structure Installation purlin crane system further improvement is that, the end of the slide rail is installed with Spacing bearing.
Brief description of the drawings
Fig. 1 is the structure that the purlin crane system of the utility model Steel Structure Installation is installed on a preferred embodiment of steel construction Schematic diagram.
Fig. 2 is that the purlin crane system of the utility model Steel Structure Installation connects the structural representation of support system.
Fig. 3 is the structural representation of the purlin crane system of the utility model Steel Structure Installation.
Fig. 4 is the structural representation of the side view of the purlin crane system of the utility model Steel Structure Installation.
Fig. 5 is the top view of the guide rail in the purlin crane system of the utility model Steel Structure Installation.
Fig. 6 be the utility model Steel Structure Installation purlin crane system in slide rail and track support body junction structural representation Figure.
Fig. 7 to Fig. 9 is slide rail in the purlin crane system of the utility model Steel Structure Installation and point of reinforcement unloading process Solution structure schematic diagram.
Embodiment
The utility model is described in further detail with specific embodiment below in conjunction with the accompanying drawings.
Refering to Fig. 1, the utility model provides a kind of purlin crane system of Steel Structure Installation, is provided for Construction of Steel Structure The hanging basket and crane of removable regulation, wherein hanging basket provide construction operation platform, and crane realizes the component in work progress Handling.Avoid is needed to set up operating platform in existing Construction of Steel Structure, and dismounting is had bad luck to next construction floor, then is set up The cumbersome construction procedure of operating platform, the whole use of tower crane is also liberated, can be with for the component of the floor of current construction layer Carry out handling installation using crane, it is less efficient to solve construction method present in existing construction, labour demand it is higher into The problem of this is also higher.The structure of the purlin crane system of the utility model Steel Structure Installation is illustrated below in conjunction with the accompanying drawings.
As shown in Figure 1 to Figure 3, the purlin crane system 30 of Steel Structure Installation provided by the utility model includes a pair of slide rails 31st, track support body 32, hanging basket 33 and crane 34, a pair of slide rails, 31 tops for being located at steel construction 10, a pair of slide rails 31 can By 20 tops for being located at steel construction 10 of support system, the support system 20 can be erected on the floor of steel construction 10, The outside of steel construction 10 can be attached to, is fixedly connected with the steel column of steel construction 10.In the constantly construction upwards of steel construction 10 When, jack can be placed in the bottom of support system 20 of purlin crane system 30 and jacked, again by support system after jacking in place 20 are fixedly connected with steel construction 10.The support system 20 itself can also have automatic climbing function, in the bottom of support system 20 Be provided with hydraulic climbing mechanism so that support system 20 can automatic climbing, and then realize the automatic climbing of purlin crane system 30. A pair of slide rails 31 are oppositely arranged, and track support body 32 is set up on a pair of slide rails 31, and track support body 32 is slidably installed in corresponding slide rail On 31, track support body 32 can be moved along slide rail 31, so that the position of track support body 32 is adjustable, hanging basket 33 is slidedly arranged on On track support body 32, hanging basket 33 can be moved along track support body 32 so that the position of hanging basket 33 is adjustable, and hanging basket 33 is logical Crossing to be slidably installed on track support body 32 realizes hanging basket 33 and hangs in the top of steel construction 10, and the hanging basket 33 is that steel construction 10 provides Construction operation platform, crane 34 are slidedly arranged on track support body 32, and crane 34 can move along track support body 32 so that crane 34 position is adjustable, and crane 34 is used for handling component.The track support body 32 that purlin is hung in system 30 can move along slide rail 31, realize The regulation of the lateral displacement of hanging basket 33 and crane 34, and track support body 32 is erected on slide rail 31 and causes what track support body 32 was set Direction and the setting direction of slide rail 31 are perpendicular, and hanging basket 33 and crane 34 can move along track support body 32, realize hanging basket 33 Length travel with crane 34 is adjusted, and hanging basket 33 provides working space for workmen, formed with operation horizontal in hanging basket 33 Platform, hanging basket 33 in system 30 and crane 34 are hung in purlin itself has liftable height adjusting function, can be according to the construction of reality The height regulation of hanging basket 33 is highly carried out, crane 34 can be according to the construction location handling component of reality, then passes through track support body 32 The regulation of the lateral attitude of hanging basket 33 and crane 34 is realized along the movement of slide rail 31, by hanging basket 33 and crane 34 along track The regulation of the lengthwise position of hanging basket 33 and crane 34 is realized in the movement of support body 32, so that hanging basket 33 and crane 34 can cover Any construction location of steel construction 10, meet the construction requirement of aerial work.
Purlin crane system provided by the utility model is located above steel construction the and removable hanging basket adjusted by branch and can The crane of mobile regulation, realize while provides operating platform for Construction of Steel Structure, additionally it is possible to directly handling steel member, without Lifting operation is carried out using tower crane.Operating platform is provided using hanging basket, solve needs to repeat to move in existing Construction of Steel Structure The problem of dynamic operating platform, purlin crane system of the present utility model are located at the top of steel construction by branch, and the purlin crane system can be with The construction of steel construction and climbed, this, which climbs, to be jacked using jack.Crane system energy in purlin of the present utility model Labour demand is enough reduced, greatly improves efficiency of construction and quality, it is cost-effective.
As a better embodiment of the present utility model, with reference to shown in Fig. 4 and Fig. 5, track support body 32 includes relative set The a pair of guide rails 321 put and the spacing bearing 322 for being installed on the end of guide rail 231, a pair of guide rails 321 be arranged in parallel, spacing bearing 322 are fixedly arranged on the both ends at the top of guide rail 321.For accelerating construction progress, the track support body 32 set in system 30 is hung in purlin can Think multiple, constructed while many places can be realized.The bottom of guide rail 321 is formed with the first track 3211, first track Sliding on 3211 to set hanging basket 33, the first track 3211 is the basis that hanging basket 33 provides sliding, and hanging basket 33 can be along the first track 3211 Carry out slidable adjustment so that hanging basket 33 can be moved at the construction location of needs.Two are provided with one track support body 32 Guide rail 321, i.e., cunning sets a hanging basket 33 on each guide rail 321, so that a track support body 32 can provide two hanging baskets 33 are used as construction operation platform.Guide rail 321 can carry out transverse shifting along slide rail 31, and the lateral attitude for realizing hanging basket 33 is adjusted Section, hanging basket 33 can carry out lengthwise position regulation along guide rail 321, and hanging basket 33 itself has lift adjustment function, realize height Position adjustments on direction, three-dimensional regulation enable hanging basket 33 to be accurately adjusted to desired position of constructing.Further, One track 3211 is in inverted T-shaped structure, including is fixedly arranged on the riser of the bottom of guide rail 321 and is vertically connected at the transverse slat of bottom of the riser, The transverse slat forms the first track 3211 positioned at the upper surface of riser both sides, and hanging basket 33 is slided by the travel mechanism 332 at top and set On the first track 3211.Specifically, the hoisting structure 331 of liftable regulation, hoisting structure are connected with the top of hanging basket 33 331 top is fixedly connected with travel mechanism 332, and the travel mechanism 332 includes the first roller 3321 and support 3322, the first roller 3321 are placed in the both sides of riser and are slidably installed in the upper surface of transverse slat, the support 3322 include located at transverse slat lower section lateral strut and It is connected to lateral strut both ends and positioned at the U-shaped pole of the riser both sides, is provided with two top flanges of U-shaped pole Rotatable first roller 3321, the support 3322 are folded in the first track by the first roller 3321 positioned at riser both sides On 3211, the first roller 3321 can only be vertically moved along the upper surface of transverse slat, without producing lateral shift, in support Motor is installed with 3322, first roller of motor drive connection 3321, it is achieved thereby that the first roller of control 3321 movement.The bottom of the support 3322 is fixedly connected with hoisting structure 331, and the hoisting structure 331 includes wire spool, winding In the lifting rope on wire spool, be connected to the suspension hook of lifting rope end, hoisting structure 331 also includes motor, and with coiling dish driving Connection, drive wire spool to rotate it is achieved thereby that the folding and unfolding of lifting rope by motor, be also achieved that the lift adjustment of suspension hook.This hangs Hook, which hooks, sets connection hanging basket 33, and the lift adjustment of suspension hook has correspondingly driven the lifting of hanging basket 33.Specifically attachment structure is:Hanging basket 33 periphery is installed with hanger 333, and lifting rope 334 is connected with hanger 333, and the top of lifting rope 334 is fixedly connected with vertical loading board 335, the top of the vertical loading board 335 is connected with the suspension hook of hoisting structure 331, and suspension hook 333 is hooked and is located on vertical loading board 335.
As another better embodiment of the present utility model, as shown in Figures 3 to 5, position is provided with a pair of guide rails 321 The second track 3212 above the first track 3211, crane 34 are hung between a pair of guide rails 321 and are slidedly arranged on corresponding lead On second track 3212 of rail 321.Second track 3212 is located at the top of the first track 3211 so that the mobile regulation of crane 34 It is relatively independent with the mobile regulation of hanging basket 33, it does not interfere with each other, crane 34 is used to lift 10 working steel member of steel construction, can save The slightly use of tower crane.In a preferred embodiment, guide rail 321 is box beam, and the second track is provided with the top of box beam 3212.Crane 34 includes spandrel girder 341 and is installed in the drive mechanism 342 at the both ends of spandrel girder 341, and the drive mechanism 342 is slided and set In on corresponding second track 3212, and spandrel girder 341 is driven to be moved along the second track 3212, in spandrel girder 341 Bottom hoisting mechanism 343 is installed, the hoisting mechanism 343 has elevating function, and bottom is connected with the hanging beam 3431 of lifting. The handling of the assembled component of steel construction 10 is realized by hoisting mechanism 343.It is installed in the spacing bearing of the end of guide rail 321 322 are blocked in the end of the second track 3212, prevent the drive mechanism 342 on spandrel girder 341 from derailing.With reference to shown in Fig. 6, one Purlin rail drive mechanism 323 is installed with to the bottom of guide rail 321, the purlin rail drive mechanism 323 is slidably installed on slide rail 31, and can be along Slide rail 31 moves, so as to be moved with a pair of guide rails 321 along slide rail 31.Spacing branch also is provided with the both ends of slide rail 31 Seat, prevents guide rail 321 from derailing by spacing bearing.It is arranged on the spacing bearing of the end of slide rail 31 and is arranged on the end of guide rail 321 The structure of spacing bearing 322 in portion is identical, and the spacing bearing 322 includes the baffle plate erected and the stiffener for being fixedly arranged on the baffle plate back side, Baffle plate and stiffener are fixedly connected with the end in corresponding slide rail 31 or guide rail 321, spacing work(is realized by baffle plate Energy.
As another better embodiment of the present utility model, as shown in figure 3, slide rail 31 includes multiple be detachably connected Slide rail beam 311, by adjusting the length adaptation of the quantity of slide rail beam 311 and slide rail 31 in the construction area of steel construction 10 Length.Slide rail 31 is arranged to the structure of detachable splicing connection, is easy to the length adjustment of slide rail 31, steel construction can be adapted to The construction of 10 changes of section and various sizes of steel construction, can be according to the actual cross-section chi of steel construction 10 in practice of construction The very little regulation that adaptability is carried out to slide rail 31, when the section of steel construction 10 becomes big, increase the length of slide rail 31, when steel construction 10 Section become hour, reduce slide rail 31 length.It can be fastenedly connected between two adjacent slide rail beams 311 by connection otic placode, It is achieved thereby that be detachably connected, when needing to increase the length of slide rail 31, increase a slide rail beam 311 in end, by its with Originally the slide rail beam of end is fastenedly connected by connection otic placode.When needing to reduce the length of slide rail 31, by end Slide rail beam 311 is removed.Further, to improve the stability of slide rail 31, reinforcement is connected with the both ends of slide rail 31 36, reinforcement 36 connects two slide rails 31, forms stable force structure.At the end of each slide rail beam 311 of slide rail 31 The reserved connecting plate 312 for being connected with reinforcement 36 is equipped with portion, the end of reinforcement 36 rests upon the end of slide rail 31 It is fixedly connected on the slide rail beam 311 at place and with corresponding reserved connecting plate 312.As another preferable embodiment party of the present utility model Formula, as shown in fig. 7, to adapt to the change of Design of Steel Structural Element Sections width, reinforcement 36 includes multiple joggle beams being detachably connected 361, by adjusting the length adaptation of the quantity of joggle beam 361 and reinforcement 36 in the width of the construction area of steel construction 10 Degree.So with reference to slide rail 31 length adaptation in steel construction 10 construction area length, reinforcement 36 and slide rail 31 enclose shape Into the size of frame structure adaptability regulation can be done according to the change of the construction area of steel construction 10.On reinforcement 36 Being detachably connected between joggle beam 361 can be realized by the connection otic placode that end is set, and be connected in two joggle beams 361 When, two ends of joggle beam 361 are docked, two connection otic placodes of end fit, then pass through two connection otic placodes The bolt run through is fastenedly connected, and realizes the connection of two joggle beams 361.When dismantling joggle beam 361, at connection otic placode Connection is removed and can remove the joggle beam 361 positioned at end.
As shown in Figure 7 to 9, slide rail 31 and reinforcement 36 enclose the size of the frame structure to be formed can be according to actual use Needs and be adjusted so that the frame structure can adapt to the changes of section of steel construction 10 and various sizes of steel construction Construction.The size of slide rail 31 and reinforcement 36 is adjusted, and can only change length of the length of slide rail 31 without changing reinforcement 36, Length of the length of reinforcement 36 without changing slide rail 31 can also only be changed, can be equal with the length of slide rail 31 and reinforcement 36 Change.Diminished with slide rail 31 and the length of reinforcement 36 below to illustrate how sized frame structure is, in Construction of Steel Structure Become hour in the section for running into the steel construction 10 of construction, the size of the slide rail 31 on the crane system of purlin and reinforcement 36 can be reduced to fit The construction operating mode for the steel construction 10 that section diminishes is answered, specifically, by positioned at the company of the reinforcement 36 of the first side and two slide rails 31 Releasing is connect, removes the slide rail beam 311 of two ends of slide rail 31, removes the quantity of slide rail beam 311 according to the section of steel construction 10 To determine, after the completion of dismounting, the length of reinforcement 36 is determined further according to the section of steel construction 10, by positioned at the reinforcement of the second side 36 one end is removed with the connection of slide rail 31, then removes the joggle beam 361 of the end of reinforcement 36 of second side, after the completion of The end of the reinforcement 36 of second side is connected with the end of slide rail 31 again, the reserved connecting plate of the end of slide rail 31 can be passed through 312 are fastenedly connected.The joggle beam 361 on the reinforcement 36 of the first side is subjected to corresponding dismounting again, then again with two Reserved connecting plate 312 on the slide rail beam 311 of the end of slide rail 31 is fastenedly connected.Realize slide rail 31 and reinforcement 36 encloses shape Into the size of frame structure diminish, the function of flexible modulation is provided for purlin crane system of the present utility model, becomes in construction and cuts During the structure of face, can flexibly it be adjusted as needed.
The utility model is described in detail above in association with accompanying drawing embodiment, those skilled in the art can root Many variations example is made to the utility model according to described above.Thus, some details in embodiment should not be formed to this practicality New restriction, the utility model will be used as the scope of protection of the utility model using the scope that appended claims define.

Claims (10)

  1. A kind of 1. purlin crane system of Steel Structure Installation, it is characterised in that including:
    A pair of slide rails of the branch above steel construction;
    Track support body on a pair of described slide rails is set up in, the track support body is slidedly arranged on corresponding slide rail;
    The hanging basket being slidedly arranged on the track support body;And
    The crane being slidedly arranged on the track support body.
  2. 2. the purlin crane system of Steel Structure Installation as claimed in claim 1, it is characterised in that the track support body includes relative A pair of guide rails of setting and the spacing bearing for being installed on the rail end, the bottom of the guide rail is formed with the first track, institute State cunning on the first track and set the hanging basket.
  3. 3. the purlin crane system of Steel Structure Installation as claimed in claim 2, it is characterised in that first track is in inverted T-shaped Structure, including be fixedly arranged on the guide rail bottom riser and with riser transverse slat connected vertically;
    Liftable hoisting structure is connected with the top of the hanging basket, moving machine is fixedly connected with the top of the hoisting structure Structure, the travel mechanism are slidedly arranged on the transverse slat.
  4. 4. the purlin crane system of Steel Structure Installation as claimed in claim 2, it is characterised in that set on described a pair of guide rails There is the second track above first track;
    Crane hanging is between a pair of guide rails and being slidedly arranged on corresponding second track.
  5. 5. the purlin crane system of Steel Structure Installation as claimed in claim 4, it is characterised in that the crane is provided with liftable Hoisting mechanism.
  6. 6. the purlin crane system of Steel Structure Installation as claimed in claim 2, it is characterised in that the bottom of described a pair of guide rails Purlin rail drive mechanism is installed with, the purlin rail drive mechanism is located at the both ends of the guide rail and is slidedly arranged on corresponding slide rail, leads to Crossing the purlin rail drive mechanism drives the guide rail to be moved along the slide rail.
  7. 7. the purlin crane system of Steel Structure Installation as claimed in claim 1, it is characterised in that the slide rail includes multiple removable The slide rail beam of connection is unloaded, by adjusting the length adaptation of the quantity of the slide rail beam and the slide rail in the steel construction The length of construction area.
  8. 8. the purlin crane system of Steel Structure Installation as claimed in claim 7, it is characterised in that also include branch and be located at a pair of slide rails Both ends at reinforcement;
    The end of each slide rail beam is equipped with the reserved connecting plate for being connected with the reinforcement;
    The end of the reinforcement is resisted against the slide rail beam at extreme, and fixes and connect with corresponding reserved connecting plate Connect.
  9. 9. the purlin crane system of Steel Structure Installation as claimed in claim 8, it is characterised in that the reinforcement include it is multiple can The joggle beam of dismantling connection, by adjusting the length adaptation of the quantity of the joggle beam and the reinforcement in the steel knot The width of the construction area of structure.
  10. 10. the purlin crane system of Steel Structure Installation as claimed in claim 1, it is characterised in that the end of the slide rail is fixed Limited location bearing.
CN201720643105.8U 2017-06-05 2017-06-05 The purlin crane system of Steel Structure Installation Active CN206971764U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720643105.8U CN206971764U (en) 2017-06-05 2017-06-05 The purlin crane system of Steel Structure Installation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720643105.8U CN206971764U (en) 2017-06-05 2017-06-05 The purlin crane system of Steel Structure Installation

Publications (1)

Publication Number Publication Date
CN206971764U true CN206971764U (en) 2018-02-06

Family

ID=61411023

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720643105.8U Active CN206971764U (en) 2017-06-05 2017-06-05 The purlin crane system of Steel Structure Installation

Country Status (1)

Country Link
CN (1) CN206971764U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107178211A (en) * 2017-06-05 2017-09-19 中国建筑第八工程局有限公司 The purlin crane system of Steel Structure Installation
CN108285085A (en) * 2018-03-27 2018-07-17 中国建筑第八工程局有限公司 Pipe installing vertical-horizontal means of transport and transportation resources
CN110467112A (en) * 2019-09-18 2019-11-19 山东华泰钢结构工程有限公司 A kind of especially big formed steel construction longitudinal direction climbing device
CN113216650A (en) * 2021-05-19 2021-08-06 西南石油大学 Integral lifting type automatic building construction platform

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107178211A (en) * 2017-06-05 2017-09-19 中国建筑第八工程局有限公司 The purlin crane system of Steel Structure Installation
CN107178211B (en) * 2017-06-05 2024-03-12 中国建筑第八工程局有限公司 Truss hanging system for installing steel structure
CN108285085A (en) * 2018-03-27 2018-07-17 中国建筑第八工程局有限公司 Pipe installing vertical-horizontal means of transport and transportation resources
CN108285085B (en) * 2018-03-27 2023-06-13 中国建筑第八工程局有限公司 Pipeline installation vertical and horizontal transport tool and transport method
CN110467112A (en) * 2019-09-18 2019-11-19 山东华泰钢结构工程有限公司 A kind of especially big formed steel construction longitudinal direction climbing device
CN113216650A (en) * 2021-05-19 2021-08-06 西南石油大学 Integral lifting type automatic building construction platform

Similar Documents

Publication Publication Date Title
CN107178211A (en) The purlin crane system of Steel Structure Installation
CN206971764U (en) The purlin crane system of Steel Structure Installation
CN107355067B (en) The automatic lifting purlin crane system construction operation platform of Steel Structure Installation
CN105672673B (en) A kind of quick positioning apparatus of precast floor slab and method
CN205713147U (en) A kind of quick positioning apparatus of precast floor slab
CN104150353A (en) Liftable and detachable bridge crane
CN109025234A (en) A kind of building high-altitude vacantly construct with can level, vertically the track crane ship that walk
CN110259226A (en) Multistory parking frame installation vehicle hoisting mechanism, multistory parking frame installation and Transport Vehicle method
CN106988314A (en) A kind of counter weight type formwork jumbo, counter weight type outrigger platform, and construction method
CN106800245B (en) A kind of floorings lifting hanger, hanging apparatus and hanging method
CN208249734U (en) One kind is built the road gantry crane
CN112753414A (en) Automatic flowerpot loading and unloading system for urban vertical greening
CN207061690U (en) Bridge crane with suspender maintenance rig
CN206815943U (en) A kind of pole upside-down mounting group founds lifting device
CN214495431U (en) Prefabricated component installation auxiliary device
CN208328717U (en) A kind of U-shaped beam bridge formation machine
CN210216177U (en) Anchor machine dragging system for beam erecting
CN110284428B (en) Undercarriage for integrally removing large-tonnage steel pipe support and construction method
CN209906186U (en) Building template cross-floor transportation equipment
CN209193385U (en) Tunnel gantry crane
CN111115461A (en) Reinforcing steel bar and mould transportation and automatic assembling equipment
CN218843695U (en) Asynchronous hanging basket for cantilever cast-in-place
CN109457700A (en) Stake top walking Pile Installation Platform, its erection method and pile base construction method
CN209651750U (en) A kind of single driving spacing adjusting mechanism
CN211897898U (en) Sliding type high-pier tie beam formwork support system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant