CN206955504U - One kind can have enough to meet the need people's escape way on regularization tower crane - Google Patents

One kind can have enough to meet the need people's escape way on regularization tower crane Download PDF

Info

Publication number
CN206955504U
CN206955504U CN201720888171.1U CN201720888171U CN206955504U CN 206955504 U CN206955504 U CN 206955504U CN 201720888171 U CN201720888171 U CN 201720888171U CN 206955504 U CN206955504 U CN 206955504U
Authority
CN
China
Prior art keywords
steel
meet
enough
escape way
tower crane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720888171.1U
Other languages
Chinese (zh)
Inventor
肖亮
林伟
张勇
康青云
石深文
张哲宇
要峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Construction Group Co Ltd
Original Assignee
China Railway Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Construction Group Co Ltd filed Critical China Railway Construction Group Co Ltd
Priority to CN201720888171.1U priority Critical patent/CN206955504U/en
Application granted granted Critical
Publication of CN206955504U publication Critical patent/CN206955504U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses one kind can have enough to meet the need people's escape way on regularization tower crane, including base, enclosing and steel wire rope, the base includes two I-steel be arrangeding in parallel, two I-steel be arrangeding in parallel are fixedly connected by some spiral heads, steel plate is equipped between two I-steel be arrangeding in parallel, at least one pair of suspension ring is equipped with the every I-steel, each suspension ring are connected with the steel wire rope;The enclosing is enclosed and formed by some vertical rods and some guard rails, and the vertical rod and the guard rail are arranged at intervals, and are fixedly connected between the vertical rod and the guard rail by bindiny mechanism, the bottom of upright rod is fixedly connected with the I-steel.The beneficial effects of the utility model:Escape way described in the utility model can be lifted by the round steel suspension ring on passage, and the later stage can be used in turn gradually to carry out lifting upwards with the rising of tower body and floor, use very simple, conveniently.

Description

One kind can have enough to meet the need people's escape way on regularization tower crane
Technical field
Building safety technical field of construction is the utility model is related to, it particularly relates to which one kind can have enough to meet the need regularization tower crane Upper people's escape way.
Background technology
Tower crane is a kind of crane gear the most frequently used on construction site, also known as " derrick crane ", by a section Spreading(Referred to as " standard knot "), it is on building site for hanging the raw material of the constructions such as working reinforcing bar, wood stupefied, concrete, steel pipe A kind of essential equipment.Adhesion tower-crane is one kind relatively common in numerous tower crane types, because building height compares Height, it is rigidly connected between tower crane and building to strengthen the stability of derrick crane, typically against proposed building Arrangement.Because tower crane distance structure floor has a certain distance, tower body can rise with the rising of story height, in order to save Save the time of tower above and below tower department and ensure the personal safety of tower department, it is necessary to set a safety between tower body and structural floor Passage.
People's escape way is typically set up using steel pipe on traditional tower crane, and passage is usually chosen in attachment rack position, Easy passage is set up into using steel pipe, it is current for tower department that scaffold board is laid on the horizontal steel pipe of channel bottom.Steel pipe is taken If the major defect of escape way is:The passage needs repeatedly to be set up with the rising of tower body and story height, takes simultaneously If operation need to carry out high aerial, operation is got up inconvenience, and certain security risk be present.
The problem of in correlation technique, effective solution is not yet proposed at present.
Utility model content
For the above-mentioned technical problem in correlation technique, the utility model proposes one kind directly to be made on the ground Make be molded have enough to meet the need people's escape way on the tower crane of regularization, after ground moulding can by the round steel suspension ring on passage come Lifted, the later stage can be used in turn gradually to carry out lifting upwards with the rising of tower body and floor, use very simple Singly, conveniently.
To realize above-mentioned technical purpose, what the technical solution of the utility model was realized in:
One kind can have enough to meet the need people's escape way on regularization tower crane, including base, enclosing and steel wire rope, and the base includes two The I-steel that root be arranged in parallel, two I-steel be arrangeding in parallel are fixedly connected by some spiral heads, and described two Steel plate is equipped between the I-steel that root be arranged in parallel, at least one pair of suspension ring is equipped with the every I-steel, it is each described Suspension ring are connected with the steel wire rope;The enclosing is enclosed and formed by some vertical rods and some guard rails, the vertical rod and described Guard rail is arranged at intervals, and is fixedly connected between the vertical rod and the guard rail by bindiny mechanism, the bottom of upright rod and institute I-steel is stated to be fixedly connected.
Further, the spiral head includes being arranged at the upper spiral head at the I-steel upper plate plate bottom and set The lower spiral head of the I-steel lower plate plate face is placed in, the steel plate is arranged at the top of the upper spiral head.
Further, the spiral head is arranged on the I-steel by welding by both sides, and weld bead height is the spiral shell The half of line steel bar end diameter, the spacing between the upper spiral head is 500mm, the lower spiral head with it is described on The welding position of spiral head corresponds.
Further, one end of the I-steel is provided with casual labourer's word steel toe.
Further, the bindiny mechanism includes connection sheet and connecting bolt.
Further, the steel plate is made up of some checkered steel plates, the checkered steel plate by manual electric arc welding with it is described The inward flange of I-steel upper plate is connected, and the joint between the checkered steel plate is connected by manual electric arc welding, the joint Lower section be provided with supplement spiral head, the supplement spiral head connects the upper plate of two I-steel be arrangeding in parallel Plate bottom.
Further, it is provided with dodge gate on the enclosing, the dodge gate, which is arranged at, described can have enough to meet the need regularization tower crane Upper people's escape way is close to the side of structural floor.
Further, the dodge gate is arranged between two adjacent vertical rods, and described two adjacent described vertical In bar, wherein a vertical rod is provided with L-shaped steel bar end, a vertical rod in addition is provided with bolt hole, the dodge gate be provided with The latch that the L-shaped steel bar end is engaged, the dodge gate are provided with the keeper being engaged with the bolt hole.
Further, the bottom of upright rod is provided with vertical rod base, and the vertical rod base offers some circular holes, the I-shaped Steel upper plate is provided with mounting hole corresponding with the circular hole, and the circular hole is bolted with the mounting hole.
Further, the base is 100 × 100 × 3mm square bar plate, and the sheet steel surrounding uniformly offers 4 diameter 10mm circular hole.
The beneficial effects of the utility model:By setting base, and suspension ring and steel wire rope are set so that the utility model institute The escape way stated can be lifted by the round steel suspension ring on passage, the later stage can come with the rising of tower body and floor by It is secondary to carry out lifting upwards and be used in turn, use very simple, conveniently.
Brief description of the drawings
, below will be to embodiment in order to illustrate more clearly of the utility model embodiment or technical scheme of the prior art In the required accompanying drawing used be briefly described, it should be apparent that, drawings in the following description are only of the present utility model Some embodiments, for those of ordinary skill in the art, on the premise of not paying creative work, can also be according to this A little accompanying drawings obtain other accompanying drawings.
Fig. 1 is a kind of side view for having enough to meet the need people's escape way on regularization tower crane according to the utility model embodiment Figure;
Fig. 2 is a kind of vertical view for having enough to meet the need people's escape way on regularization tower crane according to the utility model embodiment Figure;
Fig. 3 is that a kind of according to the utility model embodiment is having enough to meet the need on regularization tower crane people's escape way just Elevation;
Fig. 4 is the top view of vertical rod and vertical rod base;
Fig. 5 is vertical rod base and I-steel is connected schematic diagram.
In figure:1. I-steel;2. I-shaped steel toe;3. vertical rod;4. connection sheet;5. connecting bolt;6. guard rail;7. suspension ring; 8. bolt;9. steel wire rope;10. spiral head;11. steel plate;12. guard rail cross bar;13. vertical rod base;14. keeper;15. live Dynamic door;16.L shape steel bar ends;17. latch;18. circular hole.
Embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, the technical scheme in the embodiment of the utility model is carried out Clearly and completely describing, it is clear that described embodiment is only the utility model part of the embodiment, rather than whole Embodiment.Based on the embodiment in the utility model, every other embodiment that those of ordinary skill in the art are obtained all belongs to In the scope of the utility model protection.
As shown in Fig. 1 ~ 5, one kind according to the utility model embodiment can have enough to meet the need people on regularization tower crane and lead to safely Road, including base, enclosing and steel wire rope 9, the base include two I-steel 1 be arrangeding in parallel, and described two be arranged in parallel I-steel 1 be fixedly connected by some spirals first 10, be equipped with steel plate between described two I-steel 1 be arrangeding in parallel 11, at least one pair of suspension ring 7 is equipped with the every I-steel 1, and each suspension ring 7 are connected with the steel wire rope 9;It is described Enclosing is enclosed and formed by some vertical rods 3 and some guard rails 6, and the vertical rod 3 and the guard rail 6 are arranged at intervals, the vertical rod 3 It is fixedly connected between the guard rail 6 by bindiny mechanism, the bottom of vertical rod 3 is fixedly connected with the I-steel 1.
I-steel 1, spiral are first 10, steel plate 11 forms the base of escape way, instead of traditional steel pipe and trick The structure type of plate, stabilized structure is reliable, and intensity is high, can ensure the security performance of whole escape way, the wherein He of I-steel 1 Spiral head is used for the bulk strength for ensureing escape way, and steel plate 11 is used for the standing and walking of tower department.Vertical rod 3 and guard rail 6 form the enclosing of escape way, are further ensured that the personal safety of tower department during upper and lower tower.Suspension ring 7 and steel wire rope 9 are matched somebody with somebody Close so that escape way can directly carry out making shaping on the ground, as the rising of tower body and floor comes gradually during use Be lifted up being used in turn, without as in conventional method as the rise of tower body and floor, each layer of passage are required for spreading again If.On the other hand, I-steel 1, steel plate 11, spiral be first 10, steel wire rope 9, suspension ring 7, guard rail 6, vertical rod 3 are commonly to build Material is built, the suitable parts of model are chosen according to construction site situation, it is simple in construction without particularly customized part, can Directly to be manufactured on-site by worker.
Specific set-up mode between spiral first 10 and I-steel 1 is that the spiral first 10 includes being arranged at The upper spiral head at the upper plate plate bottom of I-steel 1 and the lower spiral head for being arranged at the lower plate plate face of I-steel 1, institute State the top that steel plate 11 is arranged at the upper spiral head.
Double-layer threaded steel bar end 10 is set, further ensures the intensity of base, that is, add the peace of escape way Full performance;On the other hand, steel plate 11 is arranged at the top of the upper spiral head, and is layed between I-steel 1, not only may be used To allow spiral first 10 to bear the pressure from steel plate 11, the upper surface of base can also be made to seem regular and attractive in appearance, especially It is the top of steel plate 11 and the upper plate top horizontal of I-steel 11 when the thickness of steel plate 11 is equal with the thickness of the upper plate of I-steel 1 Together, whole base is neat and attractive in appearance.
More specifically, the spiral first 10 is arranged on the I-steel 1 by welding by both sides, weld bead height is described The half of first 10 diameter of spiral, the spacing between the upper spiral head is 500mm, the lower spiral head and institute The welding position for stating spiral head corresponds.
It according to this setup, can both ensure the fastness welded, ensure the security performance of escape way, in appearance Also it is relatively more neat and attractive in appearance.
Later safe copper sheathing passage can be stuck on the horizon bar of tower-body standard section for convenience, play fixed effect, One end of the I-steel 1 is provided with casual labourer's word steel toe 2.
Enclosing is encircled a city by guard rail 6 and vertical rod 3, is connected between guard rail 6 and vertical rod 3 by bindiny mechanism, wherein, it is described Bindiny mechanism includes connection sheet 4 and connecting bolt 5.Guard rail 6, vertical rod 3, connection sheet 4 and connecting bolt 5 can with Assembling into Enclosing, provide conveniently for the transport of raw material early stage, can also be dismantled using finishing, save and used for successive projects.
A kind of paving mode of specific steel plate 11 is provided below, the steel plate 11 is made up of some checkered steel plates, described Checkered steel plate is connected by manual electric arc welding with the inward flange of the upper plate of I-steel 1, the joint between the checkered steel plate Connected by manual electric arc welding, the lower section of the joint is provided with supplement spiral head, the supplement spiral head connection The upper plate plate bottom of described two I-steel 1 be arrangeding in parallel.The splicing of polylith checkered steel plate, the fortune of raw material early stage can be facilitated Defeated, supplement spiral head can eliminate the unstable hidden danger that joint is likely to occur.Size and upper screw thread when checkered steel plate When the spacing of steel bar end is equal,(Such as when the spacing between upper spiral head is 500mm, checkered steel plate is grown in I-steel 1 The size spent on direction is also 500mm)Spiral first 10 is just directed at the joint of checkered steel plate 10, it is possible to no longer needs Supplement spiral head is set.
Escape way is passed in and out in order to facilitate tower department, is provided with dodge gate 15 on the enclosing, the dodge gate 15 is arranged at By the passage that steel plate 11 is formed close to the side of structural floor.
The specific set-up mode of dodge gate 15 is that the dodge gate 15 is arranged between two adjacent vertical rods 3, institute State in two adjacent vertical rods 3, wherein a vertical rod 3 is provided with L-shaped steel bar end 16, a vertical rod 3 in addition is provided with door Keyhole, the dodge gate 15 are provided with the latch 17 being engaged with the L-shaped steel bar end 16, and the dodge gate 15 is provided with and institute State the keeper 14 that bolt hole is engaged.
Vertical rod 3 and the connection concrete mode of I-steel 1 are that the bottom of vertical rod 3 is provided with vertical rod base 13, the vertical rod bottom Seat 13 offers some circular holes 18, and the upper plate of I-steel 1 is provided with and the 18 corresponding mounting hole of circular hole, the circular hole 18 It is connected with the mounting hole by bolt 8.
More specifically, the base 13 is 100 × 100 × 3mm square bar plate, the sheet steel surrounding uniformly opens up There is 4 diameter 10mm circular hole 18.
Specific raw material size selection is provided below, can meet the needs of most construction sites, also can be from Common building materials market is bought.I-steel 1 uses 16 I-steel, if tower body is from structural floor Edge Distance>During 9m, it can use The welding point of two I-steel of base can be staggered and set if necessary to butt welding spreading by 18 or 20 I-steel, single I-steel Put, and to set the wide 10mm thickness connecting plates of 300mm to carry out being welded with reinforcement between two parties in joint location in the position of joint, welding is adopted Use welding by both sides.
The length of casual labourer's word steel toe 2 is 30cm.
Guard rail 6 is grating type enclosing, and height 1200mm, vertical rod 3 is 50 × 50 × 3mm square steel tube.Guard rail cross bar 12 be 30 × 30 × 3mm cross bar.
The side of every I-steel 1 is welded with a pair of 16 round steel suspension ring 7.
The horizontal spacing 800mm of two I-steel 1, the C25 spirals first 10 grown by 900mm between two I-steel Connect.
The thickness of checkered steel plate is 5mm.
Dodge gate height 1200mm.
Preferred embodiment of the present utility model is the foregoing is only, it is all at this not to limit the utility model Within the spirit and principle of utility model, any modification, equivalent substitution and improvements made etc., the utility model should be included in Protection domain within.

Claims (10)

1. one kind can have enough to meet the need people's escape way on regularization tower crane, it is characterised in that including base, enclosing and steel wire rope(9), institute Stating base includes two I-steel be arrangeding in parallel(1), two I-steel be arrangeding in parallel(1)Pass through some spirals Head(10)It is fixedly connected, two I-steel be arrangeding in parallel(1)Between be equipped with steel plate(11), the every I-steel (1)On be equipped with least one pair of suspension ring(7), each suspension ring(7)With the steel wire rope(9)Connection;If the enclosing by Dry vertical rod(3)With some guard rails(6)Enclose and form, the vertical rod(3)With the guard rail(6)It is arranged at intervals, the vertical rod (3)With the guard rail(6)Between be fixedly connected by bindiny mechanism, the vertical rod(3)Bottom and the I-steel(1)It is fixed Connection.
2. one kind according to claim 1 can have enough to meet the need people's escape way on regularization tower crane, it is characterised in that the screw thread Steel bar end(10)Including being arranged at the I-steel(1)The upper spiral head at upper plate plate bottom and it is arranged at the I-steel(1) The lower spiral head of lower plate plate face, the steel plate(11)It is arranged at the top of the upper spiral head.
3. one kind according to claim 2 can have enough to meet the need people's escape way on regularization tower crane, it is characterised in that the screw thread Steel bar end(10)The I-steel is arranged at by welding by both sides(1)On, weld bead height is the spiral head(10)Diameter Half, the spacing between the upper spiral head is 500mm, the weldering of the lower spiral head and the upper spiral head Connect position one-to-one corresponding.
4. one kind according to claim 1 can have enough to meet the need people's escape way on regularization tower crane, it is characterised in that the I-shaped Steel(1)One end be provided with casual labourer's word steel toe(2).
5. one kind according to claim 1 can have enough to meet the need people's escape way on regularization tower crane, it is characterised in that the connection Mechanism includes connection sheet(4)And connecting bolt(5).
6. one kind according to claim 1 can have enough to meet the need people's escape way on regularization tower crane, it is characterised in that the steel plate (11)It is made up of some checkered steel plates, the checkered steel plate passes through manual electric arc welding and the I-steel(1)The inward flange of upper plate Connect, the joint between the checkered steel plate is connected by manual electric arc welding, and the lower section of the joint is provided with supplement screw thread Steel bar end, the supplement spiral head connect two I-steel be arrangeding in parallel(1)Upper plate plate bottom.
7. one kind according to claim 1 can have enough to meet the need people's escape way on regularization tower crane, it is characterised in that the enclosing On be provided with dodge gate(15), the dodge gate(15)The close knot of people's escape way on regularization tower crane can be had enough to meet the need described in being arranged at The side of structure floor.
8. one kind according to claim 7 can have enough to meet the need people's escape way on regularization tower crane, it is characterised in that the activity Door(15)It is arranged at two adjacent vertical rods(3)Between, the described two adjacent vertical rods(3)In, wherein one is vertical Bar(3)It is provided with L-shaped steel bar end(16), a vertical rod in addition(3)It is provided with bolt hole, the dodge gate(15)It is provided with and institute State L-shaped steel bar end(16)The latch being engaged(17), the dodge gate(15)It is provided with the keeper being engaged with the bolt hole (14).
9. one kind according to claim 1 can have enough to meet the need people's escape way on regularization tower crane, it is characterised in that the vertical rod (3)Bottom is provided with vertical rod base(13), the vertical rod base(13)Offer some circular holes(18), the I-steel(1)Upper plate It is provided with and the circular hole(18)Corresponding mounting hole, the circular hole(18)Pass through bolt with the mounting hole(8)Connection.
10. one kind according to claim 9 can have enough to meet the need people's escape way on regularization tower crane, it is characterised in that described vertical Bar base(13)For 100 × 100 × 3mm square bar plate, the sheet steel surrounding uniformly offers 4 diameter 10mm circle Hole(18).
CN201720888171.1U 2017-07-21 2017-07-21 One kind can have enough to meet the need people's escape way on regularization tower crane Active CN206955504U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720888171.1U CN206955504U (en) 2017-07-21 2017-07-21 One kind can have enough to meet the need people's escape way on regularization tower crane

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720888171.1U CN206955504U (en) 2017-07-21 2017-07-21 One kind can have enough to meet the need people's escape way on regularization tower crane

Publications (1)

Publication Number Publication Date
CN206955504U true CN206955504U (en) 2018-02-02

Family

ID=61382213

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720888171.1U Active CN206955504U (en) 2017-07-21 2017-07-21 One kind can have enough to meet the need people's escape way on regularization tower crane

Country Status (1)

Country Link
CN (1) CN206955504U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107311052A (en) * 2017-07-21 2017-11-03 中铁建设集团有限公司 One kind can have enough to meet the need people's escape way on regularization tower crane

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107311052A (en) * 2017-07-21 2017-11-03 中铁建设集团有限公司 One kind can have enough to meet the need people's escape way on regularization tower crane

Similar Documents

Publication Publication Date Title
CN207144449U (en) A kind of hoistway operation platform
CN206917085U (en) A kind of prefabricated overlapping steel framed concrete beam
CN206467994U (en) A kind of novel hanging basket support
CN106930531A (en) A kind of pull-up manomelia is encorbelmented the construction method of heavy frame
CN206955504U (en) One kind can have enough to meet the need people's escape way on regularization tower crane
CN206722378U (en) A kind of pull-up manomelia is encorbelmented heavy frame
CN205116768U (en) Superelevation layer instrument formula protection platform of encorbelmenting
CN104278828B (en) A kind of concrete chimney dismantling operation platform
CN107311052A (en) One kind can have enough to meet the need people's escape way on regularization tower crane
CN211524021U (en) Climbing frame with good safety
CN206053393U (en) One kind can have enough to meet the need steel stair operating platform
CN114182646B (en) Assembled ladder cage buttress with adjustable length
CN206753087U (en) A kind of lighting roof operating platform structure
CN207003970U (en) A kind of building scaffold being easily installed
CN206409014U (en) A kind of electric pole for being easy to climb
CN205954972U (en) Steel structure floor slab
CN205116685U (en) Can dismantle shaped steel of encorbelmenting platform of unloading
CN209837752U (en) Anti-overturning type temporary protection device for hole
CN207739184U (en) Road central corrugated beam barrier and anti-dazzle net connection structure
CN205348824U (en) Outer facade safety plain net device of prefabricated construction
CN206110674U (en) Transit platform is measured to a superelevation layer core section of thick bamboo
CN110409321A (en) A kind of bridge finishing scaffold device and bridge fitment operation structure
CN205777810U (en) A kind of steel tower being applicable to high slope
CN216405142U (en) Along with hanging gliding continuous web's of basket fitment platform structure
CN220643868U (en) Detachable operation platform for high-speed rail hanging fence construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant