CN206925351U - A kind of multi-functional top plate hanger erection constructing device - Google Patents
A kind of multi-functional top plate hanger erection constructing device Download PDFInfo
- Publication number
- CN206925351U CN206925351U CN201720465632.4U CN201720465632U CN206925351U CN 206925351 U CN206925351 U CN 206925351U CN 201720465632 U CN201720465632 U CN 201720465632U CN 206925351 U CN206925351 U CN 206925351U
- Authority
- CN
- China
- Prior art keywords
- support bar
- steel pipe
- top plate
- protective cover
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Earth Drilling (AREA)
Abstract
The utility model proposes a kind of multi-functional top plate hanger erection constructing device, to solve the technical problem that conventional construction method efficiency is low, cost is high, construction effect is poor.Including boring of electric hammer device and clamp nut erecting device, boring of electric hammer device includes support frame, protective cover and fixing device, and clamp nut erecting device includes crank, steel pipe and sleeve.The utility model is simple in construction, reasonable in design and easy for construction, and input cost is relatively low, reduces labor intensity, greatly improves construction speed.
Description
Technical field
Technical field of building construction is the utility model is related to, particularly relates to a kind of multi-functional top plate hanger erection construction dress
Put.
Background technology
In decorations, water and electricity installation project work progress, especially to being needed in furred ceiling, airduct, crane span structure work progress
In building top mounting suspension., it is necessary to install suspension rod on the top plate of building body when reality is constructed to suspension bracket.At present,
When being constructed to suspension rod, typically all using scaffold is set up, artificial restocking boring of electric hammer installs suspension rod, because suspension rod is in top plate
Installation, drilling, installation suspension rod need to lift construction equipment and instrument, and difficulty of construction is larger, and the suspension rod out of plumb, easily installed
Displacement, accordingly causes that the construction quality of constructed suspension bracket is poor, qualification rate is relatively low, is unsatisfactory for construction requirement.Further, since need to pacify
The suspension rod quantity of dress is more, and, per one suspension rod of installation, is required to movable Scaffold and removes set greatly not in same working face
Batch instrument, also, be both needed to per one suspension bracket of installation up and down scaffold for several times, thus the installation quality of suspension bracket and speed by
Limit, during actual installation suspension bracket suspension rod, often there is boom location skew, tilt, the fixed situation such as loosely, so that suspension bracket
Construction qualification rate is greatly reduced.Thus, nowadays need a kind of simple in construction, reasonable in design, input cost relatively low and construction letter
Just, the good top plate hanger erection constructing device of using effect, the deficiency that can effectively solve conventional construction method improve applying for suspension rod
Working medium amount and installation rate.
Utility model content
The utility model proposes a kind of multi-functional top plate hanger erection constructing device, solves conventional construction method efficiency
Technical problem low, cost is high, construction effect is poor.
What the technical solution of the utility model was realized in:
A kind of multi-functional top plate hanger erection constructing device, including boring of electric hammer device and clamp nut erecting device, electricity
Hammer drill aperture apparatus includes support frame, protective cover and fixing device, and support frame includes upper support bar, lower support bar, upper support bar
Bottom is connected by the top of quarter butt and operation handle and lower support bar, quarter butt and operation handle respectively by connecting bolt with it is upper
Support bar and lower support bar are hinged, and lower support bar bottom is provided with pedestal, and fixing device, fixing device are provided with the top of upper support bar
The upper support bar of downside is provided with protective cover, and noise reduction layer is provided with protective cover;Clamp nut erecting device include crank, steel pipe and
Sleeve, the crank are connected by rotating shaft with steel pipe bottom, and sleeve is fixed on steel pipe top by the fastening screw outside steel pipe
Inside, the steel pipe below fastening screw are provided with dust-proof pallet.
The protective cover is transparent hemi type, is fixed on by the steady pin of bottom on upper support bar;Dust-proof pallet is
Bright disc-shape, by the pallet fork steady pin of bottom on steel pipe.
The noise reduction layer is bonded setting with protective cover, and noise reduction layer is transparent wavy.
The sleeve is hollow six square socket, and size and the expansion bolt of sleeve match.
Beneficial effect caused by the technical program energy:
1st, the utility model is simple in construction, reasonable in design and easy for construction, and input cost is relatively low, reduces labor intensity, greatly
Width improves construction speed.
2nd, boring of electric hammer constructing device simple processing using effect is good used by the utility model, during practice of construction, only
Boring of electric hammer constructing device need to be placed in needs below bore position on ground, and now electric hammer switch need to be locked to normally open position, turn
Head alignment needs bore position, connects electric hammer power supply, uniformly firmly pushes mid-handle, make to fix electric hammer one end using leverage
Upper bracket move up, so just obtain installation suspension rod bolt hole.
3rd, clamp nut erecting device is simple in construction used by the utility model, reasonable in design, and processing and fabricating is easy, makes
It is good with effect.After suspension rod bolt hole is drilled, expansion bolt external member is connected installation with suspension rod one end, and is screwed to correct position,
By the ready suspension rod other end, insertion bolt is fixed in the steel pipe of constructing device in the middle part of interior six square socket, until expansion bolt
Nut coincide with interior six square socket, by the roof bolt hole that is drilled of expansion bolt insertion, firmly swinging handle, until expanding screw
Bolt fastens completely, hang spring is extracted out out of interior six square socket and steel pipe, suspension rod just installation.
4th, constructing device is simple in construction used by the utility model, and use is light, time saving and energy saving, it is not necessary to sets up pin hand
Frame and the large quantities of instruments of carrying, are not limited by place.
5th, economic benefit and social benefit of the present utility model are notable, and top plate hanger erection qualification rate greatly improves, thus
Hanger erection can be greatly decreased and reprocess operating expenses, improve construction effect and construction quality.
In summary, the utility model is simple in construction, easy to use, can effectively reduce construction cost, improves top plate suspension rod
The construction quality and speed of application of installation.
Brief description of the drawings
, below will be to embodiment in order to illustrate more clearly of the utility model embodiment or technical scheme of the prior art
Or the required accompanying drawing used is briefly described in description of the prior art, it should be apparent that, drawings in the following description are only
It is some embodiments of the utility model, for those of ordinary skill in the art, is not paying the premise of creative work
Under, other accompanying drawings can also be obtained according to these accompanying drawings.
Fig. 1 is boring of electric hammer apparatus structure schematic diagram of the present utility model.
Fig. 2 is boring of electric hammer device Construction State schematic diagram of the present utility model.
Fig. 3 is clamp nut erecting device structural representation of the present utility model.
Fig. 4 is clamp nut erecting device Construction State schematic diagram of the present utility model.
Embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, the technical scheme in the embodiment of the utility model is carried out
Clearly and completely describing, it is clear that described embodiment is only the utility model part of the embodiment, rather than whole
Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are not under the premise of creative work is paid
The every other embodiment obtained, belong to the scope of the utility model protection.
As Figure 1-4, the utility model embodiment provides a kind of multi-functional top plate hanger erection constructing device, including
Boring of electric hammer device and clamp nut erecting device, boring of electric hammer device include support frame, protective cover 12 and fixing device 5, branch
Support includes upper support bar 4, lower support bar 16, and the bottom of upper support bar 4 passes through quarter butt 3 and operation handle 2 and lower support bar 4
Top is connected, and quarter butt 3 and operation handle 2 are hinged by connecting bolt 15 and upper support bar 4 and lower support bar 16 respectively, lower branch
The bottom of strut 16 is provided with pedestal 1, and the top of upper support bar 4 is provided with fixing device 5, and the fixing device 5 is flexible binding strap or solid
Determine buckle, electric hammer is fixed on by boring of electric hammer device top by fixing device, set on the upper support bar 4 of the downside of fixing device 5
There is protective cover 12, noise reduction layer 13 is provided with protective cover 12;Clamp nut erecting device includes crank 18, steel pipe 7 and sleeve 9, institute
State crank 18 and the top of steel pipe 7 is fixed on by the fastening screw 8 outside steel pipe 7 by rotating shaft 6 and the bottom connection of steel pipe 7, sleeve 9
Inside, the steel pipe 7 of the lower section of fastening screw 8 are provided with dust-proof pallet 17;During installation, substantial amounts of dirt can be produced unavoidably
Soil, dust, which falls, easily falls into the eyes influence sight of worker, and dust-proof pallet 17 is that spill disk is made by transparent material, can be both
The dust to fall is collected, and does not influence observation construction site situation.
Boring of electric hammer constructing device simple processing using effect is good used by the utility model, during practice of construction, only needs
Boring of electric hammer constructing device, which is placed in, to be needed below bore position on ground, and now electric hammer switch need to be locked to normally open position, rotary head
Alignment needs bore position, connects electric hammer power supply, uniformly firmly pushes mid-handle, make to fix electric hammer one end using leverage
Upper bracket moves up, and so just obtains the bolt hole of installation suspension rod;Used clamp nut erecting device is simple in construction, and design is closed
Reason, processing and fabricating is easy, and using effect is good.After suspension rod bolt hole is drilled, expansion bolt external member is connected installation with suspension rod one end,
And correct position is screwed to, by the ready suspension rod other end, insertion bolt fixes the steel of constructing device in the middle part of interior six square socket
In pipe, until the nut of expansion bolt coincide with interior six square socket, the roof bolt hole that expansion bolt insertion is drilled, firmly shake
Shake handle, until expansion bolt fastens completely, hang spring is extracted out out of interior six square socket and steel pipe, suspension rod just installation.
Preferably, above-mentioned protective cover 12 is transparent hemi type, is fixed on by the steady pin 14 of bottom on upper support bar 4;
The setting of protective cover 12 can prevent that caused dust disorderly flies during boring of electric hammer, will be constructed rubbish by the protective cover of dome-type
Collect, and do not influence worker and observe construction progress;Dust-proof pallet 17 is transparent disc-shape, the pallet fork steady pin by bottom
On steel pipe 7.
Preferably, above-mentioned noise reduction layer 13 is bonded setting with protective cover 12, and noise reduction layer 13 is transparent wavy, passes through noise reduction
The setting of layer 13 can substantially reduce caused noise pollution in work progress, protect the physical and mental health of worker.
Preferably, above-mentioned sleeve 9 is hollow six square socket, and size and the expansion bolt of sleeve 9 match.
Application method of the present utility model is as follows:Electric hammer is fixed on above upper support bar, only need to be electricity during practical operation
Hammer switch is locked to normally open position, and lower support bar is put on ground, connection electric hammer power supply, uniform depression handle, in driving
Support and electric hammer move up, and just obtain required bolt hole.Then expansion bolt external member is connected with hang spring 10 and installed, by hang spring one
Hold in insertion sleeve and steel pipe, it is ensured that expansion bolt nut coincide with square socket, the top plate for being then drilled expansion bolt insertion
Bolt hole, crank is rotated, until expansion bolt fastens completely, extract hang spring out, complete hanger erection.
Preferred embodiment of the present utility model is the foregoing is only, it is all at this not to limit the utility model
Within the spirit and principle of utility model, any modification, equivalent substitution and improvements made etc., the utility model should be included in
Protection domain within.
Claims (4)
- A kind of 1. multi-functional top plate hanger erection constructing device, it is characterised in that:Pacify including boring of electric hammer device and clamp nut Assembling device, boring of electric hammer device include support frame, protective cover(12)And fixing device(5), support frame includes upper support bar(4)、 Lower support bar(16), upper support bar(4)Bottom pass through quarter butt(3)And operation handle(2)With lower support bar(4)Top connect Connect, quarter butt(3)And operation handle(2)Pass through connecting bolt respectively(15)With upper support bar(4)And lower support bar(16)It is hinged, Lower support bar(16)Bottom is provided with pedestal(1), upper support bar(4)Top is provided with fixing device(5), fixing device(5)Downside Upper support bar(4)It is provided with protective cover(12), protective cover(12)It is interior to be provided with noise reduction layer(13);Clamp nut erecting device includes shaking (18), steel pipe(7)And sleeve(9), the crank(18)Pass through rotating shaft(6)With steel pipe(7)Bottom connection, sleeve(9)Pass through Steel pipe(7)Outside fastening screw(8)It is fixed on steel pipe(7)Inside top, fastening screw(8)The steel pipe of lower section(7)It is provided with Dust-proof pallet(17).
- 2. multi-functional top plate hanger erection constructing device as claimed in claim 1, it is characterised in that:The protective cover(12)For Transparent hemi type, pass through the steady pin of bottom(14)It is fixed on upper support bar(4)On;Dust-proof pallet(17)For transparent disc Shape, by the pallet fork steady pin of bottom in steel pipe(7)On.
- 3. multi-functional top plate hanger erection constructing device as claimed in claim 1, it is characterised in that:The noise reduction layer(13)With Protective cover(12)Fitting is set, noise reduction layer(13)To be transparent wavy.
- 4. multi-functional top plate hanger erection constructing device as claimed in claim 1, it is characterised in that:The sleeve(9)For in Empty six square sockets, sleeve(9)Size match with expansion bolt.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720465632.4U CN206925351U (en) | 2017-04-28 | 2017-04-28 | A kind of multi-functional top plate hanger erection constructing device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720465632.4U CN206925351U (en) | 2017-04-28 | 2017-04-28 | A kind of multi-functional top plate hanger erection constructing device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206925351U true CN206925351U (en) | 2018-01-26 |
Family
ID=61351213
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720465632.4U Expired - Fee Related CN206925351U (en) | 2017-04-28 | 2017-04-28 | A kind of multi-functional top plate hanger erection constructing device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206925351U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110405252A (en) * | 2019-07-26 | 2019-11-05 | 中冶天工集团天津有限公司 | Hanger rod mounting device and method in a kind of building |
-
2017
- 2017-04-28 CN CN201720465632.4U patent/CN206925351U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110405252A (en) * | 2019-07-26 | 2019-11-05 | 中冶天工集团天津有限公司 | Hanger rod mounting device and method in a kind of building |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206925351U (en) | A kind of multi-functional top plate hanger erection constructing device | |
CN114408045B (en) | Robot for climbing upright column | |
CN207892019U (en) | A kind of energy-saving steel structure workshop support column base fixture | |
CN102661077A (en) | Method for erecting fulcrum bar | |
CN208676577U (en) | A kind of environment art design architectural design multifunctional drawing platform | |
CN205817742U (en) | Street lamp post installation tool | |
CN206397211U (en) | A kind of bridge construction deposits protector with steel reinforcement cage | |
CN109441087A (en) | A kind of cantilever builder's jack being attached on structures | |
CN206369009U (en) | A kind of natural gas line supporting construction | |
CN210919157U (en) | A interim plugging device for mine | |
CN204827279U (en) | Pendulum pipe mechanism is moved to combined type | |
CN204511032U (en) | Temporary construction fence fixedly uses stand base | |
CN209129238U (en) | The furred ceiling dried hanging hang structure of ceiling | |
CN202467221U (en) | Power plant main workshop steel roof truss hoisting lifting device | |
CN206158205U (en) | A auxiliary device for hoist and mount of large -span steel truss | |
CN204386631U (en) | A kind of Portable protective net | |
CN207727778U (en) | A kind of concrete slab aperture grouting reparation erecting device | |
CN214402379U (en) | Reusable suspended ceiling fixing mechanism in movable board house | |
CN208168305U (en) | A kind of novel fabricated building operation platform | |
CN212866474U (en) | Novel combined wallboard for architectural design | |
CN208907213U (en) | A kind of consolidation process device for unfavorable geology section landslide of high slope | |
CN207794588U (en) | Attachment device for civil engineering exterior wall and the scaffold of curtain wall | |
CN204139170U (en) | A kind of stake formula ground pin device | |
CN211992775U (en) | Novel roof nut is fixed device | |
CN219023184U (en) | Quincuncial pile convenient assembling structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180126 Termination date: 20200428 |