CN206158205U - A auxiliary device for hoist and mount of large -span steel truss - Google Patents

A auxiliary device for hoist and mount of large -span steel truss Download PDF

Info

Publication number
CN206158205U
CN206158205U CN201621028163.1U CN201621028163U CN206158205U CN 206158205 U CN206158205 U CN 206158205U CN 201621028163 U CN201621028163 U CN 201621028163U CN 206158205 U CN206158205 U CN 206158205U
Authority
CN
China
Prior art keywords
steel truss
steel
truss
support
adjustable support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621028163.1U
Other languages
Chinese (zh)
Inventor
吴启程
明楼春
姚成新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201621028163.1U priority Critical patent/CN206158205U/en
Application granted granted Critical
Publication of CN206158205U publication Critical patent/CN206158205U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses an auxiliary device for hoist and mount of large -span steel truss, including left side section steel truss, right side section steel truss, the permanent support in the left side, the permanent support in the right, interim supplementary adjustable support, steel corbel, steel quil, the lifting pin, the crossbeam, screw jack and laser range finder, one side of left side section steel truss is equipped with right side section steel truss, the opposite side of left side section steel truss is equipped with the permanent support in the left side, one side of right side section steel truss is equipped with the permanent support in the right, left side section steel truss is equipped with the crossbeam with the bottom of right side section steel truss, the bottom of crossbeam is equipped with interim supplementary adjustable support, one side of interim supplementary adjustable support is equipped with steel quil, the lifting pin is connected by steel quil to interim supplementary adjustable support, the bottom of lifting pin is equipped with hoist device, this set device is simple, low cost, easily purchase, increase the security of hoist and mount, the simple preparation, can change into ground with a lot of work aloft goes on, easy operation.

Description

A kind of servicing unit for large span steel truss lifting
Technical field
The utility model be related in and construction technology of steel configuration field, and in particular to it is a kind of for large span steel truss lifting Servicing unit.
Background technology
Large-span truss because its reasonable stress, can give full play to the strength of materials, consumptive material it is few, from heavy and light, low cost and knot The features such as structure is various informative, becomes the structure type faster of development at present, large-span industrial building, the long span being used in industrial building Degree vestibule, aircraft assembly shop and bulk storage plant etc., due to its manufacture and having high demands of installing, particularly installation difficulty is big, because This, the construction of large span spatial structure is one of important symbol of a national building technology level, from a side, reflects one The building technology level of individual country.
In Steel Structure Installation industry, when the steel truss of large span is installed, because its span is big, weight weight, not large-scale Crane can be used in particular cases, and truss can be caused to lift, and engineering is stagnated, and to enterprise economy and reputation aspect are brought Loss.
For the difficult problem for overcoming large span steel truss to lift, often lifted using merogenesis, arrange in the position of partial node and prop up Frame, after the connection work at each node to be done, completes unloaded operation, then striking, completes whole lifting work, no Super large heavy-duty hoisting equipment need to be selected.Due in the middle of the process installed in high-altitude, the more difficult control of height value of adjacent two sections truss, control That what is made is bad, will have a strong impact on the installation quality of section header, is related to the success or failure of whole truss installa-tion.
Utility model content
The purpose of this utility model is that and provide one kind in order to solve the above problems for large span steel truss lifting Servicing unit, so as to solve the above problems
In order to solve above-mentioned technical problem, the utility model provides following technical scheme:
The utility model provides a kind of servicing unit for large span steel truss lifting, including left section of steel truss, the right side Section steel truss, left side permanent support, temporarily the right permanent support, auxiliary adjustable support, steel corbel, steel hoop, lifting pin, horizontal stroke Beam, screw jack and laser range finder, the side of the left section of steel truss is provided with the right section of steel truss, the left section of steel truss The opposite side of frame is provided with the left side permanent support, and the side of the right section of steel truss is provided with the right permanent support, described Left section of steel truss is provided with the crossbeam with the bottom of the right section of steel truss, and the bottom of the crossbeam is provided with the interim auxiliary can Support, the side of the interim auxiliary adjustable support is adjusted to be provided with the steel hoop, the interim auxiliary adjustable support is by the steel Cuff connects the lifting pin, and the bottom of the lifting pin is provided with hanging apparatus.
Used as a kind of optimal technical scheme of the present utility model, the bottom of the lifting pin is provided with the screw jack, The bottom of the screw jack is provided with the steel corbel.
Used as a kind of optimal technical scheme of the present utility model, the screw jack withstands one end of steel truss, described The side of screw jack is provided with the laser range finder.
The beneficial effect that the utility model is reached is:The covering device is simple, low cost, be easy to buying, in adjustable support The inner side of post arranges four jack, and per two jack one end of steel truss is withstood, and each jack side arranges a survey Distance meter, according to the reading of rangefinder, adjusts at any time the flexible value of jack, reaches the height value of design, makes the truss of adjacent two section Holding level, completes the connection work of joint, by the supporting role of interim auxiliary adjustable support, can complete large span steel truss The lifting of frame, method is easy, and many high-level work can be changed into into ground is carried out, it is easy to operated, adjustable by aiding in temporarily The devices such as lifting pin, screw jack, the laser range finder installed on support, can make the docking of steel truss Holder joint simple, easy, apply Workman person is easy to use in terrestrial operation, safe and reliable.
Description of the drawings
Accompanying drawing is used for providing further understanding to of the present utility model, and constitutes a part for specification, with this practicality New embodiment is used to explain the utility model together, does not constitute to restriction of the present utility model.In the accompanying drawings:
Fig. 1 is overall structure diagram of the present utility model;
Fig. 2 is partial structural diagram of the present utility model;
In figure:1st, left section of steel truss;2nd, right section of steel truss;3rd, left side permanent support;4th, the right permanent support;5th, it is interim auxiliary Help adjustable support;6th, steel corbel;7th, steel hoop;8th, lifting pin;9th, crossbeam;10th, screw jack;11st, laser range finder.
Specific embodiment
Preferred embodiment of the present utility model is illustrated below in conjunction with accompanying drawing, it will be appreciated that described herein excellent Select embodiment to be merely to illustrate and explain the utility model, be not used to limit the utility model.
Embodiment 1
As shown in Figure 1-2, the utility model provides a kind of servicing unit for large span steel truss lifting, including a left side Section steel truss 1, right section of steel truss 2, left side permanent support 3, the right permanent support 4, interim auxiliary adjustable support 5, steel corbel 6, Steel hoop 7, lifting pin 8, crossbeam 9, screw jack 10 and laser range finder 11, the side of left section of steel truss 1 is provided with right section of steel Truss 2, the opposite side of left section of steel truss 1 is provided with left side permanent support 3, and the side of right section of steel truss 2 is provided with the right permanent support 4, left section of steel truss 1 and the bottom of right section of steel truss 3 are provided with crossbeam 9, left section of truss 1, right section of truss 2, left side permanent support 3, The right permanent support 4 and crossbeam 9 are used in supporting role, and the bottom of crossbeam 9 is provided with interim auxiliary adjustable support 2, interim auxiliary The side of adjustable support 5 is provided with steel hoop 7, and steel hoop 7 is used for the position of fixed interim auxiliary adjustable support 5 and the grade of lifting pin 8 Relation, interim auxiliary adjustable support 5 connects lifting pin 8 by steel hoop 7, and the bottom of lifting pin 8 is provided with hanging apparatus.
The bottom of lifting pin 8 is provided with screw jack 10, and the bottom of screw jack 10 is provided with steel corbel 6, and spiral is very heavy The side on top 10 is provided with laser range finder 11, by the lifting pin 8, screw jack 11 installed on interim auxiliary adjustable support 5, The grade device of laser range finder 11, can make the docking of steel truss Holder joint simple.
Screw jack 10 withstands one end of steel truss, and the side of each screw jack 10 is provided with laser range finder 11, Laser range finder 11 is conducive to more preferable reading, determines height value.
During specific work:After left side permanent support 3 and the right permanent support 4 is installed, will according to line setting Interim auxiliary adjustable support 5 is arranged between left side permanent support 3 and the right permanent support 4, while in interim auxiliary adjustable supporting The inside of frame 5 installs bracket 6 (steel corbel must be levelling, in one plane), steel hoop 7, lifting pin 8, and on top two are put Root crossbeam 9, adjusts jack 10, makes lifting pin withstand crossbeam 9, left section of steel truss 1 is lifted respectively and right section of steel truss 2 is placed on and faces When aid on the crossbeam of adjustable support, and to good axis, according to the reading of rangefinder, adjust jack, make left section of steel truss 1 Design height is reached with right section of steel truss 2, the connection work of joint is completed.
The beneficial effect that the utility model is reached is:The covering device is simple, low cost, be easy to buying, in adjustable support The inner side of post arranges four jack, and per two jack one end of steel truss is withstood, and each jack side arranges a survey Distance meter, according to the reading of rangefinder, adjusts at any time the flexible value of jack, reaches the height value of design, makes the truss of adjacent two section Holding level, completes the connection work of joint, by the supporting role of interim auxiliary adjustable support, can complete large span steel truss The lifting of frame, method is easy, and many high-level work can be changed into into ground is carried out, it is easy to operated, adjustable by aiding in temporarily The devices such as lifting pin, screw jack, the laser range finder installed on support, can make the docking of steel truss Holder joint simple, easy, apply Workman person is easy to use in terrestrial operation, safe and reliable.
Finally it should be noted that:Preferred embodiment of the present utility model is the foregoing is only, this is not limited to Utility model, although being described in detail to the utility model with reference to the foregoing embodiments, for those skilled in the art For, it still can modify to the technical scheme described in foregoing embodiments, or to which part technical characteristic Carry out equivalent.It is all it is of the present utility model spirit and principle within, any modification, equivalent substitution and improvements made etc., Should be included within protection domain of the present utility model.

Claims (3)

1. a kind of servicing unit for large span steel truss lifting, including left section of steel truss (1), right section of steel truss (2), the left side Permanent support (3), temporarily the right permanent support (4), auxiliary adjustable support (5), steel corbel (6), steel hoop (7), lifting pin (8), crossbeam (9), screw jack (10) and laser range finder (11), it is characterised in that the side of the left section of steel truss (1) The right section of steel truss (2) is provided with, the opposite side of the left section of steel truss (1) is provided with the left side permanent support (3), the right side The side of section steel truss (2) is provided with the right permanent support (4), the left section of steel truss (1) and the right section of steel truss (2) Bottom be equipped with the crossbeam (9), the bottom of the crossbeam (9) is provided with the interim auxiliary adjustable support (5), described interim The side of auxiliary adjustable support (5) is provided with the steel hoop (7), and the interim auxiliary adjustable support (5) is by the steel hoop (7) Connect the lifting pin (8), the bottom of the lifting pin (8) is provided with hanging apparatus.
2. it is according to claim 1 it is a kind of for large span steel truss lifting servicing unit, it is characterised in that the top The bottom of rising stem (8) is provided with the screw jack (10), and the bottom of the screw jack (10) is provided with the steel corbel (6)。
3. it is according to claim 2 it is a kind of for large span steel truss lifting servicing unit, it is characterised in that the spiral shell One end of steel truss is withstood in rotation jack (10), and the side of each screw jack (10) is provided with the laser range finder (11)。
CN201621028163.1U 2016-08-31 2016-08-31 A auxiliary device for hoist and mount of large -span steel truss Active CN206158205U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621028163.1U CN206158205U (en) 2016-08-31 2016-08-31 A auxiliary device for hoist and mount of large -span steel truss

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621028163.1U CN206158205U (en) 2016-08-31 2016-08-31 A auxiliary device for hoist and mount of large -span steel truss

Publications (1)

Publication Number Publication Date
CN206158205U true CN206158205U (en) 2017-05-10

Family

ID=58651579

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621028163.1U Active CN206158205U (en) 2016-08-31 2016-08-31 A auxiliary device for hoist and mount of large -span steel truss

Country Status (1)

Country Link
CN (1) CN206158205U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111101718A (en) * 2019-12-30 2020-05-05 倡创(上海)咨询管理事务所 Steel truss assembling system and construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111101718A (en) * 2019-12-30 2020-05-05 倡创(上海)咨询管理事务所 Steel truss assembling system and construction method

Similar Documents

Publication Publication Date Title
CN105178609B (en) Steel structure net rack high altitude bulk construction method
CN106760197B (en) Method for allowing error in installation of steel column structure
CN103216105B (en) Construction method of overhanging inhaul cable type hyperbolic glass curtain wall
CN106939707A (en) A kind of restricted clearance large-scale steel structure supporting platform from method for improving
CN101936536B (en) Method for constructing ship chimney section
CN103643800B (en) The erection & lift system of buckling-restrained bracing member and construction method thereof
CN103216112B (en) The disposable installing and fixing method of upper and lower steel column butt joint structural system
CN105442839A (en) Erecting method of cantilever structure formwork bent
CN110171768A (en) A kind of derrick tower and the crossing construction safeguard containing it
CN110792265B (en) Integral synchronous jacking equipment for large-span combined type overweight eccentric slope angle steel structure
CN106544959B (en) The construction method of king-tower lifting segment and bridge main tower saddle containing saddle
CN206158205U (en) A auxiliary device for hoist and mount of large -span steel truss
CN103276907B (en) Hoisting method for large-span hinged type herringbone steel arch
CN103043543A (en) Device for reinforcing tower crane in coastal zone
CN205591224U (en) Steel of area direction function protects a section of thick bamboo and transfers frame
CN201634347U (en) Ultra-large tower crane and lower support assembly thereof
CN204938800U (en) Tower crane rood beam basis
WO2023206851A1 (en) Drum joint installation method, steel reticulated shell, and assembly unit construction method
CN205400216U (en) Steel construction silo flip -chip construction auxiliary device
CN105464215A (en) Reverse construction method construction method of hanging structure incapable of being provided with vertical temporary support
CN203568661U (en) Built-in tail-sliding lifting lug
CN210457249U (en) Electric pole holding structure with self-jacking machine body
CN106245695B (en) The revolving platform of dumping plough and pylon assembly method
CN206034874U (en) Elevartor shaft combination formula integrally lift up operation platform
CN111705931A (en) Construction method of large-span grid structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant