CN206888561U - The Deformation control system of structure is reserved after Removing Columns - Google Patents

The Deformation control system of structure is reserved after Removing Columns Download PDF

Info

Publication number
CN206888561U
CN206888561U CN201720380704.5U CN201720380704U CN206888561U CN 206888561 U CN206888561 U CN 206888561U CN 201720380704 U CN201720380704 U CN 201720380704U CN 206888561 U CN206888561 U CN 206888561U
Authority
CN
China
Prior art keywords
column
enlarging section
bracket
model
jack
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720380704.5U
Other languages
Chinese (zh)
Inventor
吴如军
唐颖
陈树波
王敏
陈曦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Shengte Building Technology Development Co Ltd
Original Assignee
Guangzhou Shengte Building Technology Development Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Shengte Building Technology Development Co Ltd filed Critical Guangzhou Shengte Building Technology Development Co Ltd
Priority to CN201720380704.5U priority Critical patent/CN206888561U/en
Application granted granted Critical
Publication of CN206888561U publication Critical patent/CN206888561U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

The utility model provides a kind of Deformation control system of reserved structure after Removing Columns, solves the more special tightened up requirement that underpinning structure system span is big, section is small, rigidity is big, crack is small.The utility model provides a kind of Deformation control system of reserved structure after Removing Columns, including:Former beam, enlarging section beam, the first column, the second column, the 3rd column, bracket and jack;Wherein, the enlarging section beam is located at below the former beam;The former beam and the enlarging section beam run through the 3rd column between first column and second column, and the part that the 3rd column is located at the enlarging section beam lower end is dismounting section;The bracket is respectively on first column and second column, and each bracket is provided with the jack, and the jack is located at the lower section of the enlarging section beam.

Description

The Deformation control system of structure is reserved after Removing Columns
Technical field
It the utility model is related to Structures Reinforced Technique field in civil engineering, and in particular to pre- after a kind of Removing Columns Stay the Deformation control system of structure.
Background technology
At present, the development of construction industry goes to newly-built and maintenance and renovation by large-scale newly-built period and laid equal stress on period, some Inhering architecture all suffers from transformation reinforcing problem, and joist post is as a kind of preferable technical side for solving the problems, such as to expand Large Column Spacing Method is widely applied.Joist post is that roof truss pulls out post to support, joist is demolished walls and the general name of Removing Columns, is not tear open or tearing open less Implement to remove in the case of superstructure, change, an integrated technology of spreading pillar, including dependency structure reinforcement technique, Superstructure jack lifting technique and disconnected column technology etc..
Compared with traditional big flip transformation, Removing Columns method have on produce and live influence smaller, the transformation time is short, The advantages that cost, its shortcoming are that technical requirements are higher, and safety measure must be careful.
Utility model content
The utility model provides the Deformation control system that structure is reserved after a kind of Removing Columns, solve underpinning structure system across Degree is big, the more special tightened up requirement that section is small, rigidity is big, crack is small.
The utility model provides a kind of Deformation control system of reserved structure after Removing Columns, including:Former beam, enlarging section Beam, the first column, the second column, the 3rd column, bracket and jack;Wherein,
The enlarging section beam is located at below the former beam;
The former beam and the enlarging section beam run through described between first column and second column 3rd column, the part that the 3rd column is located at the enlarging section beam lower end are dismounting section;
For the bracket respectively on first column and second column, each bracket is provided with described thousand Jin top, the jack are located at the lower section of the enlarging section beam.
Preferably, the enlarging section beam is reinforced beam.
Preferably, two brackets are respectively positioned at first column and the equal-height position of second column.
Preferably, two brackets are respectively welded on first column and second column.
Brief description of the drawings
, below will be to embodiment in order to illustrate more clearly of the utility model embodiment or technical scheme of the prior art Or the required accompanying drawing used is briefly described in description of the prior art, it should be apparent that, drawings in the following description are only It is embodiment of the present utility model, for those of ordinary skill in the art, on the premise of not paying creative work, also Other accompanying drawings can be obtained according to the accompanying drawing of offer.
Fig. 1 be a kind of Removing Columns of the utility model after reserve structure deformation control method flow chart;
Fig. 2 be a kind of Removing Columns of the utility model after reserve structure Deformation control system structure chart.
Embodiment
The utility model provides the Deformation control system that structure is reserved after a kind of Removing Columns, solve underpinning structure system across Degree is big, the more special tightened up requirement that section is small, rigidity is big, crack is small.
Below in conjunction with the accompanying drawing in the utility model embodiment, the technical scheme in the embodiment of the utility model is carried out Clearly and completely describing, it is clear that described embodiment is only the utility model part of the embodiment, rather than whole Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are not under the premise of creative work is made The every other embodiment obtained, belong to the scope of the utility model protection.
Referring to Fig. 1, the technical scheme bag of the deformation control method of structure is reserved after a kind of Removing Columns of the utility model Include:
Step 101, enlarging section beam is set below Yuan Liang;
It is specifically as follows:The former beam is located at the first column with enlarging section beam composition particular beam, the particular beam And second between column and run through the 3rd column, the 3rd column is located at the part of the enlarging section beam lower end to remove Section.Enlarging section beam can be reinforced beam.
Step 102, bracket is set respectively on first column and second column, and the bracket is provided with very heavy Top;
It is specifically as follows:Two brackets are respectively welded on the first column and the second column, and the height one of two brackets Cause.The top of bracket is provided with jack, for jacking particular beam.
Step 103, particular beam both sides concrete is cut on the basis of reinforcing bar is retained;
In the present embodiment, particular beam both sides concrete is cut, the both sides of the particular beam are respectively vertical respectively close to described first Post and close second column.
Step 104, the jack is jacked, removes section;
In the present embodiment, jack jacking particular beam is extremely suitable with the 3rd column upper load, then removes the 3rd column On dismounting section.
Step 105, in the particular beam both sides again casting concrete.
In the present embodiment, the both sides of particular beam are respectively respectively close to first column and close to second column.
The palpus monitored over time of Removing Columns work progress.During the jacking of disconnected post, it is necessary to monitor whether post puts down Shifting, inclination and other structure change situations.The way for taking artificial, advanced electronic monitoring instrument, computer to be combined in construction. Labeling chi and foil gauge etc. are set on beam column during jacking, by the electronic instrument of pinpoint accuracy to jacking amount, malformation, whole Work progress etc. carries out displacement and inclination conditions monitoring, and the monitoring record of all appts is inputted into computer, passes through the remittance of computer Always, analysis determines the influence situation of Construction on Structure compared with artificial observation result, and malformation cracking is provided pre- It is alert, data support and foundation are provided to construct and handling decision-making, once pinpointing the problems, takes treatment measures in time, it is ensured that safety Construction.The electronic monitoring equipment of use includes:
(1) fracture width tester:Mainly for detection of and record, the quantitative inspection of the fracture width such as measurement structure surface Survey.
(2) electric slope angle instrument:In two horizontal levels of structure and this instrument is installed at the top of underpinning structure, it is using possessing MEMS acceleration transducer technologies, and using technologies such as signal acquisition, amplification and compensation, vertically and horizontally precision is 2 seconds for it, directly aobvious Show the function for the angle that angle value, measurement angle scope are wide, measurement deviates horizontal plane direction.
(3) electron displacement meter:In jacking, when it is mainly used in survey and underpined, the lifting of structure or settling amount.Display screen is Carry, measured value can be directly displayed.Parameter is changed by the menu on lower column.Port can directly connect printer field print some when Between segment data.
(4) static strain measuring system:Can automatically, it is accurate, reliable, quickly measure large scale structure, model and material stress The static strain stress value of multiple spot in experiment.Can be to the static power of multiple spot, pressure;The physical quantitys such as moment of torsion, displacement measure.
The utility model also provides a kind of Deformation control system of reserved structure after Removing Columns, including:Former beam 1, increase Cut section bar the 2, first column 3, the second column 4, the 3rd column 5, bracket 6 and jack 7;Wherein,
The enlarging section beam 2 is located at below the former beam 1, and enlarging section beam 2 can be reinforced beam;
The former beam 1 and the enlarging section beam 2 pass through between first column 3 and second column 4 The 3rd column 5 is worn, the part 51 that the 3rd column 5 is located at the lower end of enlarging section beam 2 is dismounting section;
The bracket 6 is respectively welded on first column 3 and second column 4, and bracket 6 is arranged on the first column 3 and second column 4 equal-height position, each bracket is provided with the jack 7, and the jack 7 is cut positioned at described increase The lower section of face beam 2.
As shown in the thick blackboard in Fig. 2 point, first the local concrete for cutting former beam 1 and enlarging section beam 2 both ends, is treated very heavy After the jacking of top 7, then casting concrete again.
Above example is only to illustrate the technical solution of the utility model, rather than its limitations;Although with reference to foregoing reality Example is applied the utility model is described in detail, it will be understood by those within the art that:It still can be to preceding State the technical scheme described in each embodiment to modify, or equivalent substitution is carried out to which part technical characteristic;And these Modification is replaced, and the essence of appropriate technical solution is departed from the spirit and model of various embodiments of the utility model technical scheme Enclose.

Claims (5)

1. the Deformation control system of structure is reserved after a kind of Removing Columns, it is characterised in that including:Former beam, enlarging section beam, One column, the second column, the 3rd column, bracket and jack;Wherein,
The enlarging section beam is located at below the former beam;
The former beam and the enlarging section beam run through the described 3rd between first column and second column Column, the part that the 3rd column is located at the enlarging section beam lower end are dismounting section;
Respectively on first column and second column, each bracket is provided with described very heavy the bracket Top, the jack are located at the lower section of the enlarging section beam.
2. system according to claim 1, it is characterised in that the enlarging section beam is reinforced beam.
3. system according to claim 1, it is characterised in that two brackets are located at first column and institute respectively State the equal-height position of the second column.
4. system according to claim 3, it is characterised in that one of them described bracket is welded on first column On.
5. system according to claim 3, it is characterised in that one of them described bracket is welded on second column On.
CN201720380704.5U 2017-04-12 2017-04-12 The Deformation control system of structure is reserved after Removing Columns Active CN206888561U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720380704.5U CN206888561U (en) 2017-04-12 2017-04-12 The Deformation control system of structure is reserved after Removing Columns

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720380704.5U CN206888561U (en) 2017-04-12 2017-04-12 The Deformation control system of structure is reserved after Removing Columns

Publications (1)

Publication Number Publication Date
CN206888561U true CN206888561U (en) 2018-01-16

Family

ID=61324250

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720380704.5U Active CN206888561U (en) 2017-04-12 2017-04-12 The Deformation control system of structure is reserved after Removing Columns

Country Status (1)

Country Link
CN (1) CN206888561U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106836845A (en) * 2017-04-12 2017-06-13 广州市胜特建筑科技开发有限公司 Beam is dragged to pull out the deformation control method and system that structure is reserved after post
CN112267672A (en) * 2020-10-09 2021-01-26 史润涛 Residential formwork's erection equipment is used in building engineering construction
CN114482592A (en) * 2021-11-26 2022-05-13 北京建工四建工程建设有限公司 Belt corridor joist post pulling transformation construction method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106836845A (en) * 2017-04-12 2017-06-13 广州市胜特建筑科技开发有限公司 Beam is dragged to pull out the deformation control method and system that structure is reserved after post
CN112267672A (en) * 2020-10-09 2021-01-26 史润涛 Residential formwork's erection equipment is used in building engineering construction
CN114482592A (en) * 2021-11-26 2022-05-13 北京建工四建工程建设有限公司 Belt corridor joist post pulling transformation construction method

Similar Documents

Publication Publication Date Title
CN106836845A (en) Beam is dragged to pull out the deformation control method and system that structure is reserved after post
CN104165807B (en) Large-deflection destruction testing device and method for prestressed concrete plate beam
CN112649046B (en) Overall pushing monitoring method for whole-process simulation tied arch bridge
CN206888561U (en) The Deformation control system of structure is reserved after Removing Columns
CN206512764U (en) A kind of horizontally loading test system for applying vertical load in stake top
CN102808383B (en) Curved bridge counter-slope jacking construction process
CN106120559B (en) A kind of bridge limited bracket construction method and bridge
CN110230328A (en) Pile foundation underpinning System information construction electronic monitoring method
CN204738324U (en) Clump of piles basis single pile vertical bearing capacity detecting system
CN109208488B (en) High pier pre-pressing device with high combined weight at high altitude and construction method thereof
CN103758359B (en) A kind of safe and reliable joist post construction system and construction method thereof
CN105423880B (en) A kind of method for hanging main push-towing rope measurement deflection of bridge span
CN102927944B (en) Land movement measuring method and device in large-scale experiment
CN109238606A (en) A kind of loading detection device and its measuring method suitable for bridge main beam
CN113323446A (en) Building construction supporting device, monitoring system and dismounting method
CN100465578C (en) Large-scale truss type stake leg segmentation data detection method
CN210376011U (en) Large-area on-site direct shear test equipment
CN206607613U (en) A kind of bored concrete pile displacement acquisition device
CN205857744U (en) A kind of large-span concrete floor flatness control system
CN112144422B (en) Construction method for dismantling temporary support system of large-span ultra-wide continuous steel box girder
CN211696331U (en) Cast-in-place support strain monitoring system
CN209468793U (en) A kind of static test settlement observer for exempting from datum line beam
CN110205944A (en) A kind of observation platform device suitable for Large Span Bridges girder steel construction survey
CN208920996U (en) Bridge jacking auxiliary positioning monitoring device
CN207351817U (en) A kind of device for fast detecting of construction site large bridge bracket damage

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant