CN206886566U - Hanging operating platform under a kind of tower crane attachment installation - Google Patents

Hanging operating platform under a kind of tower crane attachment installation Download PDF

Info

Publication number
CN206886566U
CN206886566U CN201720585155.5U CN201720585155U CN206886566U CN 206886566 U CN206886566 U CN 206886566U CN 201720585155 U CN201720585155 U CN 201720585155U CN 206886566 U CN206886566 U CN 206886566U
Authority
CN
China
Prior art keywords
tower crane
operating platform
frame
stress
skeleton
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720585155.5U
Other languages
Chinese (zh)
Inventor
贾文月
李明
吕豪
张敏
梁新利
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
No7 Building Engineering Co Ltd Beijing Urban Construction Group
Original Assignee
No7 Building Engineering Co Ltd Beijing Urban Construction Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by No7 Building Engineering Co Ltd Beijing Urban Construction Group filed Critical No7 Building Engineering Co Ltd Beijing Urban Construction Group
Priority to CN201720585155.5U priority Critical patent/CN206886566U/en
Application granted granted Critical
Publication of CN206886566U publication Critical patent/CN206886566U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Movable Scaffolding (AREA)

Abstract

Hanging operating platform under being installed the utility model discloses a kind of tower crane attachment, including the framework on standard section of tower crane, the framework are square, and the framework is made up of hanging frame unit under four, and frame unit is respectively on two groups of square opposite side;The frame unit is from top to bottom provided with protective fence, scaffold board and at least three stress frames;The scaffold board bottom surface is fixedly connected with stress frame, and the stress frame parallel interval is set, and is fixedly connected between stress frame by being arranged on the connecting rod of vertical skeleton lateral surface.Hanging operating platform is set up very simple under attachment installation on standard section of tower crane, installation and removes all convenient every time, globality is strong, is easy to set up lifting;The substantial amounts of material, time, artificial has been saved, has greatly reduced construction cost, project construction efficiency high, short time limit, only needs several hours to complete, installation difficulty is low, is not influenceed that stability is high, reasonable stress by tower crane height.

Description

Hanging operating platform under a kind of tower crane attachment installation
Technical field
Technical field of building construction is the utility model is related to, it is flat that particularly a kind of tower crane attachment peace holds hanging operation Platform.
Background technology
Tower crane is the conventional crane gear in construction site, for the handling such as construction material such as reinforcing bar, truss, with its retractility By force, the advantages of bearing capacity is big plays increasing effect in the realm of building construction.Often need to adhere in high-level structure construction Tower crane installation needs, and sets up operating platform using steel pipe, putting up platform often wastes the substantial amounts of engineering time, drags slow integral construction Progress.
Such as the patent of Application No. 201620049940.4, a kind of tower crane attachment structure is disclosed, it is flat in operation It is provided with four mounting seats on platform, each mounting seat has base and support column straight up, is provided with support column and standard The shank that grafting coordinates is saved, upper installing hole and lower mounting hole is plugged in together and completes stage+module during construction.This construction party Formula, potential safety hazard, grafting complex operation be present.At present, the operating platform for adhering to tower crane is typically that cannot dismantle recycling. Existing subject matter is:Set up using steel pipe, complicated, installation and dismounting every time all consumes substantial amounts of material, time, people Work, construction cost is added, project construction efficiency is low, long in time limit, potential safety hazard is big.
Utility model content
In view of the deficienciess of the prior art, the purpose of this utility model be to provide it is hanging under a kind of tower crane attachment installation Operating platform.The time that installation needs to expend is greatly reduced, is articulated on standard section of tower crane, construction is simple, operation peace Entirely, the platform set up is fixed, reusable.
To achieve the above object, the utility model adopts the following technical scheme that:
Hanging operating platform under a kind of tower crane attachment installation, including the framework on standard section of tower crane, the framework To be square, the framework is made up of hanging frame unit under four, and frame unit is respectively on two groups of square opposite side;
The frame unit is from top to bottom provided with protective fence, scaffold board and at least three stress frames;The protection Fence is vertically installed on three edges of the scaffold board away from standard section of tower crane, is bonded the protective fence and is provided with skirt Plate;
The stress frame includes horizontal skeleton and vertical skeleton, and the vertical skeleton upper vertical is welded on horizontal skeleton On, the horizontal skeleton is vertically welded with edge close to standard section of tower crane one end, and the edge be arranged in parallel with vertical skeleton, and Neck is formed with vertical skeleton, the standard section of tower crane middle beam clamping enters neck;The vertical skeleton bottom is close to tower crane Standard knot side is vertically welded with carrier block, and the carrier block is parallel with horizontal skeleton, under the carrier block and standard section of tower crane End floor beam is fixedly connected;
The scaffold board bottom surface is fixedly connected with stress frame, and the stress frame parallel interval is set, between stress frame It is fixedly connected by the connecting rod for being arranged on vertical skeleton lateral surface.
Further, 1400 mm of the vertical backbone length~1550mm, horizontal skeleton length 600mm~750mm.
Further, connected between the frame unit by fastener.
Further, the scaffold board is punching press Steel scaffold board.
Further, the protective fence height 1000mm~1200mm, width 480mm~550mm.
Further, the skirting board is welded and fixed with protective fence, and the skirting board is thickness 1mm steel plate.
Further, the protective fence is welded using 20mm × 20mm square steel tubes.
Further, it is provided with escape way between the frame unit and building.
Preferably, in certain embodiments, the connecting rod 5 can be 50mm × 5mm angle steel.
Preferably, in certain embodiments, the stress frame 8 is welded using channel-section steel.
Preferably, in certain embodiments, the length of edge 3 is 200mm.
Preferably, in certain embodiments, the length of carrier block 4 is 100mm.
The utility model has the characteristics that and beneficial effect compared with prior art:
(1), overcome at present attachment tower crane operating platform it is non-dismountable, can not reuse, set up place materials zero Dissipate the problem of mixed and disorderly, lifting is uneasy congruent.
(2), hanging operating platform is set up very simple under attachment installation on standard section of tower crane, installation and removes all every time Convenient, globality is strong, is easy to set up lifting.
(3), the substantial amounts of material, time, artificial has been saved, has greatly reduced construction cost, project construction efficiency high, duration It is short, only need several hours to complete.
(4), installation difficulty is low, is not influenceed by tower crane height, on standard section of tower crane under hanging operation it is flat Platform stability is high, reasonable stress, does not interfere with resistance to overturning during tower crane work.
The utility model can be widely applied in the installation of tower crane attachment operating platform.
Other features and advantages of the utility model will illustrate in the following description, and partly from specification Become apparent, or understood by implementing the utility model.Main purpose and further advantage of the present utility model can lead to Specifically noted scheme in specification, claims is crossed to realize and obtain.
Brief description of the drawings
The utility model is described in more detail below in conjunction with the accompanying drawings.
Fig. 1 is hanging operating platform whole structure figure under being installed on standard section of tower crane.
Fig. 2 is the structural representation of frame unit.
Fig. 3 is the structural representation of stress frame.
Reference:1- standard section of tower crane, 2- frame units, 3- edges, 4- carrier blocks, 5- connecting rods, 6- pin hands Plate, 7- protective fences, 8- stress frames, 81- horizontal skeletons, the vertical skeletons of 82-, 9- skirting boards
Embodiment
In order that the purpose of this utility model, technical scheme and advantage are more clearly understood, below in conjunction with accompanying drawing and implementation Example, the utility model is further elaborated.It should be appreciated that specific embodiment described herein is only explaining this Utility model, it is not used to limit the utility model.
The utility model provides hanging operating platform under a kind of tower crane attachment installation, hanging under being installed on standard section of tower crane 1 The whole structure figure of operating platform as shown in figure 1, including the framework on standard section of tower crane 1, framework be it is square, framework by Hanging frame unit 2 forms under four, and the frame unit 2 on two groups of square opposite side, leads between frame unit 2 respectively Cross bolt connection.
The structural representation of frame unit 2 is as shown in Figure 2.The frame unit 2 be from top to bottom provided with protective fence 7, Scaffold board 6 and stress frame 8;The protective fence 7 is vertically installed on three edges of the scaffold board 6 away from standard section of tower crane 1, Fitting protective fence 7 is provided with skirting board 9, protective fence 7 height 1100mm, width 500mm, protective fence 7 using 20mm × 20mm square steel tubes are welded.The scaffold board 6 is punching press Steel scaffold board, and the skirting board 9 uses titanium dioxide with protective fence 7 Carbon gas shielded arc welding is welded and fixed, and skirting board 9 is thickness 1mm steel plate.
As shown in figure 3, the stress frame 8 includes horizontal skeleton 81 and vertical skeleton 82, the length of horizontal skeleton 81 700mm, the vertical length 1500mm of skeleton 82.The vertical upper vertical of skeleton 82 is welded on horizontal skeleton 81, and horizontal skeleton 81 leans on Nearly one end of standard section of tower crane 1 is vertically welded with edge 3, and the edge 3 be arranged in parallel with vertical skeleton 82, and with vertical skeleton 82 Neck is formed, the middle beam clamping of standard section of tower crane 1 enters neck;The vertical bottom of skeleton 82 is close to the side of standard section of tower crane 1 Carrier block 4 is vertically welded with, the carrier block 4 is parallel with horizontal skeleton 81, and the carrier block 4 is horizontal with the lower end of standard section of tower crane 1 Beam is fixedly connected.
The bottom surface of scaffold board 6 is set using carbon dioxide gas arc welding welding stress frame 8, the parallel interval of stress frame 8, It is fixedly connected between stress frame 8 by being arranged on the connecting rod 5 of the vertical lateral surface of skeleton 82, during construction, the number of stress frame 8 Amount determines according to actual demand, general to be no less than 3.First stress frame 8 can be connected in turn one with two connecting rods 5 Rise, then weld the stress frame 8 and the bottom surface of scaffold board 6., can be with order to further improve the stability of stress frame 8 Weld more than two connecting rod 5., can be with bolt connection between connecting rod 5 and stress frame 8 for convenient disassembly.The company Extension bar 5 can be 50mm × 5mm angle steel.
After with said structure feature, with reference to Fig. 1 to Fig. 3, field conduct can be carried out by procedure below:
First, stress frame 8 is welded in installation on ground, the quantity of stress frame 8 determines according to actual demand, general frame At least provided with 3 stress frames 8 on frame unit 2.Scaffold board 6 is set up on stress frame 8, protective fence 7 is set, installs skirt additional Plate 9, a frame unit 2 is completed, for the sake of security, the height 1100mm of protective fence 7 on frame unit 2, width 500mm, protective fence 7 can set intermediate rail in 300mm position, protection network be installed additional, to increase the intensity of protective fence 7. Scaffold board 6 can select punching press Steel scaffold board;
Specifically, the edge 3 of frame unit 2 is connected on the crossbeam of standard section of tower crane 1, is welded and fixed, carrier block 4 and tower Hang 1 time end floor beam of standard knot to be fixedly connected, frame unit 2 is fixed on standard section of tower crane 1, providing construction for operating personnel makees Industry platform, reasonable stress, Stability Analysis of Structures.Connected between frame unit 2 by fastener(Can be that four connecting screws mutually interconnect Connect, can also be fastener)Hanging frame unit 2 under four is set to enclose the surrounding shape in standard section of tower crane 1 in setting height assembly Into an entirety.
So far, consolidate quickly to hang under whole operation platform and be placed on standard section of tower crane 1.
Escape way can also be set between frame unit 2 and building, and frame structure one end of escape way is arranged on On frame unit 2, the other end is by being fixedly connected on skin, erection, safety net, fence and the frame of escape way The setting of body passage is the conventional construction mode of this area, no longer redundant later herein.
The utility model is easy for installation, safe, fixed, and there is simple for production, peace to tear open, and quick, cost is low, can The advantages of recycling.
It the foregoing is only the preferable embodiment of the utility model, but the scope of protection of the utility model not office Be limited to this, change that any one skilled in the art is expected in the technical scope that the utility model discloses or Replace, should all cover within the scope of protection of the utility model.

Claims (8)

1. hanging operating platform under a kind of tower crane attachment installation, it is characterised in that including installed in standard section of tower crane(1)On frame Frame, the framework are square, and the framework is by hanging frame unit under four(2)Composition, frame unit(2)Respectively positioned at square Two groups of opposite side on;
The frame unit(2)From top to bottom it is provided with protective fence(7), scaffold board(6)With at least three stress frames(8); The protective fence(7)It is vertically installed at the scaffold board(6)Away from standard section of tower crane(1)Three edges on, described in fitting Protective fence(7)It is provided with skirting board(9);
The stress frame(8)Including horizontal skeleton(81)With vertical skeleton(82), the vertical skeleton(82)Upper vertical is welded It is connected on horizontal skeleton(81)On, the horizontal skeleton(81)Close to standard section of tower crane(1)One end is vertically welded with edge(3), institute State edge(3)With vertical skeleton(82)Be arranged in parallel, and with vertical skeleton(82)Form neck, the standard section of tower crane(1)In Portion's crossbeam clamping enters neck;The vertical skeleton(82)Bottom is close to standard section of tower crane(1)Side is vertically welded with carrier block (4), the carrier block(4)With horizontal skeleton(81)It is parallel, the carrier block(4)With standard section of tower crane(1)Lower end floor beam is fixed Connection;
The scaffold board(6)Bottom surface is fixedly connected with stress frame(8), the stress frame(8)Parallel interval is set, stress frame (8)Between by being arranged on vertical skeleton(82)The connecting rod of lateral surface(5)It is fixedly connected.
2. operating platform as claimed in claim 1, it is characterised in that the vertical skeleton(82)The mm of length 1400~ 1550mm, horizontal skeleton(81)Length 600mm~750mm.
3. operating platform as claimed in claim 1, it is characterised in that the frame unit(2)Between connected by fastener.
4. operating platform as claimed in claim 1, it is characterised in that the scaffold board(6)For punching press Steel scaffold board.
5. operating platform as claimed in claim 1, it is characterised in that the protective fence(7)Highly 1000 mm~ 1200mm, width 480mm~550mm.
6. operating platform as claimed in claim 1, it is characterised in that the skirting board(9)With protective fence(7)Welding is solid It is fixed, the skirting board(9)For thickness 1mm steel plate.
7. operating platform as claimed in claim 1, it is characterised in that the protective fence(7)Using 20mm × 20mm square steel Pipe is welded.
8. operating platform as claimed in claim 1, it is characterised in that the frame unit(2)It is provided between building Escape way.
CN201720585155.5U 2017-05-24 2017-05-24 Hanging operating platform under a kind of tower crane attachment installation Active CN206886566U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720585155.5U CN206886566U (en) 2017-05-24 2017-05-24 Hanging operating platform under a kind of tower crane attachment installation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720585155.5U CN206886566U (en) 2017-05-24 2017-05-24 Hanging operating platform under a kind of tower crane attachment installation

Publications (1)

Publication Number Publication Date
CN206886566U true CN206886566U (en) 2018-01-16

Family

ID=61320045

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720585155.5U Active CN206886566U (en) 2017-05-24 2017-05-24 Hanging operating platform under a kind of tower crane attachment installation

Country Status (1)

Country Link
CN (1) CN206886566U (en)

Similar Documents

Publication Publication Date Title
CN212534174U (en) Raft foundation steel bar supporting tool
CN205775852U (en) A kind of active force conversion support for steel structure support moulding bed top
CN107178203A (en) A kind of planar dimension and adjustable for height operating platform
CN206646835U (en) It is a kind of from hoisting type steel structure slipping measure support
CN201793330U (en) Gantry hanger frame device
CN206886566U (en) Hanging operating platform under a kind of tower crane attachment installation
CN105952129B (en) A kind of elevator combined type entirety lifting operation platform and its construction method
CN209741895U (en) Connection structure of assembled elevator steel construction and base
CN208618838U (en) A kind of safety device
CN206942160U (en) Steel bar truss floor support plate lifting device
CN206616840U (en) A kind of portable construction operation platform
CN206957175U (en) A kind of planar dimension and adjustable for height operating platform
CN206646858U (en) The double column construction elevator protection canopy of construction site assembled, tool-type
CN206428986U (en) A kind of detachable turnover type support jig
CN206144127U (en) Simple and easy butt clamp integral type operation platform
CN201052950Y (en) Crane
CN205472340U (en) People's passageway on instrument formula tower crane
CN209723570U (en) Steel column docking installation operation platform
CN209384617U (en) Multi-functional construction operation platform for vertical hoistway
CN208981152U (en) A kind of fast-type high-speed rail Bridge Pier Construction hanging basket mounting platform
CN210917735U (en) Supporting jig frame structure for large-span prestressed inhaul cable structure
CN208347279U (en) A kind of building faces side structural column construction protecting rack
CN108824214A (en) A kind of fast-type high-speed rail Bridge Pier Construction hanging basket mounting platform and application method
CN209369298U (en) A kind of suspension centre truss of attachment type raise scaffold
CN206220547U (en) A kind of operating platform for steel structure column installation

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant