CN206873965U - It is a kind of to build the elevator opening safety protective door of building - Google Patents

It is a kind of to build the elevator opening safety protective door of building Download PDF

Info

Publication number
CN206873965U
CN206873965U CN201720414828.0U CN201720414828U CN206873965U CN 206873965 U CN206873965 U CN 206873965U CN 201720414828 U CN201720414828 U CN 201720414828U CN 206873965 U CN206873965 U CN 206873965U
Authority
CN
China
Prior art keywords
elevator
building
plate
clamping part
sill
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720414828.0U
Other languages
Chinese (zh)
Inventor
陈力
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201720414828.0U priority Critical patent/CN206873965U/en
Application granted granted Critical
Publication of CN206873965U publication Critical patent/CN206873965U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Elevator Door Apparatuses (AREA)

Abstract

The elevator opening safety protective door of building is being built the utility model discloses a kind of, the protective plate vertically spliced successively including polylith, the protective plate includes rectangular framework and the protection network being laid in framework, the framework includes two vertically arranged longerons, and the entablature and sill being connected on two longerons;The entablature has towards the side of elevator upwardly extends the upper plate to be formed, and the upper end edge of the upper plate is to away from the first L-shaped clamping part of the direction of elevator bending;The sill has the lower plate being downwardly extending away from the side of elevator, and the lower end of the lower plate bends the second L-shaped clamping part towards the direction of elevator;The side that two longerons mutually deviate from respectively is welded with 2 installing plates, has on the installing plate due to the bolt hole of installation bolt.The utility model has easy disassembling, and convenient in carrying is time saving and energy saving, is advantageous to save material, reduces cost, it is applied widely the advantages that.

Description

It is a kind of to build the elevator opening safety protective door of building
Technical field
Construction safety protection technology field is the utility model is related to, in particular to a kind of in the elevator hole for building building Mouth safety protective door.
Background technology
The all very universal presence elevator shaft of modern construction engineering, for high-rise and Super High elevator door opening in work progress Middle progress security protection is the trouble free service that job site must be carried out.But how efficiently elevator door opening to be carried out Security protection, difficulty of construction is reduced, reduce construction cost, become a practical problem that must be solved.
In order to efficiently solve elevator door opening facade security protection problem, generally use elevator door opening dress safety is anti- The method that guard rail rod is completely hung safety net or is fixed on B16 reinforcement welding finished product protective doors in elevator door opening both walls carries out safety Protection, but the method for completely hanging with safety guide rail safety net, it mounts and dismounts trouble, and vertical rod and horizontal pole length be not during installation Consistent or installer installs horizontal problem and causes that vertical rod is not vertical, horizon bar is not horizontal, causes safe protective railing unsightly, And installation or removal cost is higher, finished product turnover installation can not be made.Though the latter can carry out turnover installation, reinforcing bar amount is consumed Greatly, safe protective railing is heavier, and bar-mat reinforcement space is larger, and the small articles such as flitch, short steel pipes, fastener easily drop to elevator shaft It is interior.
Utility model content
For above-mentioned the deficiencies in the prior art, technical problem to be solved in the utility model is:One kind how is provided to tear open Dressing is easy, convenient in carrying, time saving and energy saving, is advantageous to save material, reduce cost is building the elevator opening security protection of building Door.
In order to solve the above-mentioned technical problem, the utility model employs following technical scheme:
It is a kind of to build the elevator opening safety protective door of building, it is characterised in that vertically to splice successively including polylith Protective plate, the protective plate include rectangular framework and the protection network being laid in framework, and the framework includes two and erected To the longeron of setting, and the entablature and sill being connected on two longerons;The entablature is towards elevator Side, which has, upwardly extends the upper plate to be formed, and the upper end edge of the upper plate is L-shaped to being bent away from the direction of elevator First clamping part;The sill has the lower plate that is downwardly extending away from the side of elevator, under the lower plate Hold and the second L-shaped clamping part is bent towards the direction of elevator;The side that two longerons mutually deviate from respectively is welded with 2 peaces Loading board, have due to the bolt hole of installation bolt on the installing plate.
The width of elevator door is usually 800mm~1100mm, is highly 2100mm, if safety protective door is done into integral knot Structure, the size is necessarily greater than, after stair completion is removed, security protection goalkeeper should not take out of out of building.Using above-mentioned knot Structure, safety protective door is arranged to the protective plate that polylith vertically splices successively.So, after building completion, safety can be prevented Shield door is split as the less protective plate of size, is directly carried away via elevator, is easy to the recycling of protective plate, is advantageous to carry Usury turnover rate, save material and repeat the cost of manufacture.During installation, by it is prefabricated outside the venue or by other building sites turn The protective plate moved past, which is transported to, to be built in building, is installed successively from bottom to top, without field fabrication, is advantageous to carry The efficiency of height installation, be advantageous to shorten the duration, it is time saving and energy saving.Further, since there is the first buckle of outward bending on entablature Portion, there is the second clamping part to bend inwards on sill, so, can be by the second clamping part card of protective plate above It is connected on the first clamping part of the adjacent protective plate in lower section so that the safety protective door after installation is overall more attractive in appearance.
Further, the both ends of first clamping part are respectively welded with one piece of baffle plate, the spacing of two pieces of baffle plates and institute The length for stating the second clamping part is consistent.
So, two neighboring protective plate can be made to be located in the both sides of width on same vertical curve, installation positioning is more Add conveniently.
Further, the longeron, entablature and sill are made using angle steel, and the protection network is prismatic reinforcing bar Net.
Further, the length of the longeron is 500~900mm;The length of the entablature and sill is 1200mm.
So, protective plate can be made to be adapted to the protection requirements of most of elevator opening, improve applicability.
In summary, the utility model has easy disassembling, and convenient in carrying is time saving and energy saving, is advantageous to save material, reduces Cost, it is applied widely the advantages that.
Brief description of the drawings
Fig. 1 is the structural representation of the utility model embodiment.
Fig. 2 is the first clamping part of two neighboring protective plate and the attachment structure schematic diagram of the second clamping part in Fig. 1.
Embodiment
The utility model is described in further detail below in conjunction with the accompanying drawings.
During specific implementation:As depicted in figs. 1 and 2, it is a kind of to build the elevator opening safety protective door of building, including polylith edge The vertical protective plate 1 spliced successively, the protective plate 1 include rectangular framework and the protection network being laid in framework, institute Stating framework includes two vertically arranged longerons 11, and the entablature 12 and sill 13 being connected on two longerons; The entablature 12 has towards the side of elevator upwardly extends the upper plate to be formed, the upper end edge of the upper plate to away from The direction of elevator bends the first L-shaped clamping part;The sill 13 has away from the side of elevator extends downwardly shape Into lower plate, the lower end of the lower plate bends the second L-shaped clamping part towards the direction of elevator;Two longerons The side that 11 phases deviate from respectively is welded with 2 installing plates, has on the installing plate due to the bolt hole of installation bolt.
The width of elevator door is usually 800mm~1100mm, is highly 2100mm, if safety protective door is done into integral knot Structure, the size is necessarily greater than, after stair completion is removed, security protection goalkeeper should not take out of out of building.Using above-mentioned knot Structure, safety protective door is arranged to the protective plate that polylith vertically splices successively.So, after building completion, safety can be prevented Shield door is split as the less protective plate of size, is directly carried away via elevator, is easy to the recycling of protective plate, is advantageous to carry Usury turnover rate, save material and repeat the cost of manufacture.During installation, by it is prefabricated outside the venue or by other building sites turn The protective plate moved past, which is transported to, to be built in building, is installed successively from bottom to top, without field fabrication, is advantageous to carry The efficiency of height installation, be advantageous to shorten the duration, it is time saving and energy saving.Further, since there is the first buckle of outward bending on entablature Portion, there is the second clamping part to bend inwards on sill, so, can be by the second clamping part card of protective plate above It is connected on the first clamping part of the adjacent protective plate in lower section so that the safety protective door after installation is overall more attractive in appearance.
During implementation, the both ends of first clamping part are respectively welded with one piece of baffle plate, the spacing of two pieces of baffle plates with it is described The length of second clamping part is consistent.
So, two neighboring protective plate can be made to be located in the both sides of width on same vertical curve, installation positioning is more Add conveniently.
During implementation, the longeron 11, entablature 12 and sill 13 are made using angle steel, and the protection network is prismatic steel Muscle net.
When it is implemented, the length of the longeron 11 is 700mm;The length of the entablature 12 and sill 13 is 1200mm, the safety protective door are assembled by 3 pieces of protective plates.
So, protective plate can be made to be adapted to the protection requirements of most of elevator opening, improve applicability.
Preferred embodiment of the present utility model is the foregoing is only, it is all at this not using the utility model as limitation All any modification, equivalent and improvement made within the spirit and principle of utility model etc., should be included in the utility model Protection domain within.

Claims (4)

1. a kind of building the elevator opening safety protective door of building, it is characterised in that vertically splices successively including polylith anti- Backplate (1), the protective plate (1) include rectangular framework and the protection network being laid in framework, and the framework includes two The vertically arranged longeron of root (11), and the entablature (12) and sill (13) being connected on two longerons;On described Crossbeam (12) has towards the side of elevator upwardly extends the upper plate to be formed, and the upper end edge of the upper plate is to away from elevator The direction of well bends the first L-shaped clamping part;The sill (13) has away from the side of elevator to be downwardly extending Lower plate, the lower end of the lower plate bends the second L-shaped clamping part towards the direction of elevator;Two longerons (11) side mutually deviated from is respectively welded with 2 installing plates, has on the installing plate due to the bolt hole of installation bolt.
2. building the elevator opening safety protective door of building as claimed in claim 1, it is characterised in that first clamping part Both ends be respectively welded with one piece of baffle plate, the spacing of two pieces of baffle plates is consistent with the length of second clamping part.
3. building the elevator opening safety protective door of building as claimed in claim 1, it is characterised in that the longeron (11), Entablature (12) and sill (13) are made using angle steel, and the protection network is prismatic bar-mat reinforcement.
4. building the elevator opening safety protective door of building as claimed in claim 1, it is characterised in that the longeron (11) Length is 500~900mm;The length of the entablature (12) and sill (13) is 1200mm.
CN201720414828.0U 2017-04-18 2017-04-18 It is a kind of to build the elevator opening safety protective door of building Expired - Fee Related CN206873965U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720414828.0U CN206873965U (en) 2017-04-18 2017-04-18 It is a kind of to build the elevator opening safety protective door of building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720414828.0U CN206873965U (en) 2017-04-18 2017-04-18 It is a kind of to build the elevator opening safety protective door of building

Publications (1)

Publication Number Publication Date
CN206873965U true CN206873965U (en) 2018-01-12

Family

ID=61343978

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720414828.0U Expired - Fee Related CN206873965U (en) 2017-04-18 2017-04-18 It is a kind of to build the elevator opening safety protective door of building

Country Status (1)

Country Link
CN (1) CN206873965U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108773052A (en) * 2018-06-26 2018-11-09 平湖市浩鑫塑胶有限公司 Safety device for bottle blowing machine

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108773052A (en) * 2018-06-26 2018-11-09 平湖市浩鑫塑胶有限公司 Safety device for bottle blowing machine

Similar Documents

Publication Publication Date Title
CN104196222B (en) The suspension scaffold of tools type section steel builder's jack
CN206408952U (en) A kind of construction adhesion type lifts discharging platform
CN106400691B (en) Anti-collision wall mould bases integrated construction technique
CN110259090B (en) Construction method of novel pull-up type overhanging scaffold
CN204001652U (en) The portable exterior wall operating platform of fabricated shear wall structure
CN106013774B (en) A kind of sliding formwork flexibility platform device for being suitble to dispatch
CN201786037U (en) Temporary safety protection door for elevator opening in building construction
CN202509754U (en) High-altitude steel structure node construction working platform
CN206873965U (en) It is a kind of to build the elevator opening safety protective door of building
CN103758045B (en) Box girder wet joint formwork construction method under space limitation condition
CN204282797U (en) Upset isolation walkway board
CN211341686U (en) Hanging basket support system
CN206917309U (en) Provisional elevator door opening mouth protecting device
CN108487621A (en) Assembled movement shield cage and its construction method
CN205617759U (en) Overhanging type mobile scaffold
CN111236603B (en) Comprehensive construction method for steel plate mesh overhanging scaffold
CN208380058U (en) Removable hanging basket suspension scaffold
CN205776197U (en) Idle discharge frame is hung in a kind of rock anchorage beam concrete construction
CN203200719U (en) Hanging type slope pouring template device
CN110388096A (en) A kind of structure and construction method flexibly constructed about coke oven booth
CN215670929U (en) Shear force wall elevator shaft assembled operation platform
CN201649607U (en) Overhung-type outer wall scaffold
CN111608376B (en) Comprehensive construction method for shaping component
CN211037760U (en) Novel instrument formula elevartor shaft construction operation platform
CN110306784A (en) A kind of aluminum tunnel modular system and its operating method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180112

Termination date: 20180418

CF01 Termination of patent right due to non-payment of annual fee