CN206860218U CN201720677674.4U CN201720677674U CN206860218U CN 206860218 U CN206860218 U CN 206860218U CN 201720677674 U CN201720677674 U CN 201720677674U CN 206860218 U CN206860218 U CN 206860218U
Authority
CN
China
Prior art keywords
steel
support frame
station
shield machine
space
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720677674.4U
Other languages
Chinese (zh)
Inventor
黄明峰
黄宇
林金华
何剑光
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Highway Xiamen Engineering Co Ltd
CCCC First Highway Engineering Co Ltd
Original Assignee
CCCC First Highway Engineering Co Ltd
CCCC First Highway Xiamen Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Highway Engineering Co Ltd, CCCC First Highway Xiamen Engineering Co Ltd filed Critical CCCC First Highway Engineering Co Ltd
Priority to CN201720677674.4U priority Critical patent/CN206860218U/en
Application granted granted Critical
Publication of CN206860218U publication Critical patent/CN206860218U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The utility model belongs to subway construction technical field, the interim station support frame in space is integrally originated more particularly to a kind of shield machine, described support frame includes I-steel and temporary steel support structure, I-steel is fixedly connected perpendicular to the side wall at station and one end by floor with the side wall at station along its length, the lower section of the I-steel other end is provided with can be along the temporary steel support structure that I-steel length direction moves, the temporary steel support structure contact perpendicular to the ground, the utility model is simple in construction, easy to use.

Description

A kind of shield machine integrally originates the interim station support frame in space
Technical field
The utility model belongs to subway construction technical field, and in particular to a kind of shield machine integrally originates the interim car in space Stand support frame.
Background technology
For subway engineering, the construction in station and section has certain common factor, especially with shield method section more Very, shield method section is originated typically using station termination as originating terminal, and because Shield-type machinery size is larger, shield machine underground is overall Originate, the length and width to station originating terminal have certain requirement.During practice of construction, due to architectural design, structure , often there is station platform layer central post in the influence of each factor such as design, construction speed and the distance between side wall is too small, shield Structure machinery can not be positioned in the bottom plate of station, and therefore, constructor often carries out shield running tunnel tunneling construction using separate launching, But separate launching technology construction cost is high, and ground site requirements area is big, construction period length, therefore prior art needs further Improvement.
The content of the invention
The purpose of this utility model is to provide a kind of simple in construction, and shield machine easy to use integrally originates facing for space When station support frame.
Based on above-mentioned purpose, the utility model adopts the following technical scheme that:
A kind of shield machine integrally originates the interim station support frame in space, and described support frame includes I-steel and faced When steel support structure, I-steel passes through floor and the side at station perpendicular to the side wall at station and one end along its length Wall is fixedly connected, and the lower section of the I-steel other end is provided with can be along the temporary steel support structure that I-steel length direction moves, should The contact perpendicular to the ground of temporary steel support structure.
Further, described support frame is vertically arranged between upper beam AT STATION and ground, and the support frame is number Individual and along station upper beam length direction uniformly arranges at equal intervals.
Further, described temporary steel support structure is steel pipe.
Further, described floor includes steel plate, several through holes passed through for built-in fitting is uniformly distributed on the steel plate, in advance Embedded part is stretched into inside flank wall body through through hole, and steel plate and flank wall, which are shown consideration for, to be closed, and is additionally provided with two transverse slats on steel plate, between two transverse slats With the gap passed through for I-steel, two transverse slats are located at the both sides up and down of I-steel respectively, form fixed I-steel respective end Structure.
Further, described temporary steel support structural top is located in the cell body of I-steel.
Further, described support frame also includes the first diagonal brace and the second diagonal brace, and the both ends of the first diagonal brace are solid respectively Surely I-steel and side wall are connected, second diagonal brace one end is fixedly connected with temporary steel support structure, and the other end contradicts I-steel.
Further, place is reserved with for pouring neutrality between corresponding adjacent two temporary steel supports structure below the upper beam Post pours mouth.
The utility model compared with prior art, has the beneficial effect that:
1)It is simple in construction, meet the actual demand of operating mode:Because central post of the prior art position after the completion of pouring It has been fixed that, but in actual applications, the gap that can exist between central post and side wall is smaller, causes shield machine with after The relevant device of side can not be by, and the utility model is by setting moveable temporary steel support structure come in temporary replacement Column realization carries out undertaking load to I-steel and top corresponding construction, while between temporary steel support structure and side wall Spacing can be adjusted according to practice of construction situation, meet the actual demand of construction, after the completion for the treatment of that central post pours, remove Temporary steel support structure and other useless components, rely only on central post and corresponding load are supported, effectively anti- Only shield machine and its rear portion equipment are because the fixation of central post, stops the advance of its shield machine and its rear portion equipment, influence work Efficiency.
2)The utility model is additionally provided with I-steel between upper beam and temporary steel support structure, prevents from excessively moving temporary steel Supporting construction causes upper beam unstable, and the cell body of I-steel can carry out when mobile spacing to temporary steel support structure, enter One step prevents the position adjustment of temporary steel support structure and engineering design from producing deviation, causes support effect to reduce or even produce life Production is unexpected.
Brief description of the drawings
Fig. 1 is top view of the present utility model;
Fig. 2 is temporary steel support and the connection diagram of I-steel;
Fig. 3 is the connection diagram of I-steel and floor.
Embodiment
A kind of shield machine such as Fig. 1-2 integrally originates the interim station support frame in space, is set on the upside of the interim station There is a upper beam 1, described support frame includes I-steel 2 and temporary steel support structure 3, and the temporary steel support structure 3 is steel pipe, work Word steel 2 is fixed by floor 6 and the side wall 5 at station and connected perpendicular to the side wall 5 at station and one end along its length Connect, the lower section of the other end of I-steel 2 is provided with moveable temporary steel support structure 3, and the temporary steel support structure 3 is hung down with ground 4 Directly touch, in the cell body of I-steel 2, described support frame also includes first at the described top of temporary steel support structure 3 The diagonal brace 702 of diagonal brace 701 and second, the both ends of the first diagonal brace 701 are respectively fixedly connected with I-steel 2 and side wall 5, the second diagonal brace 702 one end are fixedly connected with temporary steel support structure 3, and the other end contradicts I-steel 2, and described support frame is vertically arranged AT STATION Upper beam 1 and ground 4 between, the support frame be multiple and along station upper beam 1 length directions uniformly arrange at equal intervals, institute The temporary steel support structure 3 stated is steel pipe, and described floor 6 includes steel plate, and several confession built-in fittings are uniformly distributed on the steel plate and are worn The through hole crossed, built-in fitting are stretched into inside side wall 5 through through hole, and steel plate is vertically shown consideration for flank wall and closed, on steel plate It is additionally provided with two transverse slats, transverse slat passes through perpendicular to steel plate and parallel with bottom surface as shown in figure 3, having between two transverse slats for I-steel 2 Interval, two transverse slats are located at the both sides up and down of I-steel 2 respectively, form the structure of fixed one end of I-steel 2, under the upper beam 1 Place is reserved between the corresponding adjacent two temporary steel supports structure in side pours mouth for pour central post.
In use, shield machine is from starting room 8s, and by working as hair between metope side wall and temporary steel support structure 3 When existing temporary steel support structure 3 stops the machinery at shield machine rear, mobile temporary steel support structure, make setting for shield machine rear For by then installing central post 9, temporary steel support of finally dismantling structure 3.

Claims (7)

1. a kind of shield machine integrally originates the interim station support frame in space, it is characterised in that described support frame includes I-steel and temporary steel support structure, I-steel along its length perpendicular to station side wall and one end by floor with The side wall at station is fixedly connected, and the lower section of the I-steel other end is provided with can be along the temporary steel branch that I-steel length direction moves Support structure, the temporary steel support structure contact perpendicular to the ground.
2. a kind of shield machine according to claim 1 integrally originates the interim station support frame in space, it is characterised in that Described support frame is vertically arranged between upper beam AT STATION and ground, and the support frame is several and along the length of station upper beam Degree direction uniformly arranges at equal intervals.
3. a kind of shield machine according to claim 2 integrally originates the interim station support frame in space, it is characterised in that Described temporary steel support structure is steel pipe.
4. a kind of shield machine according to claim 3 integrally originates the interim station support frame in space, it is characterised in that Described floor includes steel plate, and several through holes passed through for built-in fitting are uniformly distributed on the steel plate, and built-in fitting stretches into through through hole Inside flank wall body, steel plate is shown consideration for flank wall and closed, and two transverse slats are additionally provided with steel plate, has between two transverse slats and passes through for I-steel Gap, two transverse slats are located at the both sides up and down of I-steel, form the structure of fixed I-steel respective end respectively.
5. a kind of shield machine according to claim 4 integrally originates the interim station support frame in space, it is characterised in that Described temporary steel support structural top is located in the cell body of I-steel.
6. a kind of shield machine according to claim 5 integrally originates the interim station support frame in space, it is characterised in that Described support frame also includes the first diagonal brace and the second diagonal brace, and the both ends of the first diagonal brace are respectively fixedly connected with I-steel and side Wall, second diagonal brace one end are fixedly connected with temporary steel support structure, and the other end contradicts I-steel.
7. a kind of shield machine according to claim 2 or 6 integrally originates the interim station support frame in space, its feature exists In place is reserved with and pours mouth for pour central post between corresponding adjacent two temporary steel supports structure below the upper beam.
CN201720677674.4U 2017-06-12 2017-06-12 A kind of shield machine integrally originates the interim station support frame in space Expired - Fee Related CN206860218U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720677674.4U CN206860218U (en) 2017-06-12 2017-06-12 A kind of shield machine integrally originates the interim station support frame in space

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720677674.4U CN206860218U (en) 2017-06-12 2017-06-12 A kind of shield machine integrally originates the interim station support frame in space

Publications (1)

Publication Number Publication Date
CN206860218U true CN206860218U (en) 2018-01-09

Family

ID=60830829

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720677674.4U Expired - Fee Related CN206860218U (en) 2017-06-12 2017-06-12 A kind of shield machine integrally originates the interim station support frame in space

Country Status (1)

Country Link
CN (1) CN206860218U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108316307A (en) * 2018-02-08 2018-07-24 青岛理工大学 The construction method that shield machine station originates

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108316307A (en) * 2018-02-08 2018-07-24 青岛理工大学 The construction method that shield machine station originates
CN108316307B (en) * 2018-02-08 2020-01-14 青岛理工大学 Construction method for starting shield machine station

Similar Documents

Publication Publication Date Title
CN105041357B (en) Single track handling tail becomes first formula advance support system
CN204402559U (en) A kind of large jacking force shield machine air pushes through hole truss-like reaction support group
CN204199297U (en) Bracing members axle force compensating device
CN206860218U (en) A kind of shield machine integrally originates the interim station support frame in space
CN205100119U (en) Steel form device in self -propelled
CN107587885B (en) Two-lining trolley structure in standard section of tunnel and assembling method
CN204152527U (en) The combined type preliminary bracing system of wall multiple-arch tunnel in implicit expression
CN205805572U (en) A kind of buttress type subway station section of track well
CN205036077U (en) Shear force wall formwork support suitable for narrow and small space usage
CN209523753U (en) The purlin vehicle of mating trolley translation after a kind of shield machine
CN104018854B (en) A kind of city gate type needle beam trolley
CN207499501U (en) A kind of adjustable for height novel building finished product stent
CN203684102U (en) Supporting system for precast beam formed by connecting span erection of ramp bridge and main line bridge
CN207177310U (en) A kind of crane beam on rock wall for underground power house reinforcing bar is from steady structure
CN206957175U (en) A kind of planar dimension and adjustable for height operating platform
CN205224272U (en) Steel construction factory building is with structure of encorbelmenting
CN205242891U (en) Prefabricated hollow staircase
CN210440048U (en) Die carrier suitable for curved well wall construction of multiple arch tunnel is used
CN205349372U (en) For a short time, construct to fold friendship tunnel controllable gate shaped steel frame apart from shield only
CN210422641U (en) Hydraulic drawing die lining construction system for tunnel
CN211621021U (en) Inclined shaft assembled support high track
CN209067234U (en) A kind of truss-like synovial membrane constructing device suitable for mid-board
CN211285276U (en) Assembly type continuous rigid frame 0# block bracket
CN203430006U (en) Quick disassembly and assembly cantilever bracket for building outer wall construction
CN209413302U (en) Movable side wall form support system with operation platform

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 361021 Yinjiang Road 139, Jimei District, Xiamen City, Fujian Province

Co-patentee after: CHINA FIRST HIGHWAY ENGINEERING Co.,Ltd.

Patentee after: CCCC FIRST HIGHWAY XIAMEN ENGINEERING Co.,Ltd.

Address before: 361021 Yinjiang Road 139, Jimei District, Xiamen City, Fujian Province

Co-patentee before: CCCC FIRST HIGHWAY ENGINEERING Co.,Ltd.

Patentee before: CCCC FIRST HIGHWAY XIAMEN ENGINEERING Co.,Ltd.

CP01 Change in the name or title of a patent holder
CF01 Termination of patent right due to non-payment of annual fee