CN206859231U - A kind of grouting device of bored concrete pile - Google Patents
A kind of grouting device of bored concrete pile Download PDFInfo
- Publication number
- CN206859231U CN206859231U CN201720802664.9U CN201720802664U CN206859231U CN 206859231 U CN206859231 U CN 206859231U CN 201720802664 U CN201720802664 U CN 201720802664U CN 206859231 U CN206859231 U CN 206859231U
- Authority
- CN
- China
- Prior art keywords
- inner tube
- elastic portion
- concrete pile
- bored concrete
- grouting device
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
The utility model provides a kind of grouting device of bored concrete pile, including outer tube and inner tube, and spacing is provided with slurry outlet on the outer tube, and the position positioned at slurry outlet on the outer tube is also arranged with rubber strip;Said inner tube is set in the outer tube, and said inner tube includes the first elastic portion of the nozzle position positioned at said inner tube, and injected hole is provided with said inner tube.The grouting device of bored concrete pile provided by the utility model, ensure the grouting quality of each slip casting hole site, pressure control quickly can be carried out to corresponding site, and control injection rate, it is possible to increase grouting pressure, the quality and effect of slip casting is effectively ensured.
Description
Technical field
A kind of grouting device of bored concrete pile is the utility model is related to, belongs to technical field of building construction.
Background technology
The present apparatus is mainly to solve the problems such as cast-in-place pile concrete quality of architectural engineering.General filling pile construction is completed
Afterwards, the problems such as pile body slag inclusion or pile bottom sediment occurs in bored concrete pile, has influence on the concrete quality of bored concrete pile, then serious point is just
Influence whether the bearing capacity of engineering pile and the normal use of structure.Common buildings filling pile construction, easily there are following several feelings
Condition:1st, during underwater gliders, conduit Transducers Embedded in Concrete depth deficiency;2nd, during tube drawing, conduit proposes concrete surface;3、
Concreting is discontinuous, pours overlong time;4th, borehole cleaning is not clean or do not carry out secondary pile hole cleaning;5th, conduit bottom is to bottom hole pitch
From excessive.These situations can all cause the concrete quality of bored concrete pile to decline, and have a strong impact on the bearing capacity of engineering pile.Also have at present
Such way:When colligation fills steel reinforcement cage, Grouting Pipe is reserved into colligation on steel reinforcement cage, after the completion for the treatment of concreting, needed
Stake detection is carried out, determines whether stake needs to carry out grouting treatment by examining report, makes up the mass defect of bored concrete pile.But this
The shortcomings that sample is done be:1st, the pulp hole site that Grouting Pipe leaves is fixed, and the position that can not judge grout outlet in advance is exactly concrete
The position of defect, reserved Grouting Pipe slurry outlet are not necessarily positioned to the position of mass defect;2nd, can not determine to work as during slip casting
The slip casting intensity of individual position, it is difficult to determine whether that slip casting should be stopped;3rd, slip casting intensity is difficult to control during slip casting, slip casting must not be determined
Amount;4th, slip casting process is to carry out slip casting to whole branch Grouting Pipe, it is difficult to determines the pressure of each slurry outlet, it is difficult to judge whether
Slip casting should be stopped, slip casting pressure skewness, slip casting effect is poor.
Utility model content
Deficiency, the technical problems to be solved in the utility model are to provide a kind of grouting device of bored concrete pile based on more than, protect
The grouting quality of each slip casting hole site is demonstrate,proved, pressure control quickly can be carried out to corresponding site, and controls injection rate, energy
Grouting pressure is enough improved, the quality and effect of slip casting is effectively ensured.
In order to solve the above technical problems, the utility model employs following technical scheme:
A kind of grouting device of bored concrete pile, including outer tube and inner tube, spacing is provided with slurry outlet on the outer tube, described
Position on outer tube positioned at slurry outlet is also arranged with rubber strip;Said inner tube is set in the outer tube, and said inner tube includes position
In being provided with injected hole in the first elastic portion of the nozzle position of said inner tube, said inner tube.
First elastic portion and the second elastic portion are made up of rubber.
The injected hole is arranged on the side wall of said inner tube.
The injected hole is oppositely arranged with the slurry outlet.
The bottom of said inner tube sets ferrule to seal.
Also include pipe shaft, first elastic portion, pipe shaft and the second elastic portion are sequentially communicated, the pipe shaft and described first
Elastic portion, the pipe shaft are connected with second elastic portion by metal joint.
The injected hole is arranged in the side wall or bottom wall of said inner tube.
Using above technical scheme, the utility model achieves following technique effect:
(1) grouting device of the utility model bored concrete pile can carry out slip casting to each injected hole in Grouting Pipe respectively,
Slip casting together is avoided to cause the slip casting pressure of each slip casting hole site to fully meet the pressure demand of the position, can be fine
Ground controls slip casting pressure, can effectively improve the quality of slip casting;And by setting the first elastic portion to strengthen the pressure of slurries
Power;
(2) slurry that the grouting device of the utility model bored concrete pile sprays in pulp hole site, can be pile body after curing
Strengthen frictional force, be advantageous to improve engineering pile bearing capacity.
Brief description of the drawings
Fig. 1 is the structure chart of the grouting device of the utility model bored concrete pile;
Fig. 2 is Fig. 1 left view;
Fig. 3 is the structure chart of the inner tube of the grouting device of the utility model bored concrete pile.
Embodiment
As shown in Figure 1-Figure 3, the grouting device of bored concrete pile provided by the utility model includes outer tube 1 and inner tube 2, described outer
Spacing is provided with slurry outlet on pipe 1, and the position positioned at slurry outlet on the outer tube 1 is also arranged with rubber strip 11;Said inner tube 2
It is set in the outer tube 1, said inner tube 2 includes the first elastic portion 21 of the nozzle position positioned at said inner tube 2, said inner tube
Injected hole 25 is provided with 2.During slip casting, with the increase of the pressure of inner tube 2, the first elastic portion 21, which expands, blocks outer tube 1, outer tube
The space of opposing seal is formed in 1, with the further increase of slurry pressure in inner tube 2, slurries flow from the injected hole 25 of inner tube 2
Go out, and sprayed from slurry outlet.
Wherein, inner tube 2 also includes pipe shaft 23, and pipe shaft 23 connects with the first elastic portion 21, and in the present embodiment, inner tube 2 is also wrapped
The second elastic portion 22 is included, the first elastic portion 21, the elastic portion 22 of pipe shaft 23 and second are sequentially communicated, pipe shaft 23 and the described first elasticity
Portion 21, pipe shaft 23 are connected with second elastic portion 22 by metal joint 24.First elastic portion 21 and the second elastic portion 22
It is made up of rubber.The injected hole 25 is arranged on the side wall of said inner tube 2, and is located at the first elastic portion 21 and the second elastic portion 22
Between.The injected hole 25 is oppositely arranged with the slurry outlet.The bottom of said inner tube 2 sets ferrule to seal.When slip casting,
First elastic portion 21 and the second elastic portion 22 expand and block outer tube 1, and outer tube 1 is located at the first elastic portion 21 and the second elastic portion 22
Between space opposing seal, and whole inner tube 2 also opposing seal substantially increases grouting pressure, now the pressure of inner chamber
Constantly lifting, the rubber strip 11 on the slurry outlet of outer tube 1 is pressed off, cement mortar sprays from gap.In other specific embodiments,
Inner tube 2 can include the first elastic portion 21 and pipe shaft 23, and the first elastic portion 21 is connected with pipe shaft 23, and the first elastic portion 21 is located at
The nozzle position of inner tube 2, injected hole 25 are arranged on side wall or the bottom wall of inner tube 2.When injected hole 25 is arranged on the side wall of inner tube 2
When upper, injected hole 25 can also be oppositely arranged with slurry outlet.When slip casting, the first elastic portion 21, which expands, blocks outer tube 1, and first
Space opposing seal between elastic portion 21 and outer tube 1, and whole inner tube 2 also opposing seal, can also improve slip casting pressure
Power, now the pressure of inner chamber constantly lifted, the rubber strip 11 on the slurry outlet of outer tube 1 is pressed off, cement mortar sprays from gap.
The process of slip casting will pay close attention to the pressure value of inner chamber, treat that pressure value declines suddenly, then constant, last to rise to design pressure again
Power can stops slip casting, completes the mortar depositing construction of an injected hole 25.
Finally it should be noted that:Preferred embodiment of the present utility model is these are only, is not limited to this practicality
It is new, although the utility model is described in detail with reference to embodiment, for those skilled in the art, its according to
The technical scheme described in foregoing embodiments can so be modified, or which part technical characteristic is equally replaced
Change, but it is all within the spirit and principles of the utility model, any modification, equivalent substitution and improvements made etc., it all should include
Within the scope of protection of the utility model.
Claims (8)
- A kind of 1. grouting device of bored concrete pile, it is characterised in that:Including outer tube and inner tube, spacing is provided with pulp on the outer tube Hole, the position positioned at slurry outlet on the outer tube are also arranged with rubber strip;Said inner tube is set in the outer tube, described interior Pipe includes the first elastic portion of the nozzle position positioned at said inner tube, and injected hole is provided with said inner tube.
- 2. the grouting device of bored concrete pile according to claim 1, it is characterised in that:Said inner tube is also included positioned at described interior Second elastic portion of the bottom of pipe.
- 3. the grouting device of bored concrete pile according to claim 1 or 2, it is characterised in that:First elastic portion and second Elastic portion is made up of rubber.
- 4. the grouting device of bored concrete pile according to claim 2, it is characterised in that:The injected hole is arranged on said inner tube Side wall.
- 5. the grouting device of bored concrete pile according to claim 4, it is characterised in that:The injected hole and the slurry outlet phase To setting.
- 6. the grouting device of bored concrete pile according to claim 5, it is characterised in that:The bottom of said inner tube sets ferrule Sealing.
- 7. the grouting device of bored concrete pile according to claim 1, it is characterised in that:Also include pipe shaft, first elasticity Portion, pipe shaft and the second elastic portion are sequentially communicated, the pipe shaft and first elastic portion, the pipe shaft and second elastic portion Connected by metal joint.
- 8. the grouting device of bored concrete pile according to claim 1, it is characterised in that:The injected hole is arranged on said inner tube Side wall or bottom wall on.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720802664.9U CN206859231U (en) | 2017-07-03 | 2017-07-03 | A kind of grouting device of bored concrete pile |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720802664.9U CN206859231U (en) | 2017-07-03 | 2017-07-03 | A kind of grouting device of bored concrete pile |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206859231U true CN206859231U (en) | 2018-01-09 |
Family
ID=60828965
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720802664.9U Active CN206859231U (en) | 2017-07-03 | 2017-07-03 | A kind of grouting device of bored concrete pile |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206859231U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111910638A (en) * | 2019-05-09 | 2020-11-10 | 中铁第五勘察设计院集团有限公司 | Grouting pipe and preparation method thereof |
-
2017
- 2017-07-03 CN CN201720802664.9U patent/CN206859231U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111910638A (en) * | 2019-05-09 | 2020-11-10 | 中铁第五勘察设计院集团有限公司 | Grouting pipe and preparation method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104088254B (en) | Pressure-bearing reinforced concrete structure leakage repair device and construction method thereof | |
CN103643657A (en) | Deep-hole chemical grouting construction method applied to water leakage treatment of hydroelectric dam | |
CN110106883A (en) | A kind of Real-time Feedback grouting method for correcting subway tunnel horizontal distortion | |
CN205422815U (en) | Big flood underground mine tunnel waterwall | |
CN206859231U (en) | A kind of grouting device of bored concrete pile | |
CN208563315U (en) | A kind of pile foundation grouting behind shaft or drift lining constructing device | |
CN203977368U (en) | Pressure-bearing reinforced concrete structure leakage repair device | |
CN207597388U (en) | Grouting sleeve valve pipe | |
CN104197129B (en) | A kind of novel reinforced concrete drainage pipe and its manufacture method | |
CN104032713B (en) | A kind of pressure diversion tunnel composite lining concrete anti-seepage structure and construction technology thereof | |
CN105507336A (en) | Method for forming composite foundation by using dewatering well | |
CN207392205U (en) | A kind of pile foundation post jacking device | |
CN111733894A (en) | Anti-floating system of deep foundation pit underground structure and construction process | |
CN110144918A (en) | Hypogee dewatering well antiseepage plugging construction method | |
CN204081064U (en) | A kind of basement sandwich | |
CN203891785U (en) | Special joint pipe assembly for throwing of gravels in pipe of hydrogeological water well | |
CN205188933U (en) | Utilize composite foundation of precipitation well formation | |
CN110453659B (en) | Construction method for rock plug reservation construction key technology of diversion tunnel of weak surrounding rock | |
CN204199324U (en) | Connecting reinforcement cage i iron in construction of diaphragm wall | |
CN106948315A (en) | A kind of stone masonry dam dam grouting reinforcing structure inferior and method | |
CN207633354U (en) | A kind of novel foundation pit leaking plugging structure | |
CN206736895U (en) | A kind of joint bar repairing type CFG stakes | |
CN206887953U (en) | Soil nailing port closing device and soil nailing wall structure | |
CN112982372A (en) | Inner drilling pipe insertion pipe compaction grouting reinforcement method based on pipe gallery bottom plate cavity | |
CN206495200U (en) | A kind of grouting behind shaft or drift lining bored concrete pile |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |