CN206801591U - The advanced conduit ball-valve type joint of constructing tunnel grouting methol - Google Patents

The advanced conduit ball-valve type joint of constructing tunnel grouting methol Download PDF

Info

Publication number
CN206801591U
CN206801591U CN201720502105.6U CN201720502105U CN206801591U CN 206801591 U CN206801591 U CN 206801591U CN 201720502105 U CN201720502105 U CN 201720502105U CN 206801591 U CN206801591 U CN 206801591U
Authority
CN
China
Prior art keywords
valve
ball
constructing tunnel
advanced
conduit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720502105.6U
Other languages
Chinese (zh)
Inventor
马小利
王红恩
路毅波
王小文
刘维号
初雷
卫强
柳吉焕
高新平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Engineering Co Ltd of China Railway 21st Bureau Group Co Ltd
Original Assignee
Third Engineering Co Ltd of China Railway 21st Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Engineering Co Ltd of China Railway 21st Bureau Group Co Ltd filed Critical Third Engineering Co Ltd of China Railway 21st Bureau Group Co Ltd
Priority to CN201720502105.6U priority Critical patent/CN206801591U/en
Application granted granted Critical
Publication of CN206801591U publication Critical patent/CN206801591U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of advanced conduit ball-valve type joint of constructing tunnel grouting methol.It is to fix Grouting Pipe in the side of conical shape check valve, opposite side hinge electron adsorption device, the valve ball that returns that its external diameter is more than to slip casting bore is positioned in the empty room of conical shape check valve, advanced conduit is placed in electron adsorption device, conical shape check valve is inserted radially into some check levers, sealing ring, sealing ring sidepiece installation Spring Card are installed between electron adsorption device and advanced conduit.The utility model overcomes the problem of current advanced pipe guide of constructing tunnel grouting methol is present, using low-voltage electronic strong absorber, that is energy-saving safe, installation is quick, it is again easy to operate, construction quality has been ensured again simultaneously, efficiency of construction has been greatly improved, is a kind of comparatively ideal constructing tunnel conduit grouting device for meeting demand of technical standard.

Description

The advanced conduit ball-valve type joint of constructing tunnel grouting methol
Technical field
It the utility model is related to a kind of jointing device that the advanced conduit of grouting methol is carried out in constructing tunnel, tool Body is a kind of advanced conduit ball-valve type joint of constructing tunnel grouting methol, belongs to road and bridge construction field.
Background technology
Road infrastructure construction at present has been enter into the global high speed development stage, and constructing tunnel is road construction Key link, both require construction safely and fast, while required energy-conserving and environment-protective again, and mitigate the labor intensity of workmen. If run into constructing tunnel geological structure it is poor when it is necessary to the chapelet face periphery in excavation squeeze into more advanced conduit, It is that can explore rock texture situation above that it, which acts on one, and two are for grouting methol in every advanced conduit, is made advanced Conduit closely links into an integrated entity with rock, is easy to the safety and stability of postorder excavation construction.Advanced conduit pressure injection cement is given at present Starch the following two methods of generally use:When be first connected to advanced tube at one end processing screw thread with ball valve, while in the another of ball valve The steel pipe to match with Grouting Pipe is installed in one end, ball valve is closed after advanced conduit grouting methol, then lead in advance to next Pipe grouting methol, until all advanced conduit grouting methol completions, because cement mortar can not be dismantled immediately before initial set, it must treat The movable ball valve of ability is dismantled after several hours, so influenceing construction progress;Also one kind is not mounting ball valve, be treat it is advanced Dismantled after the complete cement mortar of conduit pressure injection Grouting Pipe, then clog duct inlet with cloth or plastic paper, because manifold pressure is larger, So having some when dismantling Grouting Pipe, completely pre-hardening cement mortar does not eject, and causes potential safety hazard.Other ball valve Construction is more complicated, and disassembly, cleaning are difficult, and scrappage is very high, significantly increases construction cost, reduces efficiency of construction.At present still Have no the device of the comparatively ideal advanced conduit of constructing tunnel grouting methol.
Utility model content
The purpose of this utility model is the problem of overcoming the current advanced pipe guide of constructing tunnel grouting methol to exist, from And disclose a kind of advanced conduit ball-valve type joint of constructing tunnel grouting methol.
The technical solution of the utility model is as follows:
Grouting Pipe is fixed in the side of conical shape check valve, will in its opposite side by connecting hinge hinge electron adsorption device The valve ball that returns that its external diameter is more than slip casting bore is positioned in the empty room of conical shape check valve, then advanced conduit is placed in into electron adsorption In device, conical shape check valve is inserted radially into some check levers, and it be 1-2cm to go back to the laterally movable gap of valve ball, in electron adsorption device and Sealing ring, sealing ring sidepiece installation Spring Card are installed between advanced conduit.
The utility model overcomes the problem of current advanced pipe guide of constructing tunnel grouting methol is present, using low electricity Pressure force electron adsorption device, i.e. energy-saving safe, installation is quick, and easy to operate, while has ensured construction quality again, greatly carries High efficiency of construction, is a kind of comparatively ideal constructing tunnel conduit grouting device for meeting demand of technical standard.
Brief description of the drawings
Accompanying drawing 1 is front view structure diagrammatic cross-section of the present utility model.
Accompanying drawing 2 for the utility model accompanying drawing 1 A-A to left view diagrammatic cross-section.
Accompanying drawing 3 is the B-B direction left view diagrammatic cross-section of the utility model accompanying drawing 1.
Reference is as follows:Grouting Pipe 1, return valve ball 2, conical shape check valve 3, check lever 4, Spring Card 5, sealing ring 6, connection Loose-leaf 7, electron adsorption device 8, advanced conduit 9.
Embodiment
The utility model is described in further detail below in conjunction with accompanying drawing:
Grouting Pipe 1 is fixed in the side of conical shape check valve 3, passes through the hinge electron adsorption device of connecting hinge 7 in its opposite side 8, the valve ball 2 that returns that its external diameter is more than to the internal diameter of Grouting Pipe 1 is positioned in the empty room of conical shape check valve 3, then advanced conduit 9 is placed in In electron adsorption device 8, conical shape check valve 3 is inserted radially into three check levers 4, and it is 1.5cm to go back to the laterally movable gap of valve ball, in electronics Sealing ring 6, the sidepiece of sealing ring 6 installation Spring Card 5 are installed between absorber 8 and advanced conduit 9.
The utility model operate when first advanced conduit is put into electron adsorption device, then start electron adsorption device make its with Advanced conduit absorption is held tightly, and slip casting machine connects slip casting flexible pipe and starts to carry out advanced conduit slip casting again, and built-in returns valve ball automatically Cement mortar can be made, and stream is mapped in grouting pipe and rock crevice glibly.Slip casting machine release after the completion of slip casting is treated, returning valve ball will Self-closed grouting port prevents cement mortar from ejecting, to initial set after the completion of close low-voltage power switch, close electron adsorption Device, electron adsorption device are separated with advanced conduit, and advanced conduit is removed out of electron adsorption device, are led in advance to multiple by that analogy Pipe carries out slip casting.The utility model can be easily removed after all advanced conduit cement mortars fill, next time is standby after cleaning.

Claims (3)

1. the advanced conduit ball-valve type joint of constructing tunnel grouting methol, it is characterised in that:In conical shape check valve(3)Side consolidate Determine Grouting Pipe(1), pass through connecting hinge in its opposite side(7)Hinge electron adsorption device(8), its external diameter is more than Grouting Pipe(1) Internal diameter returns valve ball(2)It is positioned over conical shape check valve(3)Empty room in, then by advanced conduit(9)It is placed in electron adsorption device(8) It is interior, conical shape check valve(3)It is inserted radially into some check levers(4), return valve ball(2)Laterally movable gap is 1-2cm, is inhaled in electronics Adnexa(8)With advanced conduit(9)Between sealing ring is installed(6), sealing ring(6)Sidepiece installs Spring Card(5).
2. the advanced conduit ball-valve type joint of constructing tunnel grouting methol according to claim 1, it is characterised in that:Cone Shape check-valves(3)It is inserted radially into three check levers(4).
3. the advanced conduit ball-valve type joint of constructing tunnel grouting methol according to claim 1, it is characterised in that:Return The laterally movable gap of valve ball is 1.5cm.
CN201720502105.6U 2017-05-08 2017-05-08 The advanced conduit ball-valve type joint of constructing tunnel grouting methol Active CN206801591U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720502105.6U CN206801591U (en) 2017-05-08 2017-05-08 The advanced conduit ball-valve type joint of constructing tunnel grouting methol

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720502105.6U CN206801591U (en) 2017-05-08 2017-05-08 The advanced conduit ball-valve type joint of constructing tunnel grouting methol

Publications (1)

Publication Number Publication Date
CN206801591U true CN206801591U (en) 2017-12-26

Family

ID=60737957

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720502105.6U Active CN206801591U (en) 2017-05-08 2017-05-08 The advanced conduit ball-valve type joint of constructing tunnel grouting methol

Country Status (1)

Country Link
CN (1) CN206801591U (en)

Similar Documents

Publication Publication Date Title
WO2013056597A1 (en) Gas extraction method and device with alternating extraction and injection
CN102561977B (en) High-pressure high-flow water burst hole drilling safety system, mounting process thereof and service process
CN105696598B (en) A kind of application method for being adapted to mini-valve tube elevation angle grouting device
CN109098750B (en) Device for underground gas extraction hole to be used as coal seam water injection hole and construction method
CN207583345U (en) Mining drilling pump drainage fluid filling hole sealing device
CN108086945A (en) A kind of layer-through drilling separate type whole process gas drainage hole sealing device and its method for sealing
CN206737880U (en) A kind of underground leting speeper borehole casing sector hole wall grouting and reinforcing device
CN206957684U (en) A kind of roof fracturing system
CN202194628U (en) Integrated device of Christmas tree and gas well ground construction assembly skid
CN203879516U (en) Sequential and segmentation grouting device of tunnel grouting model test
CN206801591U (en) The advanced conduit ball-valve type joint of constructing tunnel grouting methol
CN105804691A (en) Pipe-free hole sealing method for mining gas extraction drill hole
CN202194668U (en) Automatic air pressure maintaining system for shield machine
CN204877339U (en) Down -hole drill of effective dust fall
CN204663509U (en) Anti-reflection system is shaken in carbon dioxide coal seam
CN206204974U (en) A kind of device for plugging for concrete pipe base core-drawing hole water burst
CN104879079B (en) Production wellhead gate valve replacing device operated under pressure and gate valve replacing options with pressure
CN103912289A (en) Tunnel grouting model test sequential segmented grouting device and using method thereof
CN202914026U (en) Well cementation cement head
CN203640656U (en) Conical hole packer for gas drainage
CN205135482U (en) Gas drilling pressure release manifold device
CN203285386U (en) Rapid inflation grouting hole sealing device
CN206205937U (en) A kind of post-grouting device of oil storage cavern
CN207813568U (en) A kind of detachable bridge plug
CN206831016U (en) A kind of novel rubber hose turns PU pipe rapid inserting type self sealss and connects mouth device

Legal Events

Date Code Title Description
GR01 Patent grant