CN206800711U - One kind spraying mortar beams encased in steel hoops interior wall pipe clamp connecting node - Google Patents

One kind spraying mortar beams encased in steel hoops interior wall pipe clamp connecting node Download PDF

Info

Publication number
CN206800711U
CN206800711U CN201720435278.0U CN201720435278U CN206800711U CN 206800711 U CN206800711 U CN 206800711U CN 201720435278 U CN201720435278 U CN 201720435278U CN 206800711 U CN206800711 U CN 206800711U
Authority
CN
China
Prior art keywords
pipe clamp
wallboard
interior wall
connecting node
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720435278.0U
Other languages
Chinese (zh)
Inventor
郝际平
樊春雷
薛强
刘瀚超
何梦楠
孙晓岭
张峻铭
赵子健
刘斌
陈永昌
黄育琪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xian University of Architecture and Technology
Original Assignee
Xian University of Architecture and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xian University of Architecture and Technology filed Critical Xian University of Architecture and Technology
Priority to CN201720435278.0U priority Critical patent/CN206800711U/en
Application granted granted Critical
Publication of CN206800711U publication Critical patent/CN206800711U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Building Environments (AREA)

Abstract

It the utility model is related to architectural design technical field, mortar beams encased in steel hoops interior wall pipe clamp connecting node is sprayed more particularly to one kind, wallboard including being arranged on girder steel bottom, the upper end of wallboard is provided with several pipe clamps, wallboard is connected by pipe clamp with girder steel, caulking agent is filled with gap between wallboard and girder steel, the connecting node make it that girder steel is simple with interior wall structure, easy for installation.

Description

One kind spraying mortar beams encased in steel hoops-interior wall pipe clamp connecting node
【Technical field】
It the utility model is related to architectural design technical field, and in particular to one kind spraying mortar beams encased in steel hoops-interior wall pipe clamp Connecting node.
【Background technology】
The annexation of existing girder steel and interior wall is complicated, construction inconvenience, requires higher to the construction level of worker, therefore Cause construction cost larger, and the time is longer.
【The content of the invention】
To solve problems of the prior art, the purpose of this utility model is to provide a kind of spraying mortar Covered with Angles Beam-interior wall pipe clamp connecting node, the connecting node make it that girder steel is simple with interior wall structure, easy for installation.
The purpose of this utility model is achieved through the following technical solutions:
One kind spraying mortar beams encased in steel hoops-interior wall pipe clamp connecting node, including the wallboard of girder steel bottom is arranged on, wallboard Upper end is provided with several pipe clamps, and wallboard is connected by pipe clamp with girder steel, and filleting is filled with the gap between wallboard and girder steel Agent.
The pipe clamp includes top plate and the montant vertical with top plate, the lower surface connection of montant and top plate.
The blind hole for accommodating montant is offered on the upper surface of the wallboard, blind hole is not small apart from the distance of wallboard edge In 80mm.
The distance between described pipe clamp is 600mm.
The wallboard sets some pieces, and at least one pipe clamp is set on every block of wallboard.
Gap between the wallboard and girder steel is 10~20mm.
The caulking agent is that PU is soaked agent or rock wool.
The pipe clamp welds with girder steel.
Being coated with the girder steel being capable of fireproof light mortar.
The wallboard is autoclaved lightweight sand aerated concrete sheet material.
Compared with prior art, the utility model has the advantages that:
Spraying mortar beams encased in steel hoops-interior wall pipe clamp connecting node of the present utility model, if by being set in the upper end of wallboard Dry pipe clamp, wallboard are connected by pipe clamp with girder steel, hence in so that prefabricated wallboard and the convenient connection of girder steel, simple in construction, Caulking agent is filled in gap between wallboard and girder steel, after wallboard is connected with girder steel, by caulking agent by wallboard and girder steel Connecting portion is sealed, therefore has the characteristics of easy for construction.
Further, the blind hole on wallboard is not less than 80mm apart from the distance of wallboard edge, therefore can ensure that pipe clamp is pacified After on wallboard, the montant of pipe clamp is not easy to damage wallboard.
Further, wallboard is autoclaved lightweight sand aerated concrete sheet material, therefore wallboard has excellent self-supporting and oneself The features such as insulation.
【Brief description of the drawings】
Fig. 1 is the structural representation before spraying mortar beams encased in steel hoops-interior wall pipe clamp connecting node of the present utility model connects Figure;
Fig. 2 is the structural representation of spraying mortar beams encased in steel hoops-interior wall pipe clamp connecting node of the present utility model;
Fig. 3 is the sectional view of spraying mortar beams encased in steel hoops-interior wall pipe clamp connecting node of the present utility model;
Fig. 4 is along M-M interfaces schematic cross-sectional view in Fig. 3;
Fig. 5 (a) is the front view of pipe clamp of the present utility model, and Fig. 5 (b) is the side view of pipe clamp of the present utility model.
Wherein, 1- girder steels, 2- pipe clamps, 3- caulking agents, 4- wallboards, 5- light mortars.
【Embodiment】
The utility model is further described below in conjunction with the accompanying drawings.
As shown in Figures 1 to 4, spraying mortar beams encased in steel hoops-interior wall pipe clamp connecting node of the present utility model, including set Wallboard 4 in the bottom of girder steel 1, wallboard 4 are autoclaved lightweight sand aerated concrete sheet material (i.e. ACC sheet materials), and the upper end of wallboard 4 is set There are several pipe clamps 2, wallboard 4 is connected by pipe clamp 2 with girder steel 1, and caulking agent is filled with the gap between wallboard 4 and girder steel 1 3, caulking agent 3 is that PU is soaked agent or rock wool, be coated with girder steel 1 can fireproof light mortar 5, the light mortar is containing fire prevention.
As shown in Fig. 5 (a) and Fig. 5 (b), with reference to Fig. 1-Fig. 4, pipe clamp 2 includes top plate 2-1 and vertical with top plate 2-1 erected Bar 2-2, montant 2-2 are connected with top plate 2-1 lower surface, are offered on the upper surface of wallboard 4 for accommodating the blind of montant 2-2 Hole, the depth of blind hole are less than the height of montant, and blind hole is not less than 80mm apart from the distance of the edge of wallboard 4, when mounted, by pipe clamp In 2 montant 2-2 insertion blind hole, the lower surface of top plate 2-1 and girder steel 1 is welded, that is, completes the connection of wallboard 4 and girder steel 1, Then caulking agent is filled in the gap between the top of wallboard 4 and steel beam bottom again.
As shown in figure 3, the distance between pipe clamp 2 L1For 600mm, wallboard 4 sets some pieces, set at least on every block of wallboard One pipe clamp 2, the gap h between wallboard 4 and girder steel 1 are 10~20mm.
For the utility model in construction, girder steel 1 and pipe clamp 2 carry out factory's welding, and top plate 2-1 and the girder steel 1 of pipe clamp 2 are two Millet cake welds, each 3 points.The relevant position opening holes of wallboard 4 (i.e. ACC sheet materials) pre-installation pipe clamp 2, scene is corresponding by pipe clamp Corresponding hole site is installed.Top plate 2-1 top surface is set to leave 10~20mm distances with the top surface of wallboard 4 during installation, for filling Caulking agent 3 (PU be soaked agent or rock wool), then again by the outsourcing light mortar of girder steel 1 (containing fire prevention).
The utility model is used for the connection of girder steel and inner, external wall, has the characteristics of easy for installation.

Claims (10)

1. one kind spraying mortar beams encased in steel hoops-interior wall pipe clamp connecting node, it is characterised in that including being arranged on girder steel (1) bottom Wallboard (4), the upper end of wallboard (4) is provided with several pipe clamps (2), and wallboard (4) is connected by pipe clamp (2) with girder steel (1), wall Caulking agent (3) is filled with gap between plate (4) and girder steel (1).
A kind of 2. spraying mortar beams encased in steel hoops-interior wall pipe clamp connecting node according to claim 1, it is characterised in that institute Stating pipe clamp (2) includes top plate (2-1) and the montant (2-2) vertical with top plate (2-1), the following table of montant (2-2) and top plate (2-1) Face connects.
A kind of 3. spraying mortar beams encased in steel hoops-interior wall pipe clamp connecting node according to claim 2, it is characterised in that institute State and offered on the upper surface of wallboard (4) for accommodating montant (2-2) blind hole, blind hole apart from wallboard (4) edge distance not Less than 80mm.
A kind of 4. spraying mortar beams encased in steel hoops-interior wall pipe clamp connecting node according to claim 1, it is characterised in that institute It is 600mm to state the distance between pipe clamp (2).
A kind of 5. spraying mortar beams encased in steel hoops-interior wall pipe clamp connecting node according to claim 1, it is characterised in that institute State wallboard (4) and set some pieces, at least one pipe clamp (2) is set on every block of wallboard.
A kind of 6. spraying mortar beams encased in steel hoops-interior wall pipe clamp connecting node according to claim 1, it is characterised in that institute It is 10~20mm to state the gap between wallboard (4) and girder steel (1).
A kind of 7. spraying mortar beams encased in steel hoops-interior wall pipe clamp connecting node according to claim 1, it is characterised in that institute Caulking agent (3) is stated to be soaked agent or rock wool for PU.
A kind of 8. spraying mortar beams encased in steel hoops-interior wall pipe clamp connecting node according to claim 1, it is characterised in that institute Pipe clamp (2) is stated to weld with girder steel (1).
A kind of 9. spraying mortar beams encased in steel hoops-interior wall pipe clamp connecting node according to claim 1, it is characterised in that institute State girder steel (1) on be coated with being capable of fireproof light mortar (5).
A kind of 10. spraying mortar beams encased in steel hoops-interior wall pipe clamp connecting node according to claim 1, it is characterised in that institute It is autoclaved lightweight sand aerated concrete sheet material to state wallboard (4).
CN201720435278.0U 2017-04-24 2017-04-24 One kind spraying mortar beams encased in steel hoops interior wall pipe clamp connecting node Active CN206800711U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720435278.0U CN206800711U (en) 2017-04-24 2017-04-24 One kind spraying mortar beams encased in steel hoops interior wall pipe clamp connecting node

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720435278.0U CN206800711U (en) 2017-04-24 2017-04-24 One kind spraying mortar beams encased in steel hoops interior wall pipe clamp connecting node

Publications (1)

Publication Number Publication Date
CN206800711U true CN206800711U (en) 2017-12-26

Family

ID=60733518

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720435278.0U Active CN206800711U (en) 2017-04-24 2017-04-24 One kind spraying mortar beams encased in steel hoops interior wall pipe clamp connecting node

Country Status (1)

Country Link
CN (1) CN206800711U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110359599A (en) * 2019-07-15 2019-10-22 中建钢构有限公司 Connector, ALC batten installation node structure and assembled installation method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110359599A (en) * 2019-07-15 2019-10-22 中建钢构有限公司 Connector, ALC batten installation node structure and assembled installation method

Similar Documents

Publication Publication Date Title
CN204662736U (en) Gas concrete out-hung panel slippage node
CN107386495A (en) A kind of reinforced light steel keel partition of shaped steel and construction method
CN110284587A (en) A kind of prefabricated window and connection joints of steel structure and the construction method of floaing of staggered floor
CN207017445U (en) A kind of connecting structure of girder steel and retaining wall
CN2931627Y (en) Frame and wall plate combined building
CN210421617U (en) Take autoclaved lightweight aerated concrete board of pipe strap
CN111236416A (en) Prefabricated reinforced concrete structure house and installation method thereof
CN206800711U (en) One kind spraying mortar beams encased in steel hoops interior wall pipe clamp connecting node
CN103498519A (en) Technique for anti-seismic and energy-saving wall with built-in core net
CN207277619U (en) The reinforced light steel keel partition of shaped steel
CN211873363U (en) Plugging structure and secondary structure
CN211172527U (en) Fire prevention and decoration structure of steel plate shear wall
CN210888330U (en) Prefabricated building enclosure
CN219157995U (en) Advanced seepage-proofing heat-insulating construction device for outer wall nodes of section steel beam
CN209891465U (en) Assembled outer wall
CN211200728U (en) Connecting node structure of precast concrete externally-hung wallboard
CN107859337A (en) Steel-structure factory building FPB Light trabses cracking structure constructions
CN212376009U (en) Prefabricated assembled reinforced concrete structure house
CN211229038U (en) Fast assembly type reinforced concrete shear wall structure
CN210134559U (en) Grillage-in-one outer wall plate structure with heat insulation function and building
CN209891381U (en) Building structure
CN207892066U (en) A kind of assembled fire prevention integrated building component
CN221276990U (en) Fireproof floor structure
CN106436973B (en) Steel column arranged in post-cast section of steel shear structure and casting method of steel column
CN214834067U (en) Light steel structure building

Legal Events

Date Code Title Description
GR01 Patent grant