CN206784922U - Building bearing column cast-in-situ template supporting and positioning device - Google Patents

Building bearing column cast-in-situ template supporting and positioning device Download PDF

Info

Publication number
CN206784922U
CN206784922U CN201720494868.0U CN201720494868U CN206784922U CN 206784922 U CN206784922 U CN 206784922U CN 201720494868 U CN201720494868 U CN 201720494868U CN 206784922 U CN206784922 U CN 206784922U
Authority
CN
China
Prior art keywords
pulling
piece
cross bar
template
mounting seat
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720494868.0U
Other languages
Chinese (zh)
Inventor
王艳民
狄亭
胡二永
马苇东
王艳华
王新喜
董保石
张俊伟
吴燕红
任宏飞
周成军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Xiangzhong Technology Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201720494868.0U priority Critical patent/CN206784922U/en
Application granted granted Critical
Publication of CN206784922U publication Critical patent/CN206784922U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

Building bearing column cast-in-situ template supporting and positioning device, described template-setup has four pieces, four pieces of templates are arranged in vertical, four pieces of templates be encircled into section it is square pour chamber, if the outside of four pieces of templates is disposed with dried layer fastening structure from top to bottom, every layer of fastening structure includes circumferential fastener, longitudinal pulling-on piece formula locating part and the horizontal pulling-on piece formula fastener set gradually from bottom to top, and longitudinal pulling-on piece formula locating part is identical with the construction of horizontal pulling-on piece formula fastener;The utility model has that disassembly and installation is convenient and swift, more effortlessly takes out pulling-on piece and lock hole is also kept intact after pulling-on piece is used for multiple times, the cross section of column after pouring keeps square, ensure that four pieces of template spacing keep constant, and the compactness of reinforced concrete upright column can be improved.

Description

Building bearing column cast-in-situ template supporting and positioning device
Technical field
The utility model belongs to technical field of building construction, and in particular to a kind of building bearing column cast-in-situ template support is fixed Position device.
Background technology
Emporium, underground parking etc. have more bearing column, carry out column it is cast-in-place when, it is necessary to pour in advance Position sets mould, and mould of the prior art includes four pieces of plate bodys that head and the tail connect successively, passes through connector between each plate body It is fixedly connected, then in the outside setting support Auxiliary support of mould, this structure is cumbersome for installation, and occupancy volume is larger, and The support degree of mould cannot be guaranteed, and pour the obtained integrally-built size of column(Cross section is square)It is difficult to Ensure, the compactness performance of concrete does not reach regulation requirement yet, larger potential safety hazard be present.
Utility model content
The utility model is in order to solve weak point of the prior art, there is provided a kind of mould positioning performance is strong, takes body The building bearing column cast-in-situ template supporting and positioning device that product is small, is convenient to mount and dismount and can repeatedly use.
In order to solve the above technical problems, the utility model adopts the following technical scheme that:Building bearing column cast-in-situ template branch Positioner is supportted, described template-setup there are four pieces, and four pieces of templates are arranged in vertical, and four pieces of templates are encircled into section and are in Square pours chamber, if the outside of four pieces of templates is disposed with dried layer fastening structure from top to bottom, every layer of fastening structure is equal Including the circumferential fastener, longitudinal pulling-on piece formula locating part and horizontal pulling-on piece formula fastener set gradually from bottom to top, longitudinal pulling-on piece Formula locating part is identical with the construction of horizontal pulling-on piece formula fastener;
Circumferential fastener includes structure all same and horizontally disposed first cross bar, the second cross bar, the 3rd cross bar and the Four cross bars, the first cross bar, the second cross bar, the 3rd cross bar and the 4th cross bar are horizontally disposed and are respectively parallel to one piece of template, the One cross bar, the second cross bar, the inner side of the 3rd cross bar and the 4th cross bar are fixedly installed the support contacted with template lateral surface respectively Block, the first cross bar and the abutting end of the second cross bar, the abutting end of the second cross bar and the 3rd cross bar, the 3rd cross bar and the 4th cross bar Abutting end, the 4th cross bar are connected through a screw thread fastening structure with the abutting end of the first cross bar and are connected.
Screw connection structure between first cross bar and the second cross bar include the first mounting seat, the second mounting seat, screw rod and Nut, the first mounting seat are fixedly installed on the outside of the end of the first cross bar, and the second mounting seat is fixedly installed on the end of the second cross bar On the outside of portion, screw rod is connected on screw rod through the first mounting seat and the second mounting seat, nut thread, the head of screw rod and nut point Do not contacted with the first mounting seat and the second mounting seat top pressure, screw rod is horizontally disposed and screw rod respectively with the first cross bar and the second cross bar In 45 ° of angle, between the first mounting seat and the second mounting seat.
Horizontal pulling-on piece formula fastener includes pulling-on piece and pulling-on piece sleeve pipe, and pulling-on piece and pulling-on piece sleeve pipe are in flat strip structure, Inserting hole is correspondingly offered between the template in left side and the template on right side, pulling-on piece is plugged in inserting hole, and pulling-on piece sleeve pipe is enclosed on drawing On piece and it is located between the template in left side and the template on right side, the length of pulling-on piece sleeve pipe is equal to the thickness of column, is opened up on pulling-on piece There are two to be used to plug the lock hole that latch limits the template in left side and the template spacing on right side, pulling-on piece bushing outer surface edge is long To spend direction and at least one waling is set, pulling-on piece bushing outer surface is provided with some cross reinforcings along short transverse, Cross reinforcing and waling form criss-cross construction;The both sides on pulling-on piece surface are respectively arranged with pulling-on piece sleeve pipe Sphere projection, the sphere projection of pulling-on piece both sides is symmetrical arranged on pulling-on piece, and sphere projection is in the height direction positioned at pulling-on piece Medium position.
The both sides on pulling-on piece surface are respectively arranged with the ribs on the outside of lock hole, and the thickness of ribs is dashed forward less than sphere The thickness risen, the upper edge and lower edge of ribs flush with lock hole top and bottom respectively.
The both sides on pulling-on piece surface are respectively arranged with the anti-slip veins positioned at pulling-on piece one end.
Using above-mentioned technical proposal, the nut of circumferential fastener is turned by operation, makes the first cross bar, the second cross bar, the Three cross bars and the 4th inside of cross bar connection support block respectively correspond to contact one piece of template, can securely limit four pieces of templates not to Outer movement, but cannot ensure that the cross section of four pieces of templates keeps square shape, therefore, using longitudinal pulling-on piece formula locating part and Horizontal pulling-on piece formula fastener, so ensure that the cross section of four pieces of templates keeps square shape.
Circumferential fastener is easy to fabricate, and also allows for mounting and dismounting, during installation, four screw rods are corresponding through adjacent Mounting seat between two crossbar ends, then nut thread is connected on screw rod and tightened.During dismounting, nut is unclamped, is extracted out Screw rod.Because the angle that four screw rods have between four cross bars is 45 °, in order to avoid screw rod and four pieces of templates it Between produce contact, therefore be respectively provided with support block in four inside of cross bar.
The pulling-on piece sleeve pipe of longitudinal pulling-on piece formula locating part and horizontal pulling-on piece formula fastener can be limited between relative two pieces of templates Distance, so that it is guaranteed that the square chamber that pours in section does not reduce.
Due to setting vertical and horizontal reinforcement in the outer surface of pulling-on piece sleeve pipe, so make the bearing strength of pulling-on piece sleeve pipe big It is big to improve, avoid making pulling-on piece internal surface of sleeve pipe clamp pulling-on piece surface during the casting concrete between inner template and exterior sheathing, and be difficult to Extract pulling-on piece out, the concrete for also functioning to and pouring in addition is securely joined with the effect being integrated;Further, the utility model exists Pulling-on piece surface sets sphere projection, is that sphere projection can support pulling-on piece sleeve pipe, be taken out when outwards after contingency pulling-on piece sleeve pipe is extruded When going out pulling-on piece, due to being contacted between sphere projection and pulling-on piece sleeve pipe for, frictional force also can be smaller, so also can more effortlessly Extract pulling-on piece out.Pulling-on piece sleeve pipe, waling and cross reinforcing can be made into integration using plastics, and pulling-on piece sleeve pipe is disposable Running stores, it is embedded in column, cost is also very low.
Because latch is inserted into lock hole, relative two pieces of templates outwards can oppress lock hole, ribs by latch Setting, add thickness of the pulling-on piece on the outside of lock hole, enhance the durability of lock hole, lock hole can be used for multiple times It also will not in the longitudinal direction expand afterwards, so that the distance between two pieces of relative templates keep constant, pour rear column Thickness is also uniform.
The thickness of ribs is less than the thickness of sphere projection, is so easy to ribs to follow sphere projection to pass through pulling-on piece set Pipe, avoids blocking ribs and can not taking out.
When outwards extracting pulling-on piece out after pouring, latch is taken out out of lock hole, the hand-held a pair of tongs of worker clamps anti-skidding Pulling-on piece one end at line, outwards slightly can firmly extract pulling-on piece out, and anti-slip veins play the phenomenon for preventing pliers clamping from skidding and occurred.
In summary, the utility model have disassembly and installation it is convenient and swift, more effortlessly take out pulling-on piece and Lock hole is also kept intact after pulling-on piece is used for multiple times, and the cross section of the column after pouring keeps square, it is ensured that between four pieces of templates It is constant away from holding, and the compactness of reinforced concrete upright column can be improved.
Brief description of the drawings
Fig. 1 is top view of the present utility model;
Fig. 2 is the structural representation of horizontal pulling-on piece formula fastener in Fig. 1;
Fig. 3 is the schematic surface of pulling-on piece sleeve pipe in Fig. 2;
Fig. 4 is A-A sectional views in Fig. 2;
Fig. 5 is B-B sectional views in Fig. 2.
Embodiment
As Figure 1-Figure 5, building bearing column cast-in-situ template supporting and positioning device of the present utility model, described template 15 are provided with four pieces, and four pieces of templates 15 are arranged in vertical, four pieces of templates 15 be encircled into section it is square pour chamber 27, if the outside of four pieces of templates 15 is disposed with dried layer fastening structure from top to bottom, every layer of fastening structure include from lower and On the circumferential fastener, longitudinal pulling-on piece formula locating part 16 and horizontal pulling-on piece formula fastener 17, the longitudinal pulling-on piece formula that set gradually it is spacing Part 16 is identical with the construction of horizontal pulling-on piece formula fastener 17.
Circumferential fastener includes structure all same and horizontally disposed first cross bar 18, the second cross bar 19, the 3rd cross bar 20 and the 4th cross bar 21, the first cross bar 18, the second cross bar 19, the 3rd cross bar 20 and the 4th cross bar 21 are horizontally disposed and put down respectively In one piece of template 15, the first cross bar 18, the second cross bar 19, the inner side of the 3rd cross bar 20 and the 4th cross bar 21 are fixedly installed row respectively There are abutting end, the second cross bar 19 and of the support block 22 contacted with the lateral surface of template 15, the first cross bar 18 and the second cross bar 19 Abutting end, the 3rd cross bar 20 of three cross bars 20 are adjacent with the first cross bar 18 with abutting end, the 4th cross bar 21 of the 4th cross bar 21 End is connected through a screw thread fastening structure connection.
Screw connection structure between first cross bar 18 and the second cross bar 19 includes the first mounting seat 23, the second mounting seat 24th, screw rod 25 and nut 26, the first mounting seat 23 are fixedly installed on the outside of the end of the first cross bar 18, and the second mounting seat 24 is fixed It is arranged on the outside of the end of the second cross bar 19, screw rod 25 passes through the first mounting seat 23 and the second mounting seat 24, and the screw thread of nut 26 connects It is connected on screw rod 25, the head of screw rod 25 and nut 26 contact with the first mounting seat 23 and the top pressure of the second mounting seat 24 respectively, spiral shell Bar 25 is horizontally disposed and screw rod 25 is in 45 ° of angle with the first cross bar 18 and the second cross bar 19 respectively, the first mounting seat 23 and the Between two mounting seats 24.
Horizontal pulling-on piece formula fastener 17 includes pulling-on piece 1 and pulling-on piece sleeve pipe 2, and pulling-on piece 1 and pulling-on piece sleeve pipe 2 are in flat strip Structure, inserting hole is correspondingly offered between the template 15 in left side and the template 15 on right side, pulling-on piece 1 is plugged in inserting hole, pulling-on piece Sleeve pipe 2 is enclosed between the template 15 on pulling-on piece 1 and positioned at left side and the template 15 on right side, and the length of pulling-on piece sleeve pipe 2 is equal to column Thickness, two are offered on pulling-on piece 1 and is used to plug the lock that latch limits the templates 15 in left side and the spacing of template 15 on right side Determine hole 5, the outer surface of pulling-on piece sleeve pipe 2 sets at least one waling 6 along its length, and the outer surface of pulling-on piece sleeve pipe 2 is along highly Direction is provided with some cross reinforcings 7, and cross reinforcing 7 and waling 6 form criss-cross construction;The table of pulling-on piece 1 The both sides in face are respectively arranged with the sphere projection 8 in pulling-on piece sleeve pipe 2, and the sphere projection 8 of the both sides of pulling-on piece 1 is right on pulling-on piece 1 Claim to set, sphere projection 8 is located at the medium position of pulling-on piece 1 in the height direction.
The both sides on the surface of pulling-on piece 1 are respectively arranged with the ribs 10 positioned at the outside of lock hole 5, and the thickness of ribs 10 is less than The thickness of sphere projection 8, the upper edge and lower edge of ribs 10 flush with the top and bottom of lock hole 5 respectively.
The both sides on the surface of pulling-on piece 1 are respectively arranged with the anti-slip veins 9 positioned at the one end of pulling-on piece 1.
The nut 26 of circumferential fastener is turned by operation, makes the first cross bar 18, the second cross bar 19, the 3rd cross bar 20 and the The support block 22 of the inner side of four cross bar 21 connection corresponds to one piece of template 15 of contact respectively, and it is not outside can securely to limit four pieces of templates 15 It is mobile, but cannot ensure that the cross section of four pieces of templates 15 keeps square shape, therefore, using longitudinal pulling-on piece formula locating part 16 With horizontal pulling-on piece formula fastener 17, so ensure that the cross section of four pieces of templates 15 keeps square shape.
Circumferential fastener is easy to fabricate, and also allows for mounting and dismounting, during installation, four screw rods 25 are corresponding through phase Mounting seat between adjacent two crossbar ends, then nut 26 is threadedly coupled on screw rod 25 and tightened.During dismounting, nut is unclamped 26, extract screw rod 25 out.Because the angle that four screw rods 25 have between four cross bars is 45 °, in order to avoid screw rod Produce and contact between 25 and four pieces of templates 15, therefore support block 22 is respectively provided with four inside of cross bar.
The pulling-on piece sleeve pipe of longitudinal pulling-on piece formula locating part 16 and horizontal pulling-on piece formula fastener 17 can limit relative two pieces of templates 15 The distance between, so that it is guaranteed that the square chamber 27 that pours in section does not reduce.
Due to setting vertical and horizontal reinforcement 7 in the outer surface of pulling-on piece sleeve pipe 2, so make the pressure-bearing of pulling-on piece sleeve pipe 2 strong Degree greatly improves, and avoids making the inwall of pulling-on piece sleeve pipe 2 clamp drawing when pouring casting concrete in chamber 27 between four pieces of templates 15 The surface of piece 1, and be difficult to extract pulling-on piece 1 out, the concrete for also functioning to and pouring in addition is securely joined with the effect being integrated;Further Ground, the utility model set sphere projection 8 on the surface of pulling-on piece 1, are that sphere projection 8 can support after contingency pulling-on piece sleeve pipe 2 is extruded Firmly pulling-on piece sleeve pipe 2, when outwards extracting pulling-on piece 1 out, due to being contacted between sphere projection 8 and pulling-on piece sleeve pipe 2 for point, frictional force also can It is smaller, it so also more can effortlessly extract pulling-on piece 1 out.Pulling-on piece sleeve pipe 2, waling 6 and cross reinforcing 7 can use modeling Material is made into integration, and pulling-on piece sleeve pipe 2 is expendable consumed product, is embedded in column, and cost is also very low.
Because latch is inserted into lock hole 5, relative two pieces of templates 15 outwards can oppress lock hole 5 by latch, add The setting of strong rib 10, thickness of the pulling-on piece 1 in the outside of lock hole 5 is added, the durability of lock hole 5 is enhanced, lock hole 5 can be made It will not also expand in the longitudinal direction after a number of uses, so that the distance between two pieces of relative templates 15 keep constant, The thickness for pouring rear column is also uniform.
The thickness of ribs 10 is less than the thickness of sphere projection 8, is so easy to ribs 10 to follow sphere projection 8 to pass through drawing Piece sleeve pipe 2, avoid blocking ribs 10 and can not taking out.
When pouring rear outwards extraction pulling-on piece 1, latch is taken out from lock hole 5 is interior, the hand-held a pair of tongs of worker clamps anti- One end of pulling-on piece 1 at sliding line 9, outwards slightly can firmly extract pulling-on piece 1 out, and anti-slip veins 9 play the phenomenon for preventing that pliers clamping from skidding Occur.
The present embodiment not makees any formal limitation, every foundation to shape of the present utility model, material, structure etc. Any simple modification, equivalent change and modification that the technical essence of the utility model is made to above example, belongs to this reality With the protection domain of new technique scheme.

Claims (5)

1. building bearing column cast-in-situ template supporting and positioning device, described template-setup has four pieces, and four pieces of templates are along vertical Direction set, four pieces of templates be encircled into section it is square pour chamber, it is characterised in that:The outside of four pieces of templates is from top to bottom If being disposed with dried layer fastening structure, every layer of fastening structure includes circumferential fastener, the longitudinal direction set gradually from bottom to top Pulling-on piece formula locating part and horizontal pulling-on piece formula fastener, longitudinal pulling-on piece formula locating part are identical with the construction of horizontal pulling-on piece formula fastener;
Circumferential fastener includes structure all same and horizontally disposed first cross bar, the second cross bar, the 3rd cross bar and the 4th are horizontal Bar, the first cross bar, the second cross bar, the 3rd cross bar and the 4th cross bar are horizontally disposed and are respectively parallel to one piece of template, and first is horizontal Bar, the second cross bar, the inner side of the 3rd cross bar and the 4th cross bar are fixedly installed the support block contacted with template lateral surface respectively, and One cross bar is adjacent with the 4th cross bar with abutting end, the 3rd cross bar of the 3rd cross bar with abutting end, the second cross bar of the second cross bar End, the 4th cross bar are connected through a screw thread fastening structure with the abutting end of the first cross bar and are connected.
2. building bearing column cast-in-situ template supporting and positioning device according to claim 1, it is characterised in that:First cross bar Screw connection structure between the second cross bar includes the first mounting seat, the second mounting seat, screw rod and nut, and the first mounting seat is consolidated Surely it is arranged on the outside of the end of the first cross bar, the second mounting seat is fixedly installed on the outside of the end of the second cross bar, and screw rod is through the One mounting seat and the second mounting seat, nut thread are connected on screw rod, the head of screw rod and nut respectively with the first mounting seat and Second mounting seat top pressure contacts, and screw rod is horizontally disposed and screw rod is in 45 ° of angle with the first cross bar and the second cross bar respectively, and first Between mounting seat and the second mounting seat.
3. building bearing column cast-in-situ template supporting and positioning device according to claim 1, it is characterised in that:Horizontal pulling-on piece Formula fastener includes pulling-on piece and pulling-on piece sleeve pipe, and pulling-on piece and pulling-on piece sleeve pipe are in flat strip structure, the template in left side and right side Template between correspondingly offer inserting hole, pulling-on piece is plugged in inserting hole, and pulling-on piece sleeve pipe is enclosed on pulling-on piece and positioned at left side Between template and the template on right side, the length of pulling-on piece sleeve pipe is equal to the thickness of column, and offering two on pulling-on piece is used to plug Latch limits the lock hole of the template in left side and the template spacing on right side, and pulling-on piece bushing outer surface sets at least one along its length Bar waling, pulling-on piece bushing outer surface are provided with some cross reinforcings, cross reinforcing and longitudinal direction along short transverse Reinforcement forms criss-cross construction;The both sides on pulling-on piece surface are respectively arranged with the sphere projection in pulling-on piece sleeve pipe, pulling-on piece The sphere projection of both sides is symmetrical arranged on pulling-on piece, and sphere projection is located at the medium position of pulling-on piece in the height direction.
4. building bearing column cast-in-situ template supporting and positioning device according to claim 3, it is characterised in that:Pulling-on piece surface Both sides be respectively arranged with ribs on the outside of lock hole, the thickness of ribs is less than the thickness of sphere projection, ribs Upper edge and lower edge flushed respectively with lock hole top and bottom.
5. building bearing column cast-in-situ template supporting and positioning device according to claim 3, it is characterised in that:Pulling-on piece surface Both sides be respectively arranged with the anti-slip veins positioned at pulling-on piece one end.
CN201720494868.0U 2017-05-05 2017-05-05 Building bearing column cast-in-situ template supporting and positioning device Expired - Fee Related CN206784922U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720494868.0U CN206784922U (en) 2017-05-05 2017-05-05 Building bearing column cast-in-situ template supporting and positioning device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720494868.0U CN206784922U (en) 2017-05-05 2017-05-05 Building bearing column cast-in-situ template supporting and positioning device

Publications (1)

Publication Number Publication Date
CN206784922U true CN206784922U (en) 2017-12-22

Family

ID=60709968

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720494868.0U Expired - Fee Related CN206784922U (en) 2017-05-05 2017-05-05 Building bearing column cast-in-situ template supporting and positioning device

Country Status (1)

Country Link
CN (1) CN206784922U (en)

Similar Documents

Publication Publication Date Title
CN203021899U (en) Quick-assembling template device for concrete ground construction
CN206888509U (en) A kind of box culvert plate outer side template reinforcing device
CN204703928U (en) A kind of formwork jumbo for tunnel sidewalls construction
CN206784922U (en) Building bearing column cast-in-situ template supporting and positioning device
CN204024041U (en) The double-deck shear wall formwork erecting structure of deformation joint
CN104328908A (en) Deformation joint double-layer shear wall formwork structure and method of using formwork structure to construct double-layer shear wall
CN110409432B (en) Prestressed steel pipe pile of concrete dado
CN105239778A (en) Adjustable back beam device for column formwork reinforcement
CN203626237U (en) Steel-wood square column for supporting and forming reinforced concrete member in building construction
CN202509764U (en) Template bracing structure for constructional column
CN204059958U (en) Oblique variable cross-section type column template device
CN104975715A (en) Formwork sealing method for walls or columns
CN107419897B (en) Reinforcing die for windowsill coping template
CN206844636U (en) Wall and the cast-in-place aluminum alloy pattern plate support system of superstructure
CN105442832A (en) Formwork for concrete guide wall
CN203066475U (en) Reusable pull tab component used on architectural aluminum template and detacher thereof
CN201092730Y (en) Supporting structure for construction of composite wall
CN206784923U (en) The cast-in-place aluminum alloy pattern plate fastener of building bearing column
CN206000154U (en) A kind of building pours uses template
CN109235497B (en) Fixing structure for externally-attached water stop belt at pipe gallery gap and construction method of fixing structure
CN208668966U (en) Three-stage split bolt for building
CN206784941U (en) The construction wall construction quick detachable pulling-on piece location structure of aluminum alloy pattern plate
CN110439273A (en) A kind of mold and installation method of telescopic production slope monitoring clump pedestal
CN204456824U (en) Orthogonal stacked steel pipe lever tension type fastener
CN213203839U (en) Reusable box culvert slip form

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20180608

Address after: 461300 Zhoukou County, Henan Province, Fugou County Industrial Park S102 line west of Fugou County Machinery Industrial Park No. 6 workshop.

Patentee after: HENAN DING ALUMINUM ENVIRONMENTAL PROTECTION BUILDING MATERIAL CO.,LTD.

Address before: 450000 2, 903, Xinyuan, Xinyuan, intersection of Longhai Road and Qingfeng street, 27 District, Zhengzhou, Henan.

Patentee before: Zhou Chengjun

CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 461300 Industrial Agglomeration Zone, Fugou County, Zhoukou City, Henan Province

Patentee after: Henan Xiangzhong Technology Co.,Ltd.

Address before: 461300 Fugou County Industrial Park, Zhoukou City, Henan Province, No. 6 Factory Building of Fugou County Machinery Industry Park on the West Side of Line S102

Patentee before: HENAN DING ALUMINUM ENVIRONMENTAL PROTECTION BUILDING MATERIAL CO.,LTD.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171222