CN204024041U - The double-deck shear wall formwork erecting structure of deformation joint - Google Patents
The double-deck shear wall formwork erecting structure of deformation joint Download PDFInfo
- Publication number
- CN204024041U CN204024041U CN201420448920.5U CN201420448920U CN204024041U CN 204024041 U CN204024041 U CN 204024041U CN 201420448920 U CN201420448920 U CN 201420448920U CN 204024041 U CN204024041 U CN 204024041U
- Authority
- CN
- China
- Prior art keywords
- wooden form
- outside
- shear wall
- wooden
- steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn - After Issue
Links
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
The utility model discloses the double-deck shear wall formwork erecting structure of a kind of deformation joint, it comprise first outside wooden form, wooden form outside second, wooden form inside wooden form and second inside first, outside described first, inside wooden form and first, wooden form surrounds and forms left side shear wall pouring practice layer, outside described second, inside wooden form and second, wooden form surrounds and forms right side shear wall pouring practice layer, multiple through-wall bolt is through wooden form outside first, wooden form outside second, wooden form inside wooden form and second inside first, the two ends of through-wall bolt adopt fastening nuts.In the utility model, through-wall bolt and steel chute and channel-section steel keel is adopted jointly to form firm formwork structure, be fixed by insertion groove steel joist when wherein inner side wooden form is installed, install simple, only channel-section steel keel shoe need be taken out during form removal just can the easily demoulding, the template quality formed is higher, makes shear wall also comparatively regular, the better quality of building formation.
Description
Technical field
The utility model relates to the double-deck shear wall formwork erecting structure of a kind of deformation joint.
Background technology
Gap between the double-deck shear wall of tradition deformation joint all comparatively, formwork and form removal all more for convenience, but building structure variation, nowadays building land day is becoming tight, spacing between the double-deck shear wall of deformation joint is more and more less, and in this narrow space, formwork and form removal are all very not easily.
Utility model content
In order to overcome the deficiencies in the prior art, technical problem to be solved in the utility model is to provide a kind of double-deck shear wall formwork erecting structure of deformation joint that can overcome the less double-deck shear wall formwork of spacing and form removal problem all comparatively not easily.
The utility model solves the technical scheme that its technical problem adopts: the double-deck shear wall formwork erecting structure of deformation joint, wooden form outside comprising first, wooden form outside second, wooden form inside wooden form and second inside first, outside described first, inside wooden form and first, wooden form surrounds and forms left side shear wall pouring practice layer, outside described second, inside wooden form and second, wooden form surrounds and forms right side shear wall pouring practice layer, multiple through-wall bolt is through wooden form outside first, wooden form outside second, wooden form inside wooden form and second inside first, the two ends of through-wall bolt adopt fastening nuts, inside described first inside wooden form and avoid through-wall bolt inside wooden form inside second and be vertically provided with a steel chute at interval of a segment distance, steel chute inside steel chute and second inside described first inside wooden form inside wooden form is oppositely arranged between two, inside described first, corresponding steel chute is provided with bar steel plate outside wooden form outside wooden form and inside second, bar steel plate is connected by the rivet rivet clasp penetrating wooden form with steel chute, be oppositely arranged described in two in steel chute and be inserted with channel-section steel keel, the steel chute of channel-section steel keel two side compression both sides.
In the utility model, through-wall bolt and steel chute and channel-section steel keel is adopted jointly to form firm formwork structure, be fixed by insertion groove steel joist when wherein inner side wooden form is installed, install simple, only channel-section steel keel shoe need be taken out during form removal just can the easily demoulding, the template quality formed is higher, makes shear wall also comparatively regular, the better quality of building formation.Because this cover formwork structure can reuse, economy is fine, be conducive to spread, and whole work progress is safe, easy, is conducive to time and cost of labor.
Accompanying drawing explanation
Below in conjunction with drawings and Examples, the utility model type is further illustrated.
Fig. 1 is the structure cross-sectional schematic of the double-deck shear wall of the deformation joint completing formwork that the utility model provides.
Fig. 2 is the structural representation of the steel chute of Fig. 1 first inner side template and the second inner side template, channel-section steel keel and bar steel plate.
Detailed description of the invention
As Fig. 1, shown in Fig. 2, the double-deck shear wall formwork erecting structure of the deformation joint that the utility model provides, wooden form 1 outside comprising first, wooden form 2 outside second, wooden form 4 inside wooden form 3 and second inside first, outside described first, inside wooden form 1 and first, wooden form 3 surrounds and forms left side shear wall pouring practice layer, outside described second, inside wooden form 2 and second, wooden form 4 surrounds and forms right side shear wall pouring practice layer, multiple through-wall bolt 5 is through wooden form 1 outside first, wooden form 2 outside second, wooden form 4 inside wooden form 3 and second inside first, the two ends of through-wall bolt 5 adopt nut 6 fastening, inside described first inside wooden form 3 and avoid through-wall bolt 5 inside wooden form 2 inside second and be vertically provided with a steel chute 7 at interval of a segment distance, steel chute 7 inside steel chute inside described first inside wooden form 37 and second inside wooden form 4 is oppositely arranged between two, inside described first, corresponding steel chute 7 is provided with bar steel plate 8 outside wooden form 4 outside wooden form 3 and inside second, bar steel plate 8 is connected by the rivet rivet clasp penetrating wooden form with steel chute 7, channel-section steel keel 9 are inserted with in the steel chute 7 be oppositely arranged described in two, the steel chute 7 of channel-section steel keel 9 liang of side compression both sides.In the present embodiment, conveniently hold out against steel chute 7, described channel-section steel keel 9 are slightly less than the shape on top in lower end.
The double-deck shear wall formwork erecting structure of the above-mentioned deformation joint of the employing that the utility model provides is constructed the method for double-deck shear wall: comprise A, the design of deformation joint internal mold, materials arrival is checked and accepted, and template and annex make processing; B, delimitation bit line, accomplish fluently spacing, template is temporarily in place; C, by through-wall bolt 5 through wooden form 4 inside wooden form inside wooden form 2, first outside wooden form 1, second outside first 3 and second, the two ends of through-wall bolt 5 adopt nut 6 fastening, inside steel chute 7 is fixed on first inside wooden form 3 and inside second inside wooden form 4, insertion groove steel joist 9 between relative two steel chutes 7; D, surround to template the shear wall pouring practice layer perfusion formed and water and smash structural concrete; E, dismounting framed bent, extract through-wall bolt 5, split off seam middle sleeve, by wooden form 2 demoulding outside wooden form outside first 1 and second, then omit jacking with jack and make channel-section steel keel 9 off-load, channel-section steel keel 9 are hung in recurrence, are unclamped by wooden form 4 inside wooden form inside first in two shear wall gaps 3 and second, wooden form 4 inside wooden form 3 and second inside finally lifting by crane first.
Claims (2)
1. the double-deck shear wall formwork erecting structure of deformation joint, it is characterized in that: wooden form outside comprising first, wooden form outside second, wooden form inside wooden form and second inside first, outside described first, inside wooden form and first, wooden form surrounds and forms left side shear wall pouring practice layer, outside described second, inside wooden form and second, wooden form surrounds and forms right side shear wall pouring practice layer, multiple through-wall bolt is through wooden form outside first, wooden form outside second, wooden form inside wooden form and second inside first, the two ends of through-wall bolt adopt fastening nuts, inside described first inside wooden form and avoid through-wall bolt inside wooden form inside second and be vertically provided with a steel chute at interval of a segment distance, steel chute inside steel chute and second inside described first inside wooden form inside wooden form is oppositely arranged between two, inside described first, corresponding steel chute is provided with bar steel plate outside wooden form outside wooden form and inside second, bar steel plate is connected by the rivet rivet clasp penetrating wooden form with steel chute, be oppositely arranged described in two in steel chute and be inserted with channel-section steel keel, the steel chute of channel-section steel keel two side compression both sides.
2. the double-deck shear wall formwork erecting structure of deformation joint according to claim 1, is characterized in that: described channel-section steel keel are the shape that lower end is slightly less than top.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420448920.5U CN204024041U (en) | 2014-08-11 | 2014-08-11 | The double-deck shear wall formwork erecting structure of deformation joint |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201420448920.5U CN204024041U (en) | 2014-08-11 | 2014-08-11 | The double-deck shear wall formwork erecting structure of deformation joint |
Publications (1)
Publication Number | Publication Date |
---|---|
CN204024041U true CN204024041U (en) | 2014-12-17 |
Family
ID=52063926
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201420448920.5U Withdrawn - After Issue CN204024041U (en) | 2014-08-11 | 2014-08-11 | The double-deck shear wall formwork erecting structure of deformation joint |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN204024041U (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104328908A (en) * | 2014-08-11 | 2015-02-04 | 泰昌建设有限公司 | Deformation joint double-layer shear wall formwork structure and method of using formwork structure to construct double-layer shear wall |
CN106013786A (en) * | 2016-07-18 | 2016-10-12 | 南通四建集团有限公司 | Double-faced steel mold |
CN106284981A (en) * | 2015-06-05 | 2017-01-04 | 中国建筑第四工程局有限公司 | The mold method of two side templates in a kind of shear force wall deformation slit |
CN109356378A (en) * | 2018-11-19 | 2019-02-19 | 上海市政工程设计研究总院(集团)有限公司 | A kind of loam wall version builds steel form and rammed earth wall construction method |
-
2014
- 2014-08-11 CN CN201420448920.5U patent/CN204024041U/en not_active Withdrawn - After Issue
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104328908A (en) * | 2014-08-11 | 2015-02-04 | 泰昌建设有限公司 | Deformation joint double-layer shear wall formwork structure and method of using formwork structure to construct double-layer shear wall |
CN106284981A (en) * | 2015-06-05 | 2017-01-04 | 中国建筑第四工程局有限公司 | The mold method of two side templates in a kind of shear force wall deformation slit |
CN106284981B (en) * | 2015-06-05 | 2019-08-13 | 中国建筑第四工程局有限公司 | The mold method of two side templates in a kind of shear force wall deformation slit |
CN106013786A (en) * | 2016-07-18 | 2016-10-12 | 南通四建集团有限公司 | Double-faced steel mold |
CN109356378A (en) * | 2018-11-19 | 2019-02-19 | 上海市政工程设计研究总院(集团)有限公司 | A kind of loam wall version builds steel form and rammed earth wall construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204024041U (en) | The double-deck shear wall formwork erecting structure of deformation joint | |
CN204174935U (en) | A kind of outer wall of basement one side formwork supporting and protection structure | |
CN204492190U (en) | Aluminum alloy mould plate back cord fastening devices | |
CN104328908B (en) | Movement joint bilayer shear wall formwork erecting structure and the method adopting the double-deck shear wall of described formwork erecting structure construction | |
CN104453224A (en) | Formwork support structure of basement exterior wall and construction method of formwork support structure | |
CN104295088A (en) | Steel-wood combined formwork structure of shear walls on two sides of deformation joint and construction method of steel-wood combined formwork structure | |
CN204799908U (en) | Locking mechanism of casting sand box | |
CN204940860U (en) | One prevents Form floating part | |
CN204715763U (en) | A kind of aluminum alloy mould plate diagonal brace supporting member pre-embedded bolt structure | |
CN201835440U (en) | Anti-deformation concrete steel pipe column | |
CN204456428U (en) | A kind of entirety being installed on composite wallboard is waftd window | |
CN207048312U (en) | Tool-type post formwork for Large area reinforced concrete post | |
CN203808501U (en) | Early-removing jacking support based on existing fastener-type scaffold | |
CN202509764U (en) | Template bracing structure for constructional column | |
CN203320918U (en) | Square tube scaffold | |
CN204152551U (en) | A kind of reusable mine down-hole filling barricade | |
CN203821841U (en) | Casting die for specially-shaped column | |
CN104295093B (en) | Between frame construction twin columns, deformation joint builds the construction method of formwork system | |
CN203097290U (en) | Assembled type split bolt | |
CN105442832A (en) | Formwork for concrete guide wall | |
CN204679074U (en) | A kind of novel surface observation pier structure | |
CN203334660U (en) | Base plate post-cast strip formwork for concrete pouring | |
CN207920082U (en) | A kind of magnetic-type engineering pipeline reserved opening assembling die | |
CN204850142U (en) | Outer wall body drawknot device | |
CN204510688U (en) | A kind of temporary fixing structure of precast wall panel |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
AV01 | Patent right actively abandoned |
Granted publication date: 20141217 Effective date of abandoning: 20160629 |
|
C25 | Abandonment of patent right or utility model to avoid double patenting |