CN206772123U - Novel cooling tower operation controller - Google Patents
Novel cooling tower operation controller Download PDFInfo
- Publication number
- CN206772123U CN206772123U CN201720502498.0U CN201720502498U CN206772123U CN 206772123 U CN206772123 U CN 206772123U CN 201720502498 U CN201720502498 U CN 201720502498U CN 206772123 U CN206772123 U CN 206772123U
- Authority
- CN
- China
- Prior art keywords
- cooling tower
- tower body
- module
- controller
- output end
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Abstract
The utility model discloses Novel cooling tower operation controller, including cooling tower body and higher level's external equipment, the side of the cooling tower body is connected with feeding spraying pump by pipeline, the sewage draining exit that opposite side is set is located at the lower section of controller body, the other end of the jet pipe of connection is located at the inside of cooling tower body at the top of the feeding spraying pump, and the bottom even of jet pipe is fixed with six shower nozzles, the inside of the controller body is provided with internal battery, and it is provided with display screen and control button on a side of controller body, the display location is in the side of control button, the surface cooler of the cooling tower body interior installation is located at the lower section of shower nozzle.The utility model uses single-chip microcomputer integration module mode, integrated temperature and conductivity measurement module, installed in cooling tower opening position, it is possible to provide RS485 modules carry out communication and used for upper level centralized Control, can greatly lift the control efficiency of existing cooling tower.
Description
Technical field
It the utility model is related to control system part technical field, specially Novel cooling tower operation controller.
Background technology
Cooling tower (The cooling tower) be by the use of water as circulating coolant, absorbed from system heat dissipation to
In air, to reduce the device of water temperature;It is to carry out cold and hot exchange after contacting with air flow using water to produce steam, steam that its is cold
Volatilization takes away heat and reaches the principles such as evaporative heat loss, convection heat transfer' heat-transfer by convection and radiant heat transfer to disperse industrially or be produced in refrigeration air-conditioner
Waste heat reduce the evaporating radiator of water temperature, to ensure the normal operation of system, device is generally tubbiness, therefore named for cooling
Tower.Cooling tower is collection aerodynamics, thermodynamics, fluidics, chemistry, biochemistry, materialogy, quiet, dynamic structure mechanics, is added
The condensation products that a variety of subjects such as work technology are integrated.Water quality be multivariable function, cooling it is even more multifactor, multivariable with it is more
The process of effect synthesis.
At present, existing cooling tower startup and stop be traditional approach electric controling mode, that is, manually start or PLC control
System, but PLC controls the basic need later stage artificially to increase, it is insufficient with system matches and convenience on probation, and small-sized cooling tower increases
Addition is originally higher uneconomical.
Utility model content
The purpose of this utility model is to provide Novel cooling tower operation controller, to solve to propose in above-mentioned background technology
The PLC control basic need later stages of traditional cooling tower artificially increase, insufficient and small-sized cold with system matches and convenience on probation
But the tower increase higher uneconomic problem of cost.
In order to solve the above-mentioned technical problem, the utility model provides following technical scheme:Novel cooling tower operation controller,
Including cooling tower body and higher level's external equipment, the side of the cooling tower body is connected with feeding spraying pump by pipeline, another
The sewage draining exit that side is set is located at the lower section of controller body, and the other end of the jet pipe connected at the top of the feeding spraying pump is positioned at cooling
The inside of tower body, and the bottom even of jet pipe is fixed with six shower nozzles, the inside of the controller body is provided with built-in storage
Battery, and display screen and control button are provided with a side of controller body, the display location is in control button
Side, the surface cooler of the cooling tower body interior installation are located at the lower section of shower nozzle, and the blower fan that cooling tower bodies top is fixed
Bottom be located at the setting of cooling tower body interior jet pipe top, the output end of higher level's external equipment communicates with RS485
The input connection of module, the output end of the RS485 communication modules are connected with the input of controller body, and the warming is visited
The output end of head and the input of integrated temperature module connect, the output end of the integrated temperature module and conductivity measurement module
Input with single-chip microcomputer integration module is connected, the output end of the single-chip microcomputer integration module respectively with feeding spraying pump and blower fan
Input connection, the feeding spraying pump and blower fan with controller body be electrically connected with.
Further, the temperature sensitive probe is arranged on the inside of cooling tower body.
Further, the integrated temperature module, conductivity measurement module and single-chip microcomputer integration module are respectively positioned on controller
The inside of body.
Further, the blower fan is fixedly connected with cooling tower body by fastener.
Further, it is provided with control valve on the sewage draining exit.
Compared with prior art, the beneficial effect that the utility model is reached is:The equipment, using single-chip microcomputer integration module
Mode, integrated temperature and conductivity measurement module, installed in cooling tower opening position, it is possible to provide RS485 modules carry out communication for upper
One-level centralized Control uses, and can greatly lift the control efficiency of existing cooling tower, can be reduced on small-sized and independent cooling tower
Overall use and control cost.
Brief description of the drawings
Accompanying drawing is used for providing further understanding to of the present utility model, and a part for constitution instruction, with this practicality
New embodiment is used to explain the utility model together, does not form to limitation of the present utility model.In the accompanying drawings:
Fig. 1 is the structural representation of the utility model cooling tower body;
Fig. 2 is the structural representation of the utility model controller body;
Fig. 3 is theory diagram of the present utility model;
In figure:1st, feeding spraying pump;2nd, surface cooler;3rd, jet pipe;4th, blower fan;5th, cooling tower body;6th, shower nozzle;7th, controller sheet
Body;8th, internal battery;9th, sewage draining exit;10th, display screen;11st, control button;12nd, temperature sensitive probe;13rd, integrated temperature module;
14th, higher level's external equipment;15th, RS485 communication modules;16th, conductivity measurement module;17th, single-chip microcomputer integration module.
Embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, the technical scheme in the embodiment of the utility model is carried out
Clearly and completely describing, it is clear that described embodiment is only the utility model part of the embodiment, rather than whole
Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are not under the premise of creative work is made
The every other embodiment obtained, belong to the scope of the utility model protection.
Fig. 1-3 are referred to, the utility model provides Novel cooling tower operation controller technical scheme:Novel cooling tower is run
Controller, including cooling tower body 5 and higher level's external equipment 14, the side of cooling tower body 5 are connected with shower water by pipeline
Pump 1, the sewage draining exit 9 that opposite side is set are located at the lower section of controller body 7, the other end of the jet pipe 3 of the top of feeding spraying pump 1 connection
Bottom even positioned at the inside of cooling tower body 5, and jet pipe 3 is fixed with six shower nozzles 6, the inside installation of controller body 7
There is internal battery 8, and display screen 10 and control button 11 are provided with a side of controller body 7, display screen 10
In the side of control button 11, the surface cooler 2 of the inside of cooling tower body 5 installation is located at the lower section of shower nozzle 6, and cooling tower body 5
The bottom for the blower fan 4 that top is fixed be located at the top of the jet pipe 3 of the inside of cooling tower body 5 setting, higher level's external equipment 14 it is defeated
Go out end to be connected with the input of RS485 communication modules 15, the output end of RS485 communication modules 15 and the input of controller body 7
End connection, the output end of temperature sensitive probe 12 are connected with the input of integrated temperature module 13, integrated temperature module 13 and electrical conductivity
Input of the output end of measurement module 16 with single-chip microcomputer integration module 17 is connected, the output end point of single-chip microcomputer integration module 17
Input not with feeding spraying pump 1 and blower fan 4 is connected, and feeding spraying pump 1 and blower fan 4 are electrically connected with controller body 7.
Further, temperature sensitive probe 12 is arranged on the inside of cooling tower body 5.
Further, integrated temperature module 13, conductivity measurement module 16 and single-chip microcomputer integration module 17 are respectively positioned on control
The inside of device body 7.
Further, blower fan 4 is fixedly connected with cooling tower body 5 by fastener.
Further, it is provided with control valve on sewage draining exit 9.
Operation principle:During work, internal battery 8 is connected with external power source, deposited electric energy by internal battery 8
Storage is got up, so as to provide electric energy for controller body 7, by RS485 communication modules 15 by controller body 7 with being set outside higher level
Standby 14 connect, and detect the temperature inside cooling tower body 5 by temperature sensitive probe 12 and feed back to integrated temperature module 13, lead to
Cross integrated temperature module 13 and send signal to single-chip microcomputer integration module 17 again, electrical conductivity is carried out by conductivity measurement module 16
Measurement, and measurement data is fed back into single-chip microcomputer integration module 17, then each electricity of control is realized by single-chip microcomputer integration module 17
The startup and stopping of property element, and the regulation and control of each parameter, in addition, higher level's external equipment 14 can also pass through RS485 communication modules
15 realize the centralized Control use to each module inside controller body 7, so as to improve control efficiency.
Finally it should be noted that:Preferred embodiment of the present utility model is the foregoing is only, is not limited to this
Utility model, although the utility model is described in detail with reference to the foregoing embodiments, for those skilled in the art
For, it can still modify to the technical scheme described in foregoing embodiments, or to which part technical characteristic
Carry out equivalent substitution.All any modification, equivalent substitution and improvements within the spirit and principles of the utility model, made etc.,
It should be included within the scope of protection of the utility model.
Claims (5)
1. Novel cooling tower operation controller, including cooling tower body(5)With higher level's external equipment(14), it is characterised in that:Institute
State cooling tower body(5)Side feeding spraying pump is connected with by pipeline(1), the sewage draining exit of opposite side setting(9)Positioned at control
Device body(7)Lower section, the feeding spraying pump(1)The jet pipe of top connection(3)The other end be located at cooling tower body(5)It is interior
Portion, and jet pipe(3)Bottom even be fixed with six shower nozzles(6), the controller body(7)Inside built-in electric power storage is installed
Pond(8), and controller body(7)A side on be provided with display screen(10)And control button(11), the display screen
(10)Positioned at control button(11)Side, the cooling tower body(5)The surface cooler of inside installation(2)Positioned at shower nozzle(6)'s
Lower section, and cooling tower body(5)The blower fan that top is fixed(4)Bottom be located at cooling tower body(5)The jet pipe that inside is set(3)
Top, higher level's external equipment(14)Output end and RS485 communication modules(15)Input connection, the RS485
Communication module(15)Output end and controller body(7)Input connection, temperature sensitive probe(12)Output end and integrated temperature
Spend module(13)Input connection, the integrated temperature module(13)With conductivity measurement module(16)Output end with list
Piece machine integration module(17)Input connection, the single-chip microcomputer integration module(17)Output end respectively with feeding spraying pump(1)
And blower fan(4)Input connection, the feeding spraying pump(1)And blower fan(4)With controller body(7)It is electrically connected with.
2. Novel cooling tower operation controller according to claim 1, it is characterised in that:The temperature sensitive probe(12)Installation
In cooling tower body(5)Inside.
3. Novel cooling tower operation controller according to claim 1, it is characterised in that:The integrated temperature module
(13), conductivity measurement module(16)With single-chip microcomputer integration module(17)It is respectively positioned on controller body(7)Inside.
4. Novel cooling tower operation controller according to claim 1, it is characterised in that:The blower fan(4)With cooling tower
Body(5)It is fixedly connected by fastener.
5. Novel cooling tower operation controller according to claim 1, it is characterised in that:The sewage draining exit(9)Upper setting
There is control valve.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720502498.0U CN206772123U (en) | 2017-05-08 | 2017-05-08 | Novel cooling tower operation controller |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720502498.0U CN206772123U (en) | 2017-05-08 | 2017-05-08 | Novel cooling tower operation controller |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206772123U true CN206772123U (en) | 2017-12-19 |
Family
ID=60650085
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720502498.0U Expired - Fee Related CN206772123U (en) | 2017-05-08 | 2017-05-08 | Novel cooling tower operation controller |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206772123U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108519019A (en) * | 2018-05-08 | 2018-09-11 | 江苏华塔冷却技术有限公司 | A kind of cooling tower intelligence water regulating system and its adjusting method |
-
2017
- 2017-05-08 CN CN201720502498.0U patent/CN206772123U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108519019A (en) * | 2018-05-08 | 2018-09-11 | 江苏华塔冷却技术有限公司 | A kind of cooling tower intelligence water regulating system and its adjusting method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205119873U (en) | Compound cooling tower of high temperature flue gas | |
CN203687257U (en) | Solar driving type indirect/direct evaporation cooling air conditioning unit | |
CN107560044B (en) | Evaporative cooling air-conditioning system for providing electric energy by using industrial waste heat | |
CN105650787A (en) | Solar heating and evaporative cooling combined air conditioner used in winter and summer | |
CN206772123U (en) | Novel cooling tower operation controller | |
CN103759363A (en) | Evaporative cooling air conditioner system combining passive cooling and heating | |
CN203744443U (en) | Wind energy, solar energy and dry air energy combined air conditioner | |
CN204678566U (en) | The energy-saving Evaporative Cooling Air-conditioning System of anti-freeze formula | |
CN102853494B (en) | Evaporation cooling air conditioning system capable of providing electric energy by using industrial exhaust heat | |
CN208519900U (en) | A kind of photovoltaic water cooling solution dehumidifying air-conditioning system | |
CN207179881U (en) | Low energy consumption solution dehumidifying air-conditioning system | |
CN115790200A (en) | Dry-wet combined defogging type closed cooling tower and working method | |
CN204786979U (en) | Indirect evaporative cooling air -conditioning unit of vertical high efficiency | |
CN207166456U (en) | A kind of intelligent remote manipulation photovoltaic heat pump combination hot-water heating system | |
CN202769854U (en) | Evaporative cooling air conditioner utilizing industrial residual heat to supply electric energy | |
CN203628892U (en) | Automatic-control solar power generation evaporative cooling air conditioner used for bus station | |
CN203571922U (en) | Evaporative cooling and solar power generation combined air-conditioner applicable to sentry box | |
CN102832283A (en) | Component structure for adjusting temperature of photovoltaic components by water circulation | |
CN202855786U (en) | Solar photovoltaic and photothermal integrated device | |
CN207218634U (en) | A kind of cooling heat radiator of photovoltaic plant | |
CN206459372U (en) | A kind of industrial premises of solar energy photovoltaic utilization | |
CN205718059U (en) | A kind of solar heat pump and water heating, cold air, heating installation all-in-one | |
CN220250736U (en) | Cross-flow type high-temperature cooling tower | |
CN109539372A (en) | Solar energy heating pump, multi-source heating refrigeration system | |
CN205843069U (en) | Solar Enercy Fission Geyser |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |