CN206727563U - Crane span structure attachment means - Google Patents
Crane span structure attachment means Download PDFInfo
- Publication number
- CN206727563U CN206727563U CN201621160047.5U CN201621160047U CN206727563U CN 206727563 U CN206727563 U CN 206727563U CN 201621160047 U CN201621160047 U CN 201621160047U CN 206727563 U CN206727563 U CN 206727563U
- Authority
- CN
- China
- Prior art keywords
- connecting plate
- crane span
- span structure
- attachment means
- arc
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Jib Cranes (AREA)
Abstract
The utility model discloses a kind of crane span structure attachment means, including the first connecting plate and the second connecting plate, the first described connecting plate is provided with two upper interface arrangments and two lower interface arrangments, the upper end for being placed in the first described connecting plate at described two upper interface arrangment intervals, described two lower interface arrangments are placed in the lower end both sides of the first described connecting plate;The upper end of the second described connecting plate is provided with the mounting hole being engaged with described two upper interface arrangments, and lower end is provided with the arc fold bending structure being engaged with described lower interface arrangment.The technical solution adopted in the utility model, realize that the non-bolt of crane span structure quickly clamps on the basis of crane span structure bearing capacity is met, improve installation effectiveness more than 5 times.
Description
Technical field
The invention belongs to field of machining, more particularly, to a kind of crane span structure attachment means.
Background technology
Traditional cable crane span structure when mounted, is fixed between section and section by the connecting plate of termination both sides, and every connecting plate needs
6~8 sets of connecting bolts are wanted, then each connection end needs 12~16 sets of connecting bolts to fix.Installation effectiveness is low, causes engineering
Installation progress seriously lags.
Connecting bolt shared quantity in whole engineering material doses is larger, and surface treatment general in industry at present is general
For plating, the surface treatment with crane span structure body seriously mismatches.In cable testing bridge installing engineering surface treatment be generally plastic-spraying or
Galvanizing, service life are not less than 40 years.And bolt as connection crane span structure vital part, its electroplate anticorrosive coat its use the longevity
Life is no more than 15 years, and especially the life-span can be lower in a humid environment.Traditional solution has two kinds, and one kind is periodic replacement
Bolt, another kind are to use special bolt, improve the service life of bolt.The first solve solution in service life extremely
Needing to change 3 bolts less, maintenance cost is high, in-convenience in use;Second of solution needs to improve the material of bolt, initial stage
Put into larger, construction cost height.
The content of the invention
It is an object of the invention to provide a kind of crane span structure attachment means, improve the installation progress of crane span structure engineering, reduce and safeguard
Cost.
To achieve the above object, the technical solution adopted by the present invention is:Crane span structure attachment means, including the first connecting plate and
Two connecting plates, the first described connecting plate are provided with two upper interface arrangments and two lower interface arrangments, described two upper cards
Connect the upper end for being placed in the first described connecting plate of spacing structure, described two lower interface arrangments described first that be placed in connects
The lower end both sides of fishplate bar;The upper end of the second described connecting plate is provided with the mounting hole being engaged with described two upper interface arrangments,
Lower end is provided with the arc fold bending structure being engaged with described lower interface arrangment.
The technical solution adopted by the present invention, on the basis of crane span structure bearing capacity is met, realize the non-bolt rapid card of crane span structure
Dress, more than 5 times of installation effectiveness is improved, and maintenance cost is low, crane span structure engineering whole service life length.
Further, the first described connecting plate is provided with spill muscle face, and described two upper interface arrangments are placed in spill
The upper end in muscle face, described two lower interface arrangments are placed in the lower end both sides in described spill muscle face.
Transition arc caused by upper and lower two pairs of interface arrangments shaping is located in the cavity of spill muscle, when being assembled with crane span structure
It can ensure that the first connecting plate is bonded with perfect on the inside of crane span structure.
Further, described upper interface arrangment is the upper arc hook that Open Side Down, and described lower interface arrangment is opening
Upward lower arc hook;Described upper arc hook and lower arc hook are made by mould punching stretching, the draw direction with it is described
Spill muscle face it is in opposite direction.
The punching press spill muscle face on the first connecting plate, direction stretches and arc hook is made on spill muscle face, improves first
The intensity of connecting plate, it is possible to reduce the thickness of connecting plate, reduce the deadweight of attachment means.
Further, described upper arc hook is provided with symmetrical neck, and described mounting hole is convex mouth, the convex mouth
Upper end be engaged with described neck.
Neck convex structure of mounting hole, crane span structure attachment means can be effectively improved in the convenience of construction and fixed firm
Property.
Further, the both sides of the second described connecting plate are respectively equipped with perpendicular to the second described connecting plate length direction
Convex hull-shaped reinforcement, upper end is provided with arc fold bending, the direction of described arc fold bending and the side of described convex hull-shaped reinforcement
To vertical
Convex hull-shaped reinforcement together constitutes the reinforcement structure of the second connecting plate with arc fold bending, improves the second connecting plate
Intensity.
Further, the transition position of described upper arc hook is provided with circular adjustment hole.
Circular adjustment hole adjusts the interior, cooperation position of the second connecting plate, and the second connecting plate of auxiliary in construction and installation
Installation.
Brief description of the drawings
Fig. 1, the first connecting board structure schematic diagram;
Fig. 2, the second connecting board structure schematic diagram;
Fig. 3, straight-through portal structure schematic diagram;
Fig. 4, crane span structure attachment means are arranged on the structural representation on crane span structure.
Embodiment
As depicted in figs. 1 and 2, crane span structure attachment means, including the first connecting plate 1 and the second connecting plate 2.Described first connects
Fishplate bar 1 is provided with two upper interface arrangments and two lower interface arrangments.In embodiment, in order to improve the intensity of attachment means,
Spill muscle face can be suppressed with mould on the first connecting plate, the negative drawing at spill muscle face upper end interval go out two be open to
Under upper arc hook 4, upper arc hook is provided with circular adjustment hole;Be open each stretched one of the lower end both sides in spill muscle face to
On lower arc hook 5.The mounting hole being engaged with two described arc hooks is interval with the upper end of the second connecting plate 2.
In order to which clamping is firm in actual use, neck, the second connecting plate 2 are respectively equipped with arc hook on two of the first connecting plate 1
On mounting hole be arranged to male ports 6, the upper end size of male ports 6 is consistent with the size of described neck, in the second connecting plate 2
Lower end be provided with the arc fold bending structure 7 that is engaged with the arc hook 5 of described opening upwards.
In order to improve the intensity of the second connecting plate 2, arc fold bending 8 is provided with along its length in the upper end of the second connecting plate 2,
The convex hull-shaped reinforcement 9 perpendicular to the length direction of the second connecting plate 2, the convex hull-shaped are provided with the both sides of the second connecting plate 2
Reinforcement 9 is vertical with the direction of described arc fold bending 8, arc fold bending 7, effectively raises the overall strong of the second connecting plate 2
Degree.
As shown in Figure 3 and Figure 4, installation process of the invention is to set installation respectively on the both ends on straight-through ladder 10
Hole, the first connecting plate 1 is inserted on the inside of crane span structure, and arc hook passes through from crane span structure hole;Second connecting plate 2 is tilted 15 ° -45 °,
Specified location is penetrated from the arc hook of the first connecting plate opening upwards, the projecting apertures aligned in position on convex hole site and crane span structure
When, rotate the second connecting plate 2, until the inner plane of the second connecting plate 2 and crane span structure outside be bonded, 4 male ports two of the second connecting plate
The wing is sticked into the neck of the upper arc hook of the first connecting plate 1, completes to clamp.
The operation principle of the present invention is as follows:
First, the height of the arc fold bending of the lower end of the second connecting plate 2 is more than the first connecting plate 1 and dehisced with crane span structure assembling rear side
Chamber size in formula arc hook, then the lower end circular arc bending of the second connecting plate 2 can smoothly tilt what the first connecting plate 1 of insertion was dehisced upwards
In arc hook, crane span structure can be progressively clamped in the rotary course of the second connecting plate 2, this process utilizes the rigidity of steel itself, opens upwards
The steel construction of the arc hook of mouth has preferably elasticity and tensile strength.It is more convenient for firm grip crane span structure, because under the second connecting plate 2
The center of side circular arc bending is in outside, and the power for giving the second connecting plate 2 to provide a larger despining.
2nd, the ultimate range of the both wings of the upside projecting apertures of the second connecting plate 2 and downside arc hook is less than circle on the first connecting plate
The upper plane of arc hook and the distance of downside open mouth type arc hook inner plane, so the second connecting plate 2, in rotation process, upside is convex
The track rotation of upside arc hook outer surface of the both wings in hole along the first connecting plate 1, because the upper arc hook of the first connecting plate
Rigidity be far longer than downside open mouth type circular arc hook structure elasticity, then pulled in rotation process whole second connecting plate 2 to
Upper movement, the elastic deformation of the first connecting plate open mouth type arc hook increase to maximum.Projecting apertures both wings on the upside of the second connecting plate turn
When moving to the upper arc hook neck of the first connecting plate 1, the rigidity disappearance of the upside arc hook of the first connecting plate, downside open mouth type circle
Arc uncinate gyrus bullet pulls the second connecting plate integrally to move down, and enters the first connecting plate so as to the upside projecting apertures both wings of the second connecting plate
Upside arc hook neck in, and the complete clamping of overall structure is made by despining power.
The scheme that the present invention uses, it is first, second connecting plate, by structure design, is meeting crane span structure bearing capacity basis
On realize that the non-bolt of crane span structure quickly clamps, improve more than 5 times of installation effectiveness.Avoid the use of bolt, reduce project into
This.
First connecting plate:Mould suppress matrix muscle, for increase connecting plate self-strength (matrix muscle also has an effect,
Concave bar face and arc hook are reverse, so can effectively avoid the transition arc of arc hook and base surface, make the first connection
Plate is preferably adjacent to bridge ladder side.), upper and lower each two arc hooks of concave bar face negative drawing arc hook.Arc hook is upper on wherein
Plane sets two symmetrical necks, and arc hook transition position sets technique circular hole, and lower arc hook is open mouth type, and circular hole rises when mounted
Booster action.
Second connecting plate:Upper end is adopted as arc fold bending, for increasing connecting plate longitudinal strength, naturally it is also possible to using it
The muscle of his shape;Projecting apertures coordinates with upper arc hook to be clamped;Convex closure is used to increase connecting plate transverse strength, the circular arc bending of lower end with
Lower arc hook coordinates, clamping crane span structure, and increases for increasing connecting plate longitudinal strength.
Scheme provided by the invention, the bridge joint connection in each field is widely suitable for, does not use connecting bolt.Have following
Some advantage:1. directly saving bolt cost, 2. connecting plates are consistent with crane span structure body anti-corrosion, and increase crane span structure entirety uses the longevity
Life, 3. installations are quick, save human cost.4. improve project installation progress.
Claims (6)
1. a kind of crane span structure attachment means, it is characterised in that including the first connecting plate and the second connecting plate, the first connecting plate and second
Connecting plate, the first described connecting plate are provided with two upper interface arrangments and two lower interface arrangments, described two upper clampings
The upper end for being placed in the first described connecting plate of spacing structure, described two lower interface arrangments are placed in the first described connection
The lower end both sides of plate;The upper end of the second described connecting plate is provided with the mounting hole being engaged with described two upper interface arrangments, under
End is provided with the arc fold bending structure being engaged with described lower interface arrangment.
2. according to the crane span structure attachment means described in claim 1, it is characterised in that the first described connecting plate is provided with spill muscle
Face, described two upper interface arrangments are placed in the upper end in spill muscle face, and described two lower interface arrangments are placed in described recessed
The lower end both sides in shape muscle face.
3. according to the crane span structure attachment means described in claim 2, it is characterised in that described upper interface arrangment is what Open Side Down
Upper arc hook, described lower interface arrangment are the lower arc hook of opening upwards;Described upper arc hook is with lower arc hook by mould
Tool punching stretch is made, and the draw direction is in opposite direction with described spill muscle face.
4. according to the crane span structure attachment means described in claim 3, it is characterised in that described upper arc hook is provided with symmetrical card
Groove, described mounting hole are convex mouth, and the upper end of the convex mouth is engaged with described neck.
5. according to the crane span structure attachment means described in claim 4, it is characterised in that the upper both sides difference of the second described connecting plate
Provided with the convex hull-shaped reinforcement perpendicular to the second connecting plate length direction, top and bottom are provided with arc fold bending, described
The direction of arc fold bending is vertical with the direction of described convex hull-shaped reinforcement.
6. according to the crane span structure attachment means any one of claim 3-5, it is characterised in that the mistake of described upper arc hook
The place of crossing is provided with circular adjustment hole.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621160047.5U CN206727563U (en) | 2016-11-01 | 2016-11-01 | Crane span structure attachment means |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621160047.5U CN206727563U (en) | 2016-11-01 | 2016-11-01 | Crane span structure attachment means |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206727563U true CN206727563U (en) | 2017-12-08 |
Family
ID=60498947
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201621160047.5U Expired - Fee Related CN206727563U (en) | 2016-11-01 | 2016-11-01 | Crane span structure attachment means |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206727563U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108683129A (en) * | 2018-03-20 | 2018-10-19 | 罗格朗低压电器(无锡)有限公司 | Quick Connect Kit and metal type cable conduit |
-
2016
- 2016-11-01 CN CN201621160047.5U patent/CN206727563U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108683129A (en) * | 2018-03-20 | 2018-10-19 | 罗格朗低压电器(无锡)有限公司 | Quick Connect Kit and metal type cable conduit |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105805112B (en) | A kind of universal joint assembly for the connection of rod piece space structure | |
CN206727564U (en) | Crane span structure attachment structure | |
CN206727563U (en) | Crane span structure attachment means | |
CN207010088U (en) | A kind of electric force pole tower pulley hanging point device | |
CN107181215A (en) | Crane span structure attachment structure and the installation method using the structure | |
CN206225126U (en) | A kind of device for strengthening transformer stability | |
CN202555754U (en) | Arc-shaped anvil | |
CN204899114U (en) | Argil board coupling assembling | |
CN203617637U (en) | Cable ladder plane connecting piece | |
CN206783062U (en) | A kind of light elevator solid guide rail | |
CN208844365U (en) | A kind of track type intelligent inspection robot track turn structure | |
CN201820632U (en) | Novel box edge correcting tool | |
CN209013142U (en) | Hook gear and illuminator | |
CN209369340U (en) | A kind of crossbeam mental section | |
CN105710676B (en) | A kind of flexible fixture | |
CN205669310U (en) | A kind of template pouring panel and composition thereof being easily installed | |
CN205439256U (en) | A assembly quality for rubber component | |
CN208680275U (en) | A kind of bending machine quarter bend curved arc fixture | |
CN209725448U (en) | A kind of auxiliary device for the lifting of deep well pump lifting pipe | |
CN204080157U (en) | A kind of electroplanting device of screw block | |
CN212687315U (en) | Fan blade prefabricated auxiliary beam lifting appliance | |
CN105058563B (en) | A kind of brick-making mould containing assembled peg | |
CN209943753U (en) | Conversion flange | |
CN208734720U (en) | One kind being fastenedly connected support assembling stand | |
CN208994979U (en) | A kind of workshop aluminium alloy hanger rail |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20171208 Termination date: 20211101 |
|
CF01 | Termination of patent right due to non-payment of annual fee |