CN206722829U - Hanging scaffold stabilizer is built in a kind of vertical shaft for mine pick - Google Patents
Hanging scaffold stabilizer is built in a kind of vertical shaft for mine pick Download PDFInfo
- Publication number
- CN206722829U CN206722829U CN201720507595.9U CN201720507595U CN206722829U CN 206722829 U CN206722829 U CN 206722829U CN 201720507595 U CN201720507595 U CN 201720507595U CN 206722829 U CN206722829 U CN 206722829U
- Authority
- CN
- China
- Prior art keywords
- hanging scaffold
- pole
- vertical shaft
- hinged
- hydraulic lift
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Load-Engaging Elements For Cranes (AREA)
Abstract
A kind of vertical shaft for mine pick block hanging scaffold stabilizer for building equipment technical field is dug the utility model discloses vertical shaft for mine,Including hanging scaffold body,The lower center position of the hanging scaffold body is provided with hydraulic lift,The bottom clutch end of the hydraulic lift is provided with fixed block,Hinged seat is mounted at left and right sides of the bottom of the hanging scaffold body,Pole is hinged with the hinged seat,The other end of the pole is provided with block rubber,The left and right sides of the fixed block is hinged with connecting rod,The other end of the connecting rod is hinged on the outer wall of pole,When hanging scaffold is fixed,Hydraulic lift is opened by control device,So that the power arm recovery of hydraulic lift,So as to drive pole to open by connecting rod,So that the end of pole is withstood on the inwall of vertical shaft,Serve the effect to the stabilization of hanging scaffold,Greatly reduce artificial intensity,Improve the stability of hanging scaffold.
Description
Technical field
It the utility model is related to vertical shaft for mine pick and build equipment technical field, it is stable that hanging scaffold is built in specially a kind of vertical shaft for mine pick
Device.
Background technology
During vertical shaft for mine pick is built, construction hanging scaffold serves as transport, the vital task of place apparatus.The position of hanging scaffold with
Construction speed changes up and down at any time,, in order to ensure the safety of workmen and equipment due to placed construction equipment on hanging scaffold
Asking will keep hanging scaffold to be in level at the moment in this process.Reducer and wall base segment are frequently encountered in vertical shaft driving and masonry construction,
It is simple that hanging scaffold, center can not be consolidated using former timber wedge when being dropped down onto under a certain layer of hanging scaffold or multilayer disc in expansion footpath section
Turn round out caused hanging scaffold during barren rock and swing larger, have a strong impact on the safe operation of well-bucket and the safety of hanging scaffold operating personnel.For
This, it is proposed that hanging scaffold stabilizer is built in a kind of pick of vertical shaft for mine.
Utility model content
The purpose of this utility model is that providing a kind of vertical shaft for mine pick builds hanging scaffold stabilizer, to solve above-mentioned background technology
The simple of middle proposition can not consolidate hanging scaffold using former timber wedge, and it is larger that center steering goes out caused hanging scaffold swing during barren rock,
Have a strong impact on well-bucket safe operation and hanging scaffold operating personnel it is safe the problem of.
To achieve the above object, the utility model provides following technical scheme:Hanging scaffold stabilizer is built in a kind of vertical shaft for mine pick,
Including hanging scaffold body, the lower center position of the hanging scaffold body is provided with hydraulic lift, the hydraulic lift
Bottom clutch end is provided with fixed block, and hinged seat is mounted at left and right sides of the bottom of the hanging scaffold body, described be hinged
Pole is hinged with seat, the other end of the pole is provided with block rubber, and the left and right sides of the fixed block is hinged with connecting rod,
The other end of the connecting rod is hinged on the outer wall of pole.
Preferably, control device is installed, and control device is electrically connected with hydraulic lift on the hanging scaffold body.
Preferably, the left side top of the block rubber and bottom are provided with shoulder hole, and the inner chamber of the shoulder hole is provided with
Bolt, right side and the pole of the bolt are spirally connected.
Preferably, the right side of the left side of the left side block rubber and the right side block rubber is provided with antiskid thread.
Compared with prior art, the beneficial effects of the utility model are:A kind of vertical shaft for mine pick that the utility model proposes
Hanging scaffold stabilizer is built, when hanging scaffold is fixed, hydraulic lift is opened by control device so that hydraulic lift
Power arm recovery, so as to pass through connecting rod drive pole open so that the end of pole is withstood on the inwall of vertical shaft, is played
Effect to the stabilization of hanging scaffold, greatly reduces artificial intensity, improves the stability of hanging scaffold.
Brief description of the drawings
Fig. 1 is the utility model structure diagram;
Fig. 2 is the utility model pole and block rubber attachment structure schematic diagram.
In figure:1 hanging scaffold body, 2 hydraulic lifts, 3 hinged seats, 4 fixed blocks, 5 poles, 6 connecting rods, 7 block rubbers, 8 ranks
Terraced hole, 9 bolts.
Embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, the technical scheme in the embodiment of the utility model is carried out
Clearly and completely describing, it is clear that described embodiment is only the utility model part of the embodiment, rather than whole
Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are not under the premise of creative work is made
The every other embodiment obtained, belong to the scope of the utility model protection.
Fig. 1-2 is referred to, the utility model provides a kind of technical scheme:Hanging scaffold stabilizer, bag are built in a kind of vertical shaft for mine pick
Hanging scaffold body 1 is included, the lower center position of the hanging scaffold body 1 is provided with hydraulic lift 2, the hydraulic lift 2
Bottom clutch end fixed block 4 is installed, be mounted on hinged seat 3 at left and right sides of the bottom of the hanging scaffold body 1, it is described
Pole 5 is hinged with hinged seat 3, the other end of the pole 5 is provided with block rubber 7, and the left and right sides of the fixed block 4 is cut with scissors
Connecting rod 6 is connected to, the other end of the connecting rod 6 is hinged on the outer wall of pole 5.
Wherein, control device is installed on the hanging scaffold body 1, and control device is electrically connected with hydraulic lift 2,
It is easy to control the flexible of hydraulic lift 2, the left side top of the block rubber 7 and bottom are provided with shoulder hole 8, the ladder
The inner chamber in hole 8 is provided with bolt 9, and right side and the pole 5 of the bolt 9 are spirally connected, and are connected block rubber 7 and pole 5 by bolt 9
Connect so that block rubber 7 is more firmly mounted, and bolt 9 is arranged in shoulder hole 8, is prevented the end face of bolt 9 from exposing, is led
The abrasion of bolt 9 is caused, the right side of left side and the right side block rubber 7 of the left side block rubber 7 is provided with antiskid thread, improves
The skidproof effect of block rubber 7.
Operation principle:After hanging scaffold body 1 is moved to specified location, when hanging scaffold body 1 is fixed, pass through hanging scaffold
Control device control hydraulic lift 2 on body 1 so that the power arm recovery of hydraulic lift 2, so as to pass through
Connecting rod 6 drives pole 5 to open so that the block rubber 7 of the end of pole 5 is withstood on the inwall of vertical shaft, is served to hanging scaffold body 1
Stabilization effect, the setting of block rubber 7 serves the effect of resilient support, and it is identical that pole 5 and connecting rod 6 can be arranged to structure
Three groups, when being arranged to three groups, three groups of poles 5 and connecting rod 6 it is equidistant centered on hydraulic lift 2 be in equilateral triangle
Arrangement, pole 5 and connecting rod 6 can also be arranged to four groups of structure identical, and four groups of poles 5 and connecting rod 6 are with hydraulic lift 2
The square arrangement in center, when progress hanging scaffold body 1 moves up and down, pass through control device and control the dynamic of hydraulic lift 2
The arm of force extends, so as to reclaim pole 5, you can carries out moving up and down for hanging scaffold body 1.
While there has been shown and described that embodiment of the present utility model, for the ordinary skill in the art,
It is appreciated that these embodiments can be carried out with a variety of changes in the case where not departing from principle of the present utility model and spirit, repaiied
Change, replace and modification, the scope of the utility model are defined by the appended claims and the equivalents thereof.
Claims (4)
1. hanging scaffold stabilizer, including hanging scaffold body (1) are built in a kind of vertical shaft for mine pick, it is characterised in that:The hanging scaffold body (1)
Lower center position is provided with hydraulic lift (2), and the bottom clutch end of the hydraulic lift (2) is provided with admittedly
Determine block (4), be mounted on hinged seat (3) at left and right sides of the bottom of the hanging scaffold body (1), be hinged with the hinged seat (3)
Pole (5), the other end of the pole (5) are provided with block rubber (7), the left and right sides company of being hinged with of the fixed block (4)
Bar (6), the other end of the connecting rod (6) are hinged on the outer wall of pole (5).
2. hanging scaffold stabilizer is built in a kind of vertical shaft for mine pick according to claim 1, it is characterised in that:The hanging scaffold body
(1) control device is installed, and control device is electrically connected with hydraulic lift (2) on.
3. hanging scaffold stabilizer is built in a kind of vertical shaft for mine pick according to claim 1, it is characterised in that:The block rubber (7)
Left side top and bottom be provided with shoulder hole (8), the inner chamber of the shoulder hole (8) is provided with bolt (9), the bolt (9)
Right side be spirally connected with pole (5).
4. hanging scaffold stabilizer is built in a kind of vertical shaft for mine pick according to claim 1, it is characterised in that:The left side block rubber
(7) right side of left side and the right side block rubber (7) is provided with antiskid thread.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720507595.9U CN206722829U (en) | 2017-05-09 | 2017-05-09 | Hanging scaffold stabilizer is built in a kind of vertical shaft for mine pick |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720507595.9U CN206722829U (en) | 2017-05-09 | 2017-05-09 | Hanging scaffold stabilizer is built in a kind of vertical shaft for mine pick |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206722829U true CN206722829U (en) | 2017-12-08 |
Family
ID=60509803
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720507595.9U Expired - Fee Related CN206722829U (en) | 2017-05-09 | 2017-05-09 | Hanging scaffold stabilizer is built in a kind of vertical shaft for mine pick |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206722829U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108344469A (en) * | 2018-03-14 | 2018-07-31 | 许昌学院 | A kind of radar level gauge device |
-
2017
- 2017-05-09 CN CN201720507595.9U patent/CN206722829U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108344469A (en) * | 2018-03-14 | 2018-07-31 | 许昌学院 | A kind of radar level gauge device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103850684B (en) | A kind of shaft excavation machine expands the sinking shaft technique of anti-well rig pilot shaft | |
CN206987726U (en) | A kind of all-hydraulic side roofboltier of two-arm | |
CN201747390U (en) | Suspension type multifunctional tunnel operation machine | |
CN206903582U (en) | It may move double-arm rock bolting jumbo | |
CN109296374B (en) | TBM hoisting and translation method for deep well enclosed space | |
CN204754953U (en) | Railway tunnel stock platform truck and drilling device thereof | |
CN107227934A (en) | A kind of oil-well rig tubing string automated programming system | |
CN105569692A (en) | Trolley for welding tunnel waterproof board hanging cloth | |
CN206722829U (en) | Hanging scaffold stabilizer is built in a kind of vertical shaft for mine pick | |
CN205330690U (en) | Cloth welding platform truck is hung to tunnel water proofing board | |
CN106823190B (en) | Inverted L-shaped deep well rescue device and method | |
CN112302534B (en) | Slope anchor rod construction device and rapid construction method | |
CN206467542U (en) | A kind of concrete flattening device of Construction of Civil Engineering | |
CN114045854A (en) | Bridge pile foundation composite construction method under complex geological condition | |
CN205063835U (en) | Novel hydraulic drive derrick mechanism | |
CN206128160U (en) | Operation device that open caisson sinks unearthedly | |
CN207046714U (en) | A kind of Large-scale Hoisting equipment | |
CN109607384A (en) | The turn-over method of super-large-diameter shield machine knife disk | |
CN210636446U (en) | Geotechnical engineering supports safety arrangement | |
CN113250090A (en) | Climbing device of light hydraulic climbing formwork | |
CN204475350U (en) | Bored pile construction system under high-voltage line | |
CN109736704B (en) | Reverse circulation drilling machine and construction method thereof | |
CN211549732U (en) | Novel supporting device for coal mine tunnel | |
CN209924411U (en) | Hanging flower basket for construction | |
CN207142783U (en) | A kind of chute type aerial ladder |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20171208 Termination date: 20180509 |
|
CF01 | Termination of patent right due to non-payment of annual fee |