CN206716283U - A kind of paint applicators - Google Patents

A kind of paint applicators Download PDF

Info

Publication number
CN206716283U
CN206716283U CN201720496987.XU CN201720496987U CN206716283U CN 206716283 U CN206716283 U CN 206716283U CN 201720496987 U CN201720496987 U CN 201720496987U CN 206716283 U CN206716283 U CN 206716283U
Authority
CN
China
Prior art keywords
paint
erecting bed
connecting rod
installation set
storage paint
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720496987.XU
Other languages
Chinese (zh)
Inventor
沈振飞
殷旭初
陆晓飞
陈燕伟
马曹锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Haiyan Municipal Engineering Co Ltd
Original Assignee
Haiyan Municipal Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Haiyan Municipal Engineering Co Ltd filed Critical Haiyan Municipal Engineering Co Ltd
Priority to CN201720496987.XU priority Critical patent/CN206716283U/en
Application granted granted Critical
Publication of CN206716283U publication Critical patent/CN206716283U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Spray Control Apparatus (AREA)

Abstract

The utility model discloses a kind of paint applicators, including body, wheel, plunger pump, around socket, flexible pipe, spray gun, storage paint can, erecting bed, connecting rod is rotatably connected on the downside of erecting bed, connecting rod is provided with the spring for being connected on erecting bed on one end away from erecting bed, store up and be provided with installation set on the outer wall of paint can, be provided with connecting rod for the locating rod through installation set, when spring in the raw when, locating rod passes through installation set.The utility model has advantages below and effect:This programme utilizes new mechanical structure, foot pedal, connecting rod can drive spring elongation, now locating rod can depart from out of installation set, and operating personnel can remove storage paint can from erecting bed, when needing to position storage paint can again, storage paint can is again placed on erecting bed, after operating personnel unclamp connecting rod, locating rod can again pass through installation set, final to can be achieved that eaily position of the storage paint can in flush coater is fixed.

Description

A kind of paint applicators
Technical field
Spraying equipment is the utility model is related to, more particularly to a kind of paint applicators.
Background technology
Flush coater is mainly used in by liquid spray on building, is frequently used for paint spraying in body surface, nowadays Flush coater wide variety, product tends to be ripe.
At present, Publication No. CN205851162U, the day for announcing are Chinese patent on January 4th, 2017《A kind of automotive paints spray Painting machine》Disclose a kind of automotive paints flush coater, including wheel, coating machine main body, plunger pump, universal wheel and storage paint can, spraying Wheel and universal wheel are provided with below machine body, storage paint can is provided with inside coating machine main body, makes that paint, plunger can be stored in flush coater For pump above coating machine main body, the inlet of plunger pump is arranged on the lower section of storage paint can, makes the paint in storage paint can be abundant Utilize, plunger pump front end is provided with tube wrapping device, longer flexible pipe can be wound on tube wrapping device, is easy to flush coater storage and mobile, spray Painting machine body upper part is provided with push handle so that operating personnel can easily promote flush coater, and coating machine main body front portion is provided with auxiliary Help handle so that operating personnel can be easily by flush coater lifting, and coating machine main body is provided with slide rail, is provided with below storage paint can The sliding block coordinated with slide rail so that storage paint can easily remove flush coater, the addition painted.
This kind of automotive paints flush coater is embedded in the slide rail on coating machine main body using the sliding block stored up on paint can, so as to real Paint can is now stored up conveniently to be shifted out out of flush coater, but when this kind of automotive paints flush coater climb and fall, due to storing up the position of paint can Put and do not fixed on flush coater, storage paint can may slide on the ground from slide rail, so as to cause to store up oil after paint can rollover Paint is poured out out of storage paint can.
Utility model content
The purpose of this utility model is to provide a kind of paint applicators, can be easily to storing up position of the paint can in flush coater Put and be fixed.
Above-mentioned technical purpose of the present utility model technical scheme is that:A kind of paint applicators, Including body, the wheel being arranged on the downside of the body, the plunger pump being arranged on the body, it is arranged on the plunger pump one On end around socket, the flexible pipe being arranged on the plunger pump, be arranged on the flexible pipe away from the spray on described plunger pump one end Rifle, the storage paint being arranged in the body, it is arranged on the erecting bed placed in the body for the storage paint can, the installation Connecting rod is rotatably connected on the downside of platform, the connecting rod is provided with one end away from the erecting bed for being connected to the peace The spring on platform is filled, installation set is provided with the outer wall of the storage paint can, is provided with and is used for through the peace in the connecting rod The locating rod of encapsulation, when the spring in the raw when, the locating rod passes through the installation set.
By using such scheme, this kind of paint applicators position when needs to the storage paint being placed on erecting bed When, using the connecting rod being rotatably connected on the downside of erecting bed, while using connecting rod away from the spring on erecting bed one end, spring When in the raw, the locating rod in connecting rod is that may pass through the installation set on storage paint can, now can be on erecting bed Storage paint can is positioned;When needing to remove storage paint can from erecting bed, bar is rotatablely connected, connecting rod can drive spring to draw Stretch, now locating rod can depart from out of installation set, and operating personnel can remove storage paint can from erecting bed, when needing again When being positioned to storage paint can, storage paint can is again placed on erecting bed, after operating personnel unclamp connecting rod, locating rod Installation set is again passed through, it is final to can be achieved that eaily position of the storage paint can in flush coater is fixed.
It is of the present utility model to be further arranged to:The first chute is symmetrically arranged with the erecting bed, the storage paint can Downside is symmetrically arranged with the pulley for being respectively embedded in described in both sides in the first chute, and positioning is provided with first chute Block, when the pulley is contradicted when on the locating piece, the locating rod passes through the installation set.
By using such scheme, when storage paint can needs to be placed on erecting bed, the pulley stored up on paint can is utilized to be embedded in Into the first chute, now only need storage paint being moved on erecting bed along the first chute, than relatively labor-saving and conveniently, Simultaneously using the locating piece set in the first chute, contradicted after pulley sliding when on locating piece, now unclamp connecting rod, After spring-return, the position of installation set can just pass through for locating rod, fairly simple convenience.
It is of the present utility model to be further arranged to:The connecting rod is provided with pedal on one end away from the erecting bed.
By using such scheme, when operating personnel need to be rotatablely connected bar or unclamp connecting rod, the company of being arranged on is utilized For extension bar away from the pedal on erecting bed one end, operating personnel only need the i.e. controllable connecting rod of foot pedals, operate fairly simple It is laborsaving.
It is of the present utility model to be further arranged to:Turn positioned at the erecting bed on the body of the wheel side It is dynamic to be connected with two pieces of connecting plates, the second chute being respectively embedded into for pulley described in both sides is provided with described in both sides on connecting plate.
By using such scheme, when needing to move storage paint can from erecting bed, because erecting bed has one Fixed height, storage paint can easily jolt when being slid from erecting bed, now using being rotatably connected on erecting bed close to wheel The connecting plate of side, connecting plate can contradict on the ground after putting down, while be using the second chute on connecting plate, storage paint can Can be from connecting plate than shallower landing on the ground.
It is of the present utility model to be further arranged to:Installing plate is provided with the body on the upside of the storage paint can, Be symmetrically arranged with screwed hole on the installing plate, after the connecting plate is rotated up, the connecting plate and the installing plate it Between be provided through the bolt that the connecting plate rear thread is connected in the screwed hole.
By using such scheme, after storage paint can is placed on erecting bed, connecting plate can now be received Get up, using the installing plate on the upside of storage paint can on body, after connecting plate rotates to upside, after passing through connecting plate using bolt It is threaded in installing plate upper screwed hole, you can connecting plate is stably fixed on installing plate, when needing to use connecting plate, Connecting plate can be put down by backing out bolt.
It is of the present utility model to be further arranged to:The head of the bolt is provided with the chain for being connected on the body Bar.
By using such scheme, the chain set using the head of bolt, and chain is connected on body, when screw thread is twisted It still can be hung on body after lower, avoid the loss of bolt.
In summary, the utility model has the advantages that:This kind of paint applicators are when needs are to being placed on installation When storage paint can on platform is positioned, using the connecting rod being rotatably connected on the downside of erecting bed, while using connecting rod away from peace Fill the spring on platform one end, spring in the raw when, the locating rod in connecting rod is that may pass through the installation set on storage paint can, The storage paint can on erecting bed can now be positioned;When needing to remove storage paint can from erecting bed, foot pedal is Rotate the connecting rods, connecting rod can drive spring elongation, and now locating rod can depart from out of installation set, operating personnel Storage paint can is removed from erecting bed, when needing to position storage paint can again, storage paint can is again placed at erecting bed On, after operating personnel unclamp connecting rod, locating rod can again pass through installation set, final to can be achieved eaily to paint storage Position of the bucket in flush coater is fixed.
Brief description of the drawings
Fig. 1 is the utility model structure diagram;
Fig. 2 is the enlarged drawing in A portions in Fig. 1, is mainly used in embodying installation set, erecting bed, the first chute, locating piece, connection Annexation between bar, spring, locating rod;
Fig. 3 is the enlarged drawing in B portions in Fig. 1, is mainly used in embodying the annexation between connecting plate, installing plate, bolt;
Fig. 4 is annexation sectional view between connecting plate in the utility model, installing plate, bolt.
In figure:1st, body;11st, connecting plate;111st, the second chute;12nd, installing plate;121st, screwed hole;122nd, bolt;123、 Chain;2nd, wheel;3rd, plunger pump;4th, around socket;5th, flexible pipe;6th, spray gun;7th, paint can is stored up;71st, installation set;72nd, pulley;8th, install Platform;81st, the first chute;811st, locating piece;9th, connecting rod;91st, spring;92nd, locating rod;93rd, pedal.
Embodiment
The utility model is described in further detail below in conjunction with accompanying drawing.
A kind of paint applicators, reference picture 1, this kind of paint applicators include body 1, and the downside of body 1 is provided with wheel 2, wheel 2 drives flush coater movement, and the upside of body 1 is provided with plunger pump 3, flexible pipe 5 is connected with plunger pump 3, and flexible pipe 5 is remote Spray gun 6 is installed on one end of plunger pump 3, is sprayed and painted by spray gun 6;It is provided with one end of plunger pump 3 soft for winding Pipe 5 is placed with storage paint can 7, paint can 7 is stored up by pipeline communication in plunger pump 3, positioned at storage around socket 4, the inside of wherein body 1 The erecting bed 8 placed for storage paint can 7 is welded with the body 1 of the downside of paint can 7.
Reference picture 1, Fig. 2, the first guard rail is welded with the body 1 of the left and right sides of storage paint can 7, and positioned at storage The second guard rail is also welded with the body 1 of the front side of paint can 7;Wherein positioned at the downside of erecting bed 8 and close to the second guard rail There is a connecting rod 9 one end by hinge, and connecting rod 9 is located at the middle part of erecting bed 8, connecting rod 9 away from erecting bed 8 one Pedal 93 is welded with end, spring 91 is installed on one end of pedal 93 positioned at connecting rod 9, one end of spring 91 is welded on In connecting rod 9, the other end of spring 91 is welded in the side wall of erecting bed 8 of upside.
Connecting rod 9 is welded with locating rod 92 close to the side of spring 91, and locating rod 92 is perpendicular to connecting rod 9;Wherein storage paint Installation set 71 is welded with the outer wall of bucket 7, and the downside for storing up paint can 7 is symmetrically installed with pulley 72;It is simultaneously symmetrical on erecting bed 8 Offer respectively for the first chute 81 of two side rollers 72 insertion, and the middle part of erecting bed 8 offers and passed through for locating rod 92 Notch, wherein be wholely set locating piece 811 in the first chute 81, when pulley 72 is contradicted when on locating piece 811, locating rod 92 be to be penetrated into again in installation set 71 after may pass through notch.
Reference picture 1, Fig. 3, Fig. 4, there are two pieces of companies by hinge on the body 1 of the side of wheel 2 positioned at erecting bed 8 Fishplate bar 11, connecting plate 11 offer connecting hole, the position of two side connecting plates 11 and the first chute of both sides 81 on one end away from body 1 Put it is corresponding, wherein offered on connecting plate 11 for pulley 72 be embedded in the second chute 111;Simultaneously positioned at the upside of storage paint can 7 Installing plate 12 is welded with body 1, screwed hole 121 is symmetrically offered on installing plate 12, the internal thread of screwed hole 121 is connected with bolt 122, after being contradicted after connecting plate 11 is rotated up on installing plate 12, you can pass through the company on connecting plate 11 using bolt 122 Hole rear thread is connect to be connected in screwed hole 121;The head of bolt 122 is welded with chain 123 simultaneously, and chain 123 is away from bolt 122 One end be welded on body 1.
This specific embodiment is only that it is not to limitation of the present utility model, ability to explanation of the present utility model Field technique personnel can make the modification of no creative contribution to the present embodiment as needed after this specification is read, but As long as all protected in right of the present utility model by Patent Law.

Claims (6)

1. a kind of paint applicators, including body(1), be arranged on the body(1)The wheel of downside(2), be arranged on the machine Body(1)On plunger pump(3), be arranged on the plunger pump(3)On one end around socket(4), be arranged on the plunger pump(3)On Flexible pipe(5), be arranged on the flexible pipe(5)Away from the plunger pump(3)Spray gun on one end(6), be arranged on the body(1) Interior storage paint can(7), be arranged on the body(1)It is interior to supply the storage paint can(7)The erecting bed of placement(8), it is characterised in that:Institute State erecting bed(8)Downside is rotatably connected to connecting rod(9), the connecting rod(9)Away from the erecting bed(8)One end on set Have for being connected to the erecting bed(8)On spring(91), the storage paint can(7)Outer wall on be provided with installation set(71), The connecting rod(9)On be provided with for through the installation set(71)Locating rod(92), when the spring(91)In certainly During right state, the locating rod(92)Through the installation set(71).
A kind of 2. paint applicators according to claim 1, it is characterised in that:The erecting bed(8)On be symmetrically arranged with First chute(81), the storage paint can(7)Downside be symmetrically arranged with for being respectively embedded in the first chute described in both sides(81) Interior pulley(72), first chute(81)Inside it is provided with locating piece(811), when the pulley(72)Contradict in the positioning Block(811)When upper, the locating rod(92)Through the installation set(71).
A kind of 3. paint applicators according to claim 2, it is characterised in that:The connecting rod(9)Away from the installation Platform(8)One end on be provided with pedal(93).
A kind of 4. paint applicators according to claim 3, it is characterised in that:Positioned at the erecting bed(8)Close to described Wheel(2)The body of side(1)On be rotatably connected to two pieces of connecting plates(11), connecting plate described in both sides(11)On be respectively provided with Have and supply pulley described in both sides(72)The second chute being respectively embedded into(111).
A kind of 5. paint applicators according to claim 4, it is characterised in that:Positioned at the storage paint can(7)The institute of upside State body(1)On be provided with installing plate(12), the installing plate(12)On be symmetrically arranged with screwed hole(121), when the connection Plate(11)After being rotated up, the connecting plate(11)With the installing plate(12)Between be provided through the connecting plate(11)Afterwards It is threaded in the screwed hole(121)Interior bolt(122).
A kind of 6. paint applicators according to claim 5, it is characterised in that:The bolt(122)Head be provided with For being connected to the body(1)On chain(123).
CN201720496987.XU 2017-05-05 2017-05-05 A kind of paint applicators Expired - Fee Related CN206716283U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720496987.XU CN206716283U (en) 2017-05-05 2017-05-05 A kind of paint applicators

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720496987.XU CN206716283U (en) 2017-05-05 2017-05-05 A kind of paint applicators

Publications (1)

Publication Number Publication Date
CN206716283U true CN206716283U (en) 2017-12-08

Family

ID=60510206

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720496987.XU Expired - Fee Related CN206716283U (en) 2017-05-05 2017-05-05 A kind of paint applicators

Country Status (1)

Country Link
CN (1) CN206716283U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111346754A (en) * 2020-04-29 2020-06-30 北京朋禹利明文化有限公司 High environment-friendly five metals paint spraying machine of security
CN113304906A (en) * 2021-06-24 2021-08-27 蒋林峰 Device that building safety helmet sprayed paint

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111346754A (en) * 2020-04-29 2020-06-30 北京朋禹利明文化有限公司 High environment-friendly five metals paint spraying machine of security
CN111346754B (en) * 2020-04-29 2021-09-21 肇庆市端州区海宇机械设备有限公司 High environment-friendly five metals paint spraying machine of security
CN113304906A (en) * 2021-06-24 2021-08-27 蒋林峰 Device that building safety helmet sprayed paint

Similar Documents

Publication Publication Date Title
CN105298092B (en) Hand type spray coating machine for building
CN206716283U (en) A kind of paint applicators
CN205777370U (en) A kind of external wall spraying prosthetic device
CN207254619U (en) A kind of construction site steel pipe scaffold paint spraying machine
CN204716124U (en) Portable removable level-sensing device inspection platform
CN105964455A (en) Metal inner wall antirust spraying device
CN107755130B (en) A kind of wheel hub paint spraying apparatus
CN109290105A (en) A kind of spray equipment for inner wall of the pipe even application
CN207761250U (en) It is a kind of to facilitate the clean construction wall surface spraying device of paint can inner wall
CN209303065U (en) A kind of spray equipment for inner wall of the pipe even application
CN112090641A (en) Refractory material spraying equipment
CN108086653A (en) A kind of mobile model wall surface spraying device of architectural decoration
CN207812960U (en) A kind of mobile model wall surface spraying device of architectural decoration
CN206716269U (en) The device of rust prevention by applying liquid material liquid after cleaning oil tank
CN204515822U (en) Automatic steel tube counting equipment
CN107780633A (en) A kind of wall covering spray equipment
CN204827250U (en) Whitewashing drilling tool
CN203806871U (en) Portable waterwheel frame
CN209211915U (en) A kind of high-altitude wire frame installation system
CN209310989U (en) A kind of oil tank aqueous vapor pressing detecting device
CN207368595U (en) A kind of anticorrosive plastic-steel cable tray
CN207348401U (en) A kind of inner wall of building brushing constructing device
CN206561418U (en) A kind of pneumatic type Plate feeding apparatus
CN206942082U (en) The powder of automatic plastering machine smears device
CN106824586B (en) A kind of static state casting casting spraying equipment

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171208