CN206693220U - Artificial digging pile resistance to plucking structure - Google Patents

Artificial digging pile resistance to plucking structure Download PDF

Info

Publication number
CN206693220U
CN206693220U CN201720554228.4U CN201720554228U CN206693220U CN 206693220 U CN206693220 U CN 206693220U CN 201720554228 U CN201720554228 U CN 201720554228U CN 206693220 U CN206693220 U CN 206693220U
Authority
CN
China
Prior art keywords
pile
pile body
artificial digging
resistance
prestress anchorage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720554228.4U
Other languages
Chinese (zh)
Inventor
黄伟
刘洋
卢宇明
黄天柱
陈超
蒋斌
张弛
赵宝云
董倩
李子运
许年春
吴同情
况龙川
董秀坤
王思长
王丽萍
彭燕
吕庆江
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing University of Science and Technology
Original Assignee
Chongqing University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing University of Science and Technology filed Critical Chongqing University of Science and Technology
Priority to CN201720554228.4U priority Critical patent/CN206693220U/en
Application granted granted Critical
Publication of CN206693220U publication Critical patent/CN206693220U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a kind of artificial digging pile resistance to plucking structure, the prestress anchorage cable of more than one including pile body and the axial withdrawal resistance of enhancing, the axial prestress anchor cable is arranged in pile body, and upper end is anchored in the pile crown of pile body by fixture, lower end is anchored in pile body surrounding formations radially across pile body side wall;In artificial digging pile pile body casting concrete and after reaching design strength, by stretch-draw prestressing force anchor cable to strengthen the withdrawal resistance of artificial digging pile, pile body durability and anti-pulling capacity can greatly improve.The structure construction is simple, segmentation is carried out, it is quality controllable, during for artificial digging pile by upward pulling capacity, particularly with the relatively low artificial digging pile of mountain area embedded rock pile side friction, the structure and its construction method can effectively improve the breakout capacity of artificial digging pile, greatly strengthen the durability of artificial digging pile pile body.

Description

Artificial digging pile resistance to plucking structure
Technical field
A kind of uplift pile is the utility model is related to, more particularly to a kind of artificial digging pile resistance to plucking structure.
Background technology
Artificial digging pile be widely used in science of bridge building, railway engineering, highway engineering, power engineering, hydraulic engineering and The pile foundation pore-forming of Geological Engineering.The pile foundation of artificial digging pile typically bears Compression, but under some special stressing conditions, Artificial digging pile bears upward pulling capacity, grouser in such as suspension bridge, the electric power pylon pile foundation biased.In clay stratum And in the lithostratigraphy of part, artificial digging pile lateral frictional force is relatively low, and pile body quilt is easily made in the presence of pull out force is pulled up Extract, cause huge engineering accident.In order to increase artificial digging pile withdrawal resistance, typically added in engineering practice using pile body side wall Solid method, or the method using stake top pressurization, but the increased withdrawal resistance of these methods is limited, and resistance to plucking effect is simultaneously paid no attention to Think.
Utility model content
In view of this, the purpose of this utility model is to provide a kind of artificial digging pile resistance to plucking structure, improves manually digging hole Stake withdrawal resistance and enhancing uplift pile pile body durability, construction is simple, quality controllable, be particularly suitable for use in the side such as mountain area embedded rock pile frictional resistance The relatively low artificial digging pile of power.
Artificial digging pile resistance to plucking structure of the present utility model, include more than one of pile body and enhancing pile body axial direction withdrawal resistance Prestress anchorage cable, the prestress anchorage cable is vertically to being arranged in pile body, and upper end is anchored in the pile crown of pile body, and lower end is radially Pile body surrounding formations are anchored in through pile body side wall;
Further, the prestress anchorage cable in pile body is uniform along pile body radial multilayer;
Further, the prestress anchorage cable outside pile body is vertically uniform to multilayer along pile body periphery ground;
Further, the pile body External prestressed anchor cable and the angle for forming 30-45 ° of pile body side wall;
Further, the prestress anchorage cable is sheathed in disrance sleeve;
Further, the slip casting of perfusion mortar fixation prestress anchorage cable is provided with along the pile body side wall to periphery soil layer Hole, reinforcing bar is provided with the pile body side wall;
Further, the vertical anchor cable of the anchored end of the prestress anchorage cable sets end plate;
Further, the prestress anchorage cable is anchored in pile body surrounding formations with lower inclined pull type and applies prestressing force.
The beneficial effects of the utility model:Artificial digging pile resistance to plucking structure of the present utility model, in artificial digging pile pile body On the basis of, apply prestress anchorage cable, the withdrawal resistance of artificial digging pile, pile body durability and resistance to plucking are strengthened by the tensioning of anchor cable Bearing capacity can be greatly improved, construction is simple, and segmentation is carried out, quality controllable, during for artificial digging pile by upward pulling capacity, Particularly with the relatively low artificial digging pile of the side frictions such as mountain area embedded rock pile, the structure and its construction method can effectively improve The breakout capacity of artificial digging pile, strengthen uplift pile pile body durability.
Brief description of the drawings
The utility model is further described with reference to the accompanying drawings and examples:
Fig. 1 is uplift pile of the prior art;
Fig. 2 cross-sectional views of the present utility model;
Fig. 3 is the structural representation enlarged drawing of prestress anchorage cable and disrance sleeve.
Embodiment
Fig. 1 is uplift pile of the prior art;The cross-sectional view of Fig. 2 present invention;Fig. 3 be prestress anchorage cable with every From the structural representation enlarged drawing of sleeve pipe.As shown in the figure:The prestress anchorage cable manually digging hole uplift pile of the present embodiment, including pile body 1 ' With prestress anchorage cable 2 ', the ' of prestress anchorage cable 2 of more than one of enhancing pile body axial direction withdrawal resistance vertically to being arranged at pile body 1 ' is interior, and the pile crown 3 of pile body 1 ' is fixed in upper end, and lower end is anchored in the periphery of pile body 1 ' rock stratum radially across the side wall of pile body 1 '; The ' of prestress anchorage cable 2 forms anchoring section between the side wall of pile body 1 ' 4 and surrounding formations, in artificial digging pile pile body casting concrete And after reaching design strength, by the ' of prestress anchorage cable 2 tensioning to strengthen the withdrawal resistance of artificial digging pile, while pile body is resistance to Long property and anti-pulling capacity can greatly improve.
In the present embodiment, the interior ' of prestress anchorage cable 2 of pile body 1 ' is uniform along the radial multilayer of pile body 1 ';Outer pre- of pile body 1 ' should The ' of power anchor cable 2 is vertically uniform to multilayer along the periphery of pile body 1 ' ground;Layering anchoring is carried out in the outer Rock And Soil of pile body 1 ', is anchored Section forms similar " tree root " structure, improves the bearing capacity and breakout capacity of pile body 1 ', and in use, prestressed application will Allow pile body concrete compression in advance, compression (generally 10~20MPa) is produced on pile body.When there is uplift force, uplift force Caused tension, which needs to offset, arrives compression of the prestressing force to concrete, then just allows pile concrete tension, therefore, in advance should The presence of power is to assisting pile body tension to have important contribution.
In the present embodiment, the ' of the External prestressed of pile body 1 ' anchor cable 2 and the angle for forming 30-45 ° of the side wall of pile body 1 ' 4, stake The withdrawal resistance of body is maximum.
In the present embodiment, the ' of prestress anchorage cable 2 is sheathed in disrance sleeve;Prevent anchor cable gets rusty from being corroded.
In the present embodiment, it is provided with perfusion mortar to periphery soil layer along the side wall of pile body 1 ' 4 and fixes prestressed anchor The ' of rope 2 injected hole 6, reinforcing bar is provided with the side wall of pile body 1 ' 4;Perfusion after the ' of prestress anchorage cable 2 is positioned in injected hole 6 Cement mortar added with accelerator, strengthen the intensity of anchoring section, further improve the bearing capacity and breakout capacity of pile body 1 ', stake Reinforcing bar in the side wall of body 1 ' 4 is used for the reinforcement to the side wall of pile body 1 ' 4, avoids the ' of stretch-draw prestressing force anchor cable 2 and by upward To the damage of the side wall of pile body 1 ' 4 during pulling capacity.
In the present embodiment, the 5 vertical anchor cable of anchored end of the ' of prestress anchorage cable 2 sets end plate (anchoring piece);From anchoring The fixation at end 5, increase anchor force.
In the present embodiment, the ' of prestress anchorage cable 2 is anchored in the surrounding formations of pile body 1 ' and applied with lower inclined pull type in advance should Power;Not only it is easy to anchor but also is easy to apply effective withdrawal resistance to pile body 1 '.
By the prestress anchorage cable manually digging hole uplift pile of above-mentioned the present embodiment compared with traditional uplift pile:
It is as follows usually by the way of routinely anchoring in order to increase the anti-floating of foundation structure and uplift effect in engineering Shown in Fig. 1.Due to " Multi anchorage effect ", the bottom of pile body 1 ' anchor cable 2 can't be excessive in Practical Project setting, otherwise each anchor cable Anchor force between 2 will influence each other, and so as to reduce its anchoring ability, therefore 4 typically be taken in Practical Project.
And the present invention announces a kind of resistance to plucking artificial digging pile for being similar to " tree root ", as shown in Fig. 2 its anchoring depth is L, anchoring section inclination angle are α, can arrange 4 along stake in same layer, n-layer (n >=2) is arranged along pile body.
(1) in terms of the extraction-resistant behavior of enhancing stake
For the resistance to plucking effect of both quantitative contrasts, hypothesis below is done:
1. Fig. 1 and Fig. 2 anchoring section is in identical stratum, anchoring depth is l, and the girth of anchor hole is u;
2. the two is using the fast hardening concrete mortar of same strength grade, the resistance to plucking limit side of anchoring section and surrounding Rock And Soil Resistance criteria value is qsik
3. the diameter of the two uplift pile is consistent with depth.
As it is assumed that 3. the diameter of the two uplift pile is consistent with depth, and therefore, the resistance to plucking that Fig. 1 and Fig. 2 pile bodies are provided Power is equal.Here contribution of the anchor cable to withdrawal resistance is only considered.
As shown in Figure 1:Stake 4, bottom anchor cable, injected hole 6 weeks a length of u, anchoring depth l, resistance to plucking ultimate frictional resistance standard Value is qsik, therefore, the ultimate pullout capacity of the single anchor cables of Fig. 1 is Tuk1
Tuk1=ulqsik
The ultimate pullout capacity of 4 anchor cables is Tuk, then,
Tuk=4Tuk1=4ulqsik
As shown in Figure 2:Its anchoring depth is l, and anchoring section inclination angle is α, 4 can be arranged along stake in same layer, along stake Body arranges n-layer.According to Fig. 1 result of calculations, the ultimate pullout capacity of single anchor cable is ulq under Vertical Load effectsik, that is to say, that The ultimate pullout capacity of the single anchor cables of Fig. 2 is Tuk2=ulqsik/ cos α, every layer is arranged 4 anchor cables, altogether n-layer, and therefore, Fig. 2 owns Anchor cable ultimate pullout capacity is Tuk2=4nulqsik/cosα
Therefore, Tuk2/Tuk1=n/cos α, it is assumed that n=3, α=45 °, then Tuk2/Tuk1=4.24;Assuming that n=4, α=45 °, Then Tuk2/Tuk1=5.65;Assuming that n=5, α=45 °, then Tuk2/Tuk1=7.07, with n increase, Tuk2/Tuk1Ratio can get over Come bigger, therefore, Fig. 2 enhancing effect is significantly stronger than Fig. 1.
(2) in terms of pile body durability is strengthened
Anchorage cable anchoring in Fig. 1 is at stake bottom, to assisting pile concrete resistance to plucking there is no any effect, so, when When pile body is by uplift force, pile concrete tension immediately, because the power resistance strength of concrete is extremely low, when above pull out stress exceed it is mixed Pile concrete can be caused to ftracture after coagulating the tensile strength of soil, thus expose the reinforcing bar in pile body.In underground water and other corrosion The reinforcing bar in pile body will be corroded in the presence of sexual factor, causing the bearing capacity of stake gradually reduces, and serious influences the durable of stake Property.
And each anchor cable is applied with downward prestressing force in Fig. 2, prestressed application will allow concrete compression in advance, in pile body Upper generation compression (generally 10~20MPa).When there is uplift force, tension caused by uplift force, which needs to offset, arrives prestressing force To the compression of concrete, pile concrete tension is then just allowed, it is therefore, prestressed to exist to assisting pile body tension that there is weight The contribution wanted.
(3) present invention and the comparison of stake week Rock And Soil consolidation effect
The all Rock And Soils of stake are reinforced, and such as the methods of grouting and reinforcing, although the shearing strength of Rock And Soil can be improved, increase ground The resistance to plucking ultimate frictional resistance standard value of body and pile body, but it is limited (all in the range of kPa levels) that the intensity of Rock And Soil, which improves, Therefore, it is very limited amount of to the withdrawal resistance for improving pile body using the method for reinforcing pile week Rock And Soil.
Using the ' schemes of prestress anchorage cable 2, because prestress strength is high, the general ' tensile strength of prestress anchorage cable 2 design Value can reach 510~1390MPa, be far longer than the raising (kPa levels) of Rock And Soil intensity around, therefore use Fig. 2 scheme, The withdrawal resistance of pile body can not only be improved, but also the durability of pile body can be strengthened.
Finally illustrate, above example is only unrestricted to illustrate the technical solution of the utility model, although ginseng The utility model is described in detail according to preferred embodiment, it will be understood by those within the art that, can be to this The technical scheme of utility model is modified or equivalent substitution, without departing from the objective and model of technical solutions of the utility model Enclose, it all should cover among right of the present utility model.

Claims (8)

  1. A kind of 1. artificial digging pile resistance to plucking structure, it is characterised in that:One including pile body and enhancing pile body axial direction withdrawal resistance with On prestress anchorage cable, the prestress anchorage cable is vertically to being arranged in pile body, and upper end is anchored in the pile crown of pile body, lower end footpath Pile body surrounding formations are anchored in through pile body side wall.
  2. 2. artificial digging pile resistance to plucking structure according to claim 1, it is characterised in that:Prestress anchorage cable in pile body is along stake Body radial multilayer is uniform.
  3. 3. artificial digging pile resistance to plucking structure according to claim 1, it is characterised in that:Prestress anchorage cable outside pile body is along stake Body periphery ground is vertically uniform to multilayer.
  4. 4. artificial digging pile resistance to plucking structure according to claim 3, it is characterised in that:The pile body External prestressed anchor cable with The angle for forming 30-45 ° of pile body side wall.
  5. 5. the artificial digging pile resistance to plucking structure according to Claims 2 or 3, it is characterised in that:The prestress anchorage cable is arranged In disrance sleeve.
  6. 6. artificial digging pile resistance to plucking structure according to claim 5, it is characterised in that:Along the pile body side wall to periphery rock Soil layer is provided with the injected hole that perfusion mortar fixes prestress anchorage cable, and reinforcing bar is provided with the pile body side wall.
  7. 7. artificial digging pile resistance to plucking structure according to claim 6, it is characterised in that:The anchored end of the prestress anchorage cable Vertical anchor cable sets end plate.
  8. 8. artificial digging pile resistance to plucking structure according to claim 7, it is characterised in that:The following oblique pull of prestress anchorage cable Formula is anchored in pile body surrounding formations and applies prestressing force.
CN201720554228.4U 2017-05-18 2017-05-18 Artificial digging pile resistance to plucking structure Expired - Fee Related CN206693220U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720554228.4U CN206693220U (en) 2017-05-18 2017-05-18 Artificial digging pile resistance to plucking structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720554228.4U CN206693220U (en) 2017-05-18 2017-05-18 Artificial digging pile resistance to plucking structure

Publications (1)

Publication Number Publication Date
CN206693220U true CN206693220U (en) 2017-12-01

Family

ID=60449258

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720554228.4U Expired - Fee Related CN206693220U (en) 2017-05-18 2017-05-18 Artificial digging pile resistance to plucking structure

Country Status (1)

Country Link
CN (1) CN206693220U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111576396A (en) * 2020-05-14 2020-08-25 三峡大学 Anchor rod type manual hole digging pile and construction method thereof
CN112609685A (en) * 2020-12-08 2021-04-06 江苏大学 Concrete pipe pile system suitable for soft soil foundation and construction method thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111576396A (en) * 2020-05-14 2020-08-25 三峡大学 Anchor rod type manual hole digging pile and construction method thereof
CN111576396B (en) * 2020-05-14 2022-03-08 三峡大学 Anchor rod type manual hole digging pile and construction method thereof
CN112609685A (en) * 2020-12-08 2021-04-06 江苏大学 Concrete pipe pile system suitable for soft soil foundation and construction method thereof

Similar Documents

Publication Publication Date Title
CN106968245A (en) The uplift pile of prestress anchorage cable manually digging hole and its construction method
CN105350584B (en) A kind of construction method of anti-float anchor rod
CN201722685U (en) No-adhesive prestress and pile side rear grouting punching pile structure
CN100535263C (en) Construction method for vertical prestressed anchor rope friction pile slope-sliding prevention and treatment
CN102828518A (en) Prestressed anchor cable anchoring structure of manual hole digging support pile and construction method thereof
CN1793525A (en) Novel method for reinforcing deep soft foundition-cencrete core sand stone pile compound foundition method
CN105350531B (en) The pile tube anchor pole composite foundation and construction technology of tension compression bidirectional load can be born
CN106498950A (en) Anchor head is placed in the Pile-Anchor Supporting for Deep Excavation system and its implementation of pile body
CN206599785U (en) A kind of campshed anchor draws cement earth pile diaphragm wall supporting construction
CN106702840A (en) Anchored pile reinforced earth retaining wall embankment for treating shoreside soft soil roadbed
CN205975707U (en) Glass fiber prestressed anchorage pole anchor structure, its loading device
CN103603379A (en) Anti-floating system combining anti-floating cement soil pile and anti-floating anchor rod and construction process of anti-floating system
CN109024721B (en) Reinforced foundation and method for improving bending and shearing resistance of existing building rigid foundation
CN104294823B (en) A kind of construction method of pile for prestressed pipe anti-floating pile raft structure
CN106638655A (en) Conical-head tendon body post-tensioning pile foundation and construction process thereof
CN108385715A (en) A kind of assembled stake arch combination retaining wall and its construction method
CN207660614U (en) Roadway floor prestress anchorage cable group coordinates ruggedized construction with slip casting
CN206693220U (en) Artificial digging pile resistance to plucking structure
CN103410144B (en) Prestressed reinforcement piles set into rock and construction method
CN201272968Y (en) Combined anchorage system
CN108842792B (en) Layered lifting and unloading type ground pulling anchor rod and construction method
CN110486070A (en) A kind of constructing structure of the prestressed anchor of tunnel or Culvert engineering
CN102363957A (en) Post-tensioned pre-stressed compound uplift pile
CN104264695A (en) Skid resistance device for fractured rock mass and construction method thereof
CN209523218U (en) Prestress anchorage cable fan foundation structure for Rock Region

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171201