CN206691837U CN201720416883.3U CN201720416883U CN206691837U CN 206691837 U CN206691837 U CN 206691837U CN 201720416883 U CN201720416883 U CN 201720416883U CN 206691837 U CN206691837 U CN 206691837U
Authority
CN
China
Prior art keywords
hopper
guide rail
carrier chain
aggregate bin
ore deposit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720416883.3U
Other languages
Chinese (zh)
Inventor
王洪兵
王振华
张协兵
张伟
黎新春
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Molong Petroleum Machinery Co Ltd
Original Assignee
Shandong Molong Petroleum Machinery Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Molong Petroleum Machinery Co Ltd filed Critical Shandong Molong Petroleum Machinery Co Ltd
Priority to CN201720416883.3U priority Critical patent/CN206691837U/en
Application granted granted Critical
Publication of CN206691837U publication Critical patent/CN206691837U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Manufacture And Refinement Of Metals (AREA)

Abstract

The utility model discloses hot ore deposit bucket elevator, support and upper sprocket wheel and lower sprocket and carrier chain are provided with the frame of elevator, carrier chain is fixed with hopper;Insulation dust cover cladding carrier chain and hopper, the periphery wall of hopper are provided with insulating;Hopper backplate is provided between adjacent skips.Under the drive of carrier chain, the support wheel of hopper supports hopper and run on up guide rail, after reaching up guide rail peak, hopper departs from up guide rail, under the independent role of carrier chain, descending guide rail is translated under hopper, starts to topple over material in the main aggregate bin on the downside of at the top of insulation dust cover and secondary aggregate bin.The utility model is during material is conveyed, insulation dust cover and insulating play Double insulating effect to the material of heating, it ensure that the material into iron-smelting furnace possesses certain temperature, and hopper backplate and secondary aggregate bin set up the conevying efficiency for improving material.

Description

Hot ore deposit bucket elevator
Technical field
The utility model belongs to elevator technical field, more particularly, to a kind of bucket lifting for being used to convey hot miberal powder thing Machine.
Background technology
The function of bucket elevator be material is widely used in from lower lifting to discharging after certain altitude metallurgy, chemical industry, The industries such as mine, building materials, but the miberal powder material that ironmaking technique of fusion and reduction requirement enters in stove possesses certain temperature, and this is not only It is required that miberal powder material is heated in advance, it is often more important that how these miberal powder materials after heating are transported to aggregate bin In, iron-smelting furnace is entered by hot ore deposit collecting bin.
In the process of running, in order to avoid being scattered for material, each hopper needs to be resident under blanking port most of elevators, And tipping when of falling material, all can not topple over material totally at aggregate bin under hopper.
Utility model content
The utility model is intended to overcome above-mentioned the deficiencies in the prior art, it is proposed that a kind of hot ore deposit bucket elevator, To avoid thermal loss of the hot mineral material in course of conveying.
Technical scheme is used by the utility model solves its technical problem:Hot ore deposit bucket elevator includes frame, institute State frame and be provided with upper sprocket wheel and lower sprocket, carrier chain is surrounded between the upper sprocket wheel and the lower sprocket, it is described defeated Chain is sent to be fixed with hopper;The elevator also includes the insulation dust cover for coating the carrier chain and the hopper, the hopper Periphery wall be provided with insulating.
Further, charging aperture is provided with the upside of the bottom of the insulation dust cover, downside is provided with the top of the insulation dust cover Main aggregate bin, the downstream of the main aggregate bin are provided with secondary aggregate bin.
Further, it is provided with hopper backplate between the adjacent hopper.
Further, up guide rail and descending guide rail are provided with below the carrier chain, the feed hopper bottom is installed with Support wheel, the support wheel are positioned on the up guide rail or the descending guide rail.
The beneficial effects of the utility model are:
1) insulation dust cover is added on the track that hopper is advanced, not only plays insulation effect and also play dustproof effect, that is, save Environmental protection again;Hopper periphery wall has additional insulating, avoids the loss of hot mineral material, has saved the energy that heating needs.
2) a secondary aggregate bin is set up in main aggregate bin downstream, and the residual heat mineral material that fallen in hopper can be carried out again Collect;Had additional between adjacent skips hopper backplate carry out transition, material from charging aperture fall when, each hopper need not stay in blanking port Stay, continuously-running, the unrestrained of material is avoided in lasting charging;Material is also prevent while improving conevying efficiency to fall into It is incubated the operation of disabling facility in dust cover.
3) up guide rail and descending guide rail are provided with below carrier chain, hopper and carrier chain is played a supporting role, avoided defeated Chain is sent to be damaged because load-carrying is excessive.
Brief description of the drawings
Fig. 1 is the structural representation of the hot ore deposit bucket elevator of the utility model;
Fig. 2 is the close-up schematic view of hot ore deposit bucket elevator shown in Fig. 1;
Fig. 3 is hopper when hot ore deposit bucket elevator completely struggles against shown in Fig. 1, up guide rail structure schematic diagram;
Hopper, descending guide rail structure schematic diagram when Fig. 4 is hot ore deposit bucket elevator sky bucket shown in Fig. 1;
In figure:1- frames, 2- upper sprocket wheels, 3- lower sprockets, 4- carrier chains, 5- hoppers, 51- insulatings, 52- hoppers shield Plate, 53- support wheels, 6- insulation dust covers, 61- charging apertures, the main aggregate bins of 62-, 63- pair aggregate bins, the up guide rails of 7-, 8- are descending Guide rail.
Embodiment
The utility model is described in further detail with reference to accompanying drawing.
In description of the present utility model, it is to be understood that " on ", " under ", "left", "right", " level ", " vertical " etc. Either position relationship is to be based on orientation shown in the drawings or position relationship in the orientation of description, it is only for is easy to describe this reality With new and simplify description, rather than instruction or imply that signified device or element there must be specific orientation, with specific Azimuth configuration and operation, therefore it is not intended that to limitation of the present utility model.
As shown in Figure 1 to Figure 2, the angle of inclination of elevator is determined according to live actual demand, hot ore deposit is fixed using frame 1 Bucket elevator, frame 1 are provided with upper sprocket wheel 2 and lower sprocket 3, carrier chain 4 are surrounded between upper sprocket wheel 2 and lower sprocket 3, Carrier chain 4 is fixed with hopper 5;Elevator also includes the insulation dust cover 6 of cladding carrier chain 4 and hopper 5, insulation dust cover 6 Charging aperture 61 is provided with the upside of bottom, downside is provided with main aggregate bin 62 at the top of insulation dust cover, and the downstream of main aggregate bin 62 is set There is secondary aggregate bin 63;The periphery wall of hopper 5, which is provided between insulating 51 and adjacent skips 5, is provided with hopper backplate 52.It is defeated The lower section of chain 4 is sent to be provided with up guide rail 7 and descending guide rail 8, the bottom of hopper 5 is installed with support wheel 53, and support wheel 53 is placed On up guide rail 7 or descending guide rail 8.
When hot ore deposit bucket elevator completely struggles against up and when empty material is descending hopper with the structure of up guide rail or downing track such as Shown in Fig. 3 and Fig. 4.
The course of work of above-mentioned hot ore deposit bucket elevator is as follows:
The angle of inclination of elevator is determined according to live actual demand, hot ore deposit bucket elevator is fixed using frame 1;Protecting Under the guarantee of warm dust cover 6, the material of heating is fallen into hopper 5 by charging aperture 61;Hopper backplate is had additional between adjacent skips 5 52 carry out transition, material from charging aperture fall when, each hopper need not blanking port be resident, continuously-running, kept away in lasting charging Exempt from material to trickle down;The periphery wall of hopper 5 is provided with insulating 51, avoids the loss of material heat in transportation.Conveying Under the drive of chain 4, the support wheel 53 of hopper 5 supports hopper 5 and run on up guide rail 7, when the material that hopper 5 conveys reaches After the up peak of guide rail 7, depart from up guide rail 7, under the independent role of carrier chain 4, descending guide rail 8 is translated under hopper 5 simultaneously Start to topple over material, in actual moving process, material can not all topple at main aggregate bin 62 totally, in hopper 5 sometimes The salvage stores fallen needs to be collected again at secondary aggregate bin 63, the thing that main aggregate bin 62 and secondary aggregate bin 63 are collected Material delivers to collecting bin and is transferred to iron-smelting furnace.Whole course of conveying avoids the thermal loss of hot mineral material.Hopper backplate 52 simultaneously The conevying efficiency of material is improved with setting up for secondary aggregate bin 63.

Claims (4)

1. hot ore deposit bucket elevator, including:
Frame, the frame are provided with upper sprocket wheel and lower sprocket, are surrounded between the upper sprocket wheel and the lower sprocket defeated Chain is sent, the carrier chain is fixed with hopper;Characterized in that,
The elevator also includes the insulation dust cover for coating the carrier chain and the hopper, and the periphery wall of the hopper is set There is insulating.
2. hot ore deposit bucket elevator as claimed in claim 1, it is characterised in that be provided with the upside of the bottom of the insulation dust cover Charging aperture, the insulation dust cover top downside are provided with main aggregate bin, and the downstream of the main aggregate bin is provided with secondary aggregate bin.
3. hot ore deposit bucket elevator as claimed in claim 2, it is characterised in that hopper shield is provided between the adjacent hopper Plate.
4. hot ore deposit bucket elevator as claimed in claim 1, it is characterised in that be provided with up guide rail below the carrier chain With descending guide rail, the feed hopper bottom is installed with support wheel, the support wheel be positioned over the up guide rail or it is described under On row guide rail.
CN201720416883.3U 2017-04-19 2017-04-19 Hot ore deposit bucket elevator Active CN206691837U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720416883.3U CN206691837U (en) 2017-04-19 2017-04-19 Hot ore deposit bucket elevator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720416883.3U CN206691837U (en) 2017-04-19 2017-04-19 Hot ore deposit bucket elevator

Publications (1)

Publication Number Publication Date
CN206691837U true CN206691837U (en) 2017-12-01

Family

ID=60445836

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720416883.3U Active CN206691837U (en) 2017-04-19 2017-04-19 Hot ore deposit bucket elevator

Country Status (1)

Country Link
CN (1) CN206691837U (en)

Similar Documents

Publication Publication Date Title
CN202465830U (en) Residual heat reclaiming system for pellets and sintered ores
CN206827555U (en) A kind of bar automatic charging device
WO2014127597A1 (en) Arc furnace automatic feeding device
CN104154728A (en) Chain plate conveying coal ball heat conduction oil dryer
CN109880959B (en) Method for increasing addition proportion of converter scrap steel
CN204495069U (en) A kind of heating furnace material feeder
CN209069003U (en) A kind of continuous charging pre-heating device
CN202380045U (en) Solid solution trolley type heat treatment furnace
CN204975318U (en) Aluminum alloy ingot casting automation line
CN206691837U (en) Hot ore deposit bucket elevator
CN204268902U (en) A kind of electric induction furnace steel scrap continuously pre-heating promotes feeding device
CN109237950A (en) Continuous charging pre-heating device
CN211084816U (en) Automatic feeding device for aluminum ingots
CN104315853A (en) Electric furnace burden feeding conveyance device
CN202099316U (en) Quick charging device for charging steel scrap into electric furnace
CN209485071U (en) A kind of waste steel for electric furnace continuously pre-heating conveyer
CN206905554U (en) Furnace charge pushing structure
CN205174427U (en) Feeding system of living beings charcoal gas electric heat energy comprehensive utilization project
CN205346406U (en) A dust collector that is used for flue gas entrapment of iron -smelter blast furnace ore deposit groove
CN208765488U (en) Frame of handwheel raw material melt automatic feeder
CN204896636U (en) Sediment mechanism is scraped to steel rolling heating furnace
CN210560239U (en) Put out stove futilely and adorn cold burnt conveyor
CN207276645U (en) Air heating furnace roof feed arrangement
CN209802091U (en) Automatic feeding system of reclaimed copper smelting furnace
CN218580095U (en) Curing oven for electrophoretic coating

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract
EE01 Entry into force of recordation of patent licensing contract

Assignee: Hebei Xinggang Technology Co.,Ltd.

Assignor: SHANDONG MOLONG PETROLEUM MACHINERY Co.,Ltd.

Contract record no.: X2023980034949

Denomination of utility model: Hot mineral bucket elevator

Granted publication date: 20171201

License type: Common License