CN209485071U - A kind of waste steel for electric furnace continuously pre-heating conveyer - Google Patents

A kind of waste steel for electric furnace continuously pre-heating conveyer Download PDF

Info

Publication number
CN209485071U
CN209485071U CN201920116316.5U CN201920116316U CN209485071U CN 209485071 U CN209485071 U CN 209485071U CN 201920116316 U CN201920116316 U CN 201920116316U CN 209485071 U CN209485071 U CN 209485071U
Authority
CN
China
Prior art keywords
delivery chute
insulation cover
electric furnace
heating
continuously pre
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920116316.5U
Other languages
Chinese (zh)
Inventor
吕长太
黄磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Quan Shun Vibration Equipment Co Ltd
Original Assignee
Henan Quan Shun Vibration Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Quan Shun Vibration Equipment Co Ltd filed Critical Henan Quan Shun Vibration Equipment Co Ltd
Priority to CN201920116316.5U priority Critical patent/CN209485071U/en
Application granted granted Critical
Publication of CN209485071U publication Critical patent/CN209485071U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P10/00Technologies related to metal processing
    • Y02P10/20Recycling

Landscapes

  • Vertical, Hearth, Or Arc Furnaces (AREA)
  • Furnace Details (AREA)

Abstract

The utility model discloses a kind of waste steel for electric furnace continuously pre-heating conveyers, it includes a disresonance type steel scrap continuously pre-heating conveyer, it is that one reciprocating vibration excitor is installed in the rear end of delivery chute, vibration excitor and delivery chute are suspended on support base, feeding section is reserved in delivery chute rear end, and insulation cover is installed in top, water-cooling cover is installed before insulation cover, uniformly distributed heating burner and flue-gas temperature detection device are installed in insulation cover two sides or top into delivery chute, combustion air heat exchanger is installed before exhanst gas outlet, water cooled seal system is installed between insulation cover and delivery chute, flame detecting device and pressure transmitter are respectively equipped with behind each burner, mobile transport trolley is installed between delivery chute and electric furnace, material pressing device and dynamic sealing means are installed at feed opening on delivery chute.The utility model is greatly improved the preheating temperature of scrap smelting, shortens the heat, plays the role of energy efficiency.

Description

A kind of waste steel for electric furnace continuously pre-heating conveyer
Technical field
The utility model relates to conveyer, especially a kind of continuously pre-heating conveyer of waste steel for electric furnace smelting.
Background technique
Currently, the feed way used when waste steel for electric furnace smelting, big mostly use expect that basket charging or disresonance type steel scrap are continuous Conveyer charging is preheated, the material of addition is mostly the waste material of cold burden or preheating temperature not high (only 300-400 °), primary to be added greatly Cold burden or the not high waste material of preheating temperature are measured, the duration of heat is long, and production efficiency is low, and the performance of enterprises is poor.
Summary of the invention
It is high that the purpose of the utility model is to provide a kind of charging preheating temperatures, can effectively improve production efficiency, increases economical The waste steel for electric furnace continuously pre-heating conveyer of benefit.
The technical solution of the utility model is completed as follows, it includes a disresonance type steel scrap continuously pre-heating Conveyer, it is characterised in that: be to be equipped with a reciprocating vibration excitor in the rear end of delivery chute, vibration excitor and delivery chute are hung On support base, feeding section is reserved in delivery chute rear end, insulation cover is installed in top, water-cooling cover is installed before insulation cover, Uniformly distributed heating burner and flue-gas temperature detection device are installed in insulation cover two sides or top into delivery chute, in exhanst gas outlet Before combustion air heat exchanger is installed, water cooled seal system is installed between insulation cover and delivery chute, behind each burner point Not She You flame detecting device and pressure transmitter, mobile transport trolley is installed between delivery chute and electric furnace, in delivery chute Material pressing device and dynamic sealing means are installed at upper feed opening.Platform and ladder are equipped on the delivery chute of insulation cover two sides.
The utility model is greatly improved the preheating temperature of scrap smelting, the work for energy efficiency of shortening the heat, play With.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model.
Specific embodiment
Embodiment is described in detail in conjunction with attached drawing, it includes a disresonance type steel scrap continuously pre-heating conveyer, main to improve Place is to be equipped with a reciprocating vibration excitor 1 in the rear end of delivery chute 2, and vibration excitor and delivery chute are suspended on support base 3, Feeding section is reserved in delivery chute rear end, insulation cover 6 is installed in top, water-cooling cover 7 is installed before insulation cover, in insulation cover Two sides or top are equipped with uniformly distributed heating burner 8 and flue-gas temperature detection device 9 into delivery chute, pacify before exhanst gas outlet 16 Equipped with combustion air heat exchanger 10, water cooled seal system 11 is installed between insulation cover and delivery chute, divides behind each burner Not She You flame detecting device 12 and pressure transmitter 13, mobile transport trolley 5 is installed between delivery chute and electric furnace 4, Material pressing device 15 and dynamic sealing means 14 are installed at feed opening on delivery chute.
Platform and ladder are equipped on the delivery chute of insulation cover two sides.
The utility model does reciprocal horizontal anharmonic by the reciprocal vibration excitor driving delivery chute of tail portion when work through above-mentioned improvement Raw scrap material is sent into insulation cover the preheating section conveying for being evenly equipped with heating burner by vibration through material pressing device and dynamic sealing means In slot, fuel value is can be improved after preheating by heat exchanger in the coal gas and combustion air of each burner combustion, is played energy-saving effect, is being protected Water cooled seal system is set between temperature cover and preheating section delivery chute, it is ensured that flue gas is not excessive, and flame is arranged behind burner and examines Device and pressure transmitter are surveyed, can detecte the size of flame;Dynamic sealing means and material pressing device are set at material inlet, Certifiable cool exterior air does not enter in insulation cover and delivery chute, and the material of high blow tank is forced down convenient for conveying;In addition exist Platform and ladder are set on the delivery chute on insulation cover both sides, maintenance can be facilitated.The utility model can make to enter the original before electric furnace The coal gas that material preheating temperature reaches 700-800 °, and burnt is mostly the coal gas generated in enterprise production process, has section The benefit of energy emission reduction, shortens smelting cycle, improves production efficiency and economic benefit.

Claims (2)

1. a kind of waste steel for electric furnace continuously pre-heating conveyer, it includes a disresonance type steel scrap continuously pre-heating conveyer, feature It is: is that one reciprocating vibration excitor is installed in the rear end of delivery chute, vibration excitor and delivery chute are suspended on support base, Delivery chute rear end reserves feeding section and is equipped with insulation cover in top, and water-cooling cover is equipped with before insulation cover, in insulation cover two sides Or top is equipped with uniformly distributed heating burner and flue-gas temperature detection device into delivery chute, is equipped with before exhanst gas outlet combustion-supporting Air heat exchanger is equipped with water cooled seal system between insulation cover and delivery chute, and flame inspection is respectively equipped with behind each burner Device and pressure transmitter are surveyed, mobile transport trolley is installed between delivery chute and electric furnace, is pacified at feed opening on delivery chute Equipped with material pressing device and dynamic sealing means.
2. a kind of waste steel for electric furnace continuously pre-heating conveyer according to claim 1, it is characterised in that: in insulation cover two sides Delivery chute is equipped with platform and ladder.
CN201920116316.5U 2019-01-24 2019-01-24 A kind of waste steel for electric furnace continuously pre-heating conveyer Active CN209485071U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920116316.5U CN209485071U (en) 2019-01-24 2019-01-24 A kind of waste steel for electric furnace continuously pre-heating conveyer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920116316.5U CN209485071U (en) 2019-01-24 2019-01-24 A kind of waste steel for electric furnace continuously pre-heating conveyer

Publications (1)

Publication Number Publication Date
CN209485071U true CN209485071U (en) 2019-10-11

Family

ID=68132319

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920116316.5U Active CN209485071U (en) 2019-01-24 2019-01-24 A kind of waste steel for electric furnace continuously pre-heating conveyer

Country Status (1)

Country Link
CN (1) CN209485071U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110982978A (en) * 2019-12-18 2020-04-10 河南全顺振动设备有限公司 Smelting production system based on continuous preheating conveyor
CN111979372A (en) * 2020-09-17 2020-11-24 中冶华天南京工程技术有限公司 Dynamic sealing device for electric furnace continuous feeding device

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110982978A (en) * 2019-12-18 2020-04-10 河南全顺振动设备有限公司 Smelting production system based on continuous preheating conveyor
CN110982978B (en) * 2019-12-18 2021-07-09 河南全顺振动设备有限公司 Smelting production system based on continuous preheating conveyor
CN111979372A (en) * 2020-09-17 2020-11-24 中冶华天南京工程技术有限公司 Dynamic sealing device for electric furnace continuous feeding device

Similar Documents

Publication Publication Date Title
CN101269919B (en) Vertical kiln apparatus for materials calcination
CN202465830U (en) Residual heat reclaiming system for pellets and sintered ores
CN103950087B (en) High temperature furnace slag energy recovery and brick-making method
CN209485071U (en) A kind of waste steel for electric furnace continuously pre-heating conveyer
CN102818254A (en) Slag treatment system and method of biomass boiler
CN103834755A (en) Pulverized coal preheating technique of blast furnace coal injection system
CN202092456U (en) Roller kiln using mixed air and light hydrocarbon gas
CN208562441U (en) Converter continuous charging preheats jigging conveyer
CN204461053U (en) Living beings melt aluminium stove
CN206643358U (en) With the equipment of the hot-forming metallurgical raw material metal bloom of waste metal rubbish
CN201795677U (en) Energy-saving muffle furnace
CN205175060U (en) Rubbish drying equipment
CN203498411U (en) Intermediate frequency furnace scrap preheating stepping conveyer device
CN204509202U (en) Gas-conducting cells, gas operated device and pulverized coal pyrolysis device
CN203068947U (en) Cupola furnace waste heat rock wool plate curing furnace
CN203132357U (en) Feeding and preheating platform for secondary aluminum smelting furnace
CN205368407U (en) Even feeding device of blast furnace
CN202648371U (en) External-heat, air-blowing and water-cooling cupola furnace with long furnace age
CN220418125U (en) Waste heat utilization system in rock wool production
CN204594260U (en) A kind of central cooler Low Temperature Thermal waste gas utilize system
CN102878671A (en) Broken branch sawdust particle direct-combustion type hot-blast furnace
CN204286132U (en) Bismuth smelting furnace
CN204227920U (en) A kind of furnace construction with heat recovery function
CN202032887U (en) Energy-saving gravity furnace
CN203385287U (en) Dual-door charging system for tunnel kiln

Legal Events

Date Code Title Description
GR01 Patent grant