CN206672590U - Construction site fixing wind resistance propaganda board device - Google Patents

Construction site fixing wind resistance propaganda board device Download PDF

Info

Publication number
CN206672590U
CN206672590U CN201720380597.6U CN201720380597U CN206672590U CN 206672590 U CN206672590 U CN 206672590U CN 201720380597 U CN201720380597 U CN 201720380597U CN 206672590 U CN206672590 U CN 206672590U
Authority
CN
China
Prior art keywords
mounting base
construction site
preceding installing
pipes
installing pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720380597.6U
Other languages
Chinese (zh)
Inventor
王山峰
樊新胜
付飞
田友才
张晓莉
孙永鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Second Engineering Bureau Co Ltd
Original Assignee
China Construction Second Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Second Engineering Bureau Co Ltd filed Critical China Construction Second Engineering Bureau Co Ltd
Priority to CN201720380597.6U priority Critical patent/CN206672590U/en
Application granted granted Critical
Publication of CN206672590U publication Critical patent/CN206672590U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Tents Or Canopies (AREA)

Abstract

Construction site fixing wind resistance propaganda board device, including the mounting base set parallel to ground, left side, right side and the rear side of mounting base are fixed on ground by connector respectively, the lower rotation of mounting base is connected with least three support rollers, three support rollers rolls are connected to ground, and the center line of three support rollers is set along anterior-posterior horizontal direction;The plan vertical of mounting base is fixed with installing pipe after two preceding installing pipes and two, and two preceding installing pipes are arranged side by side in left-right direction, the corresponding rear side positioned at two preceding installing pipes of installing pipe after two;In summary, the left side of mounting base of the present utility model, right side and rear side are fixed on ground by connector, save material, firmly install;Top rain visor end upwarps, and optimizes exhaust system design, and mounting base bottom sets movable pulley, is easy to the mobile working in later stage, the propaganda work for next construction site.

Description

Construction site fixing wind resistance propaganda board device
Technical field
The utility model belongs to building temporary facility technical field, and in particular to a kind of construction site is publicized with wind resistance is fixed Column device.
Background technology
Face build propaganda board device have simple in construction, stress clearly, the effect of rain cover, wind resistance, propaganda board is according to structure stress Form is divided into gravity type, consolidation formula and gravity consolidation formula, is divided into wooden, steel and steel wood mixed structure according to material;Weight The propaganda board of power formula structure exist consumable material, construction trouble, it is irremovable the shortcomings that, consolidate formula structure propaganda board it is general under Portion's setting armored concrete is pre-buried, and top vertical bar is directly placed into embedded bar concrete or concrete, vertical to support body Material requires higher, and safety coefficient is not high;The propaganda board of gravity consolidation formula structure, which exists, wastes material, uneconomical, is not easy to move The shortcomings that dynamic, but its safety coefficient is high.
Utility model content
The utility model is in order to solve weak point of the prior art, there is provided one kind saves material, optimization ant wind load Design, construction site easy to remove fixing wind resistance propaganda board device.
In order to solve the above technical problems, the utility model adopts the following technical scheme that:Construction site is publicized with wind resistance is fixed Column device, including consolidated respectively by connector parallel to the mounting base that ground is set, left side, right side and the rear side of mounting base Ground is scheduled on, the lower rotation of mounting base is connected with least three support rollers, and three support rollers rolls are connected to ground, The center line of three support rollers is set along anterior-posterior horizontal direction;The plan vertical of mounting base is fixed with two preceding installing pipes With two after installing pipe, two preceding installing pipes are arranged side by side in left-right direction, installing pipe is corresponding after two be located at two before installs An at least connecting tube is connected between the rear installing pipe of the rear side of pipe, preceding installing pipe and corresponding rear side, in two preceding installing pipes It is in channel steel type and downward opening spacing clamping plate to be horizontally fixed with a section, is positioned in two preceding installing pipes by lift adjustment It is in channel steel type and opening up supporting splint that mechanism horizontal connection, which has a section, and supporting splint is parallel positioned at spacing clamping plate Lower section, panel is provided between spacing clamping plate and supporting splint, spacing clamping plate card is enclosed on the upper edge of panel, and supporting splint is fastened in The lower edge of panel;
The upper end of installing pipe is respectively and fixedly provided with a L-shaped pipe after two, and the top surface of two L-shaped pipes, which is fixedly connected with, to be extended forward The rain visor of setting.
Connector positioned at left side includes the supporting steel that profile is L-type, and the side plate of supporting steel, which is bolted, is pacifying The left side of bottom plate is filled, another side plate of supporting steel is fixedly connected with the steel plate for being embedded in underground.
Lift adjustment detent mechanism includes some jacks being opened in two preceding installing pipes, and the center line of jack is vertical Set with panel, length direction of the jack along preceding installing pipe is set, and left and right is one by one in height for the jack in two preceding installing pipes It is correspondingly arranged, correspondingly offers two perforation on supporting splint and panel, on the jack, supporting splint and panel in preceding installing pipe Bolt, the nut being threaded with bolt on front side of supporting splint are equipped between corresponding perforation.
The front side edge of rain visor is folded up setting.
The upper-end part of driving of preceding installing pipe is in the rear side of the bottom of the preceding installing pipe.
Using above-mentioned technical proposal, the utility model with it is existing face build compared with propaganda board, have the advantages that: The supporting steel side plate of L-type is fixedly connected with mounting base by bolt, and another plate-side plate welding of the supporting steel of L-type has steel Plate, original soil is then backfilled, tamped, or masonry is placed on steel plate top, is poured without carrying out armored concrete, so as to save Material.
Mounting base bottom of the present utility model sets three support rollers, when needing mobile device, removes supporting steel Connecting bolt between mounting base, then pushing meanss, device move by support roller, are easy to face and build propaganda board Movement.Supporting splint of the present utility model can be moved by lift adjustment detent mechanism, so as to be applied to position limiting clamp Different size of panel is placed between plate and supporting splint.The top rain visor forward edge that the utility model uses is tilted upward Rise, be advantageous to reduce vertical wind-force of the wind load to top rain visor.
In summary, the left side of mounting base of the present utility model, right side and rear side are fixed on ground by connector, section Material is saved, is firmly installed;Top rain visor end upwarps, and optimizes exhaust system design, mounting base bottom sets movable pulley, after being easy to The mobile working of phase, the propaganda work for next construction site.
Brief description of the drawings
Fig. 1 is structural representation of the present utility model;
Fig. 2 is Fig. 1 right view;
Fig. 3 is the enlarged drawing at A in Fig. 2.
Embodiment
As Figure 1-3, construction site of the present utility model fixing wind resistance propaganda board device, including parallel to ground 1 The mounting base 2 of setting, left side, right side and the rear side of mounting base 2 are fixed on ground 1, mounting base 2 by connector respectively Lower rotation be connected with least three support rollers 4, three support rollers 4 roll and are connected to ground 1, three support rollers 4 Center line along anterior-posterior horizontal direction set;The plan vertical of mounting base 2 is pacified after being fixed with two preceding installing pipes 5 and two Tubulature 6, two preceding installing pipes 5 are arranged side by side in left-right direction, and installing pipe 6 is corresponding after two preceding installing pipes 5 after two An at least connecting tube 7 is connected between the rear installing pipe 6 of side, preceding installing pipe 5 and corresponding rear side, is consolidated in two preceding installing pipes 5 Surely it is in channel steel type and downward opening spacing clamping plate 8 to have a section, passes through lift adjustment detent mechanism in two preceding installing pipes 5 It is in channel steel type and opening up supporting splint 9 to be connected with a section, and supporting splint 9 is parallel positioned at the lower section of spacing clamping plate 8, Panel 10 is provided between spacing clamping plate 8 and supporting splint 9, spacing clamping plate 8 is fastened in the upper edge of panel 10, and supporting splint 9 blocks It is enclosed on the lower edge of panel 10;
The upper end of installing pipe 6 is respectively and fixedly provided with a L-shaped pipe 11 after two, and the top surfaces of two L-shaped pipes 11 is fixedly connected oriented Preceding extended rain visor 12.
Connector positioned at left side includes the supporting steel 13 that profile is L-type, and the side plate of supporting steel 13 is bolted In the left side of mounting base 2, another side plate of supporting steel 13 is fixedly connected with the steel plate 14 for being embedded in underground.
Lift adjustment detent mechanism includes some jacks 16 being opened in two preceding installing pipes 5, the center line of jack 16 Vertically set with panel 10, length direction of the jack 16 along preceding installing pipe 5 is set, and the jack 16 in two preceding installing pipes 5 exists Left and right, which corresponds, in height is set, and correspondingly offers two perforation on supporting splint 9 and panel 10, slotting in preceding installing pipe 5 Bolt 17 is equipped between corresponding perforation on hole 16, supporting splint 9 and panel 10, is threaded with bolt 17 positioned at support The nut 15 of the front side of clamping plate 9.
The front side edge of rain visor 12 is folded up setting.
The upper-end part of driving of preceding installing pipe 5 is in the rear side of the bottom of the preceding installing pipe 5.
The side plate of supporting steel 13 of L-type is fixedly connected with mounting base 2 by bolt, the supporting steel 13 of L-type it is another Plate-side plate welding has steel plate 14, then backfills original soil, is tamped, or masonry is placed on the top of steel plate 14, is mixed without carrying out reinforcing bar Solidifying soil pours, so as to save material.
The bottom of mounting base 2 of the present utility model sets three support rollers 4, when needing mobile device, removes support Connecting bolt between steel 13 and mounting base 2, then pushing meanss, device move by support roller 4, are easy to face and build The movement of propaganda board.Supporting splint 9 of the present utility model can be moved by lift adjustment detent mechanism, so as to be applied to Different size of panel 10 is placed between spacing clamping plate 8 and supporting splint 9.The front side of top rain visor 12 that the utility model uses Edge is upturned, and is advantageous to reduce vertical wind-force of the wind load to top rain visor 12.
The present embodiment not makees any formal limitation, every foundation to shape of the present utility model, material, structure etc. Any simple modification, equivalent change and modification that the technical essence of the utility model is made to above example, belongs to this reality With the protection domain of new technique scheme.

Claims (5)

1. construction site fixing wind resistance propaganda board device, it is characterised in that:Including the mounting base set parallel to ground, peace Left side, right side and the rear side of dress bottom plate are fixed on ground by connector respectively, and the lower rotation of mounting base is connected with least Three support rollers, three support rollers rolls are connected to ground, and the center line of three support rollers is along anterior-posterior horizontal direction Set;The plan vertical of mounting base is fixed with installing pipe after two preceding installing pipes and two, and two preceding installing pipes are along right and left To being arranged side by side, the corresponding rear side positioned at two preceding installing pipes of installing pipe after two, preceding installing pipe with it is corresponding on rear side of rear installation An at least connecting tube is connected between pipe, a section is horizontally fixed with two preceding installing pipes in channel steel type and opening down Spacing clamping plate, it is in channel steel type and opening to have a section by lift adjustment detent mechanism horizontal connection in two preceding installing pipes Supporting splint upward, supporting splint is parallel to be provided with panel between the lower section of spacing clamping plate, spacing clamping plate and supporting splint, Spacing clamping plate card is enclosed on the upper edge of panel, and supporting splint is fastened in the lower edge of panel;
The upper end of installing pipe is respectively and fixedly provided with a L-shaped pipe after two, and the top surface of two L-shaped pipes, which is fixedly connected with, to be extended forward Rain visor.
2. construction site according to claim 1 fixing wind resistance propaganda board device, it is characterised in that:Company positioned at left side Fitting includes the supporting steel that profile is L-type, and the side plate of supporting steel is bolted in the left side of mounting base, supporting steel Another side plate is fixedly connected with the steel plate for being embedded in underground.
3. construction site according to claim 1 fixing wind resistance propaganda board device, it is characterised in that:Lift adjustment positions Mechanism includes some jacks being opened in two preceding installing pipes, and the center line of jack is vertically set with panel, and jack is before The length direction of installing pipe is set, and left and right corresponds and set the jack in two preceding installing pipes in height, supporting splint and Correspondingly offer two perforation on panel, worn on the jack, supporting splint and panel in preceding installing pipe between corresponding perforation There are bolt, the nut being threaded with bolt on front side of supporting splint.
4. construction site according to claim 1 fixing wind resistance propaganda board device, it is characterised in that:The front side of rain visor While it is folded up setting.
5. construction site according to claim 1 fixing wind resistance propaganda board device, it is characterised in that:Preceding installing pipe it is upper End is located at the rear side of the bottom of the preceding installing pipe.
CN201720380597.6U 2017-04-12 2017-04-12 Construction site fixing wind resistance propaganda board device Active CN206672590U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720380597.6U CN206672590U (en) 2017-04-12 2017-04-12 Construction site fixing wind resistance propaganda board device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720380597.6U CN206672590U (en) 2017-04-12 2017-04-12 Construction site fixing wind resistance propaganda board device

Publications (1)

Publication Number Publication Date
CN206672590U true CN206672590U (en) 2017-11-24

Family

ID=60381378

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720380597.6U Active CN206672590U (en) 2017-04-12 2017-04-12 Construction site fixing wind resistance propaganda board device

Country Status (1)

Country Link
CN (1) CN206672590U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107871462A (en) * 2017-12-04 2018-04-03 李刚 Slideable propaganda board in a kind of Cardiological

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107871462A (en) * 2017-12-04 2018-04-03 李刚 Slideable propaganda board in a kind of Cardiological
CN107871462B (en) * 2017-12-04 2019-09-03 青岛市海慈医疗集团 Slideable propaganda board in a kind of Cardiological

Similar Documents

Publication Publication Date Title
CN208039267U (en) A kind of support connection structure of subway foundation pit steel purlin
CN103306208A (en) Formwork creeping method for novel 1.6 parabola-shaped four-column type hollow variable section high pier
CN113417455B (en) Self-reinforcing supporting rod for slip form construction
CN104674684A (en) Movable cast-in-place culvert cover plate framework support
CN206672590U (en) Construction site fixing wind resistance propaganda board device
CN203583380U (en) Movable cast-in-situ culvert cover plate template support
CN113668344B (en) Construction auxiliary device is backfilled in maintenance of highway section
CN207083672U (en) A kind of ancient tree supporting bar structure
CN204717144U (en) A kind of concrete pump pipe setting tool cribbing
CN202953653U (en) Telescopic guiding rail bracket of lift
CN207245243U (en) Prefabricated superimposed sheet vertical supporting device
CN206570810U (en) A kind of roof pressing type pile compacting equipment
CN205443828U (en) Novel modularization road integrated system
CN203361170U (en) Supporting upright column pile for building foundation pit support
CN212052218U (en) Ore road terrace template
CN204782194U (en) Simple and easy emergency communication tower
CN113006508A (en) Movable shallow trench steel constructs protector
CN209603113U (en) A kind of undercrossing tunnel frame bridge foundation-reinforcing device and constructing device
CN207419702U (en) The high-order single frame attaching structure of tower crane non-floor
CN202625670U (en) Adjustable wall-attached support device of tower crane of building
CN206352299U (en) A kind of cage car device constructed for water seepage mechanism
CN206539103U (en) A kind of electric pole bracing means
CN110777837A (en) Construction method of fabricated building mixed tower crane
CN205188978U (en) Integration stull formula bearing structure
CN212835411U (en) Foundation ditch construction support for railway engineering

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant