CN206671011U CN201720327571.5U CN201720327571U CN206671011U CN 206671011 U CN206671011 U CN 206671011U CN 201720327571 U CN201720327571 U CN 201720327571U CN 206671011 U CN206671011 U CN 206671011U
Authority
CN
China
Prior art keywords
bypass
switch valve
gas
pipeline
sampling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720327571.5U
Other languages
Chinese (zh)
Inventor
梁艳浩
刘浩
王世超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING YANSHAN HECHENG ENERGY-SAVING ENVIRONMENTAL PROTECTION ENGINEERING TECHNOLOGY Co Ltd
Original Assignee
BEIJING YANSHAN HECHENG ENERGY-SAVING ENVIRONMENTAL PROTECTION ENGINEERING TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING YANSHAN HECHENG ENERGY-SAVING ENVIRONMENTAL PROTECTION ENGINEERING TECHNOLOGY Co Ltd filed Critical BEIJING YANSHAN HECHENG ENERGY-SAVING ENVIRONMENTAL PROTECTION ENGINEERING TECHNOLOGY Co Ltd
Priority to CN201720327571.5U priority Critical patent/CN206671011U/en
Application granted granted Critical
Publication of CN206671011U publication Critical patent/CN206671011U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Sampling And Sample Adjustment (AREA)

Abstract

The utility model provides a kind of gas sample bypass processing unit, including shell and the main sampling pipeline being arranged in shell, the inlet end of the main sampling pipeline is connected with the air inlet pipe being fixed on gas pipeline, outlet side is connected with appendix, first switch valve and second switch valve are sequentially provided with appendix, the bypass flow pipe being connected with appendix and bypass exhaust pipe are provided between first switch valve and second switch valve, bypass exhaust pipe is connected with an air extractor;Also include some bypass sampling lines being in parallel with main sampling pipeline, the bypass sampling line is provided with gas storage chamber, and gas storage chamber both sides are respectively equipped with switch valve;Normally close valve is equipped with the air inlet pipe and escape pipe.Using multiple Parallel testing analysis can be carried out after the utility model single sample to same batch gas sampled, and then more accurate testing result is obtained, and it is simple to operate, sampling is convenient, can also carry out continuous several times sampling.

Description

Gas sample bypasses processing unit
Technical field
Gas pipeline sampling field is the utility model is related to, particularly a kind of gas sample bypass processing unit.
Background technology
Data are shown according to statistics, and the Eleventh Five-Year Plan period, the rapid growth of discharged nitrous oxides exacerbates the evil of region acid rain Change trend, the great efforts that partial offset China is paid in terms of sulfur dioxide emission reduction.Because nitrogen oxides is to big compression ring The adverse effect in border and the severe situation of current thermal power plant's discharged nitrous oxides control, State Ministry of Environmental Protection issue at 2010 beginning of the years Cloth《Thermal power plant's nitrogen oxides technological policy for treatment》, it is proposed that " 12 during " control discharged nitrous oxides planning and It is required that.The emphasis of technical policy control is domestic 200MW and above Thermal generation unit, and atmosphere pollution priority control area All Thermal generation units and cogeneration units in domain.Meanwhile appearance is mandatory《Thermal power plant's air pollution emission mark It is accurate》Denitration norm controlling will strictly be carried out.
Current domestic power plant mainly uses selective catalytic reduction (SCR) gas denitrifying technology.SCR methods are to use NH3As reducing agent, by NOxIt is reduced into N2。NH3It is selective, it only and NO react, without with the O in flue gas2Reaction.Conversely, O2NH can be promoted3With NO reaction.The denitration rate of SCR methods is up to 80%~90%.
During national " 12 ", a mandatory project of the denitrating flue gas project as thermal power plant, and included ring Protect detection project.Smoke on-line monitoring system CEMS reflects the effect of fume treatment environmental protecting device operation, is environmental administration pair Discharge the necessary means of enterprise's supervision management.
Domestic denitration CEMS metering systems are mainly at present:The direct method of measurement, extraction method, dilution method.Typically by infrared Spectroscopic methodology is to NOxDetected.Currently used method is heat tracing extraction method.Its sampler generally directly exports in denitration Flue perforate, 1-3 representative position is chosen, each independent sampler is installed.
Existing sampler is mostly Simple air-extracting device (syringe-like), can only once be divided for detector after primary sample Analysis uses, and in order to obtain more definite testing result, generally require to carry out multiple detection to the gas sampled of same batch Analysis, the detected value of this batch gas is determined by the contrast of repeated detection result, existing sampler can not meet more Secondary detection demand.
Utility model content
For overcome the deficiencies in the prior art, the utility model provides a kind of gas sample bypass processing unit, to same Batch pipeline gas can carry out multiple Parallel testing analysis after carrying out primary sample, to obtain more accurate testing result.
Technical scheme is used by the utility model solves its technical problem:A kind of gas sample bypasses processing unit, Including shell and the main sampling pipeline being arranged in shell, the inlet end of the main sampling pipeline is with being fixed on gas pipeline Air inlet pipe is connected, and outlet side is connected with appendix, and first switch valve and second switch valve are sequentially provided with appendix, and its feature exists In, the bypass flow pipe being connected with appendix and bypass exhaust pipe are provided between first switch valve and second switch valve, The bypass flow pipe is provided with the 3rd switch valve, bypasses the outlet side of flow pipe and the outlet being fixed on gas pipeline Pipe is connected, and bypass exhaust pipe is connected with an air extractor;Also include some bypass probe tubes being in parallel with main sampling pipeline Road, the bypass sampling line are provided with gas storage chamber, and gas storage chamber both sides are respectively equipped with the 4th switch valve and the 5th switch valve, One end of this bypass sampling line is connected with main sampling pipeline, defeated between the other end and first switch valve and second switch valve Tracheae is connected;Normally close valve is equipped with the air inlet pipe and escape pipe.
As further preferred embodiment, the quantity of the bypass sampling line is 6, and in main sampling pipeline week Enclose rounded array.
As further preferred embodiment, the bypass flow pipe is provided with air pump.
As further preferred embodiment, downward bending is sequentially provided with the gas pipeline on gas circulating direction The first folded plate and the second folded plate for being folded upward at, the inlet end of the air inlet pipe be in the first folded plate inner side, escape pipe goes out Gas end is on the inside of the second folded plate.
As further preferred embodiment, the air extractor includes suction bottle and pumping piston, and the pumping is lived Plug is connected with a piston rod.
As further preferred embodiment, the air extractor is arranged in pumping housing, and the pumping housing is consolidated It is scheduled on the outer side.
Good effect of the present utility model:It is more using that can be carried out after the utility model single sample to same batch gas sampled Secondary Parallel testing analysis, and then more accurate testing result is obtained, and it is simple to operate, sampling is convenient, can also carry out continuous more Sub-sampling.
Brief description of the drawings
Fig. 1 is the structural representation of gas sample bypass processing unit described in the utility model preferred embodiment;
Fig. 2 is the structural representation that sampling line is bypassed described in the utility model preferred embodiment;
Fig. 3 is the structural representation of gas pipeline described in the utility model preferred embodiment.
Embodiment
Preferred embodiment of the present utility model is described in detail below in conjunction with the accompanying drawings.
Referring to figs. 1 to Fig. 3, the utility model preferred embodiment provides a kind of gas sample bypass processing unit, including outer Shell 1 and the main sampling pipeline 2 being arranged in shell 1, the inlet end of the main sampling pipeline 2 is with being fixed on gas pipeline 3 Air inlet pipe 4 is connected, and outlet side is connected with appendix 9, and first switch valve 7 and second switch valve 8 are sequentially provided with appendix 9, its It is characterised by, the bypass flow pipe 10 being connected with appendix 9 and side is provided between first switch valve 7 and second switch valve 8 Road exhaust pipe 16, the bypass flow pipe 10 are provided with the 3rd switch valve 11, bypass the outlet side of flow pipe 10 with consolidating The escape pipe 5 being scheduled on gas pipeline 3 is connected, and bypass exhaust pipe 16 is connected with an air extractor;Also taken including some with master The bypass sampling line 12 that sample pipeline 2 is in parallel, the bypass sampling line 12 are provided with gas storage chamber 13,13 liang of gas storage chamber Side is respectively equipped with the 4th switch valve 14 and the 5th switch valve 15, and one end of this bypass sampling line 12 is connected with main sampling pipeline 2 Logical, the appendix 9 between the other end and first switch valve 7 and second switch valve 8 is connected;In the air inlet pipe 4 and escape pipe 5 It is equipped with normally close valve 6.
Preferably, as shown in Fig. 2 the quantity of the bypass sampling line 12 is 6, and it is in around main sampling pipeline 2 Circular array.
As shown in figure 3, the He of the first folded plate 21 bent downwards is sequentially provided with the gas pipeline 3 on gas circulating direction The second folded plate 22 being folded upward at, the inlet end of the air inlet pipe 4 is on the inside of the first folded plate 21, at the outlet side of escape pipe 5 In the inner side of the second folded plate 23, during sampling, gas in pipelines is stopped by the first folded plate enters air inlet pipe, simultaneously because air current flow exists Negative pressure is formed on the inside of second folded plate, realizes that gas flows sampling naturally using pressure difference, naturally it is also possible to directly in bypass runner pipe Air pump is set on road, gas sample is realized in the presence of air pump.
The air extractor includes suction bottle 17 and pumping piston 18, and the pumping piston 18 is connected with a piston rod 19.
The air extractor is arranged in pumping housing 20, and the pumping housing 20 is fixed on the outside of shell 1.
When being sampled using the utility model, normally close valve 6 is opened, while opens first switch valve, the 3rd switch valve, the 4th open Valve and the 5th switch valve are closed, second switch valve is closed, realizes that gas flows sampling naturally using the pressure difference of inlet end and outlet side, Normally close valve 6 is closed after the completion of to be sampled, simultaneously closes off first switch valve, the 3rd switch valve, the 4th switch valve and the 5th switch valve, Now need test sample gas in main sampling pipeline and six air storing cavity rooms, when treating test sample gas and being tested and analyzed, first open First switch valve, pull piston to realize pumping, i.e., the sample gas in main sampling pipeline is extracted into suction bottle, is then shut off first and opens Valve 7 is closed, second switch valve 8 is opened, the sample gas in suction bottle is distributed to detector, realizes and detects for the first time.Six are extracted successively Sample gas in individual air storage chamber is detected, and can obtain seven sub-sampling results, can be more by the comparative analysis of next sampling result Accurately determination takes the analysis result of gas.
Above-described is only preferred embodiment of the present utility model, should be understood that the explanation of above example only It is to be used to help understand method and its core concept of the present utility model, is not used to limit the scope of protection of the utility model, All any modifications made within thought of the present utility model and principle, equivalent substitution etc., it is new to should be included in this practicality Within the protection domain of type.

Claims (6)

1. a kind of gas sample bypasses processing unit, including shell and the main sampling pipeline that is arranged in shell, the main sampling The inlet end of pipeline is connected with the air inlet pipe being fixed on gas pipeline, and outlet side is connected with appendix, is set successively on appendix There are first switch valve and second switch valve, it is characterised in that:It is provided with and appendix phase between first switch valve and second switch valve The bypass flow pipe and bypass exhaust pipe of connection, the bypass flow pipe are provided with the 3rd switch valve, bypass runner pipe The outlet side on road is connected with the escape pipe being fixed on gas pipeline, and bypass exhaust pipe is connected with an air extractor;Also include Some bypass sampling lines being in parallel with main sampling pipeline, the bypass sampling line are provided with gas storage chamber, gas storage chamber Both sides are respectively equipped with the 4th switch valve and the 5th switch valve, and one end of this bypass sampling line is connected with main sampling pipeline, separately Appendix between one end and first switch valve and second switch valve is connected;It is equipped with the air inlet pipe and escape pipe normally closed Valve.
A kind of 2. gas sample bypass processing unit according to claim 1, it is characterised in that:The bypass sampling line Quantity be 6, and the rounded array around main sampling pipeline.
A kind of 3. gas sample bypass processing unit according to claim 1 or 2, it is characterised in that:The bypass circulation Pipeline is provided with air pump.
A kind of 4. gas sample bypass processing unit according to claim 1 or 2, it is characterised in that:The gas pipeline The first folded plate bent downwards and the second folded plate being folded upward at are sequentially provided with interior gas circulating direction, the air inlet pipe is entered Gas end is on the inside of the first folded plate, and the outlet side of escape pipe is on the inside of the second folded plate.
A kind of 5. gas sample bypass processing unit according to claim 1 or 2, it is characterised in that:The air extractor Including suction bottle and pumping piston, the pumping piston is connected with a piston rod.
A kind of 6. gas sample bypass processing unit according to claim 5, it is characterised in that:The air extractor is set In pumping housing, the pumping housing is fixed on the outer side.
CN201720327571.5U 2017-03-31 2017-03-31 Gas sample bypasses processing unit Expired - Fee Related CN206671011U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720327571.5U CN206671011U (en) 2017-03-31 2017-03-31 Gas sample bypasses processing unit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720327571.5U CN206671011U (en) 2017-03-31 2017-03-31 Gas sample bypasses processing unit

Publications (1)

Publication Number Publication Date
CN206671011U true CN206671011U (en) 2017-11-24

Family

ID=60366485

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720327571.5U Expired - Fee Related CN206671011U (en) 2017-03-31 2017-03-31 Gas sample bypasses processing unit

Country Status (1)

Country Link
CN (1) CN206671011U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110596311A (en) * 2019-08-05 2019-12-20 苏州迈优医疗科技有限公司 Novel multichannel exhaled gas analyzer and operation method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110596311A (en) * 2019-08-05 2019-12-20 苏州迈优医疗科技有限公司 Novel multichannel exhaled gas analyzer and operation method

Similar Documents

Publication Publication Date Title
CN106596867A (en) SCR outlet flue cross section nitric oxide and oxygen concentration online monitoring method and system
CN203587579U (en) Online continuous smoke monitoring system
CN108344604A (en) A kind of SCR reative cells NOXThe online data-logger of concentration and control method
CN105944568A (en) Multi-point sampling and measurement system for exhaust smoke from inlet and outlet of denitration CEMS of thermal power plant
CN110243638A (en) A kind of smoke collecting apparatus and method for SCR denitration device
CN206132125U (en) Flue total cross -section nitrogen oxide on line measurement system for SCR denitrification process
CN207541048U (en) A kind of exhaust gas on-line period monitoring device
CN103245762A (en) Flue gas distribution measuring device and method of SCR (Selective Catalytic Reduction) flue gas denitration system
CN102103046B (en) Ball bladder sampling device and sampling method
CN207570855U (en) CEMS flue gas sampling probes
CN206671011U (en) Gas sample bypasses processing unit
CN206270239U (en) A kind of uv analyzer of nitrogen oxides in effluent content measurement
CN108905395A (en) A kind of VOCs exhaust gas concentration detection method
CN205787818U (en) A kind of coal-burning power plant SCR denitration device on-line monitoring system
CN104390836A (en) Copper smelting smoke analysis and sample injection processing system and method
CN206740687U (en) Flue gas pretreatment, collection and the on-line analysis device of cone calorimetry
CN207231861U (en) A kind of waste gas collecting device
CN107478469A (en) A kind of waste gas collecting device
CN210923164U (en) Sampling pipeline of atmosphere analyzer in furnace
CN205229042U (en) Portable normal position UV spectrum flue gas analyzer
CN202393631U (en) Gas detection device for urban underground pipeline network
CN209476006U (en) A kind of NOx subregion patrols survey dynamic spray ammonia balance control system
CN208833731U (en) A kind of flue gas analysis system
CN205903797U (en) Denitration CEMS access & exit flue gas multi point sampled measurement system of thermal power factory
CN207540841U (en) A kind of sampling pre-processing device of chemical method the escaping of ammonia on-line analysis monitor

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171124